File ID: 2023-01558 1/9/2024 Consent Item 4.
Mitigation Fee Act Five-Year Report for the Period Ended June 30, 2023 (Noticed 12/22/2023) File ID: 2023-01558
Location: District 4, Represented by Mayor Steinberg and Councilmember Valenzuela Recommendation: Receive and file the Mitigation Fee Act Five-Year Report for the Fiscal Year Ended June 30, 2023.
Contact: Jessica Steinhauer, Senior Development Project Manager, (916) 808-8243, [email protected], Sheri Smith, Special Districts Manager, (916) 808-7204, [email protected]; Department of Finance
Presenter: None
Attachments:
1-Description/Analysis
2-Mitigation Fee Act Five-Year Report
Description/Analysis
Issue Detail: The City imposes impact fees pursuant to the Mitigation Fee Act (California Government Code section 66000 et seq., hereafter the Act) on new development for the purpose of defraying all or a portion of the cost of public facilities associated with or required to support new development. The types of development for which impact fees are generally charged include new residential dwelling units, non- residential buildings, and commercial and residential additions or changes in use of existing buildings. These types of development stress existing public facilities and triggers demand for new and improved facilities. Therefore, using impact fee revenues to support the demand for new and improved facilities can provide consistent levels of service for residents.
For the City to charge impact fees, the City is required to identify a reasonable relationship between the need for public facilities and the type of proposed development. In addition, the City may only utilize the fee revenues for the specific type of public facilities for which purpose the fee was paid.
The City establishes separate funds for each impact fee program. When an impact fee is paid, the payment is credited to the appropriate fund. Interest earned on the money in each fund is credited to such fund.
File ID: 2023-01558 1/9/2024 Consent Item 4.
The Act requires that every five years the City report certain information regarding unexpended development impact fees. The Mitigation Fee Act Five-Year Report for the Fiscal Year Ended June 30, 2022 (Attachment 2) fulfills the five-year reporting requirement for the River District Fee Fund.
The report presents the following information as required by the Act:
1. Identifies the purposes to which the fees are to be put.
2. Demonstrates a reasonable relationship between the fees and the purposes for which they have been charged.
3. Identifies all funding sources and amounts of funding anticipated to complete the financing of incomplete improvements, if any.
4. Designates the approximate dates on which the funding of incomplete improvements is expected to be deposited into the appropriate fund or account.
Pursuant to the Act, the report included as Attachment 2 was made available to the public on December 22, 2023.
Policy Considerations: Filing the required five-year report will satisfy the requirements of the Act.
Economic Impacts: Not applicable.
Environmental Considerations:
California Environmental Quality Act (CEQA): Under the CEQA Guidelines, this report constitutes administrative activities that do not constitute a “project” as defined by the CEQA Guidelines section 15378(b)(2).
Sustainability: Not applicable.
Commission/Committee Action: None.
Rationale for Recommendation: The Act requires a report to be filed every five years with the Council for all unexpended amounts contained in the City’s impact fee funds.
Financial Considerations: There are no financial impact to any City funds.
Local Business Enterprise (LBE): Not applicable.
MiƟgaƟon Fee Act Five‐Year Report
River District Specific Plan
Development Impact Fees
Fiscal Year Ended June 30, 2023
December 21, 2023
CITY OF SACRAMENTO
MITIGATION FEE ACT FIVE-YEAR REPORT TABLE OF CONTENTS
TABLE OF CONTENTS
Page No.
Section I – Introduction .................................................................................................... 1 Purpose ..................................................................................................................... 1 Organization and Contents of Report ......................................................................... 2
Section II – River District Specific Plan Area Development Impact Fee Program ........... 3 Transportation Impact Fee ......................................................................................... 3 Storm Drainage Impact Fee ....................................................................................... 5 Water Impa ct Fee ...................................................................................................... 8 Transportation and Utili ty Impact Fee ...................................................................... 10 Open Space Facilitie s Impact Fee ........................................................................... 11 Public Transit Fac ilities Impact Fee ......................................................................... 13 Library Facilitie s Impact Fee .................................................................................... 14 Public Safety Fac ilities Impact Fee .......................................................................... 15
CITY OF SACRAMENTO
MITIGATION FEE ACT FIVE YEAR REPORT SECTION I
1 SECTION I
INTRODUCTION
The City of Sacramento (the “City”) imposes impact fees pursuant to the Mitigation Fee Act (California Government Code section 66 000 et seq., hereafter the “Act”) on new development for the purpose of defraying all or a portion of t he cost of public facilities associated with or required to support new development. The types of development for which impact fees are generally charged include new residential dwelling units, non- residential buildings, and commercial and residential additions or changes in use of existing buildings. These types of development stress existing public facilities and triggers demand for new and improved faciliti es. Therefore, usin g impact fee revenues to support the demand for new and improved facilities can pr ovide consistent levels of service for residents.
For the City to charge impact fees, the City is required to identify a reasonable relationship between the need for public facilities and the type of proposed development. In addition, the City may only utilize the fee revenues for the specific type of public facilities for which purpose the fee was paid. The City establishes separate funds for each impact fee program.
When an impact fee is paid, the payment is credited to the appropriate fund. Interest earned on the money in each fund is credited to such fund.
PURPOSE
This report was prepared on behalf of the City to fulfill the five-year reporting requirements set forth in the Act. Section 66001(d) of the Act requires local agencies to report for the fifth fiscal year following the first deposit of impact fees into the account or fund, and every five years thereafter, certain information rega rding unexpended deve lopment impact fee revenue.
This report presents the five-year findings required by the Act for the City’s River District Specific Plan Area Development Impact Fee Program (“River District Fee Program” or “Program”) as of June 30, 2023.
Pursuant to California Government Code section 66001(d), the following requirements are addressed within this report for the Program’s Development Impact Fees (“Impact Fees”):
Identify the purpose to wh ich the fee is to be put.
Demonstrate a reasonable relationship between the fee and the purpose for which it is charged.
Identify all sources and am ounts of funding anticipated to complete financing of incomplete improvements.
Designate the approximate dates on which the identifi ed funding referred to is expected to be deposited into the appropriate account or fund.
CITY OF SACRAMENTO
MITIGATION FEE ACT FIVE YEAR REPORT SECTION I
2 ORGANIZATION AND CONTENTS OF REPORT
General information for the Program and corresponding Impact Fees follows in Section II.
Information includes the use, pur pose, and relationship of the fee to the public facilities funded by the Program’s Impact Fees. In addition, fund balances for the Program’s Impact Fees are provided as of June 30, 2023. Fund balances for the Program’s Impact Fees have been identified as the “Available Fund Balance” and allocated amongst the incomplete projects in Table 1 of Section II of the report. Please be advised, the Available Fund Balance allocations presented in Table 1 for the Program’s Impact Fees are not dedicated funds for that specific incomplete project. Fund balances will be used for incomplete projects at the City’s discretion based on funding and infrastructure needs, along with consideration for the timing of new development. Outstanding obligations identified in the report include unpaid loans, unused Impact Fee credits earned by developer s, and reimbursement amounts due to developers. Developers can earn Impact Fee credits or are due reimbursements upon constructing impact f ee eligible improvements that exceed the value of the Impact Fees due for their respective development. As of June 30, 2023, the River District Fee Program has no outstanding obligations. Furthermore, Section II provides the following additional information:
A listing of incomplete projec ts and outstanding obligations. An estimate of the remaining co st to complete each project. A breakdown of the sources of funding anticipated for projects. The anticipated fiscal year(s ) as to when funding may be available for the incomplete projects.
A summary of the overall projected revenues and expenditures and estimated shortfall or surplus at completion for the Program’s Impact Fees.
For additional details related to the Program, please see the latest Finance Plan for the Program, which is available on file with the Infrastructure Finance Division of the City’s Finance Department.
CITY OF SACRAMENTO
MITIGATION FEE ACT FIVE YEAR REPORT SECTION II
3 SECTION II
RIVER DISTRICT SPECIFIC PLAN AREA IMPACT FEE PROGRAM
The River District Specific Plan Area (the “River District Area”) was established in 2011, and the River District Fee Program was established in 2016 to fund backbone infrastructure improvements in the River District Area of the City, all of which are identified in more detail in the Updated River District Finance Plan (adopted by the Sacramento City Council on February 14, 2017, per Resolution No. 2017-0075). The Rive r District Area is centrally located in the City and is immediately north of the Railyards Specific Plan Area, east of the Sacramento River, south of the American River, and west of the 16 th Street Corridor. Fee
revenues collected from the River District Impact Fee Program are used to fund the design, construction, installation, improvement, a nd acquisition of storm drainage, water, transportation and roadway, open space, light rail transportation stations, library, and public safety facilities and improvements.
TRANSPORTATION IMPACT FEE
New development in the River District Area generates new residents, employees, and patrons that create new vehicl e, bicycle, and pede strian trips. The increase in traffic demands requires expanded roadway capacity and improved connectivity through roadway enhancements to accommodate new development. The purpose of the Transportation Impact Fee is to fund the construction, enhancements, and ex pansion of roadway improvements and facilities that mitigate t he impacts of the additi onal vehicular trips generated by the new development. Roadway improvements funded by the Transportation Impact Fee include construction and expans ion of roadway segments, intersection improvements, freeway improvements, and bi keway improvements. Completion of the roadway improvements is crucial to allow for expanded roadway capacity, which provides the improvements necessary fo r a continued stable flow of traffic which mitigates the impacts of additional vehicle, bicycle, and pedestrian trips resulting from new development.
As of June 30, 2023, the Tr ansportation Impact Fee had a fund bala nce of $4,180,554.
Table 1A below shows a summary of the estimated remaining construction costs along with funding sources for each incomplete project.
CITY OF SACRAMENTO
MITIGATION FEE ACT FIVE YEAR REPORT SECTION II
4 Available
Fund
Balance1
Projected
Future
Impact Fees
City
Economic
Incentives2
Downtown/
Railyards Plan
Area Fees Measure A
State, and
Federal
Funding3
Total
Estimated
Funding
Onsite Roadway - Street O to N. 10th St-52-2L-PP $1,055,672 $24,412 $1,002,185 $821 $28,254 $0 $0 $1,055,672 Onsite Roadway - N. 10th St. to Dos Rios St.-52-2L-PP $1,222,860 $28,278 $1,160,902 $952 $32,729 $0 $0 $1,222,860 Onsite Roadway - N. 7th St. to Street O-68-2L-PP $698,284 $16,147 $662,904 $543 $18,689 $0 $0 $698,284 Onsite Roadway - Street O to N.10th St.-68-2L-PP $843,730 $19,511 $800,982 $657 $22,582 $0 $0 $843,730 Onsite Roadway - Street W to N. 12th St.-80-3L-PP $812,745 $18,794 $771,566 $632 $21,752 $0 $0 $812,745 Onsite Roadway - Dos Rios St to Street W-107-4L-BB-P-LRT $3,519,953 $81,396 $3,341,610 $2,739 $94,208 $0 $0 $3,519,953 Onsite Roadway - Street W to N. 12th St-107-4L-BB-P-LRT $1,836,375 $42,465 $1,743,333 $1,429 $49,149 $0 $0 $1,836,375 Onsite Roadway - N. 12th St to N. 16th St-100-5L-BB $3,124,855 $72,260 $2,966,530 $2,431 $83,634 $0 $0 $3,124,855 Onsite Roadway - Bercut Drive to N 3rd St.-90-3L-BP-Park $1,469,529 $33,982 $1,395,074 $1,143 $39,330 $0 $0 $1,469,529 Onsite Roadway - N. 3rd St. to Sequoia Pacific-90-3L-BP-Park $1,565,349 $36,198 $1,486,038 $1,218 $41,895 $0 $0 $1,565,349 Onsite Roadway - Sequoia Pacific to N. 5th St-90-3L-BB-PP $1,904,068 $44,030 $1,807,596 $1,482 $50,960 $0 $0 $1,904,068 Onsite Roadway - N. 5th St. to Judah St-90-3L-BB-PP $1,412,284 $32,658 $1,340,728 $1,099 $37,798 $0 $0 $1,412,284 Onsite Roadway - Judah St to N. 6th St-90-3L-BB-PP $1,406,639 $32,527 $1,335,369 $1,095 $37,647 $0 $0 $1,406,639 Onsite Roadway - N. 6th St. to N. 7th St-90-3L-BB-PP $1,399,247 $32,357 $1,328,352 $1,089 $37,449 $0 $0 $1,399,247 Onsite Roadway - N. 7 St to Street N-90-3L-BB-PP $2,124,763 $49,134 $2,017,109 $1,653 $56,867 $0 $0 $2,124,763 Onsite Roadway - Street N to N. 10th St-90-3L-BB-PP $2,083,915 $48,189 $1,978,331 $1,621 $55,774 $0 $0 $2,083,915 Onsite Roadway - N. 10th St. to N. 11th St.-90-3L-BB-PP $1,169,077 $27,034 $1,109,844 $910 $31,289 $0 $0 $1,169,077 Onsite Roadway - N. 11th St. to Dos Rios St.-90-3L-BB-PP $1,169,077 $27,034 $1,109,844 $910 $31,289 $0 $0 $1,169,077 Onsite Roadway - Dos Rios St to Street W-90-3L-BB-PP $1,137,368 $26,301 $1,079,742 $885 $30,441 $0 $0 $1,137,368 Onsite Roadway - Street W to N. 12th St-90-3L-BB-PP $866,605 $20,040 $822,698 $674 $23,194 $0 $0 $866,605 Onsite Roadway - Sequoia Pacific To N. 5th St.-85-4L-BB-PP $591,273 $13,673 $561,315 $460 $15,825 $0 $0 $591,273 Onsite Roadway - N. 5th St. to N. 7th St.-85-4L-BB-PP $293,271 $6,782 $278,412 $228 $7,849 $0 $0 $293,271 Onsite Roadway - N. 7th St. to N 10th St.-85-4L-BB-PP $316,036 $7,308 $300,023 $246 $8,458 $0 $0 $316,036 Onsite Roadway - N 10th St. to N. 12th St.-80-4L-BB $223,100 $5,159 $211,797 $174 $5,971 $0 $0 $223,100 Onsite Roadway - N. 12th St. to N. 14th St.-80-4L-BB $237,027 $5,481 $225,018 $184 $6,344 $0 $0 $237,027 Onsite Roadway - N 14th St. to N. 16th St.-80-4L-BB $231,402 $5,351 $219,678 $180 $6,193 $0 $0 $231,402 Onsite Roadway - N. B St. to N. C St-85-4L-BB-PP $823,811 $19,050 $782,072 $641 $22,048 $0 $0 $823,811 Onsite Roadway - N. C St. to Bannon St.-85-4L-BB-PP $1,163,797 $26,912 $1,104,832 $906 $31,148 $0 $0 $1,163,797 Onsite Roadway - River District's Boundary to N. B St-5TH-RY $358,351 $8,287 $340,195 $279 $9,591 $0 $0 $358,351 Onsite Roadway - N. B St to N. C St.-68-2L-PP $1,134,540 $26,235 $1,077,057 $883 $30,365 $0 $0 $1,134,540 Onsite Roadway - N. C St to Bannon St.-68-2L-PP $1,932,252 $44,682 $1,834,352 $1,503 $51,715 $0 $0 $1,932,252 Onsite Roadway - Bannon St to Richards Blvd.-68-2L-PP $909,751 $21,037 $863,658 $708 $24,349 $0 $0 $909,751 Onsite Roadway - N. B Street to N. C Street-68-2L-PP $436,511 $10,094 $414,395 $340 $11,683 $0 $0 $436,511 Onsite Roadway - N. C Street to Bannon St.-68-2L-PP $493,419 $11,410 $468,420 $384 $13,206 $0 $0 $493,419 Onsite Roadway - Bannon St. to Richards Blvd.-68-2L-PP $532,368 $12,311 $505,395 $414 $14,248 $0 $0 $532,368 Onsite Roadway - Street 10 to Vine St.-50-B $2,027,011 $46,873 $1,924,309 $1,577 $54,251 $0 $0 $2,027,011 Onsite Roadway - Vine St. to Riverfront Dr.-68-2L-PP $1,117,039 $25,831 $1,060,442 $869 $29,896 $0 $0 $1,117,039 Onsite Roadway - N. B St. to Sproule Ave.-80-4L-LRT $852,121 $19,705 $808,947 $663 $22,806 $0 $0 $852,121 Onsite Roadway - Sproule Ave. to Richards Blvd.-80-4L $2,073,850 $47,956 $1,968,776 $1,614 $55,505 $0 $0 $2,073,850 Onsite Roadway - Richards Ave. to Vine Ave.-80-4L $1,537,427 $35,552 $1,459,531 $1,196 $41,148 $0 $0 $1,537,427 Onsite Roadway - N. B St to Sproule-80-4L-PP $795,055 $18,385 $754,772 $619 $21,279 $0 $0 $795,055 Onsite Roadway - Sproule Ave. to Richards Blvd.-80-4L-PP $312,726 $7,232 $296,881 $243 $8,370 $0 $0 $312,726 Onsite Roadway - Richards Blvd. to Vine Ave.-80-4L-PP $142,352 $3,292 $135,140 $111 $3,810 $0 $0 $142,352 Onsite Roadway - N.12th St. to N. 16th St.-80-4L $1,769,226 $40,912 $1,679,585 $1,377 $47,352 $0 $0 $1,769,226 Intersections & Roundabouts - Bercut Drive / Richards Boulevard $927,093 $21,438 $904,933 $721 $0 $0 $0 $927,093 Intersections & Roundabouts - 3rd Street / Richards Boulevard $7,443 $172 $7,265 $6 $0 $0 $0 $7,443 Intersections & Roundabouts - North 4th St / Richards Boulevard $268,445 $6,208 $262,028 $209 $0 $0 $0 $268,445 Intersections & Roundabouts - 7th Street / Richards Boulevard $268,445 $6,208 $262,028 $209 $0 $0 $0 $268,445 Intersections & Roundabouts - Dos Rios Street / Richards Boulevard $257,526 $5,955 $251,370 $200 $0 $0 $0 $257,526 Intersections & Roundabouts -Street W / New Richards Boulevard $495,068 $11,448 $483,234 $385 $0 $0 $0 $495,068 Intersections & Roundabouts -New 12th Street / New Richards Boulevard $824,083 $19,056 $804,385 $641 $0 $0 $0 $824,083 Intersections & Roundabouts -16th Street / New Richards Boulevard $844,685 $19,533 $824,495 $657 $0 $0 $0 $844,685 Intersections & Roundabouts -Vine Street / New Richards Boulevard $51,505 $1,191 $50,274 $40 $0 $0 $0 $51,505 Intersections & Roundabouts -Vine Street / Richards Boulevard $463,546 $10,719 $452,467 $361 $0 $0 $0 $463,546 Intersections & Roundabouts -Vine Street / New 12th Street $824,083 $19,056 $804,385 $641 $0 $0 $0 $824,083 Intersections & Roundabouts -12th Street / 16th Street / Richards Boulevard $257,526 $5,955 $251,370 $200 $0 $0 $0 $257,526 Intersections & Roundabouts -12th Street / Sunbeam Avenue / Sproule Avenue $257,526 $5,955 $251,370 $200 $0 $0 $0 $257,526 Intersections & Roundabouts -Bercut Drive / Bannon Street $370,837 $8,575 $361,973 $289 $0 $0 $0 $370,837 Intersections & Roundabouts -3rd Street / Bannon Street $370,837 $8,575 $361,973 $289 $0 $0 $0 $370,837 Intersections & Roundabouts -5th Street / Bannon Street $463,546 $10,719 $452,467 $361 $0 $0 $0 $463,546 Intersections & Roundabouts -North 4th St / Bannon Street $463,546 $10,719 $452,467 $361 $0 $0 $0 $463,546 Intersections & Roundabouts -7th Street / Bannon Street $463,546 $10,719 $452,467 $361 $0 $0 $0 $463,546 Intersections & Roundabouts -10th Street / Bannon Street $463,546 $10,719 $452,467 $361 $0 $0 $0 $463,546 Intersections & Roundabouts -Dos Rios Street / Bannon Street $463,546 $10,719 $452,467 $361 $0 $0 $0 $463,546 Intersections & Roundabouts -12th Street / Bannon Street $824,083 $19,056 $804,385 $641 $0 $0 $0 $824,083 Intersections & Roundabouts - 7th Street / North B Street $463,546 $10,719 $452,467 $361 $0 $0 $0 $463,546 Intersections & Roundabouts -12th Street / North B Street $257,526 $5,955 $251,370 $200 $0 $0 $0 $257,526 Intersections & Roundabouts - 14th Street / North B Street $474,466 $10,972 $463,125 $369 $0 $0 $0 $474,466 Intersections & Roundabouts -Ahern / North B Street $495,068 $11,448 $483,234 $385 $0 $0 $0 $495,068 Intersections & Roundabouts -North 16th St / North B Street $7,045 $163 $6,876 $5 $0 $0 $0 $7,045 Intersections & Roundabouts -10th Street / C Street $731,991 $16,927 $714,495 $570 $0 $0 $0 $731,991 Intersections & Roundabouts -12th St / C Street $257,526 $5,955 $251,370 $200 $0 $0 $0 $257,526 Intersections & Roundabouts - 14th Street / C Street $463,546 $10,719 $452,467 $361 $0 $0 $0 $463,546 Intersections & Roundabouts -16th Street / C Street $525,971 $12,163 $513,399 $409 $0 $0 $0 $525,971 Intersections & Roundabouts - 7th Street / F Street $463,546 $10,719 $452,467 $361 $0 $0 $0 $463,546 Intersections & Roundabouts -10th Street / F Street $463,546 $10,719 $452,467 $361 $0 $0 $0 $463,546 Intersections & Roundabouts -14th Street/ F Street $257,526 $5,955 $251,370 $200 $0 $0 $0 $257,526 Intersections & Roundabouts - 7th Street / G Street $20,336 $470 $19,850 $16 $0 $0 $0 $20,336 Intersections & Roundabouts - 5th Street / H Street $495,068 $11,448 $483,234 $385 $0 $0 $0 $495,068 Intersections & Roundabouts -6th Street/ H Street $20,336 $470 $19,850 $16 $0 $0 $0 $20,336 Intersections & Roundabouts -7th Street H Street $257,526 $5,955 $251,370 $200 $0 $0 $0 $257,526 Intersections & Roundabouts -16th Street/H Street $14,089 $326 $13,752 $11 $0 $0 $0 $14,089 Intersections & Roundabouts -5th Street / I Street $14,089 $326 $13,752 $11 $0 $0 $0 $14,089 Intersections & Roundabouts -6th Street / I Street $257,526 $5,955 $251,370 $200 $0 $0 $0 $257,526 Intersections & Roundabouts -3rd Street / J Street $13,292 $307 $12,974 $10 $0 $0 $0 $13,292 Intersections & Roundabouts - B Street/Judah Street $309,031 $7,146 $301,644 $240 $0 $0 $0 $309,031 Intersections & Roundabouts - B Street/6th Street $309,031 $7,146 $301,644 $240 $0 $0 $0 $309,031 Intersections & Roundabouts - B Street/8th Street $309,031 $7,146 $301,644 $240 $0 $0 $0 $309,031 Intersections & Roundabouts - B Street / 9th Street $309,031 $7,146 $301,644 $240 $0 $0 $0 $309,031 Intersections & Roundabouts -Bercut / St C $1,236,124 $28,584 $1,206,578 $962 $0 $0 $0 $1,236,124 Intersections & Roundabouts -Vine/10th Street $1,236,124 $28,584 $1,206,578 $962 $0 $0 $0 $1,236,124 Freeway Interchange - Richards Blvd. I-5-0 $108,991,570 $2,520,347 $8,294,004 $84,806 $10,899,157 $19,937,482 $67,255,773 $108,991,570 Bikeways Connection - Jibboom St/American River Bike Trail $206,021 $4,764 $201,096 $160 $0 $0 $0 $206,021 Bikeways Connection - N. 4th St./American River $206,021 $4,764 $201,096 $160 $0 $0 $0 $206,021 Bikeways Connection - Street S/American River $206,021 $4,764 $201,096 $160 $0 $0 $0 $206,021 Bikeways Connection - Richards Blvd/American River Bike Trail $206,021 $4,764 $201,096 $160 $0 $0 $0 $206,021 Bikeways Path - connecting Signature St. to Street S $178,989 $4,139 $174,711 $139 $0 $0 $0 $178,989 Bikeways Path - south of Richards Blvd. $192,177 $4,444 $187,584 $150 $0 $0 $0 $192,177 Bikeways Path - Richards Blvd. to Street S $65,944 $1,525 $64,368 $51 $0 $0 $0 $65,944 Totals: $180,786,645 $4,180,554 $77,001,583 $140,670 $12,270,584 $19,937,482 $67,255,773 $180,786,645 1Available Fund Balance is allocated proportionately based on the estimated remaining construction costs and does not represent dedicated funds. Available Fund Balance will be utilized at the City's discretion to fund incomplete projects. 2Economic Incentive funding is anticipated to be funded by future grants. These amounts will not be funded by impact fees. 3Regional, State, and Federal Funding reflects future funding anticipated by participating in various government transportation programs. These amounts will not be funded by impact fees, nor will they be funded by the City.
TABLE 1A - TRANSPORTATION IMPACT FEE (On-Site Roadways, Freeways, Intersections and Roundabouts, and Bikeways)
SUMMARY OF INCOMPLETE PROJECTS AND ANTICIPATED FUNDING SOURCES Funding Sources
Description
of Incomplete
Projects
Estimated
Remaining
Construction
Costs
CITY OF SACRAMENTO
MITIGATION FEE ACT FIVE YEAR REPORT SECTION II
5 Table 2A below shows the ap proximate timing of deposit related to the funding of incomplete projects.
Table 3A below shows a summ ary of the revenue and expenditure projections for the Transportation Impact Fee, and the estimated shortfall or surplus at completion.
As a result, the City finds that there is a co ntinued need to collect Transportation Impact Fees from new developm ent within the River District Ar ea to pay for the costs of the construction and expansion of roadway improvements and facilities to mitigate the impact of new development.
STORM DRAINAGE IMPACT FEE
Development planned for the River District Area necessitates enhancements to the current storm drainage system to accommodate development and the anticipated growth. These improvements aim to enhance water quality, limit stormwater runoff, improve efficiency of the existing system, and reduce and prevent flooding in the River District Area. As new developments create additional impervious surfaces, increases in stormwater runoff will be generated, prompting the need for expanded collection and conveyance capacity in the existing storm drainage system. The purpose of the Storm Drainage Impact Fee is to fund Funding
Sources
FY 2022-23
Actuals
FY 2023-24
Estimate
FY 2024-25
Estimate
FY 2025-26
Estimate
FY 2026-27
Estimate
FY 2027-28
Estimate
After
FY 2028-29
Estimate
Total
Estimated
Funding
Available Fund Balance1
$4,180,554 $0 $0 $0 $0 $0 $0 $4,180,554
Projected Future Impact Fees $0 $1,051,612 $1,072,644 $1,094,097 $1,115,979 $1,138,298 $71,528,952 $77,001,583 City Economic Incentives $0 $0 $0 $0 $0 $0 $140,670 $140,670 Downtown/Railyards Plan Area Fees $0 $0 $0 $0 $0 $0 $12,270,584 $12,270,584 Measure A $0 $0 $0 $0 $0 $0 $19,937,482 $19,937,482
Regional, State, and Federal Funding $0 $0 $0 $0 $0 $0 $67,255,773 $67,255,773 Totals: $4,180,554 $1,051,612 $1,072,644 $1,094,097 $1,115,979 $1,138,298 $171,133,461 $180,786,645 1Includes unspent impact fees previously collected and other available funds as of June 30, 2023.
TABLE 2A - TRANSPORTATION IMPACT FEE (On-Site Roadways, Freeways, Intersections and Roundabouts, and Bikeways)
APPROXIMATE TIMING OF DEPOSIT FOR FUNDING OF INCOMPLETE PROJECTS Revenues
Available Fund Balance as of June 30, 2023 $4,180,554
Projected Future Impact Fees $77,001,583
City Economic Incentives $140,670
Downtown/Railyards Plan Area Fees $12,270,584
Measure A $19,937,482
Regional, State, and Federal Funding $67,255,773
Total Future Funding: $176,606,091
Total Projected Revenues: $180,786,645
Remaining Construction Costs
Total Estimated Remaining Construction Costs $180,786,645 Total Remaining Construction Costs: $180,786,645
Estimated Shortfall/Surplus to Completion: $0
TABLE 3A
TRANSPORTATION IMPACT FEE STATUS SUMMARY
CITY OF SACRAMENTO
MITIGATION FEE ACT FIVE YEAR REPORT SECTION II
6 the storm drainage improvements necessary to mitigate the impact of new developments.
The Storm Drainage Impact Fee will be used to fund the improvements to facilitate the modifications to the existing pump station and construction of drainage mains to convey increased stormwater flows generated by new development to the detention basins. The construction and completion of these im provements are necessary to mitigate the increased storm water run-off generated by new development.
As of June 30, 2023, the Storm Drainage Impact Fee had a fund balance of $1,600,259.
Table 1B below shows a summary of the estimated remaining construction costs that are to be paid by the Storm Drai nage Impact Fees, along with funding sources for each incomplete project.
CITY OF SACRAMENTO
MITIGATION FEE ACT FIVE YEAR REPORT SECTION II
7 Available
Fund
Balance1
Projected
Future
Impact Fees
City
Economic
Incentives2
Total
Estimated
Funding
Street 9 to Street 8 Section - 52-2L-PP $278,128 $14,298 $263,349 $481 $278,128 N. 7th St. to Street O Section - 68-2L-PP $556,256 $28,595 $526,698 $962 $556,256 N. 10th Street to Dos Rios St. Section - 80-3L-PP $556,132 $28,589 $526,581 $962 $556,132 Dos Rios St. to Street W Section - 80-3L-PP $605,083 $31,105 $572,931 $1,047 $605,083 Street W to N. 12th St. Section - 80-3L-PP $321,578 $16,531 $304,491 $556 $321,578 Street G to N. 5th Street Section - 68-2L-PP $304,086 $15,632 $287,928 $526 $304,086 Bercut Dr. to Street C Section - 68-2L-PP $296,670 $15,251 $280,906 $513 $296,670 Street C to N. 3rd St. Section - 68-2L-PP $267,003 $13,726 $252,815 $462 $267,003 N. 3rd St. to Street E Section - 68-2L-PP $252,169 $12,963 $238,770 $436 $252,169 Street E to Sequoia Pacific Section - 68-2L-PP $259,586 $13,345 $245,792 $449 $259,586 Sequoia Pacific To Street G Section - 68-2L-PP $192,835 $9,913 $182,589 $334 $192,835 Street G to N. 5th St. Section - 68-2L-PP $304,086 $15,632 $287,928 $526 $304,086 Street N to N. 10th St Section - A1 $370,837 $19,064 $351,132 $641 $370,837 Bercut Drive to N. 3rd St. Section - 122-7L-B $422,754 $21,732 $400,291 $731 $422,754 N. 3rd St. to Sequoia Pacific Section - 122-7L-B $591,856 $30,425 $560,407 $1,024 $591,856 Sequoia Pacific To N. 5th St. Section - 118-4L-BB-PP-LRT $542,474 $27,887 $513,648 $938 $542,474 N. 10th St. to Dos Rios St. Section - 107-4L-BB-P-LRT $615,590 $31,646 $582,879 $1,065 $615,590 Dos Rios St to Street W Section - 107-4L-BB-P-LRT $519,172 $26,689 $491,585 $898 $519,172 N. 3rd St. to Sequoia Pacific Section - 90-3L-BP-Park $590,765 $30,369 $559,374 $1,022 $590,765 Sequoia Pacific to N. 5th St Section - 90-3L-BB-PP $415,338 $21,351 $393,268 $718 $415,338 N. 5th St. to Judah St Section - 90-3L-BB-PP $311,503 $16,013 $294,951 $539 $311,503 Judah St to N. 6th St Section - 90-3L-BB-PP $289,253 $14,870 $273,883 $500 $289,253 N. 6th St. to N. 7th St Section - 90-3L-BB-PP $281,836 $14,488 $266,860 $488 $281,836 N. 7 St to Street N Section - 90-3L-BB-PP $463,546 $23,829 $438,915 $802 $463,546 Street N to N. 10th St Section - 90-3L-BB-PP $407,921 $20,970 $386,245 $706 $407,921 Dos Rios St to Street W Section - 90-3L-BB-PP $194,690 $10,008 $184,344 $337 $194,690 Richards Blvd. To Signature Blvd. Section - 68-2L-PP $293,703 $15,098 $278,097 $508 $293,703 Signature Blvd. To Street 9 Section - 68-2L-PP $566,331 $29,113 $536,238 $980 $566,331 Signature Blvd. To Street 9 Section - 68-2L-PP $278,128 $14,298 $263,349 $481 $278,128 Richards Blvd. To Signature St. Section - 68-2L-PP $305,941 $15,727 $289,684 $529 $305,941 Signature Blvd. To Street 9 Section - 68-2L-PP $289,253 $14,870 $273,883 $500 $289,253 Street 9 to Street 8 Section - 68-2L-PP $206,021 $10,591 $195,073 $356 $206,021 Signature St. to Street 9 Section - 68-2L-PP $333,753 $17,157 $316,019 $577 $333,753 Street 9 to Street 8 Section - 68-2L-PP $324,483 $16,681 $307,241 $561 $324,483 N. C St. to Bannon St. Section - 85-4L-BB-PP $123,612 $6,355 $117,044 $214 $123,612 Richards Blvd to Signature Street Section - 125-3L-BB-LRT $290,736 $14,946 $275,288 $503 $290,736 Signature St to Street 9 Section - 125-3L-BB-LRT $148,335 $7,625 $140,453 $257 $148,335 Street 9 to Street 8 Section - 125-3L-BB-LRT $76,392 $3,927 $72,333 $132 $76,392 New Street D to New Street B Section - 68-2L-PP $274,420 $14,107 $259,838 $475 $274,420 New Street B to Street 3 Section - 68-2L-PP $252,169 $12,963 $238,770 $436 $252,169 N. B St to N. C St. Section - 68-2L-PP $274,420 $14,107 $259,838 $475 $274,420 N. C St to Bannon St. Section - 68-2L-PP $333,753 $17,157 $316,019 $577 $333,753 Bannon St to Richards Blvd. Section - 68-2L-PP $18,542 $953 $17,557 $32 $18,542 N. B St to N. C St. Section - 68-2L-PP $237,336 $12,201 $224,725 $411 $237,336 N. C St to Bannon St. Section - 68-2L-PP $333,753 $17,157 $316,019 $577 $333,753 N. B St to N. C St. Section - 100-BT $310,465 $15,960 $293,968 $537 $310,465 N. C St to Bannon St. Section - 100-BT $468,269 $24,072 $443,387 $810 $468,269 Bannon St to Richards Blvd. Section - 100-BT $530,619 $27,277 $502,423 $918 $530,619 N. B Street to N. C Street Section - 68-2L-PP $267,003 $13,726 $252,815 $462 $267,003 N. C Street to Bannon St. Section - 68-2L-PP $326,337 $16,776 $308,996 $564 $326,337 Bannon St. to Richards Blvd. Section - 68-2L-PP $370,837 $19,064 $351,132 $641 $370,837 N. B St. to N. C St. Section - 80-3L-PP $185,419 $9,532 $175,566 $321 $185,419 N. C St. to N. Bannon St. Section - 80-3L-PP $278,128 $14,298 $263,349 $481 $278,128 Bannon St. to Richards Blvd. Section - 80-3L-PP $397,414 $20,430 $376,297 $687 $397,414 Richards Blvd. To Signature St. Section - 60-P $237,830 $12,226 $225,193 $411 $237,830 N. C St. to Bannon St. Section - 80-3L-PP $370,837 $19,064 $351,132 $641 $370,837 Bannon St. to Richards Blvd. Section - 80-3L-PP $571,770 $29,393 $541,388 $989 $571,770 Richards Blvd. To Vine St. Section - 80-3L-PP $593,339 $30,502 $561,811 $1,026 $593,339 Bannon St. to Richards Blvd. Section - 100-2L-BB-PP $778,758 $40,034 $737,377 $1,347 $778,758 N.12th St. to N. 16th St. Section - 80-4L $296,670 $15,251 $280,906 $513 $296,670 Storm Drain Miscellaneous $9,973,332 $512,698 $9,443,382 $17,252 $9,973,332 Totals: $31,129,255 $1,600,259 $29,475,150 $53,846 $31,129,255 1Available Fund Balance is allocated proportionately based on the estimated remaining construction costs and does not represent dedicated funds.
Available Fund Balance will be utilized at the City's discretion to fund incomplete projects. 2Economic Incentive funding is anticipated to be funded by fu ture grants. These amounts will not be funded by impact fees.
TABLE 1B - STORM DRAINAGE IMPACT FEE
SUMMARY OF INCOMPLETE PROJECTS AND ANTICIPATED FUNDING SOURCES Description
of Incomplete
Projects
Estimated
Remaining
Construction
Costs
Funding Sources
CITY OF SACRAMENTO
MITIGATION FEE ACT FIVE YEAR REPORT SECTION II
8 Table 2B below shows the ap proximate timing of deposit related to the funding of incomplete projects.
Table 3B below shows a summary of the revenue and expenditure projections for the Storm Drainage Impact Fee, and the estimated shortfall or surplus at completion.
As a result, the City finds that there is a continued need to collect Storm Drainage Impact Fees from new development within the River District Area to pay for the costs of new storm drainage improvements and facilities to mitigate the impact of new development.
WATER IMPACT FEE
New development in the River District Area generates new residents, employees, and patrons that generate additio nal water consumption demands, necessitating a need for water infrastructure. The existing water supply infrastructure serving the developed River District Area is sufficient, requiring no new transmission lines for water service. The purpose of the Water Impact Fee is to fund the installation of ne w distribution lines crucial for connecting the current water infrastructure system to new developments within the River District Area. The water distribution enhance ments involve the establishment of a more refined grid network of 8- and 12-inch mains located in existing roadway right-of-way. Costs associated with water improvements linked to specific transportation improvements are largely included in the costs of those par ticular transportation improvements. Any miscellaneous water improvements not accounted for in the roadway improvement project costs will be funded by t he Water Impact Fee. Completion of the water improvements Funding
Sources
FY 2022-23
Actuals
FY 2023-24
Estimate
FY 2024-25
Estimate
FY 2025-26
Estimate
FY 2026-27
Estimate
FY 2027-28
Estimate
After
FY 2028-29
Estimate
Total
Estimated
Funding
Available Fund Balance1
$1,600,259 $0 $0 $0 $0 $0 $0 $1,600,259
Projected Future Impact Fees $0 $380,048 $387,649 $395,402 $403,310 $411,376 $27,497,366 $29,475,150 City Economic Incentives $0 $0 $0 $0 $0 $0 $53,846 $53,846 Totals: $1,600,259 $380,048 $387,649 $395,402 $403,310 $411,376 $27,551,212 $31,129,255 1Includes unspent impact fees previously collected and other available funds as of June 30, 2023.
TABLE 2B - STORM DRAINAGE IMPACT FEE
APPROXIMATE TIMING OF DEPOSIT FOR FUNDING OF INCOMPLETE PROJECTS Revenues
Available Fund Balance as of June 30, 2023 $1,600,259
Projected Future Impact Fees $29,475,150
City Economic Incentives $53,846
Total Future Funding: $29,528,996
Total Projected Revenues: $31,129,255
Remaining Construction Costs
Total Estimated Remaining Construction Costs $31,129,255 Total Remaining Construction Costs: $31,129,255
Estimated Shortfall/Surplus to Completion: $0
TABLE 3B
STORM DRAINAGE IMPACT FEE STATUS SUMMARY
CITY OF SACRAMENTO
MITIGATION FEE ACT FIVE YEAR REPORT SECTION II
9 ensures new developments can connect to the water infrastructure resulting in a reliable water source to accommodate the increas ed water consumption resulting from new development.
As of June 30, 2023, the Water Impact Fee had a fund balance of $38,537. Table 1C below shows a summary of the estimated remaining construction costs that are to be paid by the Water Impact Fees, along with funding sources for each incomplete project.
Table 2C below shows the ap proximate timing of deposit related to the funding of incomplete projects.
Table 3C below shows a summary of the revenue and expenditure projections for the Water Impact Fee, and the estimated shortfall or surplus at completion.
Available
Fund
Balance1
Projected
Future
Impact Fees
City
Economic
Incentives2
Total
Estimated
Funding
Water Improvements $749,649 $38,537 $709,815 $1,297 $749,649 Totals: $749,649 $38,537 $709,815 $1,297 $749,649
1Available Fund Balance is allocated proportionately based on the estimated remaining construction costs and does not represent dedicated funds.
Available Fund Balance will be utilized at the City's discretion to fund incomplete projects. 2Economic Incentive funding is anticipated to be funded by future grants. These amounts will not be funded by impact fees.
TABLE 1C - WATER IMPACT FEE
SUMMARY OF INCOMPLETE PROJECTS AND ANTICIPATED FUNDING SOURCES Description
of Incomplete
Projects
Estimated
Remaining
Construction
Costs
Funding Sources
Funding
Sources
FY 2022-23
Actuals
FY 2023-24
Estimate
FY 2024-25
Estimate
FY 2025-26
Estimate
FY 2026-27
Estimate
FY 2027-28
Estimate
After
FY 2028-29
Estimate
Total
Estimated
Funding
Available Fund Balance1
$38,537 $0 $0 $0 $0 $0 $0 $38,537
Projected Future Impact Fees $0 $9,160 $9,343 $9,530 $9,721 $9,915 $662,146 $709,815 City Economic Incentives $0 $0 $0 $0 $0 $0 $1,297 $1,297 Totals: $38,537 $9,160 $9,343 $9,530 $9,721 $9,915 $663,443 $749,649 1Includes unspent impact fees previously collected and other available funds as of June 30, 2023.
TABLE 2C - WATER IMPACT FEE
APPROXIMATE TIMING OF DEPOSIT FOR FUNDING OF INCOMPLETE PROJECTS Revenues
Available Fund Balance as of June 30, 2023 $38,537
Projected Future Impact Fees $709,815
City Economic Incentives $1,297
Total Future Funding: $711,112
Total Projected Revenues: $749,649
Remaining Construction Costs
Total Estimated Remaining Construction Costs $749,649
Total Remaining Construction Costs: $749,649
Estimated Shortfall/Surplus to Completion: $0
TABLE 3C
WATER IMPACT FEE STATUS SUMMARY
CITY OF SACRAMENTO
MITIGATION FEE ACT FIVE YEAR REPORT SECTION II
10 As a result, the City finds that there is a continued need to collect Water Impact Fees from new development within the River District Area to pay for the costs to construct and expand the water improvements and facilities to mitigate the impact of new development.
TRANSPORTATION AND UTILITY IMPACT FEE
New development in the River District Area generates new residents, employees, and patrons that places additio nal demands for transportation and utility infrastructure, necessitating the orderly construction of necessary roadways and utilities and the linking of new improvements to the existing infrastruc ture grid. Since development in the River District Area is anticipated to occur irregularly, the purpose of the Transportation and Utility Impact Fee is to provide matching, gap, or additional funding for certain transportation and utility costs to avoid piecemeal construction of major roadway facilities. The Transportation and Utility Fee is intended to fund frontage improvements in the circumstance where road frontage improvements are required before adjacent development is prepared to proceed, and to facilitate development of nearby and adjoining parcels using the same utility lines for installation of connection s that will serve future development. Completion of these transportation and utility improvements ensures the orderly construction of roadways and utilities that will accommodate the increased demand and population resulting from new development.
As of June 30, 2023, the Transportation and Utility Impact Fee had a fund balance of $1,024,924. Table 1D below shows a summary of the es timated remaining construction costs that are to be paid by the Transportation and Utility Impact Fees, along with funding sources for each incomplete project.
Table 2D below shows the ap proximate timing of deposit related to the funding of incomplete projects.
Available
Fund
Balance1
Projected
Future
Impact Fees
City
Economic
Incentives2
Total
Estimated
Funding
Miscellaneous Transportation and Utility Improvements $19,937,482 $1,024,924 $18,878,071 $34,487 $19,937,482 Totals: $19,937,482 $1,024,924 $18,878,071 $34,487 $19,937,482 1Available Fund Balance is allocated proportionately based on the estimated remaining construction costs and does not represent dedicated funds.
Available Fund Balance will be utilized at the City's discretion to fund incomplete projects. 2Economic Incentive funding is anticipated to be funded by future grants. These amounts will not be funded by impact fees.
TABLE 1D - TRANSPORTATION AND UTILITY IMPACT FEE
SUMMARY OF INCOMPLETE PROJECTS AND ANTICIPATED FUNDING SOURCES Description
of Incomplete
Projects
Estimated
Remaining
Construction
Costs
Funding Sources
Funding
Sources
FY 2022-23
Actuals
FY 2023-24
Estimate
FY 2024-25
Estimate
FY 2025-26
Estimate
FY 2026-27
Estimate
FY 2027-28
Estimate
After
FY 2028-29
Estimate
Total
Estimated
Funding
Available Fund Balance1
$1,024,924 $0 $0 $0 $0 $0 $0 $1,024,924
Projected Future Impact Fees $0 $243,620 $248,493 $253,463 $258,532 $263,703 $17,610,260 $18,878,071 City Economic Incentives $0 $0 $0 $0 $0 $0 $34,487 $34,487 Totals: $1,024,924 $243,620 $248,493 $253,463 $258,532 $263,703 $17,644,748 $19,937,482 1Includes unspent impact fees previously collected and other available funds as of June 30, 2023.
TABLE 2D - TRANSPORTATION AND UTILITY IMPACT FEE
APPROXIMATE TIMING OF DEPOSIT FOR FUNDING OF INCOMPLETE PROJECTS
CITY OF SACRAMENTO
MITIGATION FEE ACT FIVE YEAR REPORT SECTION II
11 Table 3D below shows a summ ary of the revenu e and expenditure pr ojections for the Transportation and Utility Impact Fee, and the estimated shortfall or surplus at completion.
As a result, the City finds that there is a continued need to collect Transportation and Utility Impact Fees from new development within the River District Area to pay for the costs to construct and expand the transportation and utility improvements and facilities to mitigate the impact of new development.
OPEN SPACE FACILITIES IMPACT FEE
New development in the River District Area generates new residents, employees, and patrons that places additional demands on par k and other recreational amenities. The purpose of the Open Space Facilities Impact Fee is to provide funding for the acquisition of
5.7 acres of open space situated alongside the American River. This acquisition serves a dual purpose: it establishes the appropriate buffer between the American River and the new developments, while also augmenting the impacts placed on the parks and recreational amenities for those in the River District Area. Acquisition of the new open space will provide a recreational amenity that will be primaril y used by the River District Area residents.
As of June 30, 2023, the Open Space Facilities Impact Fee had a fund balance of $340,203.
Table 1E below shows a summary of the estimated remaining construction costs that are to be paid by the Open Space Facilities Impact Fees, along with funding sources for each incomplete project.
Revenues
Available Fund Balance as of June 30, 2023 $1,024,924
Projected Future Impact Fees $18,878,071
City Economic Incentives $34,487
Total Future Funding: $18,912,558
Total Projected Revenues: $19,937,482
Remaining Construction Costs
Total Estimated Remaining Construction Costs $19,937,482 Total Remaining Construction Costs: $19,937,482
Estimated Shortfall/Surplus to Completion: $0
TABLE 3D
TRANSPORTATION AND UTILITY IMPACT FEE STATUS SUMMARY
CITY OF SACRAMENTO
MITIGATION FEE ACT FIVE YEAR REPORT SECTION II
12 Table 2E below shows the ap proximate timing of deposit related to the funding of incomplete projects.
Table 3E below shows a summary of the revenue and expenditure projections for the Open Space Facilities Impact Fee, and the estimated shortfall or surplus at completion.
As a result, the City finds that there is a continued need to collect Open Space Facilities Impact Fees from new development within the River District Area to pay for the costs to acquire and expand the open space improvements and facilities to mitigate the impact of new development.
Available
Fund Balance1
Projected
Future
Impact Fees
City
Economic
Incentives2
Total
Estimated
Funding
Open Space Lot 100 $443,580 $22,803 $420,009 $767 $443,580 Open Space Lot 409/410/411 $1,586, 872 $81,576 $1,502,551 $2,745 $1,586,872 Open Space Lot 500 $940,860 $48,367 $890,866 $1,627 $940,860 Open Space Lot 515/516 $3,646,528 $187,457 $3,452,764 $6,308 $3,646,529 Totals: $6,617,841 $340,203 $6,266,191 $11,447 $6,617,841 1Available Fund Balance is allocated proportionately based on t he estimated remaining construction costs and does not represent dedicated funds.
Available Fund Balance will be utilized at the City's discretion to fund incomplete projects. 2Economic Incentive funding is anticipated to be funded by future grants. These amounts will not be funded by impact fees.
TABLE 1E - OPEN SPACE FACILITIES IMPACT FEE
SUMMARY OF INCOMPLETE PROJECTS AND ANTICIPATED FUNDING SOURCES Description
of Incomplete
Projects
Estimated
Remaining
Construction
Cost
Funding Sources
Funding
Sources
FY 2022-23
Actuals
FY 2023-24
Estimate
FY 2024-25
Estimate
FY 2025-26
Estimate
FY 2026-27
Estimate
FY 2027-28
Estimate
After
FY 2028-29
Estimate
Total
Estimated
Funding
Available Fund Balance1
$340,203 $0 $0 $0 $0 $0 $0 $340,203
Projected Future Impact Fees $0 $81,207 $82,831 $84,488 $86,177 $87,901 $5,843,588 $6,266,191 City Economic Incentives $0 $0 $0 $0 $0 $0 $11,447 $11,447 Totals: $340,203 $81,207 $82,831 $84,488 $ 86,177 $87,901 $5,855,035 $6,617,841 1Includes unspent impact fees previously collected and other available funds as of June 30, 2023.
TABLE 2E - OPEN SPACE FACILITIES IMPACT FEE
APPROXIMATE TIMING OF DEPOSIT FOR FUNDING OF INCOMPLETE PROJECTS Revenues
Available Fund Balance as of June 30, 2023 $340,203
Projected Future Impact Fees $6,266,191
City Economic Incentives $11,447
Total Future Funding: $6,277,638
Total Projected Revenues: $6,617,841
Remaining Construction Costs
Total Estimated Remaining Construction Costs $6,617,841 Total Remaining Construction Costs: $6,617,841
Estimated Shortfall/Surplus to Completion: $0
TABLE 3E
OPEN SPACE FACILITIES IMPACT FEE STATUS SUMMARY
CITY OF SACRAMENTO
MITIGATION FEE ACT FIVE YEAR REPORT SECTION II
13 PUBLIC TRANSIT FACILITIES IMPACT FEE
New development in the River District Area generates new residents, employees, and patrons that will impose additional demands on public transit facilities, resulting in the need to construct transit facilities to serve the increased needs of the River District Area. The purpose of the Public Transit Facilities Impact Fee is to contribute towards the funding of construction of two light rail stations in the River District Area, one of which was completed in 2019. Completion of the publ ic transit facilities ensures that adequate public transit facilities and services are available to accommodate the growing population resulting from new development in the River District Area.
As of June 30, 2023, the Publ ic Transit Facilities Impact Fee had a fund balance of $150,322. Table 1F below shows a summary of the estimated remaining construction costs that are to be paid by the Public Transit Facilities Impact Fees, along with funding sources for each incomplete project.
Table 2F below shows the appro ximate timing of deposit related to the funding of incomplete projects.
Available
Fund
Balance1
Projected
Future
Impact Fees
City
Economic
Incentives2
Total
Estimated
Funding
Light Rail Station (Sequoia Pacific Blvd) $2,924,164 $150,322 $2,768,784 $5,058 $2,924,164 Totals: $2,924,164 $150,322 $2,768,784 $5,058 $2,924,164 1Available Fund Balance is allocated proportionately based on the estimated remaining construction costs and does not represent dedicated funds.
Available Fund Balance will be utilized at the City's discretion to fund incomplete projects. 2Economic Incentive funding is anticipated to be funded by fu ture grants. These amounts will not be funded by impact fees.
TABLE 1F - PUBLIC TRANSIT FACILITIES IMPACT FEE (Light Rail Station Facilities)
SUMMARY OF INCOMPLETE PROJECTS AND ANTICIPATED FUNDING SOURCES Description
of Incomplete
Projects
Estimated
Remaining
Construction
Costs
Funding Sources
Funding
Sources
FY 2022-23
Actuals
FY 2023-24
Estimate
FY 2024-25
Estimate
FY 2025-26
Estimate
FY 2026-27
Estimate
FY 2027-28
Estimate
After
FY 2028-29
Estimate
Total
Estimated
Funding
Available Fund Balance1
$150,322 $0 $0 $0 $0 $0 $0 $150,322
Projected Future Impact Fees $0 $51,972 $53,012 $54,072 $55,153 $56,257 $2,498,317 $2,768,784 City Economic Incentives $0 $0 $0 $0 $0 $0 $5,058 $5,058 Totals: $150,322 $51,972 $53,012 $54,072 $55,153 $56,257 $2,503,376 $2,924,164 1Includes unspent impact fees previously collected and other available funds as of June 30, 2023.
TABLE 2F - PUBLIC TRANSIT FACILITIES IMPACT FEE (Light Rail Station Facilities)
APPROXIMATE TIMING OF DEPOSIT FOR FUNDING OF INCOMPLETE PROJECTS
CITY OF SACRAMENTO
MITIGATION FEE ACT FIVE YEAR REPORT SECTION II
14 Table 3F below shows a summary of the revenue and expenditure projections for the Public Transit Facilities Impact Fee, and the estimated shortfall or surplus at completion.
As a result, the City finds that there is a continued need to collect Public Transit Facilities Impact Fees from new development within the River District Area to pay for the costs to construct and expand the public transit facilities to mitigate the impact of new development.
LIBRARY FACILITIES IMPACT FEE
New development in the River District Area will generate additional service population through new residents, necessitating the need for new library facilities. While no library facilities are currently planned for the Rive r District Area, the purpose of the Library Facilities Impact Fee is to contribute funding towards the expansion of existing library facilities or construction of new library facilities needed in the future to serve residents of the River District Area. Expansion of existing library facilities and the construction of new facilities ensures the City library facilities can effectively address the needs of the increased resident population resulting from the new developments in the River District Area.
As of June 30, 2023, the Library Facilities Impact Fee had a fund balance of $27,331. Table 1G below shows a summary of the estimated remaining construction costs that are to be paid by the Library Facilities Impact Fees, along with funding sources for each incomplete project.
Revenues
Available Fund Balance as of June 30, 2023 $150,322
Projected Future Impact Fees $2,768,784
City Economic Incentives $5,058
Total Future Funding: $2,773,842
Total Projected Revenues: $2,924,164
Remaining Construction Costs
Total Estimated Remaining Construction Costs $2,924,164 Total Remaining Construction Costs: $2,924,164
Estimated Shortfall/Surplus to Completion: $0
TABLE 3F
PUBLIC TRANSIT FACILITIES IMPACT FEE STATUS SUMMARY
Available
Fund
Balance1
Projected
Future
Impact Fees
City
Economic
Incentives2
Total
Estimated
Funding
Library Facilities $531,666 $27,331 $503,415 $920 $531,666 Totals: $531,666 $27,331 $503,415 $920 $531,666
1Available Fund Balance is allocated proportionately based on the estimated remaining construction costs and does not represent dedicated funds.
Available Fund Balance will be utilized at the City's discretion to fund incomplete projects. 2Economic Incentive funding is anticipated to be funded by future grants. These amounts will not be funded by impact fees.
TABLE 1G - LIBRARY FACILITIES IMPACT FEE
SUMMARY OF INCOMPLETE PROJECTS AND ANTICIPATED FUNDING SOURCES Description
of Incomplete
Projects
Estimated
Remaining
Construction
Cost
Funding Sources
CITY OF SACRAMENTO
MITIGATION FEE ACT FIVE YEAR REPORT SECTION II
15 Table 2G below shows the app roximate timing of deposit related to the funding of incomplete projects.
Table 3G below shows a summ ary of the revenue and expe nditure projections for the Library Facilities Impact Fee, and the estimated shortfall or surplus at completion.
As a result, the City finds that there is a continued need to collect Library Facilities Impact Fees from new development within the River District Area to pay for the costs to construct and expand the library impr ovements and facilities, to mitigate the impact of new development.
PUBLIC SAFETY FACILITIES IMPACT FEE
New development in the River District Area will generate additional service population through new residents, employees, and patrons that places additional demands for public safety, particularly police and fire services, warranting the need for additional police and fire facilities. The purpose of the Public Safety Facilities Impact Fee is to contribute funding towards the construction and expansion of police and fire facilities that will serve residents of the River District Area. Expansion and constr uction of new police and fire facilities is crucial to ensuring the City police and fire facilities have the capacity to effectively address the needs of the increased resident population resulting from the new development in the River District Area.
Funding
Sources
FY 2022-23
Actuals
FY 2023-24
Estimate
FY 2024-25
Estimate
FY 2025-26
Estimate
FY 2026-27
Estimate
FY 2027-28
Estimate
After
FY 2028-29
Estimate
Total
Estimated
Funding
Available Fund Balance1
$27,331 $0 $0 $0 $0 $0 $0 $27,331
Projected Future Impact Fees $0 $6,497 $6,626 $6,759 $6,894 $7,032 $469,607 $503,415 City Economic Incentives $0 $0 $0 $0 $0 $0 $920 $920
Totals: $27,331 $6,497 $6,626 $6,759 $6,894 $7,032 $470,527 $531,666 1Includes unspent impact fees previously collected and other available funds as of June 30, 2023.
TABLE 2G - LIBRARY FACILITIES IMPACT FEE
APPROXIMATE TIMING OF DEPOSIT FOR FUNDING OF INCOMPLETE PROJECTS Revenues
Available Fund Balance as of June 30, 2023 $27,331
Projected Future Impact Fees $503,415
City Economic Incentives $920
Total Future Funding: $504,335
Total Projected Revenues: $531,666
Remaining Construction Costs
Total Estimated Remaining Construction Costs $531,666
Total Remaining Construction Costs: $531,666
Estimated Shortfall/Surplus to Completion: $0
TABLE 3G
LIBRARY FACILITIES IMPACT FEE STATUS SUMMARY
CITY OF SACRAMENTO
MITIGATION FEE ACT FIVE YEAR REPORT SECTION II
16 As of June 30, 2023, the Publ ic Safety Facilities Impact Fee had a fund balance of $478,298. Table 1H below shows a summary of the estimated remaining construction costs that are to be paid by the Public Safety Facilities Impact Fee, along with funding sources for each incomplete project.
Table 2H below shows the ap proximate timing of deposit related to the funding of incomplete projects.
Table 3H below shows a summary of the revenue and expenditure projections for the Public Safety Facilities Impact Fee, and the estimated shortfall or surplus at completion.
As a result, the City finds that there is a continued need to collect Public Safety Facilities Impact Fee from new development within the Ri ver District Area to pay for the costs to construct and expand the police and fire improvements and facilities to mitigate the impact of new development.
Available
Fund
Balance1
Projected
Future
Impact Fees
City
Economic
Incentives2
Downtown/
Railyards Plan
Area Fees
Total
Estimated
Funding
Police Station $11,297,907 $239,149 $4,404,883 $8,047 $6,645,827 $11,297,907 Fire Station $11,297,907 $239,149 $4,404,883 $8,047 $6,645,827 $11,297,907 Totals: $22,595,813 $478,298 $8,809,766 $16,094 $13,291,655 $22,595,813 1Available Fund Balance is allocated proportionately based on the estimated remaining construction costs and does not represent dedicated funds.
Available Fund Balance will be utilized at the City's discretion to fund incomplete projects. 2Economic Incentive funding is anticipated to be funded by future grants. These amounts will not be funded by impact fees.
TABLE 1H - PUBLIC SAFETY FACILITIES IMPACT FEE
SUMMARY OF INCOMPLETE PROJECTS AND ANTICIPATED FUNDING SOURCES Description
of Incomplete
Projects
Estimated
Remaining
Construction
Costs
Funding Sources
Funding
Sources
FY 2022-23
Actuals
FY 2023-24
Estimate
FY 2024-25
Estimate
FY 2025-26
Estimate
FY 2026-27
Estimate
FY 2027-28
Estimate
After
FY 2028-29
Estimate
Total
Estimated
Funding
Available Fund Balance1
$478,298 $0 $0 $0 $0 $0 $0 $478,298
Projected Future Impact Fees $0 $113,690 $115,963 $118,283 $120,648 $123,061 $8,218,122 $8,809,766 City Economic Incentives $0 $0 $0 $0 $0 $0 $16,094 $16,094 Downtown/Railyards Plan Area Fees $0 $0 $0 $0 $0 $0 $13,291,655 $13,291,655 Totals: $478,298 $113,690 $115,963 $118,283 $120,648 $123,061 $21,525,870 $22,595,813 1Includes unspent impact fees previously collected and other available funds as of June 30, 2023.
TABLE 2H - PUBLIC SAFETY FACILITIES IMPACT FEE
APPROXIMATE TIMING OF DEPOSIT FOR FUNDING OF INCOMPLETE PROJECTS Revenues
Available Fund Balance as of June 30, 2023 $478,298
Projected Future Impact Fees $8,809,766
City Economic Incentives $16,094
Downtown/Railyards Plan Area Fees $13,291,655
Total Future Funding: $22,117,515
Total Projected Revenues: $22,595,813
Remaining Construction Costs
Total Estimated Remaining Construction Costs $22,595,813 Total Remaining Construction Costs: $22,595,813
Estimated Shortfall/Surplus to Completion: $0
TABLE 3H
PUBLIC SAFETY FACILITIES IMPACT FEE STATUS SUMMARY