File ID: 2024-00266 1/16/2024 Consent Item 6.
Budgetary Adjustments and Contract: Sacramento EV Blueprint - Vehicle Chargers Project - Phase 1 (C15210000)
File ID: 2024-00266
Location: 4799 Stockton Blvd., Represented by Councilmember Guerra and Mayor Steinberg; 5600 South Land Park Dr., Represented by Councilmember Jennings and 2450 Meadowview Represented by Councilmember Vang
Recommendation: Adopt a Resolution: 1) authorizing the City Manager or the City Manager’s designee to amend the revenue and expense budgets to add $108,000 (Fund 3702, CIP Reimbursable) to the Sacramento Electric Vehicle (EV) Blueprint Vehicle Chargers Phase 1 (C15210000) to reflect rebates from the Sacramento Municipal Utilities District (SMUD); 2) awarding the construction contract to North Star Construction & Engineering, Inc. in an amount not to exceed $868,000 for the Sacramento EV Blueprint - Vehicle Chargers- Phase 1 (C15210000); and 3) authorizing the City Manager or the City Manager’s designee to execute the contract specified above.
Contact: Ezra Roati, Senior Architect, (916) 808-5877, [email protected]; David Avila, Supervising Architect, (916) 808-7501, [email protected]; James Christensen, Facilities Manager, (916) 808-5863, [email protected], Department of Public Works Presenter: None.
Attachments:
1-Description/Analysis
2-Resolution
3-Contract- North Star Construction & Engineering, Inc.
Description/Analysis
Issue Detail: In 2021, the City of Sacramento was awarded a California Energy Commission (CEC) Sacramento EV Blueprint Grant. One of the major tasks is to install publicly facing EV infrastructure.
The goal is to install at least 34 Level 2 networked EV chargers (for a minimum of 66 EV connectors) across 13 libraries and community centers located within the City, with two-thirds of connectors located within disadvantaged communities to support EV adoption where there may not be adequate charging infrastructure. Implementation of this grant will assist the City with EV charger installations,
File ID: 2024-00266 1/16/2024 Consent Item 6.
facilitating the City’s alignment with Statewide EV goals. This project is funded with support from EV support programs through the Sacramento Metropolitan Air Quality Management District (SMAQMD) and the Sacramento Municipal Utilities District (SMUD).
Phase 1 of the project will install 12 EV chargers, with a total of 24 EV connectors, at three locations, including the Colonial Heights Library, Belle Cooledge Library, and the Pannell Community Center.
Each location will have 4 EV chargers and 8 connectors.
Sacramento is uniquely poised to implement and test this program to increase EV charger installations throughout the City, with the goal of increasing electric vehicle adoption and use in the greater Sacramento area. The region, community, and private sector in Sacramento are supportive and successfully collaborating to advance EV deployment in Sacramento, with the goal of installing EV chargers that provide a model for future projects throughout the region and state. Success in these areas promises to deliver environmental and economic benefits.
Policy Considerations: The 2035 General Plan, Policy M 1.5.5 Support Zero- and Low-Emission Vehicle Adoption states: “The City shall continue to collaborate with its State and regional partners to support rapid adoption of zero-emissions and low-emission vehicles …”. Implementation of this grant is also consistent with Sacramento’s Electric Vehicle Strategy.
The recommendation in this report is in accordance with City Code Section 3.60, which requires City Council approval of contracts of $250,000 or more.
Economic Impacts: The recommended contract is expected to create 6.42 jobs (4.08 direct jobs and 2.34 jobs through indirect and induced activities) and create $847,621 in total economic output ($543,347 of direct output and another $304,274 of output in indirect and induced activities).
The indicated economic impacts are estimates calculated using a calculation tool developed by the Center for Strategic Economic Research (CSER). CSER utilized the IMPLAN input-output model (2009 coefficients) to quantify the economic impacts of a hypothetical $1 million of spending in various construction categories within the City of Sacramento in an average one-year period. Actual impacts could differ significantly from the estimates and neither the City of Sacramento nor CSER shall be held responsible for consequences resulting from such differences.
Environmental Considerations:
California Environmental Quality Act (CEQA): The action is exempt from review under the California Environmental Quality Act (CEQA) pursuant to CEQA Guidelines, Section 15301.
The action involves the operation, repair, maintenance, permitting, leasing, licensing, or minor alteration of existing public or private structures, facilities, or mechanical equipment, involving negligible or no expansion of use beyond that existing at the time of the lead agency's determination. The exemption covers interior or exterior alterations involving such things as
File ID: 2024-00266 1/16/2024 Consent Item 6.
interior partitions, plumbing, and electrical conveyances; and similar facilities; restoration or rehabilitation of deteriorated or damaged structures, facilities, or mechanical equipment to meet current standards of public health and safety, unless it is determined that the damage was substantial and resulted from an environmental hazard such as earthquake, landslide, or flood. The project qualifies for a Categorical Exemption under Article 19 of CEQA Guidelines Section 15301, existing facilities. No environmental review is necessary, and a Notice of Exemption (NOE) is on-file for all three sites as part of this phase one.
Sustainability: In 2016, the transportation sector accounted for 57% of community-wide greenhouse gas emissions, the largest single sector in the community. Electrification of the transportation sector leads to reductions in petroleum use, both reducing greenhouse gas emissions and improving local air quality.
Commission/Committee Action: Not applicable.
Rationale for Recommendation: Despite momentum towards goals established in the City of Sacramento’s EV Strategy, continued investment is critical to achieve transformative progress in EV equity, access, and infrastructure. Public investment is key to addressing gaps in geographic and programmatic implementation and advance equitable investments. Given limited City funding, advancing opportunities to areas that lack adequate EV infrastructure relies on partnering with granting agencies and other local agencies that support EV adoption, including SMAQMD and SMUD.
On December 23, 2020, the Department of Public Works issued a Request for Qualifications for On- Call General Contracting Services (Q20014541004). The purpose of the RFQ was to develop a list of qualified on-call general contractors that would be solicited to assist staff by delivering larger projects utilizing a variety of delivery methods. On May 18, 2021, the City Council passed Motion No. 2021- 0125 approving the creation of a pre-qualified list of On-Call General Contractors. Public Works staff utilized the pre-qualified list of On-Call General Contractors to solicit proposals for the Sacramento EV Blueprint - Vehicle Chargers- Phase 1. Three General Contractors from the list were contacted to provide proposals to complete the scope of work. Only one contractor submitted a proposal. Staff has reviewed the proposal and supports awarding the construction contract for the Sacramento EV Blueprint - Vehicle Infrastructure Phase 1 Project to North Star Construction & Engineering, Inc. for an amount not to exceed $868,000.
Financial Considerations: The total cost to install chargers at these three sites is estimated to cost $868,000. This will be paid for using CEC grant funds, SMAQMD funds, and SMUD rebates. With the grant application, SMUD committed $99,000 to this effort. Since that time, SMUD has agreed to provide rebates of $4,700 per EV handle, equal to $108,000 for Phase 1. With the addition of $108,000 (Other Reimbursable Fund, Fund 3702), there is sufficient funding available in the Sacramento EV Blueprint Infrastructure Project (C15210000) to execute the construction contract
File ID: 2024-00266 1/16/2024 Consent Item 6.
with North Star Construction and Engineering, Inc. in the not-to-exceed amount of $868,000.
Local Business Enterprise (LBE): North Star Construction and Engineering is not an LBE but has partnered with Edges Electrical Group to meet the meet the minimum LBE participation requirement.
Edges Electrical Group will be providing electrical equipment. ..End
RESOLUTION NO. 2024-XXXX
Adopted by the Sacramento City Council
Sacramento EV Blueprint- Vehicle Chargers Project- Phase 1 (C15210000)
BACKGROUND
A. In 2021, the City of Sacramento was awarded a California Energy Commission (CEC) Sacramento EV Blueprint Grant. One of the major tasks is to install publicly-facing EV infrastructure installations to support EV adoption.
B. Phase 1 improvements include 24 new EV charger handles and the associated infrastructure at three locations: the Colonial Heights Library, Belle Cooledge Library, and Pannell Community Center.
C. Various grant funding and rebates have been secured to fund this project such as a California Energy Commission (CEC) grant, Sacramento Metro Air Quality Management District (SMAQMD) programs, and Sacramento Metro Utility District (SMUD) funding and rebates, and City funding.
D. With the grant application, SMUD committed $99,000 to this effort. Since that time, SMUD has agreed to provide rebates of $4,700 per EV handle, equal to $108,000 for this phase.
E. On May 18, 2021, the City Council passed Motion No. 2021-0125 approving the creation of a pre-qualified list of On-Call General Contractors. Public Works staff utilized the pre-qualified list of On-Call General Contractors to solicit proposals for the Sacramento EV Blueprint - Vehicle Chargers- Phase 1.
F. Staff analyzed the proposal submitted by North Star Construction & Engineering to complete the work and recommends awarding a contract.
BASED ON THE FACTS SET FORTH IN THE BACKGROUND, THE CITY COUNCIL RESOLVES AS FOLLOWS:
Section 1: The City Manager or the City Manager’s designee is authorized to increase revenue and expense budgets by $108,000 (Fund 3702, CIP Reimbursable) in the Sacramento EV Blueprint Phase 2 Project (C15210000) to reflect rebates from SMUD.
Section 2: The City Manager or the City Manager’s designee is authorized to execute the contract with North Star Construction & Engineering in an amount not to exceed $868,000.
Form approved by City Attorney 1-11-17 1
AGREEMENT
(Construction Contract Over $25,000)
THIS AGREEMENT, dated for identification , 2024, is made and entered into between the CITY OF SACRAMENTO, a municipal corporation (“City”), and NORTH STAR CONSTRUCTION & ENGINEERING, INC., 1282 Stabler Lane #630- 109, Yuba City, CA 95993 (“Contractor”) in the amount not to exceed EIGHT HUNDRED SIXTY-EIGHT THOUSAND DOLLARS AND ZERO CENTS ($868,000.00).
The City and Contractor hereby mutually agree as follows:
1 . CONTRACT DOCUMENTS
T
he Contract Documents, sometimes also referred to as the “Contract,” consist of the following items, which are hereby incorporated by reference as if set forth in full in this Agreement:
N
otice to Contractors
Proposal Form submitted by the Contractor
Instructions to Bidders
Subcontractor and Local Business Enterprise Participation Form Drug-Free Workplace Policy and Affidavit
Construction and Demolition (C&D) Debris Recycling Requirements Workers’ Compensation Insurance Certification
Federal or State funding requirements (if applicable)
Local Business Enterprise (LBE) Requirements
Requirements of the Non-Discrimination in Employee Benefits Code Ban-The-Box Requirements
Addenda, if any
This Agreement
Standard Specifications
Special Provisions
Plans and Technical Specifications
The drawings and other data and all developments thereof prepared by City pursuant to the Contract
Any modifications of any of the foregoing made or approved by City, including but not limited to duly authorized change orders
U
nless specifically noted otherwise, references to t he “Standard Specifications” shall mean and refer to the Standard Specifications for Public Construction of the City of Sacramento approved by the Sacramento City Council on November 10, 2020 (Resolution No. 2020-0354), and any subsequent amendments thereto approved by the Sacramento City Council or the Sacramento City Manager. Work called for in any one Contract Document and not mentioned in another is to be performed and executed as if mentioned in all Contract Documents. The table of contents, titles and headings contained in the Contract Documents are provided solely to facilitate reference to various provisions of the Contract Documents and in no way affect or limit the interpretation of the provisions to which they refer.
Form approved by City Attorney 1-11-17 2
2. DEFINITIONS
Unless otherwise specifically provided herein, all words and phrases defined in the Standard Specifications shall have the same meaning and intent in this Agreement.
3. AGREEMENT CONTROLS
In the event of a conflict between any of the terms and conditions set forth in this Agreement and the terms and conditions set forth in other Contract Documents, the terms and conditions set forth in this Agreement shall prevail, except that the provisions of any duly authorized change order shall prevail over any conflicting provisions of this Agreement.
4. SCOPE OF CONTRACT
Contractor agrees to furnish all tools, equipment, apparatus, facilities, labor, material and transportation necessary to perform and complete in a good and workmanlike manner to the satisfaction of City, all the Work called for in the Contract Documents entitled:
SACRAMENTO EV BLUEPRINT-VEHICLE CHARGER PROJECT-PHASE 1 (PN: C15210050)
Including the Work called for in the following alternative bid items described in the Proposal Form:
NONE
Contractor agrees to perform such Work in the manner designated in and in strict conformity with the Contract Documents.
5. CONTRACT AMOUNT AND PAYMENTS
City agrees to pay and Contractor agrees to accept, as complete payment for the above Work, in accordance with the schedule and procedures set forth in the Contract Documents and subject to deductions, withholdings and additions as specified in the Contract Documents , a total sum that shall not exceed the total bid amount set forth in Contractor’s Proposal Form.
In addition, subject to deductions, withholdings and additions as specified in the Contract Documents, payment for individual items of the Work shall be computed as follows:
A. For items of the Work for which a lump sum price is specified in Contractor’s Proposal Form, Contractor shall be paid the lump sum price(s) specified in Contractor’s Proposal Form; and
B. For items of the Work for which a unit price is specified in Contractor’s Proposal Form, Contractor shall be paid the sum computed at such unit price , or computed at a different price if such different price is determined by City in accordance with the Standard Specifications, based on the actual amount of each such item performed and/or furnished and incorporated in the Work ; provided that in no event shall the Form approved by City Attorney 1-11-17 3
total sum for a unit price item exceed the total bid amount set forth for such item in the Contractor’s Proposal Form, unless authorized by Change Order.
6. PROGRESS PAYMENTS
Subject to the terms and conditions of the Contract, City shall cause payments to be made upon demand of Contractor as follows:
A. On or about the first of the month, the Engineer shall present to the Contractor a statement showing the amount of labor and materials incorporated in the Work through the twentieth (20) calendar day of the preceding month. After both Contractor and Engineer approve the statement in writing, and the City’s labor compliance officer provides written approval, the City shall issue a certificate for ninety-five (95) percent of the amount it shall find to be due, subject to any deductions or withholdings authorized or required under the Contract or any applicable Laws or Regulations.
B. No inaccuracy or error in said monthly estimates shall operate to release Contractor from damages arising from such Work or from enforcement of each and every provision of the Contract Documents, and City shall have the right subsequently to correct any error made in any estimate for payment.
C. Contractor shall not be paid for any defective or improper Work.
D. The remaining five (5) percent of the value of the Work performed under the Contract, if unencumbered and subject to any deductions or withholdings authorized or required under the Contract or any applicable Laws or Regulations, shall be released not later than sixty (60) days after completion and final acceptance of the Work by City. Acceptance by Contractor of the final payment shall constitute a waiver of all claims against the City arising under the Contract Documents, except for disputed claims in stated amounts that the Contractor specifically reserves in writing , but only to the extent that the Contractor has complied with all procedures and requirements applicable to the presentation and processing of such claim(s) under the Contract Documents. Contractor shall be entitled to substitute securities for retention or to direct that payments of retention be made into escrow, as provided in Public Contract Code Section 22300, upon execution of the City’s Escrow Agreement for Security Deposits in Lieu of Retention.
E. The parties agree that, for purposes of the timely progress payment requirements specified in Public Contract Code Section 20104.50, the date that the City receives a statement jointly approved by the Contractor and the Engineer as provided above shall be deemed to constitute the date that City receives an undisputed and properly submitted payment request from the Contractor. Progress payments not made within 30 days after this date may be subject to payment of interest as provided in Public Contract Code Section 20104.50.
Form approved by City Attorney 1-11-17 4
F. This Contract is subject to compliance monitoring and enforcement by the California Department of Industrial Relations, as specified in California Labor Code section 1771.4.
7. RETENTION OF SUMS CHARGED AGAINST CONTRACTOR
When, under the provisions of this Contract or any applicable Laws or Regulations, City is authorized or required to withhold, deduct or charge any sum of money against Contractor, City may deduct and retain the amount of such charge from the amount of the next succeeding progress estimate (s), or from any other moneys due or that may become due Contractor from City. If, on completion or termination of the Contract, sums due Contractor are insufficient to pay City's charges, City shall have the right to recover the balance from Contractor or its Sureties.
8. COMMENCEMENT AND PROSECUTION OF WORK
Contractor shall commence the Work not later than fifteen (15) working days after the date of the written Notice to Proceed from City to Contractor and shall diligently prosecute the Work to final completion. The phase “commence the Work” means to engage in a continuous program on-site including, but not limited to, site clearance, grading, dredging, land filling and the fabrications, erection, or installation of the Work. The Notice to Proceed shall be issued within fifteen (15) calendar days following execution of the Agreement by the City and the filing by Contractor of the required Bonds and proof of insurance , provided that the Engineer may delay issuance of the Notice to Proceed if the Engineer determines in the Engineer’s sole discretion that conditions on the site of the Work are unsuitable for commencement of the Work . After the Notice to Proceed is issued, the continuous prosecution of Work by Contractor shall be subject only to Excusable Delays as defined in this Agreement.
9. TIME OF COMPLETION
The entire Work shall be brought to completion in the manner provided for in the Contract Documents on or before ONE-HUNDRED TWENTY (120) CALENDAR days from the date of the Notice to Proceed (hereinafter called the “ Completion Date”) unless extensions of time are granted in accordance with the Contract Documents.
Failure to complete the entire Work by the Completion Date and in the manner provided for in the Contract Documents shall subject Contractor to liquidated damages as provided in this Agreement. Time is and shall be of the essence in the performance of the Contract and the Work.
10. PAYMENTS DO NOT IMPLY ACCEPTANCE OF WORK
The payment of any progress payment, or the acceptance thereof by Contractor, shall not constitute acceptance of the Work or any portion thereof and shall in no way reduce the liability of Contractor to replace unsatisfactory work or material, whether or not the Form approved by City Attorney 1-11-17 5
unsatisfactory character of such work or material was apparent or detected at the time such payment was made.
11. ACCEPTANCE NOT RELEASE
Contractor shall correct immediately any defective or imperfect work or materials that may be discovered before final acceptance of the entire Work , whether or not such defect or imperfection was previously noticed or identified by the City. The inspection of the Work, or any part thereof, shall not relieve Contractor of any of its obligations to perform satisfactory work as herein specified.
Failure or neglect on the part of City or any of its officers, employees or authorized agents to discover, identify, condemn or reject defective or imperfect work or materials shall not be construed to imply an acceptance of such work or materials , if such defect or imperfection becomes evident at any time prior to final acceptance of the entire Work, nor shall such failure or neglect be construed as barring City from enforcing Contractor’s warranty(ies) or otherwise recovering damages or such a sum of money as may be required to repair or rebuild the defective or imperfect work or materials whenever City may discover the same , subject only to any statutes of limitation that may apply to any such claim.
12. CITY'S RIGHT TO TAKE POSSESSION OF THE WORK IN WHOLE OR IN PART
The City shall have the right at any time to enter upon the Work and perform work not covered by this Contract, or to occupy and use a portion of the Work, prior to the date of the final acceptance of the Work as a whole, without in any way relieving Contr actor of any obligations under this Contract.
13. NO WAIVER OF REMEDIES
Neither the inspection by City, its officers, employees or agents, nor any certificate or other approval for the payment of money, nor any payment for, nor acceptance of the whole or any part of the Work by City, nor any extensions of time, nor any position taken by City , its officers, employees or its agents shall operate as a waiver of any provision of the Contract Documents nor of any power herein reserved to City or any right to damages herein provided, nor shall any waiver of any breach of this Agreement be held to be a waiver of any other or subsequent breach. All remedies provided in the Contract Documents shall be taken and construed as cumulative; in addition to each and every other remedy herein provided, the City shall have any and all equitable and legal remedies that it would in any case have.
14. WARRANTY
Except as otherwise expressly provided in the Contract Documents, and excepting only items of routine maintenance, ordinary wear and tear and unusual abuse or neglect by City , Contractor warrants and guarantees all Work executed and all supplies, materials and devices of whatsoever nature incorporated in or attached to the Work, or otherwise provided as a part of the Work pursuant to the Contract, to be absolutely free of all defects of workmanship and materials for a period of one year after final acceptance of the entire Work by the C ity.
Form approved by City Attorney 1-11-17 6
Contractor shall repair or replace all work or material, together with any other work or material that may be displaced or damaged in so doing, that may prove defective in workmanship or material within this one year warranty period without expense or charge of any nature whatsoever to City.
In the event that Contractor shall fail to comply with the conditions of the foregoing warranty within ten (10) days after being notified of the defect in writing, City shall have the right, but shall not be obligated, to repair, or obtain the repair of, t he defect and Contractor shall pay to City on demand all costs and expense of such repair. Notwithstanding anything herein to the contrary, in the event that any defect in workmanship or material covered by the foregoing warranty results in a condition that constitutes an immediate hazard to public health or safety, or any property interest, or any person, City shall have the right to immediately repair, or cause to be repaired, such defect, and Contractor shall pay to City on demand all costs and expense of such repair. The foregoing statement relating to hazards to health, safety or property shall be deemed to include both temporary and permanent repairs that may be required as determined in the sole discretion and judgment of City.
In addition to the above, the Contractor shall make a written assignment of all manufacturer’s and other product warranties to the City, prior to completion and final acceptance of the Work by City.
The Contractor’s Performance Bond shall secure the performance of the Contractor’s obligations under this Section 14 , and the Contractor and its Surety shall be jointly and severally liable for these obligations.
15. LIQUIDATED DAMAGES IF WORK NOT COMPLETED ON TIME
A. The actual fact of the occurrence of damages and the actual amount of the damages that City would suffer if the entire Work, and/or any specified portion ther eof, were not completed within the time(s) specified herein are dependent upon many circumstances and conditions that could prevail in various combinations, and for this reason, it is impracticable and extremely difficult to fix the actual damages. Damages that City would suffer in the event of such delay include: loss of the use of the project; expenses of prolonged assignment to the project of an architectural and /or engineering staff; prolonged costs of administration, inspection, and supervision; increased operational expenses and/or impaired operation of other facilities dependent upon completion of the project; and the loss and inconvenience suffered by the public within the City of Sacramento by reason of the delay in the completion of the project or portion thereof. Accordingly, the parties agree, and by execution of this Agreement, Contractor acknowledges that it understands and agrees, that the amount(s) set forth herein as liquidated damages reflect the parties’ best efforts at the time of entering into the Contract to estimate the damages that may be incurred by City and the public due to the Contractor’s delay in completion of the Work and/or any specified portion thereof, and shall be presumed to be the amount of damages sustained by the failure of Contractor to complete the entire Work and/or any specified portion thereof within the time(s) specified herein.
Form approved by City Attorney 1-11-17 7
B. Contractor shall pay liquidated damages to City for failure to complete the entire Work by the Completion Date (as extended in accordance with the Contract Documents, if applicable) in the amount of 1000 A DAY for each calendar day after the Completion Date (as extended in accordance with the Contract Documents, if applicable), continuing to the time at which the entire Work is completed. Such amount is the actual cash value agreed upon by the City and Contractor as the loss to City and the public resulting from Contractor's default.
The parties agree, and by execution of this Agreement, Contractor acknowledges that it understands and agrees, that the foregoing provisions provide for the imposition of liquidated damages from the Completion Date (as extended in accordance with the Contract Documents, if applicable) until the date of completion of the entire Work as determined by the Engineer in accordance with Section 8 -4 of the Standard Specifications, whether or not the Work or any portion thereof is claimed or determined to be substantially complete prior to such date of completion.
C. In the event Contractor shall become liable for liquidated damages, City, in addition to all other remedies provided by law, shall have the right to withhold any and all payments that otherwise would be or become due Contractor until the liability of Contractor under this section is finally determined. City shall have the right to use and apply such payments, in whole or in part, to reimburse City for all liquidated damages due or to become due to City. Any remaining balance of such payments shall be paid to Contractor only after discharge in full of all liability incurred by Contractor under this section or otherwise under any provision of the Contract Documents or any applicable Law or Regulation . If the sum so retained by City is not sufficient to discharge all such liabilities of Contractor, Contractor shall continue to remain liable to City until all such liabilities are satisfied in full. No failure by City to withhold any payment as specified above shall in any manner be construed to constitute a release of any such liabilities nor a waiver of the City’s right to withhold payment for such liabilities.
16. INDEMNITY AND HOLD HARMLESS
A. Contractor shall defend, hold harmless and indemnify the City, its officers, employees, and agents, and each and every one of them, from and against any and all actions, damages, costs, liabilities, claims, demands, losses, judgments, penalties, costs and expenses of every type and description, whether arising on or off the site of the Work, including, but not limited to, any fees and/or costs reasonably incurred by City’s staff attorneys or outside attorneys and any fees and expenses incurred in enforcing this provision (hereafter collectively referred to as “Liabilities”), including but not limited to Liabilities arising from personal injury or death, damage to personal, real or intellectual property or the environment, contractual or other economic damages, or regulatory penalties, arising out of or in any way connected with performance of or failure to perform the Work by the Contractor, any subcontractor or agent, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable, whether or not Form approved by City Attorney 1-11-17 8
(i) such Liabilities are caused in part by a party indemnified hereunder, or (ii) such Liabilities are litigated, settled or reduced to judgment ; provided that the foregoing indemnity does not apply to liability for damages for death or bodily injury to persons, injury to property, or other loss, damage or expense to the extent arising from (i) the sole negligence or willful misconduct of, or defe cts in design furnished by, City, its agents, servants, or independent contractors who are directly responsible to City, or (ii) the active negligence of City.
B. The existence or acceptance by City of any of the insurance policies or coverages described in this Agreement shall not affect or limit any of City’s rights under this Section 16, nor shall the limits of such insurance limit the liability of Contractor hereunder. The provisions of this Section 16 shall survive any expiration or termination of the Contract.
17. CONTRACTOR SHALL ASSUME RISKS
Until the completion and final acceptance by City of all Work under this Contract, the Work shall be under Contractor's responsible care and charge, and Contractor, at no cost to City, shall rebuild, repair, restore and make good all injuries, damages, re -erections, and repairs occasioned or rendered necessary by accidental causes of any nature, to all or any portions of the Work.
18. GENERAL LIABILITY OF CONTRACTOR
Except as otherwise herein expressly stipulated, Contractor shall perform all the Work and furnish all the labor, materials, tools, equipment, apparatus, facilities, transportation, power and light, and appliances, necessary or proper for performing and completing the Work herein required in the manner and within the time herein specified. The mention of any specific duty or liability of Contractor shall not be construed as a limitat ion or restriction of any general liability or duty of Contractor , and any reference to any specific duty or liability shall be construed to be solely for the purpose of explanation.
19. INSURANCE
During the entire term of the Contract, Contractor shall maintain the insurance coverage described in this Section 19.
Full compensation for all premiums that Contractor is required to pay for the insurance coverage described herein shall be included in the compensation specified for the Work performed by Contractor under this Contract. No additional compensation will be provided for Contractor’s insurance premiums. Any available insurance proceeds in excess of the specified minimum limits and coverages shall be available to the City.
It is understood and agreed by the Contractor that its liability to the City shall not in any way be limited to or affected by the amount of insurance coverage required or carried by the Contractor in connection with this Contract.
Form approved by City Attorney 1-11-17 9
A. Minimum Scope & Limits of Insurance Coverage
(1) Commercial General Liability Insurance providing coverage at least as broad as ISO CGL Form 00 01 on an occurrence basis for bodily injury, including death, of one or more persons, property damage, and personal injury, arising out of activities performed by or on behalf of Contractor and its subcontractors, products and completed operations of Contractor and its subcontractors, and premises owned, leased, or used by Contractor and its subcontractors, with limits of not less than one million dollars ($1,000,000) per occurrence. The policy shall provide contractual liability and products and completed operations coverage for the term of the policy.
(2) Au
tomobile Liability Insurance providing coverage at least as broad as ISO Form CA 00 01 for bodily injury, including death, of one or more persons, property damage, and personal injury, with limits of not less than one million dollars ($1,000,000) per accident. The policy shall provide coverage for owned, non- owned, and/or hired autos as appropriate to the operations of the Contractor.
No automobile liability insurance shall be required if Contractor completes the following certification:
“I certify that a motor vehicle will not be used in the performance of any work or services under this agreement.” ________ (Contractor initials)
(3) Excess Insurance: The minimum limits of insurance required above may be satisfied by a combination of primary and umbrella or excess insurance coverage; provided that any umbrella or excess insurance shall contain, or be endorsed to contain, a provision that it shall appl y on a primary basis for the benefit of the CITY, and any insurance or self-insurance maintained by CITY, its officials, employees, or volunteers shall be in excess of such umbrella or excess coverage and shall not contribute with it.
(4) Workers’ Compensation Insurance with statutory limits, and Employers’ Liability Insurance with limits of not less than one million dollars ($1,000,000). The Workers’ Compensation policy shall include a waiver of subrogation in favor of the City.
No Workers’ Compensation insurance shall be required if Contractor completes the following certification:
Form approved by City Attorney 1-11-17 10
“I certify that my business has no employees, and that I do not employ anyone. I am exempt from the legal requirements to provide Workers' Compensation insurance.” _________
(Contractor initials)
B. Additional Insured Coverage
(1) Commercial General Liability Insurance: The City, its officials, employees, and volunteers shall be covered by policy terms or endorsement as additional insureds as respects general liability arising out of: activities performed by or on behalf of Contractor and its subcontractors; products and completed operations of Contractor and its subcontractors; and premises owned, leased, or used by Contractor and its subcontractors.
(2) Automobile Liability Insurance: The City, its officials, employees, and volunteers shall be covered by policy terms or endorsement as additional insureds as respects auto liability.
C. Other Insurance Provisions
The policies are to contain, or be endorsed to contain, the following provisions:
(1) Contractor’s insurance coverage, including excess insurance, shall be primary insurance as respects City, its officials, employees, and volunteers.
Any insurance or self-insurance maintained by City, its officials, employees, or volunteers shall be in excess of Contractor’s insurance and shall not contribute with it.
(2) Any failure to comply with reporting provisions of the policies shall not affect coverage provided to City, its officials, employees, or volunteers.
(3) Coverage shall state that Contractor’s insurance shall apply separately to each insured against whom claim is made or suit is brought, except with respect to the limits of the insurer’s liability.
(4) City will be provided with thirty (30) days written notice of cancellation or material change in the policy language or terms.
D. Acceptability of Insurance
Insurance shall be placed with insurers with a Bests’ rating of not less than A:VI.
Self-insured retentions, policy terms or other variations that do not comply with the requirements of this Section 3 must be declared to and approved by the City in writing prior to execution of this Contract.
Form approved by City Attorney 1-11-17 11
E. Verification of Coverage
(1) Contractor shall furnish City with certificates and required endorsements evidencing the insurance required. Copies of policies shall be delivered to the City on demand. Certificates of insurance shall be signed by an authorized representative of the insurance carrier.
(2) For all insurance policy renewals during the term of this Contract, Contractor shall send insurance certificates reflecting the policy renewals directly to:
City of Sacramento
c/o EXIGIS LLC
P.O. Box 947
Murrieta, CA 92564
Insurance certificates also may be faxed to (888) 355-3599, or e-mailed to:
[email protected]
(3) The City may withdraw its offer of contract or cancel this Contract if the certificates of insurance and endorsements required have not been provided prior to execution of this Contract. The City may withhold payments to Contractor or cancel the Contract if the insurance is canceled or Contractor otherwise ceases to be insured as required herein.
F. Subcontractors
Contractor shall require and verify that all subcontractors maintain insurance coverage that meets the minimum scope and limits of insurance coverage specified in subsection A, above.
20. FAILURE TO MAINTAIN BONDS OR INSURANCE
If, at any time during the performance of this Contract, Contractor fails to maintain any item of the bonds and/or insurance required under the Contract in full force and effect, Contractor shall immediately suspend all work under the Contract and notify C ity in writing of such failure. After such notice is provided, or if City discovers such failure and notifies Contractor, the City thereafter may withhold all Contract payments due or that become due until notice is received by City that such bonds and/or insurance have been restored in full force and effect and that the premiums therefor have been paid for a period satisfactory to the Division of Risk Management. Contractor shall not resume work until notified by City to do so , and the City shall have no responsibility or liability for any costs incurred by Contractor as a result of such suspension of Work.
Form approved by City Attorney 1-11-17 12
In addition to the foregoing, any failure to maintain any item of the required bonds and/or insurance at any time during the performance of this Contract will be sufficient cause for termination of the Contract by City.
The Contractor shall be solely responsible for, and shall defend, indemnify and hold harmless the City, its officers, employees and agents against and from, any and all damages, claims, losses, actions, costs or other expenses of any kind incurred by any party as a direct or indirect result of any suspension of Work or termination of the Contract under the provisions of this Section.
21. EXCUSABLE DELAYS
For the purpose of these Contract Documents, the term "Excusable Delay" shall mean, and is limited to, delay caused directly by : acts of God; acts of a public enemy; fires; inclement weather as determined by the Engineer; riots; insurrections; epidemics; quarantine restrictions; strikes; lockouts; sitdowns; acts of a governmental agency; priorities or privileges established for the manufacture, assemble, or allotment of materials necessary in the Work by order, decree or otherwise of the United States or by any department, bureau, commission, committee, agent, or administrator of any legally constituted public authority; changes in the Work ordered by City insofar as they necessarily require additional time in which to complete the Work; the prevention of Contractor from commencing or prosecuting the Work because of the acts of others, excepting Contractor's subcontractors or suppliers; or the prevention of Contractor from commencing or prosecuting the Work because of a Citywide failure of public utility service.
The term "Excusable Delay" shall specifically not include: (i) any delay that could have been avoided by the exercise of care, prudence, foresight and diligence on the part of Contractor; (ii) any delay in the prosecution of any part of the Work that does not constitute a Controlling Operation, whether or not such delay is unavoidable; (iii) any reasonable delay resulting from time required by City for review of any Contractor submittals and for the making of surveys, measurements and inspection; and, ( iv) any delay arising from an interruption in the prosecution of the Work on account of reasonable interference by other Contractors employed by City that does not necessarily prevent the completion of the entire Work within the time specified. Excusable Delays, if any, shall operate only to extend the Completion Date (not in excess of the period of such delay as dete rmined by City) and shall not under any circumstances increase the amount City is required to pay Contractor except as otherwise provided in these Contract Documents.
22. CONTRACTOR TO SERVE NOTICE OF DELAYS
Whenever Contractor foresees any delay in the prosecution of the Work, and in any event as soon as possible (not to exceed a period of ten (10) calendar days) after the initial occurrence of any delay that Contractor regards as or may later claim to be an Excusable Delay, the Contractor shall notify the Engineer in writing of such delay and its cause, in order that the Engineer: (i) may take immediate steps to prevent if possible the occurrence or continuance of the delay ; or (ii) if this cannot be done, may determine whether the delay is to be considered excusable, how long it continues, and to what extent the prosecution and Form approved by City Attorney 1-11-17 13
completion of the Work are delayed thereby. Said written notice shall constitute an application for an extension of time only if the notice requests such an extension and sets forth the Contractor's estimate of the additional time required together with a full description of the cause of the delay relied upon.
After the completion of any part or whole of the Work, the Engineer, in estimating the amount due Contractor, will assume that any and all delays that may have occurred in its prosecution and completion were not Excusable Delays, except for such delays for which the Contractor has provided timely written notice as required herein, and that the Engineer has found to be excusable. Contractor shall not be entitled to claim Excusable Delay for any delay for which the Contractor failed to provide such timely written notice.
23. EXTENSION OF TIME
If the Contractor complies with Section 22, above, and the Engineer finds a delay claimed by the Contractor to be an Excusable Delay, the Contractor shall be allowed an extension of time to complete the Work that is proportional to the period of Excusable Delay determined by the Engineer, subject to the approval by City of a change order granting such time extension.
During a duly authorized extension for an Excusable Delay, City shall not charge liquidated damages against the Contractor for such delay.
If the City extends the time to complete the Work as provided herein, such extension shall in no way release any warranty or guarantee given by Contractor pursuant to the provisions of the Contract Documents, nor shall such extension of time relieve or release the sureties of the Bonds provided pursuant to the Contract Doc uments. By executing such Bonds, the Sureties shall be deemed to have expressly agreed to any such extension of time. The granting of any extension of time as provided herein shall in no way operate as a waiver on the part of City of its rights under this Contract , excepting only extension of the Completion Date for such period of Excusable Delay as may be determined by the Engineer and approved by a duly authorized change order.
24. NO PAYMENT FOR DELAYS
No damages or compensation of any kind shall be paid to Contractor or any subcontractor because of delays in the progress of the Work whether or not such delays qualify for extension of time under this Agreement; except that this provision shall not preclude the recovery of damages for a delay caused by the City that is unreasonable under the circumstances and that is not within the contemplation of the parties, provided that the Contractor timely submits all such written notice(s) and fully complies with s uch other procedures as may be specified in the Contract Documents or any Laws or Regulations for Contractor to claim damages for such delay.
25. CHANGES IN THE WORK
Changes in the Work authorized or directed in accordance with the Contract Documents and extensions of time of completion made necessary by reason thereof shall not in any way release any warranty or guarantee given by Contractor pursuant to the provisions of the Form approved by City Attorney 1-11-17 14
Contract Documents, nor shall such changes in the Work relieve or release the S ureties on Bonds provided pursuant to the Contract Documents. By executing such Bonds, the Sureties shall be deemed to have expressly agreed to any such change in Work and to any extension of time made by reason thereof.
26. TERMINATION AFTER COMPLETION DATE
In addition to any other rights City may have, if any services or work required under the Contract (including but not limited to punch list items) are not completed as of the Completion Date (as adjusted by any extensions of time for Excusable Delays granted pursuant to the Contract Documents), City may terminate the Contract at any time after the Completion Date ( as adjusted by any extensions of time for Excusable Delays granted pursuant to the Contract Documents), by providing a written notice to Contractor specifying the date of termination. Such notice also may specify conditions or requirements that Contractor must meet to avoid termination of the Contract on such date. If Contractor fails to fulfill all such conditions and requirements by such termina tion date, or, if no such conditions or requirements are specified, Contractor shall cease rendering services and performing work on such termination date, and shall not be entitled to receive any compensation for services rendered or work performed after such termination date. In the event of such termination, Contractor shall remain liable to City for liquidated damages incurred for any period of time prior to the termination date.
In addition to any other charges, withholdings or deductions authorized under the Contract or any Laws or Regulations, if City terminates the Contract pursuant to this section, City may withhold and deduct from any payment and/or retention funds otherwise due Contractor any sum necessary to pay the City's cost of completing or correcting , or contracting for the completion or correction of, any services or work under the Contract that are not completed to the satisfaction of the City or that otherwise are deficient or require correction as of such termination date, including but not limited to incomplete punch list items. Such costs shall include all of the City’s direct and indirect costs incurred to complete or correct such services or work, including the City’s administrative and overhead costs. If the amount of payment(s) and/or retention funds otherwise due the Contractor are insufficient to pay such costs, City shall have the right to recover the balance of such costs from the Contractor and/or its Surety(ies).
27. TERMINATION FOR CONVENIENCE
Upon written notice to the Contractor, the City may at any time, without cause and without prejudice to any other right or remedy of the City, elect to terminate the Contract for the convenience of City. In such case, the Contractor shall be paid (without duplication of any items, and after deduction and/or withholding of any amounts authorized to be deducted or withheld by the Contract Documents or any Laws or Regulations):
A. For Work executed in accordance with the Contract Documents prior to the effective date of termination and determined to be acceptable by the Engineer , including fair and reasonable sums for overhead and profit on such Work;
Form approved by City Attorney 1-11-17 15
B. For reasonable claims, costs, losses, and damages incurred in settlement of terminated contracts with subcontractors, suppliers, and others; and
C. For reasonable expenses directly attributable to termination.
Contractor shall not be paid for any loss of anticipated profits or revenue for any Work not performed prior to termination, nor for any economic loss arising out of or resulting from such termination, except for the payments listed in this section. Contractor’s warranty under Section 14 of this Agreement shall apply, and Contractor shall remain responsible for all obligations related to such warranty, with respect to all portions of the Work performed prior to the effective date of the termination for convenience pursuant to this section . The City shall be entitled to have any or all remaining Work performed by other contractors or by any other means at any time after the effective date of a termination for convenience pursuant to this section.
28. TERMINATION FOR BREACH OF CONTRACT
If Contractor abandons the Work under this Contract, or if the Contract or any portion of the Contract is sublet or assigned without the consent of the City, or if the Engineer determines in the Engineer’s sole discretion that the conditions of the Contrac t in respect to the rate of progress of the Work are not being fulfilled or any part thereof is unnecessarily delayed, or if Contractor violates or breaches, or fails to execute in good faith, any of the terms or conditions of the Contract, or if Contracto r refuses or fails to supply enough properly skilled labor or materials or refuses or fails to make prompt payment to subcontractors for material or labor, or if Contractor disregards any Laws or Regulations or proper instruction or orders of the Engineer, then, notwithstanding any provision to the contrary herein, the City may give Contractor and its Sureties written notification to immediately correct the situation or the Contract shall be terminated.
In the event that such notice is given, and, in the event such situation is not corrected, or arrangements for correction satisfactory to the City are not made, within ten (10) calendar days from the date of such notice or within such other period of time as may be specified by the City in the notice, the Contract shall upon the expiration of said period cease and terminate. In the event of any such termination, City may take over the Work and prosecute the Work to completion, or otherwise, and the Contrac tor and its Sureties shall be liable to City for any cost occasioned City thereby, as hereinafter set forth.
In the event City completes the Work, or causes the Work to be completed, no payment of any kind shall be made to Contractor until the Work is complete. The cost of completing the Work, including but not limited to, extra costs of project administration and management incurred by City, both direct or indirect, shall be deducted from any sum then due, or that becomes due, to Contractor from City. If sums due to Contractor from City are less than the cost of completing the Work, Contractor and its Sureties shall pay City a sum equal to this difference on demand. In the event City completes the Work, and there is a sum remaining due to Contractor after City deducts the costs of completing the Work, then City shall pay such sum to Contractor. The Contractor and Contractor’s Suret ies shall be jointly and severally liable for all obligations imposed on Contractor hereunder.
Form approved by City Attorney 1-11-17 16
No act by City before the Work is finally accepted, including, but not limited to, exercise of other rights under the Contract, actions at law or in equity, extensions of time, payments, assessments of liquidated damages, occupation or acceptance of any part of the Work, waiver of any prior breach of the Contract or failure to take action pursuant to this section upon the happening of any prior default or breach of Contractor, shall be construed to be a waiver or estoppel of the City’s right to act pursuant to this Section upon any subsequent event, occurrence or failure by Contractor to fulfill the terms and conditions of the Contract. The rights of City to terminate the Contract pursuant to this Section and pursuant to Sections 26 and 27 are cumulative and are in addition to all other rights of City pursuant to the Contract and at law or in equity.
29. CONTRACTOR BANKRUPT
If Contractor should commence any bankruptcy proceeding, or if Contractor is adjudged a bankrupt, or if Contractor makes any assignment for the benefit of creditors, or if a receiver is appointed on account of Contractor's insolvency, then the City may, wi thout prejudice to any other right or remedy, terminate the Contract and complete the work by giving notice as provided in Section 28 above.
30. SURETIES’ OBLIGATIONS UPON TERMINATION
If the City terminates the Contract pursuant to Section 28 or Section 29 above:
A. The Surety under Contractor’s performance bond shall be fully responsible for all of the Contractor’s remaining obligations of performance under the Contract as if the Surety were a party to the Contract , including without limitation Contractor’s obligations, as provided in the Contract Documents, to complete and provide a one - year warranty of the entire Work, pay liquidated damages and indemnify, defend and hold harmless City, up to the full amount of the performance bond.
B. The Surety under Contractor’s payment bond shall be fully responsible for the performance of all of the Contractor’s remaining payment obligations for work, services, equipment or materials performed or provided in connection with the Work or any portion thereof, up to the full amount of the payment bond.
31. ACCOUNTING RECORDS OF CONTRACTOR
During performance of the Contract and for a period of three (3) years after completing the entire Work, Contractor shall maintain all accounting and financial records related to the Contract and performance of the Work in accordance with generally accepted accounting practices, and shall keep and make such records available for inspection and audit by representatives of the City upon reasonable written notice.
Form approved by City Attorney 1-11-17 17
32. USE TAX REQUIREMENTS
During the performance of this Agreement, CONTRACTOR, for itself, its assignees and successors in interest, agrees as follows:
A. Use Tax Direct Payment Permit: For all leases and purchases of materials, equipment, supplies, or other tangible personal property used to perform the Agreement and shipped from outside California, the Contractor and any subcontractors leasing or purchasing such materials, equipment, supplies or other tangible personal property shall obtain a Use Tax Direct Payment Permit from the California State Board of Equalization (“SBE”) in accordance with the applicable SBE criteria and requirements.
B. Sellers Permit: For any construction contract and any construction subcontract in the amount of $5,000,000 or more, Contractor and the subcontractor(s) shall obtain sellers permits from the SBE and shall register the jobsite as the place of business for the purpose of allocating local sales and use tax to the City.
Contractor and its subcontractors shall remit the self- accrued use tax to the SBE, and shall provide a copy of each remittance to the City.
C. The above provisions shall apply in all instances unless prohibited by the funding source for the Agreement.
33. NON-DISCRIMINATION IN EMPLOYEE BENEFITS
This Agreement may be subject to the requirements of Sacramento City Code Chapter
3.54, Non -Discrimination in Employee Benefits by City Contractors. The Contract Documents include a summary of the requirements of Sacramento City Code Chapter
3.54, entitled “Requirements of the Non- Discrimination in Employee Benefits Code.” By signing this Agreement, Contractor acknowledges and represents that Contractor has read and understands these requirements and agrees to fully comply with all applicable requirements of Sacramento City Code Chapter 3.54. If requested by City, Contractor agrees to promptly provide such documents and information as may be required by City to verify Contractor’s compliance. Any violation by Contractor of Sacramento City Code Chapter 3.54 constitutes a material breach of this Agreement, for which the City may terminate the Agreement and pursue all available legal and equitable remedies.
34. CONSIDERING CRIMINAL CONVICTION INFORMATION IN THE EMPLOYMENT
APPLICATION PROCESS
This Agreement may be subject to the requirements of Sacramento City Code Chapter
3.62, Procedures for Considering Criminal Conviction Information in the Employment Application Process. The Contract Documents include a summary of the requirements of Sacramento City Code Chapter 3.62, entitled “Ban-The-Box Requirements.” By signing this Agreement, Contractor acknowledges and represents that Contractor has read and Form approved by City Attorney 1-11-17 18
understands these requirements and agrees to fully comply with all applicable requirements of Sacramento City Code Chapter 3.62. If requested by City, Contractor agrees to promptly provide such documents and information as may be required by City to verify Contractor’s compliance. Any violation by Contractor of Sacramento City Code Chapter 3.62 constitutes a material breach of this Agreement, for which the City may terminate the Agreement and pursue all available legal and equitable remedies.
Contractor agrees to require its subcontractors to fully comply with all applicable requirements of Sacramento City Code Chapter 3.62, and include these requirements in all subcontracts covered by Sacramento City Code Chapter 3.62.
lN WITNESS WHEREOF, the parties hereto have signed this Agreement on the date set forth opposite their names.
CONTRACTOR
Under penalty of perjury, I certify that the taxpayer identification number and all other
DATE 12/ 18/23
DATE
Original Approved As To Form:
City Attorney
Form approved by City Attorney 1-11-17
Print Name
President
Print Name
Title
1000000866
DIR Registration #
20-4481966
Federal lD#
Entity # 2788642
State lD#
119308
City of Sacramento Business Operation Tax Certificate No. (City will not award contract until
Certificate Number is obtained)
Type of Business Entity /check one/:
Individual/Sole Proprietor
Partnership
i Corporation
Limited Liability Company
other |please specif
CITY OF SACRAMENTO
a municipal corporation
BY
For: Howard chan, City Manager
Attest:
City Clerk
19 NORTH STAR CONSTRUCTION & ENGINEERING, INC.
1282 Stabler Lane #630-109 • Yuba City, CA 95993
Phone: 530-673-7080 • Fax: 530-673-1880
www.northstarinc.com
November 29, 2023
City of Sacramento | Department of Public Works
Facilities and Real Property Management
5730 24th Street, Building 4
Sacramento, CA 95822
Attn: Ezra Roati, Senior Architect
RE: Phase 1 of the Sacramento EV Blueprint Task 5- Vehicle Chargers
Ezra,
Attached you will find our bid form for the scope that consists of three sites including flat work, landscaping, electrical scope, and Electric Vehicle (EV) charger procurement and installation.
Exclusions/Clarifications:
1. Includes Prevailing Wages and Certified Payrolls.
2. PLA Not Included.
3. LBE Not Included.
4. Project requires approximately 3 weeks per site to complete onsite work.
5. Please note that Charge Point does not offer Chip readers on the 8’ stations, and that the 8’ stations are only available in the 80A version. They only have approval to price chip readers for projects in states that have incentive requirements for them, and California does not have these incentives.
Price: (See Schedule of Values on next Page)
Please let me know if you have any questions.
Regards,
Zach Milner, P.E.
Operations Manager
Sacramento EV Blueprint Task‐5 Vehicle Chargers ‐ Phase 1 Belle College
Mobilization & Demobilization 35,000.00$
Earthwork & Sitework 64,000.00 $
Concrete & Bollards 24,000.00 $
Electrical Including EV 120,000.00 $
Pavement Markings and Signage 5,000.00$
OH, Profit, Bonds, Etc. 40,000.00 $
Total 288,000.00 $
Colonial Heights Library
Mobilization & Demobilization 35,000.00$
Earthwork & Sitework 62,000.00 $
Concrete & Bollards 26,000.00 $
Electrical Including EV 115,000.00 $
Pavement Markings and Signage 5,000.00$
OH, Profit, Bonds, Etc. 39,000.00 $
Total 282,000.00 $
Sam & Bonnie Pannell CC
Mobilization & Demobilization 35,000.00$
Earthwork & Sitework 66,000.00 $
Concrete & Bollards 25,000.00 $
Electrical Including EV 125,000.00 $
Pavement Markings and Signage 5,000.00$
OH, Profit, Bonds, Etc. 42,000.00 $
Total 298,000.00 $
Grand Total 868,000.00$
SACRAMENTO EV BLUEPRINT- TASK 5
PHASE 1- THREE SITES
PRE-QUALIFIED GENERAL CONTRACTOR
PROPOSAL REQUEST FORM
Noti
ce to Bidders: This is an informal bid process. The undersigned bidder agrees, if this bid is accepted, to enter into an agreement with the City of Sacramento as a separate Contract based on a pre-selection process or utilizing an existing on-call contract at the discretion of the City.
This
Bid is submitted to: City of Sacramento
Depar tment of Public Works
5730 24th Street, Building 4
Sacramento, CA 95822
This Bid is from this submittal date: valid for ninety (90) days.
Questions regarding this bid are to be directed in-writing to Ezra Roati, Senior Architect at [email protected].
Rec
eipt of Addenda: Bidder has received and examined the following Addenda:
Addendum 1_____________________ Date__________________________ Addendum 2 ____________________ Date__________________________ Bid P
ricing: Provide lump sum pricing for this bid, with *Schedule of Values (SOV) backup indicating all major trades and line-item pricing as an attachment to this document to include all markup and overhead. This project requires performance and payment bonds and is subject to prevailing wages.
Tot
al Lump Sum Proposal Price : $_____________________ *
Experience with State Grant Funded projects: yes no Auth
orized Signature: (Signed by an individual with authority to bind the company.) _____________________________________________________________________________ Company Name: ____________________________________________ Street Address: _____________________________________________ _____________________________________________
Signat
ure: _____________________________________________
Name: _____________________________________________
Title: _____________________________________________
11/29/23
11/17/23
North Star Construction and Engineering, Inc.
1282 Stabler Lane #630-109
Yuba City, CA 95993
Iqbal Basrai
President
X
868,000.00
EV BLUEPRINT
PROJECT- TASK 5
SPECIFICATIONS
General Requirements and Technical Specs
City of Sacramento
Facilities and Real Property Management
TABLE OF CONTENTS
PROJECT SPECIFICATIONS
TABLE OF CONTENTS- EV BLUEPRINT PAGE 1 OF 1
DIVISION 1 GENERAL REQUIREMENTS
Section 01 10 00 Summary
Section 01 25 00 Substitution Procedures
Section 01 26 00 Contract Modification Procedures
Section 01 29 00 Payment Procedures
Section 01 31 00 Project Management and Coordination
Section 01 32 00 Construction Progress Documentation
Section 01 33 00 Submittal Procedures
Section 01 40 00 Quality Requirements
Section 01 42 00 References
Section 01 60 00 Product Requirements
Section 01 73 00 Execution
Section 01 74 19 Construction Waste Management and Disposal
Section 01 77 00 Closeout Procedures and Warranty Form
Section 01 77 10 Certificate of Compliance
Section 01 78 23 Operation and Maintenance Data
Section 01 78 39 Project Record Documents
DIVISION 2 SITE WORK
(None) Refer to Plans
DIVISION 3 CONCRETE
(None) Refer to Plans
DIVISION 26 ELECTRICAL
Section 26 05 00 Electrical Materials and Methods
Section 26 05 26 Grounding and Bonding for Electrical Systems
Section 26 26 53 Electrical Vehicle (EV) Charging Equipment
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
SUMMARY - 011000 - 1
SECTION 011000 - SUMMARY
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Phased construction.
4. Work by Owner.
5. Work under separate contracts.
6. Future work.
7. Owner-furnished products.
8. Access to site.
9. Coordination with occupants.
10. Work restrictions.
11. Specification and Drawing conventions.
12. Miscellaneous provisions.
B. Related Requirements:
1. Section 013100 “Project Management and Coordination” for requirements on using web-based Project software.
1.3 PROJECT INFORMATION
A. Project Identification: EV Blueprint – Task 5 EV Charger Project
1. Project Location: Various Locations. Phase 1 Includes:
a. Belle Cooledge Library, 5600 South Land Park Drive
b. Colonial Heights Library, 4799 Stockton Blvd.
c. Samuel C. Pannell Community Center, 2450 Meadowview Road B. Owner: City of Sacramento, 915 I St. Sacramento, CA 95814.
1. Owner's Representative/ Architect: Ezra Roati, Associate Architect, Facilities and Real Property Management, Department of Public Works, 5730 24 th Street, Sacramento, CA 95822, (916) 808-5877.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
SUMMARY - 011000 - 2
C. Consultants: Owner has retained the following design professionals who have prepared designated portions of the Contract Documents:
1. City Facilities Architects and Engineers developed the plans.
2. Note: City may retain the use of a Construction Manager on this set of projects.
D. Construction Inspector:
1. Construction Inspector has been engaged for this Project to serve as an advisor to Owner and to provide assistance in administering the Contract for construction between Owner and Contractor.
E. Web-Based Project Software: Project software administered by Contractor will be used for purposes of mana ging communication and documents during the construction stage.
1. See Section 013100 "Project Mana gement and Coordination." for requirements for using web-based Project software.
1.4 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Document s and consists of the following:
1. Various project sites, include s demolition, flat work , concrete, asphalt, electrical scope, installation of EV chargers and patch-back of site-work materials. Project also includes striping and signage as referenced in the plans and specifications.
B. Type of Contract:
1. Project will be constructed under a single prime contract.
1.5 WORK BY OWNER
A. General: Cooperate fully with O wner so work may be car ried out smoothly, without interfering with or delaying work under th is Contract or work by Owner. Coordinate the Work of this Contract with any work performed by Owner.
1.6 ACCESS TO SITE
A. General: Contractor shall have full use of Project site for construction operations during construction period. Contractor's use of Project site is limited only b y Owner's right to perform work or to retain other contractors on portions of Project.
1.7 WORK RESTRICTIONS
A. Work Restrictions, General: Comply with restrictions on construction operations.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
SUMMARY - 011000 - 3
1. Comply with limitations on use of public streets and with other requir ements of authorities having jurisdiction.
B. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption with Owner.
1. Notify Owner not less than two days in advance of proposed disruptive operations.
2. Obtain Owner's written permission before proceeding with disruptive operations.
C. Restricted Substances: Use of tobacco products and other controlled substances on Project site is not permitted.
D. Employee Identification: Owner will provide identification tags for Contractor personnel working on Project site. Require personnel to use identification tags at all times.
1.8 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:
1. Imperative m ood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.
C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of t he following are used on Drawings to identify materials and products:
1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.
2. Abbreviations: Materials and products are identified by ab breviations published as part of the U.S. National CAD Standard and scheduled on Drawings.
3. Keynoting: Mate rials and products are identified by reference keynotes referencing Specification Section numbers found in this Project Manual.
1.9 MISCELLANEOUS PROVISIONS
A. Security Conditions at the Construction Site: Owner is aware of conditions in the immediate vicinity of the constru ction site that may imp act contractor’s performance of the work. These conditions include a high population of un sheltered homeless persons, camping by unsheltered homeless persons, accumulations of trash, clothing, food containers, biohazards, cast -off p ersonal possessions and camping equipment, EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
SUMMARY - 011000 - 4
abandoned bikes, animals, stray animals, panhandl ing activities , person s seeking assistance, medical emergencies, and fire and police activity.
B. Responsibility for Site Security: Contractor shall retain responsib ility for site security , site maintenance, site clean -up, protection of materials and equipm ent including stored, staged and installed materials and equipment, according to contract documents. Contractor’s responsibility shall continue 24 -hours, 7 -days-per-week during the performance of the Work, and as such may require security performed with staff and/or electronic surveillance.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011000
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
SUBSTITUTION PROCEDURES - 012500 - 1
SECTION 012500 - SUBSTITUTION PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for substitutions and Value Engineering.
B. Related Requirements:
1. Section 016000 "Product Requirements" for requirements for submitting comparable product submittals for products by listed manufacturers.
1.3 DEFINITIONS
A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.
1. Substitutions for Cause: Ch anges proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms.
2. Substitutions for Convenience / Equal : Changes proposed by Contractor or Owner that are not required in order to meet other Project requirements but may offer advantage to Contractor or Owner.
1.4 ACTION SUBMITTALS
A. Substitution Requests: Submit three copies of each request for consideration. Identify product or fabrication or install ation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.
1. Substitution Request Form: Use electronic (PDF) copy of form provided in Project Manual.
2. Documentation: Show compliance with requirements for substitutions and the following, as applicable:
a. Statement indicating why specified product or fabrication, or installation method cannot be provided, if applicable.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
SUBSTITUTION PROCEDURES - 012500 - 2
b. Coordination of information, including a list of change s or revisions needed to other parts of the Work and to construction performed by Owner and separate contractors that will be necessary to accommodate proposed substitution.
c. Detailed comparison of significant qualities of proposed substitutions with those of the Work specified. Include annotated copy of applicable Specification Section. Significant qualities may include attributes, such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific feat ures and requirements indicated. Indicate deviations, if any, from the Work specified. d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.
e. Samples, where applicable or requested.
f. Certificates and qualification data, where applicable or requested. g. List of similar installations for completed projects, with project names and addresses as well as names and addresses of architects and owners. h. Material test reports from a qualified testing agency, indicating and interpreting test results for compliance with requirements indicated. i. Detailed comparison of Contractor's construction schedule using proposed substitutions with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.
j. Cost information, incl uding a proposal of change, if any, in the Contract Sum.
k. Contractor's certification that proposed substitution complies with requirements in the Contract Documents, except as indicated in substitution request, is compatible with related materials and is ap propriate for applications indicated.
l. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.
3. Architect's Action: If necessary, Architect w ill request additional information or documentation for evaluation within seven (7) days of receipt of a request for substitution. Architect will notify Contractor through Construction Manager of acceptance or rejection of proposed substitution within 15 d ays of receipt of request, or seven (7) days of receipt of additional information or documentation, whichever is later.
a. Forms of Acceptance: Change Order, Construction Change Directive, or Architect's Supplemental Instructions for minor changes in the Work. b. Use product specified if Architect does not issue a decision on use of a proposed substitution within time allocated.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
SUBSTITUTION PROCEDURES - 012500 - 3
1.5 QUALITY ASSURANCE
A. Compatibility of Substitutions: Inve stigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers.
1.6 PROCEDURES
A. Coordination: Revise or adjust affected work as neces sary to integrate work of the approved substitutions.
1.7 SUBSTITUTIONS
A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change, but not later than 10 days prior to time required for preparation and review of related submittals.
1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:
a. Requested substitution is consistent with the Contract Documents and will produce indicated results.
b. Substitution request is fully documented and properly submitted. c. Requested substitution will not adversely affect Contractor's construction schedule.
d. Requested substitution has received necessary approvals of authorities having jurisdiction.
e. Requested substitution is compatible with other portions of the Work. f. Requested substitution has been coordinated with other portions of the Work.
g. Requested substitution provides specified warranty.
h. If requested substitution involves more than one contr actor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.
B. Substitutions for Convenience / Equal:
1. Architect will consider requests for substitution if r eceived no later than 10 days prior to Bid Date.
2. All Substitutions for Convenience / Equal must be pre-approved prior to Bid Date.
3. All requests for pre -approval of Substitutions for Convenience / Equal must be in writing.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
SUBSTITUTION PROCEDURES - 012500 - 4
4. All items, materials or processes that are to be considered for pre -approval must be submitted in the manner described in the individual Specification Sections in which they appear, and must include all required and necessary support information, certificates, and product information neede d for evaluation.
Responsibility for assembling and providing adequate review material is solely that of the pre -approval application. Adequacy of the material submitted will be determined solely by the Architect, whose decision shall be final.
5. Inadequate applications will not be reviewed. Neither the Architect nor the Owner has an obligation to notify applicants of inadequate applications prior to the established cut-off dates for review.
6. Neither the Architect nor the Owner has an obligation to review proposed equals prior to Bidding unless pre -approval of a particular material, method or item of equipment is expressly required in the Specifications.
7. Conditions: Architect will consider Contractor's request for substitution when the following conditi ons are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:
a. Requested substitution offers Owner a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional responsibilities Owner must assume. Owner's additional responsibilities may include compensation to Architect for redesign and evaluation services, increased cost of other construction by Owner, and similar considerations.
b. Requested substitution does not require extensive revisions to the Contract Documents.
c. Requested substitution is consistent with the Contract Documents and will produce indicated results.
d. Substitution request is fully documented and properly submitted. e. Requested substitution will not adversely affect Contractor's construction schedule.
f. Requested substitution has received necessary approvals of authorities having jurisdiction.
g. Requested substitution is compatible with other portions of the Work. h. Requested substitution has been coordinated with other portions of the Work.
i. Requested substitution provides specified warranty.
j. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.
END OF SECTION 0125000
(SUBSTITUTION FORM TO FOLLOW)
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
SUBSTITUTION PROCEDURES - 012500 - 5
FORM FOR USE WITH SUBSTITUTION REQUESTS / EQUALS
TO:
PROJECT:
SPECIFIED ITEM:
SECTION: PAGE: PARAGRAPH: DESCRIPTION:
The undersigned requests consideration of the following:
PROPOSED SUBSTITUTION:
Attached data includes product description, specifications, drawings, photographs, performance and test data adequate for evaluation of the requests; applicable portions of the data are clearly identified. Attached data also includes description of changes to Contract Documents that pro- posed substitution will require for its proper installation.
The undersigned states that the following paragraphs, unless modified on attachments, are cor- rect:
1. The proposed substitution does not affect dimensions shown on Drawings.
2. The undersigned will pay for changes to the building design, including engineering, de- sign, detailing and construction costs caused by the requested substitution.
3. The proposed substitution will have no adverse effect on other trades, the construction schedule or specified warranty requirements.
4. Maintenance and service parts will be locally available for the proposed substitution.
The undersigned further states that the function, appearance and quality of the proposed substi- tution are equivalent or superior to the specified item.
Submitted by: Title:
Signature: Date:
Firm: Phone:
Address:
Attachments:
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * Accepted: City Architect Rejected: City Architect By: Date: (City) By: Date: (Architect)
END FORM FOR USE WITH SUBSTITUTION REQUESTS / EQUALS
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
SUBSTITUTION PROCEDURES - 012500 - 6
(This page intentionally left blank)
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
CONTRACT MODIFICATION PROCEDURES - 012600 - 1
SECTION 012600 - CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for handling and processing Contract modifications.
B. Related Requirements:
1. Section 012500 "Substitution Proced ures" for administrative procedures for handling requests for substitutions made after the Contract award.
1.3 MINOR CHANGES IN THE WORK
A. Owner will issue through Construction Manager supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time,
1.4 PROPOSAL REQUESTS
A. Owner-Initiated Proposal Requests: Construction Manager will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will incl ude supplemental or revised Drawings and Specifications.
1. Work Change Proposal Requests issued by Constru ction Manager are not instructions either to stop work in progress or to execute the proposed change.
2. Within time specifi ed in Proposal Request after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.
a. Include a list of quantities of products required or eliminated and unit cos ts, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
c. Include costs of labor and supervision directly attributable to the change.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
CONTRACT MODIFICATION PROCEDURES - 012600 - 2
d. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time. e. Quotation Form: Use EZ-PCO form provided by Owner. Sample cop y is included at the end of this section.
f. Markups, including percentages of mark -up, shall be allowed only as described within t he EZ-PCO Change Order Proposal and Change Order Proposal Summary. No mark -up is allowed for intermediate sub - contractors.
B. Contractor-Initiated Proposals: If latent or changed conditions require modifications to the Contract, Contractor may initiate a c laim by submitting a request for a change to Construction Manager.
1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.
2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
3. Indicate app licable taxes, delivery charges, equipment rental, and amounts of trade discounts.
4. Include costs of labor and supervision directly attributable to the change.
5. Include an updated Contractor's construction schedule that indicates the effect of the change, in cluding, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
6. Comply with requirements in Section 012500 "Substitution Procedures " if the proposed change requires substitution of one product or system for product or system specified.
7. Proposal Request Form: Use EZ-PCO form provided by Owner . Sample copy is included at the end of this section.
1.5 CHANGE ORDER PROCEDURES
A. On Owner's approval of a Work Change Proposal Request, Construction Manager will issue a Change Order for signatures of Owner and Contractor.
1.6 CONSTRUCTION CHANGE DIRECTIVE
A. Construction Change Directive: Construction Manager may issue a Construction Change Directive on form included in Project Manual. Construction C hange Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.
1. Construction Change Directive contains a complete description of change in the Work. It also designates method to be followed to determin e change in the Contract Sum or the Contract Time.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
CONTRACT MODIFICATION PROCEDURES - 012600 - 3
B. Documentation: Maintain detailed records on a time and material basis of work required by the Construction Change Directive.
1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 012600 (SAMPLE FORMS TO FOLLOW)
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
CONTRACT MODIFICATION PROCEDURES - 012600 - 4
SAMPLE FORMS FOR USE WITH CONTRACT MODIFICATION PROCEDURES
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
CONTRACT MODIFICATION PROCEDURES - 012600 - 5
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
CONTRACT MODIFICATION PROCEDURES - 012600 - 6
END SAMPLE FORMS FOR USE WITH CONTRACT MODIFICATION PROCEDURES City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
PAYMENT PROCEDURES - 012900 - 1
SECTION 012900 - PAYMENT PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Spec. Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements necessary to prepare and process Applications for Payment.
B. Related Requirements:
1. Section 012600 "Contract Modification Procedures" for administrative procedures for handling changes to the Contract.
2. Section 013200 "Construc tion Progress Documentation" for administrative requirements governing the preparation and submittal of the Contractor's construction schedule.
1.3 DEFINITIONS
A. Schedule of Values (SOV): A statement furnished by Contractor allocating portions of the Contract Sum to various portions of the Work and used as the basis for reviewing Contractor's Applications for Payment.
1.4 SCHEDULE OF VALUES (SOV)
A. Coordination: Coordinate the SOV with Contractor's construction schedule.
1. Coordinate line items in the SOV with items required to be indicated as separate activities in Contractor's construction schedule.
2. Submit the SOV to Owner at earliest possible date, but no later than 14 days before the date scheduled for submittal of initial Application for Payment.
3. Sub-schedules for S eparate Elements of Work: Where the Contractor's construction schedule defines separate elements of the Work, provide sub - schedules showing values coordinated with each element.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
PAYMENT PROCEDURES - 012900 - 2
B. Format and Content: Use Project Manual table of contents as a guide to establi sh line items for the SOV. Provide at least one line-item for each Specification Section.
1. Identification: Include the following Project identification on the SOV:
a. Project name and location.
b. City's Project number.
c. Contractor's name, address and phone number.
d. Date of submittal.
2. Use City provided Schedule of Values form.
3. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Provide multiple line items for principal subcontract amounts in excess of five percent (5% min.) of the Contract Sum.
4. Provide a separate line item in the SOV for each part of the Work where Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.
a. Differentiate between items stored on-site and items stored off-site.
5. Overhead Costs: Include total cost, overhead and profit for each line item.
6. Closeout Costs. Include separate line items under Contractor and principal subcontracts for Project cl oseout requirements in an amount totaling equal or greater than five percent of the Contract Sum and subcontract amount.
7. Schedule of Values Revisions: Revise the SOV when Change Orders (CO) or Construction Change Directives (CCD) result in a change in the Contract Sum.
Include at least one separate line item for each CO and CCD.
1.5 APPLICATIONS FOR PAYMENT
A. Each Application for Payment following the initial Application for Payment shall be consistent with previous applications and payments as certified by City’s Project Manager and paid for by Owner.
B. Payment Application Times: The date (20th of each month) for each progress payment is indicated in the Agreement between Owner and Contractor. The period of construction work covered by each Application for Payment is the period indicated in the Agreement.
1. Submit draft copy of Application for Payment ten days prior to due date for review by City Labor Compliance, Inspector, Project & Construction Manager.
C. Application for Payment Forms: Use City provided form for Applications for Payment.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
PAYMENT PROCEDURES - 012900 - 3
D. Application Preparation: Complete every entry on form. Execute by a person authorized to sign legal documents on behalf of Contractor. City will return incomplete applications without action.
1. Entries shall match data on the SOV and Contractor's construction schedule. Use updated schedules if revisions were made.
2. Include amounts for work completed following previous Application for Payment, whether or not payment has been received. Include only amounts for work completed at time of Application for Payment.
3. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.
4. Indicate separate amounts for work being carried out under Owner -requested project acceleration.
E. Stored Materials: Include in Application for Payment amounts applied for materials or equipment purchased or fabricated and stored, but not yet installed. Differentiate between items stored on-site and items stored off-site.
1. Provide address of warehouse fa cility, certificate of insurance, evidence of transfer of title to Owner, and consent of surety to payment for stored materials.
2. Provide supporting documentation that verifies amount requested, such as paid invoices. Match amount requested with amounts ind icated on documentation; do not include overhead and profit on stored materials.
3. Provide summary documentation for stored materials indicating the following:
a. Value of materials previously stored and remaining stored as of date of previous Applications for Payment.
b. Value of previously stored materials put in place after date of previous Application for Payment and on or before date of current Application for Payment.
c. Value of materials stored since date of previous Application for Payment and remaining stored as of date of current Application for Payment.
F. Transmittal: Submit one signed original copy of each Application for Payment to Project Manager by an electronic method ensuring receipt. Include waivers of lien and similar attachments as required.
1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application.
G. Waivers of Liens: With each Application for Payment, submit waivers of lien from subcontractors, sub-subcontractors, and suppliers for construct ion period covered by the previous application.
1. Submit partial waivers on each item for amount requested in previous application, after deduction for retainage, on each item.
2. When an application shows completion of an item, submit conditional final or full waivers.
3. Owner reserves the right to designate which entities involved in the Work must submit waivers.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
PAYMENT PROCEDURES - 012900 - 4
4. Submit final Application for Payment with or preceded by conditional final waivers from every entity involved with performance of the Work covered by t he application who is lawfully entitled to a lien.
5. Waiver Forms: Submit executed waivers of lien on forms acceptable to Owner.
H. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:
1. List of subcontractors.
2. Schedule of Values (SOV).
3. Contractor's construction schedule (preliminary if not final).
4. Products list (preliminary if not final).
5. Sustainable design action plans, including preliminary project materials cost data.
6. Schedule of unit prices.
7. Submittal schedule (preliminary if not final).
8. List of Contractor's staff assignments.
9. List of Contractor's principal consultants.
10. Copies of building permits.
11. Copies of authorizations and licenses from aut horities having jurisdiction for performance of the Work.
12. Initial progress report.
13. Report of preconstruction conference.
I. Application for Payment at Substantial Completion: After City issues the Certificate of Substantial Completion, submit an Application f or Payment showing 100 percent completion for portion of the Work claimed as substantially complete.
1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.
2. This a pplication shall reflect Certificate(s) of Substantial Completion issued previously for Owner occupancy of designated portions of the Work.
J. Final Payment Application: After completing Project closeout requirements, submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:
1. Evidence of completion of Project closeout requirements.
2. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.
3. Updated final statement, accounting for final changes to the Contract Sum.
4. Evidence that claims have been settled.
5. Final meter readings for utilities, a measured record of stored fuel, and sim ilar data as of date of Substantial Completion or when Owner took possession of and assumed responsibility for corresponding elements of the Work.
6. Final liquidated damages settlement statement.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 012900
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
PROJECT MANAGEMENT AND COORDINATION - 013100 - 1
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, includin g General and Supplementary Conditions and other Division 01 Spec. Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. General coordination procedures.
2. Coordination drawings.
3. RFIs.
4. Digital project management procedures.
5. Project meetings.
B. Each contractor shall participate in coordination requirements. Certain areas of responsibility are assigned to a specific contractor. However, General Contractor shall coordinate and be responsible for the entire project.
C. Related Requirements:
1. Section 013200 "Construction Progress Documentation" for preparing and submitting Contractor's construction schedule.
2. Section 017300 "Execution" for procedures for coordinating general installation and field -engineering services, including establishment of benchmarks and control points.
3. Section 017700 "Closeout Procedures" for coordinating closeout of the Contract.
1.3 DEFINITIONS
A. RFI: Request for Information. Request from Owner, Architect, or Contractor seeking information required by or clarifications of the Contract Documents.
1.4 INFORMATIONAL SUBMITTALS
A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
PROJECT MANAGEMENT AND COORDINATION - 013100 - 2
1. Name, address, telephone number, and email address of entity performing subcontract or supplying products.
2. Number and title of related Specification Section(s) covered by subcontract.
3. Drawing number and detail references, as appropriate, covered by subcontract.
B. Key Personnel Names: Within 5 days of starting construction operations, submit a list of key personnel assignments, including superintendent and other personnel in attendance at Pro ject site. Identify individuals and their duties and responsibilities; list addresses and cellular telephone numbers and e -mail addresses. Provide names, addresses, and telephone numbers of individuals assigned as alternates in the absence of individuals assigned to Project.
1. Post copies of list in project meeting room, in temporary field office, in web-based Project software directory, and in prominent location in each built facility. Keep list current at all times.
1.5 GENERAL COORDINATION PROCEDURES
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work.
Coordinate construction operations included in different Section s that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
B. Coordination: Each contractor shall coordinate its construction operations with those of other contractors and entities to ensure efficient and orderly installation of each part of the Work. Each contractor shall coordinate its own operations with operations included in different Sections that depend on each other for proper inst allation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of components with other contractors to ensure maximum performance and accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
C. Prepare memoranda for distributi on to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
1. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is required.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
PROJECT MANAGEMENT AND COORDINATION - 013100 - 3
D. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's construction schedule.
2. Preparation of the schedule of values.
3. Delivery and processing of submittals.
4. Progress meetings.
5. Preinstallation conferences.
6. Project closeout activities.
7. Startup and adjustment of systems.
1.6 COORDINATION DRAWINGS
A. Coordination Drawings, General: Prepare coordination drawings according to requirements in individual Sections , and additionally where installation is not completely indicated on Shop Drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity.
1. Content: Project-specific information, drawn accurately to a scale large enough to indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable:
a. Use applica ble Drawings as a basis for preparation of coordination drawings. Prepare sections, elevations, and details as needed to describe relationship of various systems and components.
b. Coordinate the addition of trade -specific information to coordination drawings in a sequence that best provides for coordination of the information and resolution of conflicts between installed components before submitting for review.
c. Indicate functional and spatial relationships of components of architectural, structural, mechanical, and electrical systems.
d. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation. e. Show location and size of access doors required for access to concealed dampers, valves, and other controls.
f. Indicate required installation sequences.
g. Indicate dimensions shown on Drawings. Specifically note dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternative sketches to Owner indicating proposed resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.
B. Coordination Drawing Organization: Organize coordination drawings as follows:
1. Floor Plans and Reflected Ceiling Plans: Show architectural and structural elements, and mechanical, fire -protection, fire-alarm, and electrical Work. Show EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
PROJECT MANAGEMENT AND COORDINATION - 013100 - 4
locations of visible ceiling -mounted devices. Supplement plan drawings with section drawings where required to adequately represent the Work.
2. Structural Penetrations: Indicate penetrations and openings required for all disciplines.
3. Slab Edge an d Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, door floor closers, slab depressions for floor finishes, curbs and housekeeping pads, and similar items.
4. Mechanical and Plumbing Work: Show the following:
a. Sizes and bottom elevations of ductwork, piping, and conduit runs, including insulation, bracing, flanges, and support systems. b. Dimensions of major components, such as dampers, valves, diffusers, access doors, cleanouts and electrical distribution equipment. c. Fire-rated enclosures around ductwork.
5. Electrical Work: Show the following:
a. Runs of vertical and horizontal conduit 1-1/4 inches in diameter and larger. b. Light fixture, exit light, emergency batt ery pack, smoke detector, and other fire-alarm locations.
c. Panel board, switch board, switchgear, transformer, busway, generator, and motor-control center locations.
d. Location of pull boxes and junction boxes, dimensioned from column center lines.
6. Fire-Protection System: Show the following:
a. Locations of standpipes, mains piping, branch lines, pipe drops, and sprinkler heads.
7. Review: Owner will review coordination drawings to confirm that in general the Work is being coordinated, but not for the details of the coordination, which are Contractor's responsibility. If Owner determines that coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, Owner will so inform Contractor, who shall make suitable modifications and resubmit.
8. Coordination Drawing Prints: Prepare coordination drawing prints according to requirements in Section 013300 "Submittal Procedures."
C. Coordination Digital Data Files: Prepare coordination digital data files according to the following requirements:
1. File Preparation Format: Same digita l data software program, version, and operating system as original Drawings.
2. File Submittal Format: Submit or post coordination drawing files in PDF format.
3. Owner will furnish Contractor one set of digital data files of Drawings for use in preparing coordination digital data files.
a. Owner makes no representations as to the accuracy or c ompleteness of digital data files as they relate to Drawings.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
PROJECT MANAGEMENT AND COORDINATION - 013100 - 5
b. Digital Data Software Program: Drawings are available in AutoCAD 2015 Version in Microsoft Windows operating system.
c. Contractor shall execute a data licensing agreement in the form of the Agreement included in this Project Manual.
1.7 REQUEST FOR INFORMATION (RFI)
A. General: Immediately on discovery of the need for additional information, clarification, or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.
1. Owner will return without response those RFIs submitted to Owner by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner so a s to avoid delays in Contractor's work or work of subcontractors.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. Project name.
2. Project number.
3. Date.
4. Name of Contractor.
5. Name of Architect and Owner
6. RFI number, numbered sequentially.
7. RFI subject.
8. Specification Section number and title and related paragraphs, as appropriate.
9. Drawing number and detail references, as appropriate.
10. Field dimensions and conditions, as appropriate.
11. Contractor's suggested resolu tion. If Contractor's suggested resolution impacts the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
12. Contractor's signature.
13. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Forms: Form bound in Project Manual or Software-generated form with substantially the same content as indicated above, acceptable to Owner.
1. Attachments shall be electronic files in PDF format.
D. Owner's Action: Owner will review each RFI, determine action required, and respond.
Allow five working days for Owner's response for each RFI. RFIs received by Owner after 1:00 p.m. will be considered as received the following working day.
1. The following Contractor-generated RFIs will be returned without action:
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
PROJECT MANAGEMENT AND COORDINATION - 013100 - 6
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods. d. Requests for coordination information already indicated in the Contract Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum. f. Requests for interpretation of Architect's actions on submittals. g. Incomplete RFIs or inaccurately prepared RFIs.
2. Owner's action may include a request for additional information, in which case Owner's time for response will date from time of receipt by Owner of additional information.
3. Owner's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal according to Section 012600 "Contract Modification Procedures." a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract Sum, notify Owner in writing within 5 days of receipt of the RFI response.
E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number. Submit log weekly. Software log with not less than the following:
1. Project name.
2. Name and address of Contractor.
3. Name and address of Architect.
4. RFI number including RFIs that were returned without action or withdrawn.
5. RFI description.
6. Date the RFI was submitted.
7. Date Owner's response was received.
8. Identification of related Minor Change in the Work, Construction Change Directive, and Proposal Request, as appropriate.
F. On receipt of Owner's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Owner within five days if Contractor disagrees with response.
1.8 DIGITAL PROJECT MANAGEMENT PROCEDURES
A. Use of Owner's Digital Data Files: Digital data files of Owner's drawings will be provided by Owner for Contractor's use during construction.
1. Digital data files may be used by Contractor in preparing coordination drawings, Shop Drawings, and Project record Drawings.
2. Owner makes no representations as to the accuracy or completeness of digital data files as they relate to Contract Drawings.
3. Digital Drawing Software Program: Contract Drawings are available in PDF.
4. Contractor shall execute a data licensing agreement in the form of Agreement included in Project Manual.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
PROJECT MANAGEMENT AND COORDINATION - 013100 - 7
a. Subcontractors, and other parties granted access by Contractor to Owner's digital data files shall execute a data licensing agreement in the form of Agreement included in this Project Manual.
5. The following digital data files will be furnished for each appropriate discipline:
a. Site plans.
b. Floor plans.
c. Reflected ceiling plans.
B. Web-Based Project Software: Provide, administer, and use web -based Project software site for purposes of hosting and managing Project communication and documentation until Final Completion.
1. Web-based Project software site includes, at a minimum, the following features:
a. Compilation of Project data, including Contractor, subcontractors, Architect, architect's consultants, Owner, and other entities involved in Project.
Include names of individuals and contact information.
b. Access control for each entity for each workflow process, to determine entity's digital rights to create, modify, view, and print documents. c. Document workflow planning, allowing customization of workflow between project entities.
d. Creation, logging, tracking, and notification for Project communications required in other Specification Sections, including, but not limited to, RFIs, submittals, Minor Changes in the Work, Construction Change Directives, and Change Orders.
e. Track status of each Project communication in real time, and log time and date when responses are provided.
f. Procedures for handling PDFs or similar file formats, allowing markups by each entity. Provide security features to lock markups against changes once submitted.
g. Processing and tracking of payment applications.
h. Processing and tracking of contract modifications.
i. Creating and distributing meeting minutes.
j. Document management for Drawings, Specifications, and coordination drawings, including revision control.
k. Management of construction progress photographs.
l. Mobile device compatibility, including smartphones and tablets.
2. Provide up to seven web-based Project software user licenses for use of Owner, Architect, and Architect's consultants. Upon request, p rovide four hours of software training at Owner's office for web-based Project software users.
3. At completion of Project, provide digital archive in format that is readable by Microsoft Windows applications. Provide data in locked/flattened format.
4. Provide one of the following web -based Project software packages under their current published licensing agreements:
a. Autodesk;
b. Corecon Technologies, Inc.
c. Meridian Systems; Prolog.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
PROJECT MANAGEMENT AND COORDINATION - 013100 - 8
d. Newforma, Inc.
e. Procore Technologies, Inc.
f. Viewpoint, Inc.; Viewpoint for Project Collaboration.
C. PDF Document Preparation: Where PDFs are required to be submitted to Owner, prepare as follows:
1. Assemble complete submittal package into a single indexed file incorporating submittal requirements of a single Specification Section and transmittal form with links enabling navigation to each item.
2. Name file with submittal number or other unique identifier, including revision identifier.
3. Certifications: Where digitally submitted certificates and certifications are required, provide a digital signature with digital certificate on where indicated.
1.9 PROJECT MEETINGS
A. General: Schedule a nd conduct meetings and conferences at Project site unless otherwise indicated.
1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Owner of scheduled meeting dates and ti mes a minimum of 10 working days prior to meeting.
2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.
3. Minutes: Entity responsible for conducting meeting will record significant discussions and agreements achieved. Distribut e the meeting minutes to everyone concerned, including Owner, within three days of the meeting.
B. Preconstruction Conference: Owner will schedule and conduct a preconstruction conference before starting construction, at a time conv enient to Owner, but no later than 15 days after execution of the Agreement.
1. Attendees: Authorized representatives of Owner and their consultants; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference. Participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Discuss items of significance that could aff ect progress, including the following:
a. Responsibilities and personnel assignments.
b. Tentative construction schedule.
c. Phasing.
d. Critical work sequencing and long lead items.
e. Designation of key personnel and their duties.
f. Lines of communications.
g. Use of web-based Project software.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
PROJECT MANAGEMENT AND COORDINATION - 013100 - 9
h. Procedures for processing field decisions and Change Orders. i. Procedures for RFIs.
j. Procedures for testing and inspecting.
k. Procedures for processing Applications for Payment.
l. Distribution of the Contract Documents.
m. Submittal procedures.
n. Preparation of Record Documents.
o. Use of the premises.
p. Work restrictions.
q. Working hours.
r. Procedures for moisture and mold control.
s. Construction waste management and recycling.
t. Parking availability.
u. Office, work, and storage areas.
v. Equipment deliveries and priorities.
w. First aid.
x. Security.
y. Progress cleaning.
3. Minutes: Entity responsibl e for conducting meeting will record and distribute meeting minutes.
C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity when required by other sections and when required for coordination with other construction.
1. Attendees: Installer and representatives of manufactur ers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise Owner of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:
a. Contract Documents.
b. Options.
c. Related RFIs.
d. Related Change Orders.
e. Purchases.
f. Deliveries.
g. Submittals.
h. Possible conflicts.
i. Compatibility requirements.
j. Time schedules.
k. Weather limitations.
l. Manufacturer's written instructions.
m. Warranty requirements.
n. Compatibility of materials.
o. Regulations of authorities having jurisdiction.
p. Testing and inspecting requirements.
q. Installation procedures.
r. Protection of adjacent work.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
PROJECT MANAGEMENT AND COORDINATION - 013100 - 10
s. Protection of construction and personnel.
3. Record signifi cant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.
5. Do not proceed with installation if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.
D. Project Closeout Conference: Schedule and conduct a project closeout conference, at a time convenient to Owner, but no later than 30 days prior to the scheduled date of Substantial Completion.
1. Conduct the conference to review requirements and responsibilities related to Project closeout.
2. Attendees: Authorized representatives of Owner and their consultants; Contractor and its superintendent; major subcontractors; suppliers; and o ther concerned parties shall attend the meeting. Participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
3. Agenda: Discuss items of significance that could affect or delay Project closeout, including the following:
a. Preparation of Record Documents.
b. Procedures required prior to inspection for Substantial Completion and for final inspection for acceptance.
c. Procedures for completing and archiving web -based Project software site data files.
d. Submittal of written warranties.
e. Requirements for preparing operations and maintenance data. f. Requirements for delivery of material samples, attic stock, and spare parts. g. Requirements for demonstration and training.
h. Preparation of Contractor's punch list.
i. Procedures for processing Applications for Payment at Substantial Completion and for final payment.
j. Submittal procedures.
k. Owner's partial occupancy requirements.
l. Installation of Owner's fixtures, and equipment.
4. Minutes: Entity conducting meeting will record and distribute meeting minutes.
E. Progress Meetings: Conduct progress meetings at regular intervals.
1. Coordinate dates of meetings with preparation of payment requests.
2. Attendees: In addition to representatives of Owner, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activ ities shall be represented at these meetings. All participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
PROJECT MANAGEMENT AND COORDINATION - 013100 - 11
3. Agenda: Review and correct or approve minutes of previous progress meeting.
Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.
a. Contractor's Construction Schedule: Review progress since the last meeting. Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's construction schedule.
Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether sched ule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.
1) Review schedule for next period.
b. Review present and future needs of each entity present, including the following:
1) Interface requirements.
2) Sequence of operations.
3) Status of submittals.
4) Deliveries.
5) Off-site fabrication.
6) Access.
7) Site use.
8) Quality and work standards.
9) Status of correction of deficient items.
10) Field observations.
11) Status of RFIs.
12) Status of Proposal Requests.
13) Pending changes.
14) Status of Change Orders.
15) Pending claims and disputes.
16) Documentation of information for payment requests.
4. Minutes: Entity responsible for conducting the meeting will record and distribute the meeting minutes to each party present and to parties requiring information. a. Schedule Updating: Revise Contractor's construction schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule with the report of each meeting.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 013100 (SAMPLE FORM TO FOLLOW)
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
PROJECT MANAGEMENT AND COORDINATION - 013100 - 12
SAMPLE FORM TO B E USED WITH PROJECT MANAGEMENT AND COORDINATION
PROCEDURES
END SAMPLE FORM TO BE USED WITH PROJECT MANAGEMENT AND COORDINATION
PROCEDURES
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
CONSTRUCTION PROGRESS DOCUMENTATION - 013200 - 1
SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:
1. Contractor's Construction Schedule.
2. Site condition reports.
3. Unusual event reports.
B. Related Requirements:
1. Section 011000 “Summary” for concurrent work by Owner under separate contracts.
2. Section 012900 "Payment Procedures” for requirements to prepare and process Applications for Payment.
3. Section 013100 "Project Management and Coordination" for construction coordination provisions.
4. Section 013300 “Submittal Procedures” for submittal schedule requirements and procedural requirements for submittals.
1.3 DEFINITIONS
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction Project. Activities included in a construction schedule consume time and resources.
1. Critical Activity: An activity on the critical path that must start and finish on the planned start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. Cost Loading: The allocation of the schedule of values (SOV) for completing an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
CONSTRUCTION PROGRESS DOCUMENTATION - 013200 - 2
C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on ac tivity relationships.
Network calculations determine when activities can be performed and the critical path of Project.
D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration (no float).
E. Event: The starting or ending point of an activity.
F. Float: The measure of leeway in starting and completing an activity.
1. Float time is not for the exclusive use or benefit of either Owner or Contractor, but is a jointly owned, expiring Project resource available to both parties as needed to meet schedule milestones and Contract completion date.
2. Free float is the amount of time an activity can be delayed without adversely affecting the start of the successor activity.
3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.
G. Resource Loading: The allocation of manpower and equipment necessary for completing an activity as scheduled.
1.4 INFORMATIONAL SUBMITTALS
A. Format for Submittals: Submit required submittals in the following format:
1. Working electronic copy of schedule file, where indicated.
2. PDF file emailed to Owner’s Project Manager.
B. Contractor's Construction Sched ule: Initial schedule, of size required to display entire schedule for entire construction period.
1. Submit a working digital copy of schedule, using software indicated, and labeled to comply with requirements for submittals.
C. Construction Schedule Updating Reports: Submit with Applications for Payment.
D. Site Condition Reports: Submit at time of discovery of differing conditions.
E. Unusual Event Reports: Submit at time of unusual event.
1.5 QUALITY ASSURANCE
A. Scheduling Qualifications: Experienced specialist in CPM scheduling and reporting, with capability of producing reports/ diagrams within 24 hours of Owner's request.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
CONSTRUCTION PROGRESS DOCUMENTATION - 013200 - 3
1.6 COORDINATION
A. Coordinate Contractor's Construction Schedule with SOV, list of subcontracts, submittal schedule, progress reports, payment requests, and required documents.
1. Time commitments for critical elements of the Work from entities involved.
2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.
1.7 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL
A. Computer Scheduling Software: Prepare schedules using current version of software specifically to manage construction schedules.
1. Use Scheduling component of Project s oftware specified in Section 013100 "Project Management and Coordination."
B. Time Frame: Extend schedule from date established for commencement of the Work to date of Substantial Completion.
1. Contract completion date shall not be changed by submission of a schedule, unless specifically authorized by Change Order.
C. Activities: Treat area as a separate numbered activity for each main element of the Work. Comply with the following:
1. Activity Duration: Define activities so no activity is longer than 20 days, unless specifically allowed by Owner.
2. Procurement Activities: Include procurement process activities for the followin g long lead items and major items, requiring a cycle of more than 60 days, as separate activities in schedule. Procurement cycle activities include, but are not limited to: submittals, approvals, purchasing, fabrication, and delivery.
3. Submittal Review Time : Include review and resubmittal times indicated in Section 013300 "Submittal Procedures" in schedule. Coordinate submittal review times in Contractor's Construction Schedule with submittal schedule.
4. Substantial Completion: Indicate completion in advance of date established for Substantial Completion and allow time for Owner’s administrative procedures necessary for certification of Substantial Completion.
5. Punch List and Final Completion: Include not more than 30 days for completion of punch list items and final completion.
D. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule and show how Work sequence is affected.
1. Products Ordered in Advance: Include a separate activity for each product.
Delivery dates indicated stipulate the earliest possible delivery date.
2. Work Restrictions: Show the effect of the following items on the schedule:
a. Coordination with existing construction.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
CONSTRUCTION PROGRESS DOCUMENTATION - 013200 - 4
3. Work Stages: Indicate important stages of construction for each major portion of the Work, including, but not limited to, the following:
a. Submittals.
b. Purchases.
c. Fabrication.
d. Deliveries.
e. Installation.
f. Adjusting.
g. Curing.
4. Construction Areas: Identify area of construction for each portion of the Work.
Indicate where each construction activity within a n area must be sequenced or integrated with other construction activities to provide for the following:
a. Permanent space enclosure.
b. Completion of mechanical installation.
c. Completion of electrical installation.
d. Substantial Completion.
E. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, Notice to Proceed, Substantial Completion, and final completion:
F. Upcoming Work Summary: Prepare summary report indicating activities scheduled to occur or commence prior to submittal of next schedule update. Summarize the following issues:
1. Unresolved issues.
2. Unanswered Requests for Information.
3. Rejected or unreturned submittals.
4. Notations on returned submittals.
5. Pending modifications affecting the Work and the Contract Time.
G. Distribution: Distribute copies of approved schedule to Owner, separate contractors, testing and inspecting agencies, and other parties identified by Contractor with a need- to-know schedule responsibility.
1. Post copies in Project meeting rooms and temporary field offices.
2. When revisions are made, distribute updated schedules to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in performance of construction activities.
1.8 GANTT-CHART SCHEDULE REQUIREMENTS
A. Gantt-Chart Schedule: Submit a comprehensive, fully developed, horizontal, Gantt - chart-type, Contractor's Construction Schedule within 30 days of date established for commencement of the Work.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
CONSTRUCTION PROGRESS DOCUMENTATION - 013200 - 5
1. Base schedule on the startup construction schedule and additional information received since the start of Project.
B. Preparation: Indicate each significant construction activity separately. Identify first workday of each week with a continuous vertical line.
1.9 CPM SCHEDULE REQUIREMENTS
A. General: Prepare network diagrams using AON (activity-on-node) format.
B. CPM Schedule: Prepare Contractor's Construction Schedule using a cost- and resource-loaded, time-scaled CPM network analysis diagram for the Work.
1. Develop network diagram in sufficient time to submit CPM schedule so it can be accepted for use no later than 60 days after date of Notice to Proceed. a. Failure to include any work item required for performance of this Contract shall not excuse Contractor from completing all work within applicable completion dates.
2. Use "one workday" as the unit of time for individual activities. Indicate nonworking days and holidays incorporated into the schedule to coordinate with the Contract Time.
C. CPM Schedule Preparation: Prepare a list of all activities required to complete the Work. Using the startup network diagram, prepare a skeleton network to identify probable critical paths.
1. Activities: Indicate the estimated time duration, sequence requirements, and relationship of each activity in relation to other activities. Include estimated time frames for the following activities:
a. Preparation and processing of submittals.
b. Mobilization and demobilization.
c. Purchase of materials.
d. Delivery.
e. Fabrication.
f. Installation.
g. Testing and inspection.
h. Punch list and final completion.
i. Activities occurring following final completion.
2. Critical Path Activities: Identify critical path activ ities, including those for interim completion dates. Scheduled start and completion dates shall be consistent with Contract milestone dates.
3. Processing: Process data to produce output data on a computer -drawn, time - scaled network. Revise data, reorganize a ctivity sequences, and reproduce as often as necessary to produce the CPM schedule within the limitations of the Contract Time.
4. Format: Mark the critical path. Locate the critical path near center of network; locate paths with most float near the edges.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
CONSTRUCTION PROGRESS DOCUMENTATION - 013200 - 6
D. Contract Modifications: For each proposed contract modification and concurrent with its submission, prepare a time -impact analysis using a network fragment to demonstrate the effect of the proposed change on the overall Project schedule.
E. Initial Issue of Sch edule: Prepare initial network diagram from a sorted activity list indicating straight "start-total float." Identify critical activities. Prepare tabulated reports showing the following:
1. Contractor or subcontractor and the Work or activity.
2. Description of activity.
3. Main events of activity.
4. Immediate preceding and succeeding activities.
5. Start dates.
6. Finish dates.
7. Activity duration in workdays.
8. Total float or slack time.
1.10 REPORTS
A. Site Condition Reports: Immediately on discovery of a difference between site conditions and the Contract Documents, prepare and submit a detailed report . Submit with a Request for Information. Include a detailed description of the differing conditions, together with recommendations for changing the Contract Documents.
B. Unusual Event Reports: When an event of an unusual and significant nature occurs at Project site, whether or not related directly to the Work, prepare and submit a special report. List chain of events, persons participating, responses by Contractor's personnel, evaluation of results or effects, and similar pertinent information. Advise Owner in advance when these events are known or predictable.
1. Submit unusual event reports directly to Owner within one day of an occurrence.
Distribute copies of report to parties affected by the occurrence.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 013200
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
SUBMITTAL PROCEDURES - 013300 - 1
SECTION 013300 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Spec. Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Submittal schedule requirements.
2. Administrative and procedural requirements for submittals.
B. Related Requirements:
1. Section 012900 "Payment Procedures" for submitting Applications for Payment and the schedule of values.
2. Section 013100 "Project Management and Coordination" f or submitting coordination drawings and subcontract list and for requirements for web -based Project software.
3. Section 013200 "Construction Progress Documentation" for submitting schedules and reports, including Contractor's construction schedule.
4. Section 014000 "Quality Requirements" for submitting test and inspection reports, and schedule of tests and inspections.
5. Section 017700 "Closeout Procedures" for submitting closeout submittals and maintenance material submittals.
6. Section 017823 "Operation and Maint enance Data" for submitting operation and maintenance manuals.
7. Section 017839 "Project Record Documents" for submitting record Drawings, record Specifications, and record Product Data.
1.3 DEFINITIONS
A. Action Submittals: Written and graphic information and physical samples that require Owner's responsive action. Action submittals are those submittals indicated in individual Specification Sections as "action submittals." B. Informational Submittals: Written and graphic information and physical samples that do not require Owner’s responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification Sections as "informational submittals."
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
SUBMITTAL PROCEDURES - 013300 - 2
1.4 SUBMITTAL SCHEDULE
A. Submittal Schedule: Submit, as an action submittal, a list of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delive ry when establishing dates.
Include additional time required for making corrections or revisions to submittals noted by Owner and additional time for handling and reviewing submittals required by those corrections.
1. Coordinate submittal schedule with list o f subcontracts, the schedule of values, and Contractor's construction schedule.
2. Initial Submittal: Submit concurrently with startup construction schedule. Include submittals required during the first 60 days of construction. List those submittals required to maintain orderly progress of the Work and those req uired early because of long lead time for manufacture or fabrication.
3. Final Submittal: Submit concurrently with the first complete submittal of Contractor's construction schedule.
a. Submit revised submittal schedule to reflect changes in current status and timing for submittals.
4. Format: Arrange the following information in a tabular format:
a. Scheduled date for first submittal.
b. Specification Section number and title.
c. Submittal Category: Action; informational.
d. Name of subcontractor.
e. Description of the Work covered.
f. Scheduled date for Owner's final release or approval. g. Scheduled dates for purchasing.
h. Scheduled date of fabrication.
i. Scheduled dates for installation.
j. Activity or event number.
1.5 SUBMITTAL FORMATS
A. Submittal Information: Include the following information in each submittal:
1. Project name.
2. Date.
3. Name of Architect.
4. Name of Owner’s Project Manager.
5. Name of Contractor.
6. Name of firm or entity that prepared submittal.
7. Names of subcontractor, manufacturer, and supplier.
8. Unique submittal number, including revision identifier. Include Spe cification Section number with sequential alphanumeric identifier; and alphanumeric suffix for resubmittals.
9. Category and type of submittal.
10. Submittal purpose and description.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
SUBMITTAL PROCEDURES - 013300 - 3
11. Number and title of Specification Section, with paragraph number and generic name for each of multiple items.
12. Drawing number and detail references, as appropriate.
13. Location(s) where product is to be installed, as appropriate.
14. Other necessary identification.
15. Remarks.
16. Signature of transmitter.
B. Options: Identify options requiring selection by Owner.
C. Deviations and Additional Information: On each submittal, clearly indicate deviations from requirements in the Contract Documents, including minor variations and limitations; include relevant additional information and revisions, other than th ose requested by Owner on previous submittals. Indicate by highlighting on each submittal or noting on attached separate sheet.
D. PDF Submittals: Prepare submittals as PDF package, incorporating complete information into each PDF file. Name PDF file with submittal number.
1.6 SUBMITTAL PROCEDURES
A. Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification Sections.
1. Email: Prepare submittals as a 0PDF and transmit to Owner via email. Include PDF transmittal form. Identify submittal type in email subject line. a. Owner will return annotated file. Annotate and retain one copy of file as a digital Project Record Document file.
B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Submit all submittal items required for each Specification Section concurrently .
Partial submittals are prohibited. Submit action submittals and informational submittals required by the same Specification Section as separate packages under separate transmittals.
3. Coordinate transmittal of submittal s for related parts of the Work specified in different Sections so processing will not be delayed because of need to review submittals concurrently for coordination.
a. Owner reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
C. Processing Time: Allow time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Owner’s receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
SUBMITTAL PROCEDURES - 013300 - 4
1. Initial Review: Allow 15 days for initial review of each submittal. Allow additional time if coordination with subsequent submitt als is required. Owner will advise Contractor when a submittal being processed must be delayed for coordination.
2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Resubmittal Review: Allow 15 days for review of each resubmittal.
4. Sequential Review: Where sequential review of submittals by consultants, Owner, or other parties is indicated, allow 21 days for initial submittal review.
D. Resubmittals: Make resubmittals in same form and number of copies as initial.
1. Note date and content of previous submittal.
2. Note date and content in label or title block and clearly indicate revision extent.
3. Resubmit submittals until they are marked with approval notation from Owner's action stamp.
E. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.
F. Use for Construction: Retain complete copies of submittals on Project site. Use only final action submittals that are marked with approval notation from Owner's stamp.
1.7 SUBMITTAL REQUIREMENTS
A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepar ed for submittal because standard published data are unsuitable for use, submit Shop Drawings, not Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's catalog cuts.
b. Manufacturer's product specifications.
c. Standard color charts.
d. Statement of compliance with specified referenced standards. e. Testing by recognized testing agency.
f. Application of testing agency labels and seals.
g. Notation of coordination requirements.
h. Availability and delivery time information.
4. For equipment, include the following in addition to the above, as applicable:
a. Wiring diagrams that show factory-installed wiring.
b. Printed performance curves.
c. Operational range diagrams.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
SUBMITTAL PROCEDURES - 013300 - 5
5. Submit Product Data before Shop Drawings, and before or concurrent with Samples.
B. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data. Submittal based on Architect's digital data drawing files is permitted.
1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:
a. Identification of products.
b. Schedules.
c. Compliance with specified standards.
d. Notation of coordination requirements.
e. Notation of dimensions established by field measurement. f. Relationship and attachment to adjoining construction clearly indicated. g. Seal and signature of professional engineer if specified.
C. Product Schedule: As required in individual Specification Sections, prepare a written summary indicating types of products required for the Work and their intended location.
Include the following information in tabular form:
1. Type of product. Include unique identifier for each product indicated in the Contract Documents or assigned by Contractor if none is indicated.
2. Manufacturer and product name, and model number if applicable.
D. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, contact information of Owner, and other information specified.
E. Design Data: Prepare and submit written and graphic information indicating compliance with indicated performance and design criteria in individual Specification Sections.
Include list of assumptions and summary of loads. Include load diagrams if applicable.
Provide name and version of software, if any, used for calculations. Number each page of submittal.
F. Certificates:
1. Certificates and Certifications Submittals: Submit a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an individual authorized to sign document s on behalf of that entity. Provide a notarized signature where indicated.
2. Installer Certificates: Submit written statements on manufac turer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.
3. Manufacturer Certificates: Submit written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents. Include evidence of manufacturing experience.
4. Material Certificates: Submit written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
SUBMITTAL PROCEDURES - 013300 - 6
5. Product Certificates: Submit written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.
1.8 CONTRACTOR'S REVIEW
A. Action Submittals and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and fo r compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to Owner.
B. Contractor's Approval: Indicate Contractor's approval for each submittal with a uniform approval stamp or indication in web-based Project software. Include name of reviewer, date of Contractor's approval, and statement certifying that submittal has be en reviewed, checked, and approved for compliance with the Contract Documents.
1. Owner will not review submittals received from Contractor that do not have Contractor's review and approval.
1.9 OWNER’S REVIEW
A. Action Submittals: Owner will review each submittal, indicate corrections or revisions required, and return it.
1. PDF Submittals: Owner will indicate, via markup on each submittal:
a. No Exceptions Taken
b. Make Corrections Noted
c. Revise and Resubmit
d. Rejected
B. Informational Submittals: Owner will review each submittal and will not return it or will return it if it does not comply with requirements. Owner will forward each submittal to appropriate party.
C. Incomplete submittals are unacceptable, will be considered nonresponsive, and will be returned for resubmittal without review.
D. Owner will only return with review submittals received from the Contractor.
E. Submittals not required in the Contract Documents: returned by Owner with no action.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used
END OF SECTION 013300
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
QUALITY REQUIREMENTS - 014000 - 1
SECTION 014000 - QUALITY REQUIREMENTS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Spec. Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for quality assurance and quality control.
B. Testing and inspection services are required to verify compliance with requ irements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the Contract Document requirements.
1. Specific quality -assurance and quality -control requirements for individual work results are specified in their respective Specification Sections. Requirements in individual Sections may also cover production of standard products.
2. Specified inspections, and related actions do not limit Contractor's other quality - assurance and quality -control procedures that facilitate compliance with the Contract Document requirements.
3. Specific inspection requirements are not specified in this Section.
1.3 DEFINITIONS
A. Experienced: When used with an entity or individual, "experienced" unless otherwise further described means having successfu lly completed a minimum of five previous projects similar in nature, size, and extent to this Project; being familiar with special requirements indicated; and having complied with requirements of authorities having jurisdiction.
B. Field Quality-Control Tests: Inspections that are performed on-site for installation of the Work and for completed Work.
C. Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an employee, Subcontractor, or Sub -subcontractor, to perform a particular cons truction operation, including installation, erection, application, assembly, and similar operations.
1. Use of trade-specific terminology in referring to a trade or entity does not require that certain construction activities be performed by accredited or uni onized individuals, or that requirements specified apply exclusively to specific trade(s).
D. Source Quality-Control Tests: Tests and inspections that are performed at the source; for example, plant, mill, factory, or shop.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
QUALITY REQUIREMENTS - 014000 - 2
E. Testing Agency: An entity engaged to perform specific tests, inspections, or both.
Testing laboratory shall mean the same as testing agency.
F. Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work to guard against defects and deficiencies and substantiate that proposed construction will comply with requirements.
G. Quality-Control Services: Tests, inspections , procedures, and related actions during and after execution of the Work to evaluate that actual products incorporated into the Work and completed construction comply with requirements. Contractor's quality - control services do not include contract administ ration activities performed by Architect or Construction Manager.
1.4 CONFLICTING REQUIREMENTS
A. Conflicting Standards and Other Requirements: If compliance with two or more standards or requirements are specified and the standards or requirements establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement. Refer conflicting requirements that are different, but apparently equal, to Owner for direction before proceeding.
B. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to Architect for a decision before proceeding.
1.5 ACTION SUBMITTALS
A. Delegated-Design Services Submittal: In addition to Shop Drawings, Product Data, and other required submittals, submit a statement signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certi fied by a design professional, indicating that the products and systems are in compliance with performance and design criteria indicated. Include list of codes, loads, and other factors used in performing these services.
1.6 INFORMATIONAL SUBMITTALS
A. Contractor's Quality -Control Plan: For quality -assurance and quality -control activities and responsibilities.
B. Qualification Data: For Contractor's quality-control personnel.
C. Reports: Prepare and submit certified written reports and documents as specified.
D. Permits, Licenses, and Certificates: For Owner's record, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
QUALITY REQUIREMENTS - 014000 - 3
receipts for fee payments, judgments, correspondence, records, and similar documents established for compliance with standards and regulations bearing on performance of the Work.
1.7 CONTRACTOR'S QUALITY-CONTROL PLAN
A. Quality-Control Plan, General: Submit quality -control plan within 10 days of Notice to Proceed, and not less than five days prior to commencement of work. Submit in format acceptable to Architect. Identify personnel, procedures, controls, in structions, records, and forms to be used to carry out Contractor's quality -assurance and quality -control responsibilities. Coordinate with Contractor's Construction Schedule.
B. Quality-Control Personnel Qualifications: Engage qualified personnel trained and experienced in managing and executing quality -assurance and quality -control procedures similar in nature and extent to those required for Project.
1. Project quality-control manager may also serve as Project superintendent.
C. Submittal Procedure: Describe proc edures for ensuring compliance with requirements through review and management of submittal process. Indicate qualifications of personnel responsible for submittal review.
1.8 REPORTS AND DOCUMENTS
A. Factory-Authorized Service Representative's Reports: Prepare written information documenting manufactur er's factory -authorized service representative's tests and inspections specified in other Sections. Include the following:
1. Name, address, telephone number, and email address of factory -authorized service representative making report.
2. Statement that equipment complies with requirements.
3. Results of operational and other tests and a statement of whether observed performance complies with requirements.
4. Statement whether conditions, products, and installation will affect warranty.
5. Other required items indicated in individual Specification Sections.
1.9 QUALITY ASSURANCE
A. General: Qualifications paragraphs in this article establish the minimum qualification levels required; individual Specification Sections specify additional requirements.
B. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in -service performance, as well as sufficient production capacity to produce required units. As applicable, procure products from manufacturers able to meet qualification requirements, warranty requirements, and technical or factory -authorized service representative requirements.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
QUALITY REQUIREMENTS - 014000 - 4
C. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in -service performance, as well as sufficient production capacity to produce required units.
D. Installer Qualifications: A firm or individual experienced in installing, erecting, applying, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance.
E. Manufacturer's Technical Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to observe and inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this Project.
F. Factory-Authorized Service Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this Project.
1.10 QUALITY CONTROL
A. Coordination: Coordinate sequence of activities to accommodate required qua lity- assurance and quality-control services with a minimum of delay and to avoid necessity of removing and replacing construction to accommodate inspection.
1. Schedule times for inspections and similar activities.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 TEST AND INSPECTION LOG
A. Inspection Log: Prepare a record of inspections. Including:
1. Date inspection was conducted.
2. Description of the Work inspected.
3. Date inspection results were transmitted to Architect.
4. Identification of inspector conducting inspection.
B. Maintain log at Project site. Post changes and revisions a s they occur. Provide access to test and inspection log for Architect's, and Construction Manager's reference during normal working hours.
1. Submit log at Project closeout as part of Project Record Documents.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
QUALITY REQUIREMENTS - 014000 - 5
3.2 REPAIR AND PROTECTION
A. General: On completion of i nspection and similar services, repair damaged construction and restore substrates and finishes.
1. Provide materials and comply with installation requirements specified in other Specification Sections or matching existing substrates and finishes. Restore patched areas and extend restoration into adjoining areas with durable seams that are as invisible as possible. Comply with the Contract Document requirements for cutting and patching in Section 017300 "Execution." B. Protect construction exposed by or for quality-control service activities.
C. Repair and protection are Contractor's responsibility, regardless of the assignment of responsibility for quality-control services.
END OF SECTION 014000
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
QUALITY REQUIREMENTS - 014000 - 6
(THIS PAGE INTENTIONALLY LEFT BLANK)
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
REFERENCES - 014200 - 1
SECTION 014200 - REFERENCES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Spec. Sections, apply to this Section.
1.2 DEFINITIONS
A. General: Basic Contract definitions are included in the Conditions of the Contract.
B. "Approved": When used to convey Architect's action on Contractor's submittals, applications, and requests, "approved" is limited to Architect's duties and responsibilities as stated in the Conditions of the Contract.
C. "Directed": A command or instruction by Architect. Other terms including "requested," "authorized," "selected," "required," and "permitted" have the same meaning as "directed."
D. "Indicated": Requirements expressed by graphic representations or in written form on Drawings, in Specifications, and in other Contract Documents. Other terms including "shown," "noted," "scheduled," and "specified" have the same meaning as "indicated." E. "Regulations": Laws, ordinances, statutes, and lawful orders issued by authorities having jurisdiction, and rules, conventions, and agreements within the construction industry that control performance of the Work.
F. "Furnish": Supply and deliver to Project site, ready for unloading, unpacking, assembly, installation, and similar operations.
G. "Install": Unload, temporarily store, unpack, assemble, erect, place, anchor, apply, work to dimension, finish, cure, protect, clean, and similar operations at Project site.
H. "Provide": Furnish and install, complete and ready for the intended use.
I. "Project Site ": Space available for performing construction activities. The extent of Project site is shown on Drawings and may or may not be identical with the description of the land on which Project is to be built.
1.3 INDUSTRY STANDARDS
A. Applicability of Standards: Unle ss the Contract Documents include more stringent requirements, applicable construction industry standards have the same force and effect as if bound or copied directly into the Contract Documents to the extent referenced. Such standards are made a part of the Contract Documents by reference.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
REFERENCES - 014200 - 2
B. Publication Dates: Comply with standards in effect as of date of the Contract Documents unless otherwise indicated.
C. Copies of Standards: Each entity engaged in construction on Project should be familiar with industry standards applicable to its construction activity. Copies of applicable standards are not bound with the Contract Documents.
1. Where copies of standards are needed to perform a required construction activity, obtain copies directly from publication source.
1.4 ABBREVIATIONS AND ACRONYMS
A. Industry Organizations: Where abbreviations and acr onyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities indicated in Gale's "Encyclopedia of Associations: National Organizations of the U.S." or in Columbia Books' "National Trade & Professional Associations of the U.S." B. Industry Organizations: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list. This information is subject to change and is believed to be accurate as of the date of the Contract Documents.
1. AABC - Associated Air Balance Council; www.aabc.com.
2. AAMA - American Architectural Manufacturers Association; www.aamanet.org.
3. AAPFCO - Association of American Plant Food Control Officials; www.aapfco.org.
4. AASHTO - American Association of State Highway and Transporta tion Officials; www.transportation.org.
5. AATCC - American Association of Textile Chemists and Colorists; www.aatcc.org.
6. ABMA - American Bearing Manufacturers Association;
www.americanbearings.org.
7. ABMA - American Boiler Manufacturers Association; www.abma.com.
8. ACI - American Concrete Institute; (Formerly: ACI International); www.concrete.org
9. ACPA - American Concrete Pipe Association; www.concrete-pipe.org.
10. AEIC - Association of Edison Illuminating Companies, Inc. (The); www.aeic.org.
11. AF&PA - American Forest & Paper Association; www.afandpa.org.
12. AGA - American Gas Association; www.aga.org.
13. AHAM - Association of Home Appliance Manufacturers; www.aham.org.
14. AHRI - Air-Conditioning, Heating, and Refrigeration Institute (The); www.ahrinet.org.
15. AI - Asphalt Institute; www.asphaltinstitute.org.
16. AIA - American Institute of Architects (The); www.aia.org.
17. AISC - American Institute of Steel Construction; www.aisc.org.
18. AISI - American Iron and Steel Institute; www.steel.org.
19. AITC - American Institute of Timber Construction; www.aitc-glulam.org.
20. AMCA - Air Movement and Control Association International, Inc.; www.amca.org.
21. ANSI - American National Standards Institute; www.ansi.org.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
REFERENCES - 014200 - 3
22. AOSA - Association of Official Seed Analysts, Inc.; www.aosaseed.com.
23. APA - APA - The Engineered Wood Association; www.apawood.org.
24. APA - Architectural Precast Association; www.archprecast.org.
25. API - American Petroleum Institute; www.api.org.
26. ARI - Air-Conditioning & Refrigeration Institute; (See AHRI).
27. ARI - American Refrigeration Institute; (See AHRI).
28. ARMA - Asphalt Roofing Manufacturers Association; www.asphaltroofing.org.
29. ASCE - American Society of Civil Engineers; www.asce.org.
30. ASCE/SEI - American Society of Civil Engineers/Structural Engineering Institute; (See ASCE).
31. ASHRAE - American Society of Heating, Refrigerating and Air -Conditioning Engineers; www.ashrae.org.
32. ASME - ASME International; (American Society of Mechanical Engineers); www.asme.org.
33. ASSE - American Society of Safety Engineers (The); www.asse.org.
34. ASSE - American Society of Sanitary Engineering; www.asse-plumbing.org.
35. ASTM - ASTM International; www.astm.org.
36. ATIS - Alliance for Telecommunications Industry Solutions; www.atis.org.
37. AWEA - American Wind Energy Association; www.awea.org.
38. AWI - Architectural Woodwork Institute; www.awinet.org.
39. AWMAC - Architectural Woodwork Manufacturers Association of Canada; www.awmac.com.
40. AWPA - American Wood Protection Association; www.awpa.com.
41. AWS - American Welding Society; www.aws.org.
42. AWWA - American Water Works Association; www.awwa.org.
43. BHMA - Builders Hardware Manufacturers Association; www.buildershardware.com.
44. BIA - Brick Industry Association (The); www.gobrick.com.
45. BICSI - BICSI, Inc.; www.bicsi.org.
46. BIFMA - BIFMA International; (Business and Institutional Furniture Manufacturer's Association); www.bifma.org.
47. BISSC - Baking Industry Sanitation Standards Committee; www.bissc.org.
48. CDA - Copper Development Association; www.copper.org.
49. CE - Conformite Europeenne; http://ec.europa.eu/growth/single-market/ce- marking/
50. CEA - Canadian Electricity Association; www.electricity.ca.
51. CEA - Consumer Electronics Association; www.ce.org.
52. CFFA - Chemical Fabrics and Film Association, Inc.; www.chemicalfabricsandfilm.com.
53. CFSEI - Cold-Formed Steel Engineers Institute; www.cfsei.org.
54. CGA - Compressed Gas Association; www.cganet.com.
55. CIMA - Cellulose Insulation Manufacturers Association; www.cellulose.org.
56. CISCA - Ceilings & Interior Systems Construction Association; www.cisca.org.
57. CISPI - Cast Iron Soil Pipe Institute; www.cispi.org.
58. CLFMI - Chain Link Fence Manufacturers Institute; www.chainlinkinfo.org.
59. CPA - Composite Panel Association; www.pbmdf.com.
60. CRI - Carpet and Rug Institute (The); www.carpet-rug.org.
61. CRRC - Cool Roof Rating Council; www.coolroofs.org.
62. CRSI - Concrete Reinforcing Steel Institute; www.crsi.org.
63. CSA - CSA Group; www.csa.ca.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
REFERENCES - 014200 - 4
64. CSA - CSA International; (Formerly: IAS - International Approval Services); www.csa-international.org.
65. CSI - Construction Specifications Institute (The); www.csinet.org.
66. CSSB - Cedar Shake & Shingle Bureau; www.cedarbureau.org.
67. CTI - Cooling Technology Institute; (Formerly: Cooling Tower Institute); www.cti.org.
68. CWC - Composite Wood Council; (See CPA).
69. DASMA - Door and Access Systems Manufacturers Association; www.dasma.com.
70. DHI - Door and Hardware Institute; www.dhi.org.
71. ECA - Electronic Components Association; (See ECIA).
72. ECAMA - Electronic Components Assemblies & Materials Association; (See ECIA).
73. ECIA - Electronic Components Industry Association; www.eciaonline.org.
74. EIA - Electronic Industries Alliance; (See TIA).
75. EIMA - EIFS Industry Members Association; www.eima.com.
76. EJMA - Expansion Joint Manufacturers Association, Inc.; www.ejma.org.
77. ESD - ESD Association; (Electrostatic Discharge Association); www.esda.org .
78. ESTA - Entertainment Services and Technology Association; (See PLASA).
79. ETL - Intertek (See Intertek); www.intertek.com.
80. EVO - Efficiency Valuation Organization; www.evo-world.org.
81. FCI - Fluid Controls Institute; www.fluidcontrolsinstitute.org.
82. FM Approvals - FM Approvals LLC; www.fmglobal.com.
83. FM Global - FM Global; (Formerly: FMG - FM Global); www.fmglobal.com.
84. FSA - Fluid Sealing Association; www.fluidsealing.com.
85. FSC - Forest Stewardship Council U.S.; www.fscus.org.
86. GA - Gypsum Association; www.gypsum.org.
87. GANA - Glass Association of North America; www.glasswebsite.com.
88. GS - Green Seal; www.greenseal.org.
89. HI - Hydraulic Institute; www.pumps.org.
90. HI/GAMA - Hydronics Institute/Gas Appliance Manufacturers Associ ation; (See AHRI).
91. HMMA - Hollow Metal Manufacturers Association; (See NAAMM).
92. HPVA - Hardwood Plywood & Veneer Association; www.hpva.org.
93. HPW - H. P. White Laboratory, Inc.; www.hpwhite.com.
94. IAPSC- International Association of Professional Security Consultants; www.iapsc.org.
95. IAS - International Accreditation Service; www.iasonline.org.
96. IAS - International Approval Services; (See CSA).
97. ICBO - International Conference of Building Officials; (See ICC).
98. ICC - International Code Council; www.iccsafe.org.
99. ICEA - Insulated Cable Engineers Association, Inc.; www.icea.net. 100. ICPA - International Cast Polymer Alliance; www.icpa-hq.org. 101. ICRI - International Concrete Repair Institute, Inc.; www.icri.org. 102. IEC - International Electrotechnical Commission; www.iec.ch. 103. IEEE - Institute of Electrical and Electronics Engineers, Inc. (The); www.ieee.org. 104. IES - Illuminating Engineering Society; (Formerly: Illuminating Engineering Society of North America); www.ies.org.
105. IESNA - Illuminating Engineering Society of North America; (See IES). 106. IEST - Institute of Environmental Sciences and Technology; www.iest.org. 107. IGMA - Insulating Glass Manufacturers Alliance; www.igmaonline.org.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
REFERENCES - 014200 - 5
108. IGSHPA - International Ground Source Heat Pump Association; www.igshpa.okstate.edu.
109. ILI - Indiana Limestone Institute of America, Inc.; www.iliai.com. 110. Intertek - Intertek Group; (Formerly: ETL SEMCO; Intertek Testing Service NA); www.intertek.com.
111. ISA - International Society of Automation (The); (Formerly: Instrumentation, Systems, and Automation Society); www.isa.org.
112. ISAS - Instrumentation, Systems, and Automation Society (The); (See ISA). 113. ISFA - International Su rface Fabricators Association; (Formerly: International Solid Surface Fabricators Association); www.isfanow.org. 114. ISO - International Organization for Standardization; www.iso.org. 115. ISSFA - International Solid Surface Fabricators Association; (See ISFA). 116. ITU - International Telecommunication Union; www.itu.int/home. 117. KCMA - Kitchen Cabinet Manufacturers Association; www.kcma.org. 118. LMA - Laminating Materials Association; (See CPA). 119. LPI - Lightning Protection Institute; www.lightning.org. 120. MBMA - Metal Building Manufacturers Association; www.mbma.com. 121. MCA - Metal Construction Association; www.metalconstruction.org. 122. MFMA - Maple Flooring Manufacturers Association, Inc.; www.maplefloor.org. 123. MFMA - Metal Framing Manufacturers Association, Inc.; www.metalframingmfg.org.
124. MHIA - Material Handling Industry of America; www.mhia.org. 125. MIA - Marble Institute of America; www.marble-institute.com. 126. MMPA - Moulding & Millwork Producers Association; www.wmmpa.com. 127. MPI - Master Painters Institute; www.paintinfo.com. 128. MSS - Manufacturers Standardization Society of The Valve and Fittings Industry Inc.; www.mss-hq.org.
129. NAAMM - National Association of Architectural Metal Manufacturers; www.naamm.org.
130. NACE - NACE International; (National Association of Corrosion Engineers International); www.nace.org.
131. NADCA - National Air Duct Cleaners Association; www.nadca.com. 132. NAIMA - North American Insulation Manufacturers Association; www.naima.org. 133. NBGQA - National Building Granite Quarries Association, Inc.; www.nbgqa.com. 134. NBI - New Buildings Institute; www.newbuildings.org. 135. NCAA - National Collegiate Athletic Association (The); www.ncaa.org. 136. NCMA - National Concrete Masonry Association; www.ncma.org. 137. NEBB - National Environmental Balancing Bureau; www.nebb.org. 138. NECA - National Electrical Contractors Association; www.necanet.org. 139. NeLMA - Northeastern Lumber Manufacturers Association; www.nelma.org. 140. NEMA - National Electrical Manufacturers Association; www.nema.org. 141. NETA - InterNational Electrical Testing Association; www.netaworld.org. 142. NFPA - National Fire Protection Association; www.nfpa.org. 143. NFPA - NFPA International; (See NFPA).
144. NFRC - National Fenestration Rating Council; www.nfrc.org. 145. NHLA - National Hardwood Lumber Association; www.nhla.com. 146. NLGA - National Lumber Grades Authority; www.nlga.org. 147. NOFMA - National Oak Flooring Manufacturers Association; (See NWFA). 148. NOMMA - National Ornamental & Miscellaneous Metals Association; www.nomma.org.
149. NRCA - National Roofing Contractors Association; www.nrca.net.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
REFERENCES - 014200 - 6
150. NRMCA - National Ready Mixed Concrete Association; www.nrmca.org. 151. NSF - NSF International; www.nsf.org.
152. NSPE - National Society of Professional Engineers; www.nspe.org. 153. NSSGA - National Stone, Sand & Gravel Association; www.nssga.org. 154. NTMA - National Terrazzo & Mosaic Association, Inc. (The); www.ntma.com. 155. NWFA - National Wood Flooring Association; www.nwfa.org. 156. PCI - Precast/Prestressed Concrete Institute; www.pci.org. 157. PDI - Plumbing & Drainage Institute; www.pdionline.org. 158. PLASA - PLASA; (Formerly: ESTA - Entertainment Services and Technology Association); http://www.plasa.org.
159. RCSC - Research Council on Structural Connections; www.boltcouncil.org. 160. RFCI - Resilient Floor Covering Institute; www.rfci.com. 161. RIS - Redwood Inspection Service; www.redwoodinspection.com. 162. SAE - SAE International; www.sae.org.
163. SCTE - Society of Cable Telecommunications Engineers; www.scte.org. 164. SDI - Steel Deck Institute; www.sdi.org.
165. SDI - Steel Door Institute; www.steeldoor.org.
166. SEFA - Scientific Equipment and Furniture Association (The); www.sefalabs.com.
167. SEI/ASCE - Structural Engineering Institute/American Society of Civil Engineers; (See ASCE).
168. SIA - Security Industry Association; www.siaonline.org. 169. SJI - Steel Joist Institute; www.steeljoist.org.
170. SMA - Screen Manufacturers Association; www.smainfo.org. 171. SMACNA - Sheet Metal and Air Conditioning Contractors' National Association; www.smacna.org.
172. SPFA - Spray Polyurethane Foam Alliance; www.sprayfoam.org. 173. SPIB - Southern Pine Inspection Bureau; www.spib.org. 174. SPRI - Single Ply Roofing Industry; www.spri.org.
175. SRCC - Solar Rating & Certification Corporation; www.solar-rating.org. 176. SSINA - Specialty Steel Industry of North America; www.ssina.com. 177. SSPC - SSPC: The Society for Protective Coatings; www.sspc.org. 178. STI - Steel Tank Institute; www.steeltank.com.
179. SWI - Steel Window Institute; www.steelwindows.com. 180. SWPA - Submersible Wastewater Pump Association; www.swpa.org. 181. TCA - Tilt-Up Concrete Association; www.tilt-up.org. 182. TCNA - Tile Council of North America, Inc.; www.tileusa.com. 183. TEMA - Tubular Exchanger Manufacturers Association, Inc.; www.tema.org. 184. TIA - Telecommunications Industry Association (The); (Formerly: TIA/EIA - Telecommunications Industry Association/Electronic Industries Alliance); www.tiaonline.org.
185. TIA/EIA - Telecommunications Industry Association/Electronic Industries Alliance; (See TIA).
186. TMS - The Masonry Society; www.masonrysociety.org. 187. TPI - Truss Plate Institute; www.tpinst.org.
188. TPI - Turfgrass Producers International; www.turfgrasssod.org. 189. TRI - Tile Roofing Institute; www.tileroofing.org. 190. UL - Underwriters Laboratories Inc.; http://www.ul.com. 191. UNI - Uni-Bell PVC Pipe Association; www.uni-bell.org. 192. USGBC - U.S. Green Building Council; www.usgbc.org. 193. USITT - United States Institute for Theatre Technology, Inc.; www.usitt.org.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
REFERENCES - 014200 - 7
194. WA - Wallcoverings Association; www.wallcoverings.org 195. WASTEC - Waste Equipment Technology Association; www.wastec.org. 196. WCLIB - West Coast Lumber Inspection Bureau; www.wclib.org. 197. WCMA - Window Covering Manufacturers Association; www.wcmanet.org. 198. WDMA - Window & Door Manufacturers Association; www.wdma.com. 199. WI - Woodwork Institute; www.wicnet.org.
200. WSRCA - Western States Roofing Contractors Association; www.wsrca.com. 201. WWPA - Western Wood Products Association; www.wwpa.org.
C. Code Agencies: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list. This information is believed to be accurate as of the date of t he Contract Documents.
1. IAPMO - International Association of Plumbing and Mechanical Officials; www.iapmo.org.
2. ICC - International Code Council; www.iccsafe.org.
3. ICC-ES - ICC Evaluation Service, LLC; www.icc-es.org.
D. Federal Government Agencies: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list. Information is subject to change and is up to d ate as of the date of the Contract Documents.
1. COE - Army Corps of Engineers; www.usace.army.mil.
2. CPSC - Consumer Product Safety Commission; www.cpsc.gov.
3. DOC - Department of Commerce; National Institute of Standards and Technology; www.nist.gov.
4. DOD - Department of Defense; www.quicksearch.dla.mil.
5. DOE - Department of Energy; www.energy.gov.
6. EPA - Environmental Protection Agency; www.epa.gov.
7. FAA - Federal Aviation Administration; www.faa.gov.
8. FG - Federal Government Publications; www.gpo.gov/fdsys.
9. GSA - General Services Administration; www.gsa.gov.
10. HUD - Department of Housing and Urban Development; www.hud.gov.
11. LBL - Lawrence Berkeley National Laboratory; Environmental Energy Technologies Division; www.eetd.lbl.gov.
12. OSHA - Occupational Safety & Health Administration; www.osha.gov.
13. SD - Department of State; www.state.gov.
14. TRB - Transportation Research Board; National Cooperative Highway Research Program; The National Academies; www.trb.org.
15. USDA - Department of Agriculture; Agriculture Research Service; U.S. Salinity Laboratory; www.ars.usda.gov.
16. USDA - Department of Agriculture; Rural Utilities Service; www.usda.gov.
17. USDOJ - Department of Justice; Office of Justice Programs; National Institute of Justice; www.ojp.usdoj.gov.
18. USP - U.S. Pharmacopeial Convention; www.usp.org.
19. USPS - United States Postal Service; www.usps.com.
E. Standards and Regulations: W here abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
REFERENCES - 014200 - 8
the standards and regulations in the following list. This information is subject to change and is believed to be accurate as of the date of the Contract Documents.
1. CFR - Code of Federal Regulations; Available from Gover nment Printing Office; www.gpo.gov/fdsys.
2. DOD - Department of Defense; Military Specifications and Standards; Available from DLA Document Services; www.quicksearch.dla.mil.
3. DSCC - Defense Supply Center Columbus; (See FS).
4. FED-STD - Federal Standard; (See FS).
5. FS - Federal Specification; Available from DLA Document Services; www.quicksearch.dla.mil.
a. Available from Defense Standardization Program; www.dsp.dla.mil. b. Available from General Services Administration; www.gsa.gov. c. Available from National Institute of Building Sciences/Whole Building Design Guide; www.wbdg.org/ccb.
6. MILSPEC - Military Specification and Standards; (See DOD).
7. USAB - United States Access Board; www.access-board.gov.
8. USATBCB - U.S. Architectural & Transportation Barriers Compliance Board; (See USAB).
F. State Government Agencies: Where abbreviations and acrony ms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list. This information is subject to change and is believed to be accurate as of the date of the Contract Documents.
1. CBHF; State of California; Department of Consumer Affairs; Bureau of Electronic and Appliance Repair, Home Furnishings and Thermal Insulation; www.bearhfti.ca.gov.
2. CCR; California Code of Regulations; Office of Administrative Law; California Title 24 Energy Code; www.calregs.com.
3. CDHS; California Department of Health Services; (See CDPH).
4. CDPH; Calif ornia Department of Public Health; Indoor Air Quality Program; www.cal-iaq.org.
5. CPUC; California Public Utilities Commission; www.cpuc.ca.gov.
6. SMAQMD; S acramento Metro Air Qual ity Management District; www.airquality.org.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 014200
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
PRODUCT REQUIREMENTS - 016000 - 1
SECTION 016000 - PRODUCT REQUIREMENTS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Spec. Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for selection of products for use in Project; product delivery, storage, and handling; manufacturers' st andard warranties on products; special warranties; and comparable products.
B. Related Requirements:
1. Section 012500 "Substitution Procedures" for requests for substitutions.
2. Section 014200 "References" for applicable industry standards for products specified.
3. Section 017700 “Closeout Procedures” for information on submittal times.
1.3 DEFINITIONS
A. Products: Items obtained for incorporating into the Work, whether purchased for Project or taken from previously purchased stock. The term "product" i ncludes the terms "material," "equipment," "system," and terms of similar intent.
1. Named Products: Items identified by manufacturer's product name, including make or model number or other designation shown or listed in manufacturer's published product literature that is current as of date of the Contract Documents.
2. New Products: Items that have not previously been incorporated into another project or facility. Products salvaged or recycled from other projects are not considered new products.
3. Comparable Product: Product that is demonstrated and approved by Architect through submittal process to have the indicated qualities related to type, function, dimension, in -service performance, physical properties, appearance, and other characteristics that equal or exceed those of specified product.
B. Basis-of-Design Product Specification: A specification in which a single manufacturer's product is named and accompanied by the words "basis -of-design product," including make or model number or other designation. In addition to the basis-of-design product description, product attributes and characteristics may be listed to establish the significant qualities related to type, function, in- service performance and physical properties, weight, dimension, durability, visual charac teristics, and other special EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
PRODUCT REQUIREMENTS - 016000 - 2
features and requirements for purposes of evaluating comparable products of additional manufacturers named in the specification.
C. Subject to Compliance with Requirements: Where the phrase "Subject to compliance with requirements " introduces a product selection procedure in an individual Specification Section, provide products qualified under the specified product procedure. In the event that a named product or product by a named manufacturer does not meet the other requirements o f the specifications, select another named product or product from another named manufacturer that does meet the requirements of the specifications. Submit a comparable product request, if applicable.
1.4 ACTION SUBMITTALS
A. Comparable Product Request Submittal: Submit request for consideration of each comparable product. Identify basis -of-design product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.
1. Include data t o indicate com pliance with the requirements specified in "Comparable Products" Article.
2. Architect's Action: If necessary, Architect will request additional information or documentation for evaluation within seven days of receipt of a comparable product request. Architect will notify Contractor through Construction Manager of approval or rejection of proposed comparable product request within 15 days of receipt of request, or seven days of receipt of additional information or documentation, whichever is later.
a. Form of Arc hitect's Approval of Submittal: As specified in Section 013300 "Submittal Procedures."
b. Use product specified if Architect does not issue a decision on use of a comparable product request within time allocated.
B. Basis-of-Design Product Specific ation Submittal: Comply with requirements in Section 013300 "Submittal Procedures." Show compliance with requirements.
1.5 QUALITY ASSURANCE
A. Compatibility of Options: If Contractor is given option of selecting between two or more products for use on Project, s elect product compatible with products previously selected, even if previously selected products were also options.
1. Each contractor is responsible for providing products and construction methods compatible with products and construction methods of other contractors.
2. If a dispute arises between contractors over concurrentl y selectable but incompatible products, Architect will determine which products shall be used.
B. Identification of Products: Except for required labels and operating data, do not attach or imprint manufacturer or product names or trademarks on exposed surfac es of City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
PRODUCT REQUIREMENTS - 016000 - 3
products or equipment that will be exposed to view in occupied spaces or on the exterior.
1. Labels: Locate required product labels and stamps on a concealed surface, or, where required for observation following installation, on a visually accessible surface that is not conspicuous.
2. Equipment Nameplates: Provide a permanent nameplate on each item of service-connected or power-operated equipment. Locate on a visually accessible but inconspicuous surface. Include information essential for operation, including the following:
a. Name of product and manufacturer.
b. Model and serial number.
c. Capacity.
d. Speed.
e. Ratings.
3. See individual identification sections in Divisions 15 and 16 for additional identification requirements.
1.6 PRODUCT DELIVERY, STORAGE, AND HANDLING
A. Deliver, store, and handle products using means and methods that will prevent damage, deterioration, and loss , including theft and vandalism. Comply with manufacturer's written instructions.
B. Delivery and Handling:
1. Schedule delivery to minimize long- term storage at Project site and to prevent overcrowding of construction spaces.
2. Coordinate delivery with installation time to ensure minimum holding time for items that are flammable, hazardous, easily damaged, or sensitive to deterioration, theft, and other losses.
3. Deliver products to Project site in an undamaged condit ion in manufacturer's original sealed container or other packaging system, complete with labels and instructions for handling, storing, unpacking, protecting, and installing.
4. Inspect products on delivery to determine compliance with the Contract Documents and to determine that products are undamaged and protected.
C. Storage:
1. Store products to allow for inspection and measurement of quantity of units.
2. Store materials in a manner that will not endanger Project structure.
3. Store products that are subject to damage by the elements, under c over in a weathertight enclosure above ground, with ventilation adequate to prevent condensation.
4. Protect foam plastic from exposure to sunlight, except to extent necessary for period of installation and concealment.
5. Comply with product manufacturer's writ ten instructions for temperature, humidity, ventilation, and weather-protection requirements for storage.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
PRODUCT REQUIREMENTS - 016000 - 4
6. Protect stored products from damage and liquids from freezing.
7. Provide a secure location and enclosure at Project site for storage of materials and equipment by Owner's construction forces. Coordinate location with Owner.
1.7 PRODUCT WARRANTIES
A. Warranties specified in other Sections shall be in addition to, and run concurrent with, other warranties required by the Contract Documents. Manufacturer's disclaimers and limitations on product warranties do not relieve Contractor of obligations under requirements of the Contract Documents.
1. Manufacturer's Warranty: Written warranty furnished by individual manufacturer for a particular product and specifically endorsed by manufacturer to Owner.
2. Special Warranty: Written warranty required by the Contract Documents to provide specific rights for Owner.
B. Special Warranties: Prepare a written document that contains app ropriate terms and identification, ready for execution.
1. Manufacturer's Standard Form: Modified to include Project -specific information and properly executed.
2. Specified Form: When specified forms are included w ith the Specifications, prepare a written document using indicated form properly executed.
3. See other Sections for specific content requirements and particular requirements for submitting special warranties.
C. Submittal Time: Comply with requirements in Section 017700 "Closeout Procedures." PART 2 - PRODUCTS
2.1 PRODUCT SELECTION PROCEDURES
A. General Product Requirements: Provide products that comply with the Contract Documents, are undamaged and, unless otherwise indicated, are new at installation.
1. Provide products complete with accessories, trim , finish, fasteners, and other items needed for a complete installation and indicated use and effect.
2. Standard Products: If available, and unless custom products or nonstandard options are specified, provide standard products of types that have been produced and used successfully in similar situations on other projects.
3. Owner reserves the right to limit selection to products with warranties meeting requirements of the Contract Documents.
4. Where products are accompanied by the term "as selected," Architect will select.
5. Descriptive, performance, and reference standard requirements in the Specifications establish salient characteristics of products.
B. Product Selection Procedures:
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
PRODUCT REQUIREMENTS - 016000 - 5
1. Limited List of Products: Where Specifications include a list of names of both manufacturers and products, provide one of the products listed that complies with requirements. Comparable products or substitutions for Contractor's convenience will be considered unless otherwise indicated.
a. Limited list of products may be indicated by the phrase: "Subject to compliance with requirements, provide one of the following: …"
2. Non-Limited List of P roducts: Where Specific ations include a list of names of both available manufacturers and products, provide one of the products listed, or an unnamed product, which complies with requirements.
a. Non-limited list of products is indicated by the phrase: "Subject to compliance with requirements, available products that may be incorporated in the Work include, but are not limited to, the following: …"
3. Limited List of Manufact urers: Where Specificat ions include a list of manufacturers' names, provide a product by one of the manufacturers listed that complies with requirements. Comparable products or substitutions for Contractor's convenience will be considered unless otherwise indicated. a. Limited list of manufacturers is indicated by the phrase: "Subject to compliance with requirements, provide products by one of the following: …"
4. Non-Limited List of Manufacturers: Where Specifications include a list of available manufacturers, provide a product by one of the manufacturers listed, or a product by an unnamed manufacturer, which complies with requirements. a. Non-limited list of manufacturers is indicated by the phrase: "Subject to compliance with requirements, available manufacturers whose products may be incorporated in the Work include, but are not limited to, the following: …"
5. Basis-of-Design Product: Where Specifications name a product, or refer to a product indicated on Drawings, and include a list of m anufacturers, provide the specified or indicated product or a comparable product by one of the other named manufacturers. Drawings and Specifications indicate sizes, profiles, dimensions, and other characteristics that are based on t he product named.
Comply with requirements in "Comparable Products" Article for consideration of an unnamed product by one of the other named manufacturers. a. For approval of products by unnamed manufacturers, comply with requirements in Section 012500 "Subs titution Procedures" for substitutions for convenience.
C. Visual Matching Specification: Where Specifications require "match Architect's sample," provide a product that complies with requirements and matches Architect's sample. Architect's decision will be final on whether a proposed product matches.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
PRODUCT REQUIREMENTS - 016000 - 6
1. If no product available within specified category matches and complies with other specified requirements, comply with requirements in Section 012500 "Substitution Procedures" for proposal of product.
D. Visual Selection Specification: Where Specifications include the phrase "as selected by Architect from manufacturer's full range" or similar phrase, select a product that complies with requirements. Architect will select color, gloss, pattern, density, or texture from manufacturer's product line.
2.2 COMPARABLE PRODUCTS
A. Conditions for Consideration of Comparable Products: Architect will consider Contractor's request for comparable product when the following conditions are satisfied. If the following conditions are not sati sfied, Architect may re turn requests without action, except to record noncompliance with these requirements:
1. Evidence that proposed product does not require revisions to the Contract Documents, is consistent with the Contract Documents, will produce the indicated results, and is compatible with other portions of the Work. Detailed comparison of significant qualities of proposed product with those named in the Specifications. Significant product qualities include attributes such as type, function, in- service performance and physic al properties, weight, dimension, durability, visual characteristics, and other specific features and requirements.
2. Evidence that proposed product provides specified warranty.
3. List of similar installations for completed projects with project names and addresses and names and addresses of architects and owners, if requested.
4. Samples, if requested.
B. Submittal Requirements: Approval of Contractor's request for use of comparable product is not intended to satisfy other submittal requirements. Comply with specified submittal requirements.
PART 3 - EXECUTION (Not Used)
END OF SECTION 016000
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
EXECUTION - 017300 - 1
SECTION 017300 - EXECUTION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes general administrative and procedural requirements governing execution of the Work including, but not limited to, the following:
1. Construction layout.
2. Field engineering and surveying.
3. Installation of the Work.
4. Cutting and patching.
5. Coordination of Owner-installed products.
6. Progress cleaning.
7. Starting and adjusting.
8. Protection of installed construction.
B. Related Requirements:
1. Section 011000 "Summary" for limits on use of Project site.
2. Section 013300 "Submittal Procedures" for submitting surveys.
3. Section 017700 "Closeout Procedures" for submitting final property survey with Project Record Documents, recording of Owner -accepted deviations from indicated lines and levels, replacing defective work, and final cleaning.
1.3 DEFINITIONS
A. Cutting: Removal of in- place construction necessary to permit installation or performance of subsequent work.
B. Patching: Fitting and repair work required to restore construction to original conditions after installation of subsequent work.
1.4 PREINSTALLATION MEETINGS
A. Cutting and Patching Conference: Conduct conference at Project site.
1. Prior to submitting cutting and patching plan , review extent of cutting and patching anticipated and examine procedures for ensuring satisfactory result EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
EXECUTION - 017300 - 2
from cutting and patching work. Require representatives of each en tity directly concerned with cutting and patching to attend, including the following:
a. Contractor's superintendent.
b. Trade supervisor responsible for cutting operations. c. Trade supervisor(s) responsible for patching of each type of substrate. d. Mechanical and electrical subcontractors' supervisors, to the extent each trade is affecting by cutting and patching operations.
2. Review areas of potential interference and conflict. Coordinate procedures and resolve potential conflicts before proceeding.
1.5 INFORMATIONAL SUBMITTALS
A. Qualification Data: For professional engineer.
B. Certificates: Submit certificate signed by professional engineer c ertifying that location and elevation of improvements comply with requirements.
C. Cutting and Patching Plan: Submit plan describing procedures at least 10 days prior to the time cutting and patching will be performed. Include the following information:
1. Extent: Describe reason for and extent of each occurrence of cutting and patching.
2. Changes to In-Place Construction: Describe anticipated results. Include changes to structural elements a nd operating components as well as changes in building appearance and other significant visual elements.
3. Products: List products to be used for patching and firms or entities that will perform patching work.
4. Dates: Indicate when cutting and patching will be performed.
5. Utilities and Mechanical and Electrical Systems: List ser vices and systems that cutting and patching procedures will disturb or affect. List services and systems that will be relocated and those that will be temporarily out of service. Indicate length of time permanent services and systems will be disrupted. a. Include description of provisions for temporary services and systems during interruption of permanent services and systems.
D. Landfill Receipts: Submit copy of receipts issued by a landfill facility, licensed to accept hazardous materials, for hazardous waste disposal.
E. Certified Surveys: Submit two copies signed by land surveyor.
F. Final Property Survey: Submit 10 copies showing the Work performed and record survey data.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
EXECUTION - 017300 - 3
1.6 QUALITY ASSURANCE
A. Land Surveyor Qualifications: A professional land surveyor who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing land-surveying services of the kind indicated.
B. Cutting and Patching: Comply with requirements for and limitations on cutting and patching of construction elements.
1. Structural Elements: When cutting and patching structural elements, notify Architect of locations and detai ls of cutting and await directions from Architect before proceeding. Shore, brace, and support structural elements during cutting and patching. Do not cut and patch structural elements in a manner that could change their load-carrying capacity or increase deflection.
2. Operational Elements: Do not cut and patch operating elements and related components in a manner that results in reducing their capacity to perform as intended or that results in increased maintenance or decreased operational life or safety. Operational elements include the following:
a. Primary operational systems and equipment.
b. Fire-suppression systems.
c. Plumbing piping systems.
d. Mechanical systems piping and ducts.
e. Communication systems.
f. Fire-detection and -alarm systems.
g. Electrical wiring systems.
h. Operating systems of special construction.
3. Other Construction Elements: Do not cut and patch other construction elements or components in a manner that could change their load- carrying capacity, that results in reducing their capacity to perform as intended, or that results in increased maintenance or decreased operational life or safety . Other construction elements include but are not limited to the following:
a. Water, moisture, or vapor barriers.
b. Membranes and flashings.
c. Equipment supports.
d. Piping, ductwork, vessels, and equipment.
e. Noise- and vibration-control elements and systems.
4. Visual Elements: Do not cut and patch construction in a manner that results in visual evidence of cutting and patching. Do not cut and patch exposed construction in a manner that would, in Architect's opinion, reduce the building's aesthetic qualities. Remove and replace construction that has been cut and patched in a visually unsatisfactory manner.
C. Manufacturer's Installation Instructions: Obtain and maintain on- site manufacturer's written recommendations and instructions for installation of products and equipment.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
EXECUTION - 017300 - 4
PART 2 - PRODUCTS
2.1 MATERIALS
A. General: Comply with requirements specified in other Sections.
1. For projects requiring compliance with sustainable design and construction practices and procedures, use products for patching that comply with sustainable design requirements.
B. In-Place Materials: Use materials for patching identical to in- place materials. For exposed surfaces, use materials that visually match in- place adjacent surfaces to the fullest extent possible.
1. If identical materials are unavailable or cannot be used, use materials that, when installed, will provide a match acceptable to Architect for the visual and functional performance of in-place materials.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Existing Conditions: The existence and location of utilities and construction indicated as existing are not guaranteed. Before beginning sitework, investigate and verify the existence and location of underground utilities and other construction affecting the Work.
B. Examination and Acceptance of Conditions: Before proceeding with each component of the Work, examine substrates, areas, and conditions, with Installer or Applicator present where indicated, for compliance with requirements for installation tolerances and other conditions affecting performance. Record observations.
1. Examine roughing- in for mechanical and electrical systems to verify actual locations of connections before equipment and fixture installation.
2. Examine walls, floors, and roofs for suitable conditions where products and systems are to be installed.
3. Verify compatibility with and suitability of substrates, including compatibility with existing finishes or primers.
C. Written Report: Where a written report listing conditions detrimental to performance of the Work is required by other Sections, include the following:
1. Description of the Work.
2. List of detrimental conditions, including substrates.
3. List of unacceptable installation tolerances.
4. Recommended corrections.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
EXECUTION - 017300 - 5
D. Proceed with installation only after unsatisfactory conditions have been corrected.
Proceeding with the Work indicates acceptance of surfaces and conditions.
3.2 PREPARATION
A. Field Measurements: Take field measurements as required to fit the Work properly.
Recheck measurements before installing each product. Where portions of the Work are indicated to fit to other construction, verify dimensions of other cons truction by field measurements before fabrication. Coordinate fabrication schedule with construction progress to avoid delaying the Work.
B. Space Requirements: Verify space requirements and dimensions of items shown diagrammatically on Drawings.
C. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents caused by differing field conditions outside the control of Contractor, submit a request for information to Architect according to requirements in Section 013100 "Project Management and Coordination."
3.3 CONSTRUCTION LAYOUT
A. Verification: Before proceeding to lay out the Work, verify layout information shown on Drawings, in relation to the property survey and existing benchmarks. If discrepancies are discovered, notify Architect and Construction Manager promptly.
B. General: Engage a professional engineer to lay out the Work using accepted surveying practices.
1. Establish benchmarks and control points to set lines and levels at each story of construction and elsewhere as needed to locate each element of Project.
2. Establish limits on use of Project site.
3. Establish dimensions within tolerances indicated. Do not scale Drawings to obtain required dimensions.
4. Inform installers of lines and levels to which they must comply.
5. Check the location, level and plumb, of every major element as the Work progresses.
6. Notify Architect and Construction Manager when deviations from required lines and levels exceed allowable tolerances.
3.4 INSTALLATION
A. General: Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated.
1. Make vertical work plumb and make horizontal work level.
2. Where space is limited, install components to maximize space available for maintenance and ease of removal for replacement.
3. Conceal pipes, ducts, and wiring in finished areas unless otherwise indicated.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
EXECUTION - 017300 - 6
4. Maintain minimum headroom clearance of 96 inches in occupied spaces and 90 inches in unoccupied spaces.
B. Comply with manufacturer's written instructions and recommendations for installing products in applications indicated.
C. Install products at the time and under conditions that will ensure the best poss ible results. Maintain conditions required for product performance until Substantial Completion.
D. Conduct construction operations so no part of the Work is subjected to damaging operations or loading in excess of that expected during normal conditions of occupancy.
E. Sequence the Work and allow adequate clearances to accommodate movement of construction items on site and placement in permanent locations.
F. Tools and Equipment: Where possible, select tools or equipment that minimize production of excessive noise levels.
G. Templates: Obtain and distribute to the parties involved templates for work specified to be factory prepared and field installed. Check Shop Drawings of other portions of the Work to confirm that adequate provisions are made for locating and instal ling products to comply with indicated requirements.
H. Attachment: Provide blocking and attachment plates and anchors and fasteners of adequate size and number to securely anchor each component in place, accurately located and aligned with other portions of the Work. Where size and type of attachments are not indicated, verify size and type required for load conditions.
1. Mounting Heights: Where mounting heights are not indicated, mount components at heights directed by Architect.
2. Allow for building movement, including thermal expansion and contraction.
3. Coordinate installation of anchorages. Furnish setting drawings, templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are t o be embedded in concrete or masonry. Deliver such items to Project site in time for installation.
I. Joints: Make joints of uniform width. Where joint locations in exposed work are not indicated, arrange joints for the best visual effect. Fit exposed connect ions together to form hairline joints.
J. Repair or remove and replace damaged, defective, or nonconforming Work.
1. Comply with Section 017700 "Closeout Procedures" for repairing or removing and replacing defective Work.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
EXECUTION - 017300 - 7
3.5 CUTTING AND PATCHING
A. Cutting and Patching, General: Employ skilled workers to perform cutting and patching.
Proceed with cutting and patching at the earliest feasible time, and complete without delay.
1. Cut in -place cons truction to provide for installation of other components or performance of other construction, and subsequently patch as required to restore surfaces to their original condition.
B. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during installation or cutting and patching operations, by methods and with materials so as not to void existing warranties.
C. Temporary Support: Provide temporary support of work to be cut.
D. Protection: Protect in- place construction during c utting and patching to prevent damage. Provide protection from adverse weather conditions for portions of Project that might be exposed during cutting and patching operations.
E. Cutting: Cut in-place construction by sawing, drilling, breaking, chipping, grinding, and similar operations, including excavation, using methods least likely to damage elements retained or adjoining construction. If possible, review proposed procedures with original Installer; comply with original Installer's written recommendations.
1. In general, use hand or small power tools designed for sawing and grinding, not hammering and chopping. Cut holes and slots neatly to minimum size required, and with minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use.
2. Concrete and Masonry: Cut using a cutting machine, such as an abrasive saw or a diamond-core drill.
3. Mechanical and Electrical Services: Cut off conduit in walls or partitions to be removed. Cap, valve, or plug and seal remaining portion of conduit to prevent entrance of moisture or other foreign matter after cutting.
4. Proceed with patching after construction operations requiring cutting are complete.
F. Patching: Patch construction by filling, repairing, refinishing, closing up, and similar operations following performance of other work. Patch with durable seam s that are as invisible as practicable. Provide materials and comply with installation requirements specified in other Sections, where applicable.
1. Inspection: Where feasible, test and inspect patched areas after completion to demonstrate physical integrity of installation.
2. Exposed Finishes: Restore exposed finishes of patched areas and extend finish restoration into retained adjoining construction in a manner that will minimize evidence of patching and refinishing.
a. Clean conduit, and similar features before applying paint or other finishing materials.
b. Restore damaged pipe covering to its original condition.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
EXECUTION - 017300 - 8
G. Cleaning: Clean areas and spaces where cutting and patching are performed. Remove paint, mortar, oils, putty, and similar materials from adjacent finished surfaces.
3.6 PROGRESS CLEANING
A. General: Clean Project site and work areas daily, including common areas. Enforce requirements strictly. Dispose of materials lawfully.
1. Comply with requirements in NFPA 241 for removal of combustible waste materials and debris.
2. Do not hold waste materials more than seven days during normal weather or three days if the temperature is expected to rise above 80 deg F.
3. Containerize hazardous and unsanitary waste materials separately from other waste. Mark containers appropriately and dispose of legally, according to regulations.
a. Use containers intended for holding waste materials of type to be stored.
4. Coordinate progress cleaning for joint -use areas where Contractor and other contractors are working concurrently.
B. Site: Maintain Project site free of waste materials and debris.
C. Work Areas: Clean areas where work is in progress to the level of cleanliness necessary for proper execution of the Work.
1. Remove liquid spills promptly.
2. Where dust would impair proper execution of the Work, broom -clean or vacuum the entire work area, as appropriate.
D. Installed Work: Keep installed work clean. Clean installed surfaces according to written instructions of manufacturer or fabricator of product installed, using only cleaning materials specifically recommended. If specific cleaning materials are not recommended, use cleaning materials that are not hazardous to health or property and that will not damage exposed surfaces.
E. Exposed Surfaces in Finished Areas: Clean exposed surfaces and protect as necessary to ensure freedom from damage and deterioration at time of Substantial Completion.
F. Waste Disposal: Do not bury or burn waste materials on- site. Do not wash waste materials down sewers or into waterways. Comply with waste disposal requirements in Section 017419 "Construction Waste Management and Disposal." G. During handling and installation, clean and protect construction in progress and adjoining materials already in place. Apply protective covering where required to ensure protection from damage or deterioration at Substantial Completion.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
EXECUTION - 017300 - 9
H. Clean and provide maintenance on completed construction as frequently as necessary through the remainder of the construction period. Adjust and lubricate operable components to ensure operability without damaging effects.
I. Limiting Exposures: Supervise construction operations to ensure that no part of the construction, completed or in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period.
3.7 STARTING AND ADJUSTING
A. Start equipment and operating components to confirm proper operation. Remove malfunctioning units, replace with new units, and retest.
B. Adjust equipment for proper operation. Adjust operating components for proper operation without binding.
C. Test each piece of equipment to verify proper operation. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and equipment.
D. Manufacturer's Field Service: Comply with qualification requirements in Section 014000 "Quality Requirements."
3.8 PROTECTION OF INSTALLED CONSTRUCTION
A. Provide final protection and maintain conditions that ensure installed Work is without damage or deterioration at time of Substantial Completion.
B. Protection of Existing Items: Provide protection and ensure that existing items to remain undisturbed by construction are maintained in condition that existed at commencement of the Work.
C. Comply with manufacturer's written instructions for temperature and relative humidity.
END OF SECTION 017300
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
EXECUTION - 017300 - 10
(THIS PAGE INTENTIONALLY LEFT BLANK)
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL - 017419 - 1 SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including Genera l and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for the following:
1. Salvaging nonhazardous demolition and construction waste.
2. Recycling nonhazardous demolition and construction waste.
3. Disposing of nonhazardous demolition and construction waste.
B. Related Requirements:
1. Section 013100 “Project Management and Coordination” for information on Waste Management Conferences.
1.3 DEFINITIONS
A. Construction Waste: Building, structure, and site improvement materials and other solid waste resulting from construction, remodeling, renovation, or repair operations.
Construction waste includes packaging.
B. Demolition Waste: Building, structure, and site improvement materials resulting from demolition operations.
C. Disposal: Removal of demolition or construction waste and subsequent salvage, sale, recycling, or deposit in landfill, incinerator acceptable to authorities having jurisdiction, or designated spoil areas on Owner’s property.
D. Recycle: Recov ery of demolition or construction waste for subsequent processing in preparation for reuse.
E. Salvage: Recovery of demolition or construction waste and subsequent sale or reuse in another facility.
F. Salvage and Reuse: Recovery of demolition or construction wa ste and subsequent incorporation into the Work.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL - 017419 - 2
1.4 MATERIALS OWNERSHIP
A. Unless otherwise indicated, demolition and construction waste becomes property o f Contractor.
B. Historic items, relics, antiques, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, and other items of interest or value to Owner that may be uncovered during demolition rem ain the property of Owner.
1. Carefully salvage in a manner to prevent damage and promptly return to Owner.
1.5 ACTION SUBMITTALS
A. Waste Management Plan: Submit plan within 7 days of date established for the Notice to Proceed. Waste Management Plan is available on the City website.
B. Waste Log: Submit the required Waste Log within 20 days after final inspection.
1.6 INFORMATIONAL SUBMITTALS
A. Waste Red uction Progress Reports: Concurrent with each Application for Payment, submit report. Use Construction and Demolition Waste Log available on the Cit y website.
B. Waste Reduction Calculations: Before request for Substantial Completion, submit calculated end-of-Project rates for salvage, recycling, and disposal as a percentage of total waste generated by the Work.
C. Records of Donations: Indicate receipt and acceptance of salvageable waste donated to individuals and organizations. Indicate whether organization is tax exempt.
D. Records of Sales: Indicate receipt and acceptance of salvageable waste sold to individuals and organizations. Indicate whether organization is tax exempt.
E. Recycling and Processing Facility Records: Indicate receipt and acceptance of recyclable waste by recycling and processing facilities licensed to accept them. Include manifests, weight tickets, receipts, and invoices.
F. Landfill and Incinerator Disposal Records: Indicate receipt and acceptance of waste by landfills and incinerator facilities lic ensed to accept them. Include manifests, weight tickets, receipts, and invoices.
1.7 QUALITY ASSURANCE
A. Waste Management Coordinator Qualifications: Experien ced firm, or individual employed and assigned by General Contractor, with a record of successful waste City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL - 017419 - 3 management coordination of projects with simi lar requirements. Superintendent may serve as Waste Management Coordinator.
B. Regulatory Requirements: Comply with trans portation and disposal regulations of authorities having jurisdiction.
C. Waste Management Conference(s): Conduct conference(s) at Project site t o comply with requirements in Section 013100 "Project Management and Coordination." Review methods and procedures related to waste management including, but not limited to, the following:
1. Review and discuss waste management plan including responsibilities of each contractor and waste management coordinator.
2. Review requirements for documenting quantities of each type of waste and its disposition.
3. Review and finalize procedures for materials sepa ration and verify availability of containers and bins needed to avoid delays.
4. Review procedures for periodic waste collection and transportation to recycling and disposal facilities.
5. Review waste management requirements for each trade.
1.8 WASTE MANAGEMENT PLAN
A. General: Develop a waste management plan according to requirements set forth by City of Sacramento Solid Waste Services . Plan shall consist of was te identification, compliant debris recycling goals, and material management plan , including accompanying Wa ste Log . Distinguish between demolition and construction waste.
Indicate quantities by weight or volume, but use same units of measure throughout waste management plan.
PART 2 - PRODUCTS
2.1 RECYCLING RECEIVERS AND PROCESSORS
A. Subject to compliance with requirements, available recycling receiv ers and processors include, but are not limited to, the following:
1. Kiefer Landfill, 127601 Kiefer Blvd. Sacramento, CA 95683.
2.2 PERFORMANCE REQUIREMENTS
A. General: Achieve end-of-Project rates for salvage/recycling of 50 percent by weight of total nonhazardou s solid waste generated by the Work. Practice efficient waste management in the use of materials in the course of the Work. Use all reasonable means to divert construction and demolition waste from landfills and incinerators.
Facilitate recycling and salvage of materials.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL - 017419 - 4
PART 3 - EXECUTION
3.1 PLAN IMPLEMENTATION
A. General: Implement approved waste management plan. Provide handling, containers, storage, signage, tr ansportation, and other items as required to implement waste management plan during the entire duration of the Contract.
1. Comply with operation, termination, and removal requirements in Section 015000 "Temporary Facilities and Controls."
B. Waste Management Coordinator: Engage a waste management coordinator to be responsible for implement ing, monitoring, and reporting status of waste management work plan.
C. Training: Train workers, subcontractors , and suppliers on proper waste management procedures, as appropriate for the Work.
1. Distribute waste management plan to everyone concerned within three days of submittal return.
2. Distribute waste management plan to entities when they first begin work on -site.
Review plan procedures and locations established for salvage, recycling, and disposal.
D. Site Access and Temporary Controls: Conduct waste manageme nt operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.
1. Designate and label specific areas on Project site necessary for separating materials that are to be salvaged and recycled.
3.2 RECYCLING CONSTRUCTION WASTE, GENERAL
A. General: Recycle paper and beverage containers used by on-site workers.
B. Recycling Incentives: Revenues, savings, rebates, tax credits, and other incentives received for recycling waste materials shall accrue to Contractor.
C. Preparation of Waste: Prepare and maintain recyclable waste materials according to recycling or reuse facility requirements. Maintain materials free of dir t, adhesives, solvents, petroleum contamination, and other substances deleterious to the recycling process.
D. Procedures: Process recyclable waste according to a pproved construction wa ste management plan.
1. Provide appropriately marked containers or bins for controlling recyclable waste until removed from Project site. Include list of acceptable and unacceptable materials at each container and bin.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL - 017419 - 5 a. Inspect container s and bins for contamin ation and remove contaminated materials if found.
2. Stockpile processed materials on -site without intermixing with other materials.
Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust.
3. Stockpile materials away from cons truction area. Do not store within drip line of remaining trees.
4. Store components off the ground and protect from the weather.
5. Remove recyclable waste from Owner's property and transport to recycling receiver or processor as often as required to prevent overfilling bins.
3.3 RECYCLING DEMOLITION WASTE
A. Concrete: Remove reinforcement and other metals from concrete and sort with other metals.
1. Pulverize concrete to maximum 1-1/2-inch size.
2. Crush concrete and screen to comply with requirements in Civil Specifications Section 14 "Earthwork, Excavation, Em bankment, and Subgrade " for use as satisfactory soil for fill or subbase.
3.4 RECYCLING CONSTRUCTION WASTE
A. Packaging:
1. Cardboard and Boxes: Break down packaging into flat sheets. Bundle and store in a dry location.
2. Polystyrene Packaging: Separate and bag materials.
3. Pallets: As much as possible, requi re deliveries using pallets to remove pallets from Project site. For pallets that remain on -site, break down pallets into component wood pieces and comply with requirements for recycling wood.
4. Crates: Break down crates into component wood pieces and comply with requirements for recycling wood.
B. Wood Materials:
1. Clean Cut-Offs of Lumber: Grind or chip into small pieces.
2. Clean Sawdust: Bag sawdust that does not contain painted or treated wood.
C. Gypsum Board: Stack large clean pieces on wood pallets or in co ntainer and store in a dry location.
1. Clean Gypsum Board: Grind scraps of clean gypsum board using small mobile chipper or hammer mill. Screen out paper after grinding.
D. Paint: Seal containers and store by type.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL - 017419 - 6
3.5 DISPOSAL OF WASTE
A. General: Except for items or materials to be salvaged or recycled, remove waste materials from Project site and lega lly dispose of them in a landfill or incinerator acceptable to authorities having jurisdiction.
1. Except as otherwise specified, do not allow waste materials that are to be disposed of accumulate on-site.
2. Remove and transport debris in a manner that will pre vent spillage on adjacent surfaces and areas.
B. General: E xcept for items or materials to be salvaged or recycled, remove waste materials and legally dispose of at designated spoil areas on Owner’s property.
C. Burning: Do not burn waste materials.
END OF SECTION 017419
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
CLOSEOUT PROCEDURES - 017700 - 1
SECTION 017700 - CLOSEOUT PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Spec. Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for contract closeout, including, but not limited to, the following:
1. Substantial Completion procedures.
2. Final completion procedures.
3. Warranties.
4. Final cleaning.
5. Repair of the Work.
B. Related Requirements:
1. Section 012900 "Payment Procedures" for final Application for Payment.
2. Section 017823 "Operation and M aintenance Data" for additional operation and maintenance manual requirements.
3. Section 017839 "Project Record Documen ts" for submitting Record Drawings, Record Specifications, and Record Product Data.
1.3 ACTION SUBMITTALS
A. Product Data: For each type of cleaning agent.
B. Contractor's List of Incomplete Items: Initial submittal at Substantial Completion.
C. Certified List of Incomplete Items: Final submittal at final completion.
1.4 CLOSEOUT SUBMITTALS
A. Certificates of Release: From authorities having jurisdiction.
B. Certificate of Insurance: For continuing coverage.
1.5 MAINTENANCE MATERIAL SUBMITTALS
A. Schedule of Maintenance Material Items: For maintenance materials in other Sections.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
CLOSEOUT PROCEDURES - 017700 - 2
1.6 SUBSTANTIAL COMPLETION PROCEDURES
A. Contractor's List o f Incomplete Items: Prepare and submit a list of items to be completed and corrected (Contractor's punch list), indicating the value of each item on the list and reasons why the Work is incomplete.
B. Submittals Prior to Substantial Completion: Complete the f ollowing a minimum of 10 days prior to requesting inspection for determining date of Substantial Completion. Lis t items below that are incomplete at time of request.
1. Certificates of Release: Obtain and submit releases from authorities having jurisdiction permitting Owner unrestricted use of the Work and access to services and utilities. Include occupancy permits, op erating certificates, and similar releases.
2. Submit closeout submittals specified in other Division 01 Sections, including project record documen ts, operation and maintenance manuals, damage or settlement surveys, and similar final record information.
3. Submit closeout submittals specified in individual Sections, including specific warranties, workmanship bonds, maintenance service agreements, final certifications, and similar documents.
4. Submit maintenance material submittals specified in individual Sections, including tools, spare parts, extra materials, and similar items, and deliver to location designated by Owner. Label with manu facturer's name and model number.
a. Schedule of Maintenance Material Items: Prepare and submit schedule of maintenance material submittal items, including name and quantity of each item and name and number of related Specification Section . Obtain Owner's signature for receipt of submittals.
5. Submit testing, adjusting, and balancing records.
6. Submit changeover information related to Owner's occupancy, use, operation, and maintenance.
C. Procedures Prior to Substantial Completion: Complete the fo llowing a minimum of 10 days prior to requesting inspection for determining date of Substantial Completion. List items below that are incomplete at time of request.
1. Advise Owner of pending insurance changeover requirements.
2. Make final changeover of permane nt locks and deliver keys to Owner. Advise Owner's personnel of changeover in security provisions.
3. Complete startup and testing of systems and equipment.
4. Perform preventive maintenance on equipment used prior t o Substantial Completion.
5. Complete final cleaning requirements.
6. Touch up paint and otherwise repair and restore marred exposed finishes to eliminate visual defects.
D. Inspection: Submit a written request for inspection to determine Substantial Completion a minimum of 10 days prior to date the Work will be completed and ready for final inspection and tests. On receipt of request, Owner will either proceed with inspection or City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
CLOSEOUT PROCEDURES - 017700 - 3
notify Contractor of unfu lfilled requireme nts. Architect will prepare the Certificate of Substantial Completion after inspection or will notify Contractor of items, either on Contractor's list or additional items identified by Owner, that must be completed or corrected before certificate will be issued.
1. Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.
2. Results of completed inspection are the requirements for final completion.
1.7 FINAL COMPLETION PROCEDURES
A. Submittals Prior to Final Completion: Before requesting final inspection for determining final completion, complete the following:
1. Submit a final Application for Payment according to Sec tion 012900 "Payment Procedures."
2. Certified List of Incomplete Items: Submit certified copy of Architect's Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by Owner. Certified copy of the list shall state that each item has been completed or otherwise resolved for acceptance.
3. Certificate of Insurance: Submit evidence of final, continuing insurance coverage complying with insurance requirements.
4. Submit pest-control final inspection report.
5. Submit final completion photographic documentation.
B. Inspection: Submit a written request for final inspection to determine acceptance a minimum of 10 days prior to date the work will be completed and ready for fi nal inspection and tests. On receipt of request, Owner will either proceed with inspection or notify Contractor of unfulfilled requirements. Architect will prepare a final Certificate for Payment after inspection or w ill notify Contractor of construction t hat must be completed or corrected before certificate will be issued.
1. Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.
1.8 LIST OF INCOMPLETE ITEMS (PUNCH LIST)
A. Organization of List: Include name an d identification of each space and area affected by construction operations for incomplete items and items needing correction including, if necessary, areas disturbed by Contractor that are outside the limits of construction.
1. Organize list of spaces in sequential order, starting with exterior areas first.
2. Organize items applying to each space by major element, including categories for ceiling, individual walls, floors, equipment, and building systems.
3. Include the following information at the top of each page:
a. Project name.
b. Date.
c. Name of Architect and Owner
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
CLOSEOUT PROCEDURES - 017700 - 4
d. Name of Contractor.
e. Page number.
4. Submit list of incomplete items in the following format:
a. MS Excel electronic file. Owner will return annotated file. b. PDF electronic file. Owner will return annotated file. c. Web-based project software upload (punch list).
d. Electronic PDF copies. Owner will return annotated PDF file.
1.9 SUBMITTAL OF PROJECT WARRANTIES
A. Time of Submittal: Submit written warranties on request of Owner for designated portions of the Work where warranties are indicated to commence on dates other than date of Substantial Completion, or when delay in submittal of warranti es might limit Owner's rights under warranty.
B. Partial Occupancy: Submit properly executed warranties within 15 days of completion of designated portions of the Work that are completed and occupied or used by Owner during construction period by separate agreement with Contractor.
C. Organize warranty documents into an orderly sequence based on the Project Manual.
D. Warranty Electronic File: Provide w arranties and bonds in PDF format. Assemble complete warranty and bond submittal package into a single electronic PDF file with bookmarks enabling navigation to each item. Provide bookmarked table of contents at beginning of document.
1. Submit on digital media acceptable to Owner via weblink by email.
E. Provide PDF’s of each warranty to include in operation and maintenance manuals.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces.
1. Use cleaning products that comply with California Code of Regulations maximum allowable VOC levels.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
CLOSEOUT PROCEDURES - 017700 - 5
PART 3 - EXECUTION
3.1 FINAL CLEANING
A. General: Perform final cleaning. Conduct cleaning and waste -removal operations to comply with local laws and ordinances and Federal and local environme ntal and antipollution regulations.
B. Cleaning: Employ experienced workers or professional cleaners for final cleaning.
Clean each surface or unit t o condition expected in an average commercial building cleaning and maintenance program. Comply with manufacturer's written instructions.
1. Complete the following cleaning operat ions before requesting inspection for certification of Substantial Completion for entire Project or for a desi gnated portion of Project:
a. Clean Project site in areas disturbed by construction activities of rubbish, waste material, litter, and other foreign substances.
b. Sweep paved areas broom clean. Remove petrochemical spills, stains, and other foreign deposits.
c. Remove tools, construction equipment, machinery, and surplus material from Project site.
d. Sweep concrete floors broom clean in unoccupied spaces. e. Remove labels that are not permanent.
f. Wipe surfaces of mechanical and electrical equipment, and similar equipment. Remove excess lubrication, paint and mortar dro ppings, and other foreign substances.
g. Clean luminaires, lamps, globes, and reflectors to fully function. h. Leave Project clean and ready for occupancy.
C. Construction Waste D isposal: Comply with waste disposal requirements in Section 017419 "Construction Waste Management and Disposal."
3.2 REPAIR OF THE WORK
A. Complete repair and restoration operations before requesting inspection for determination of Substantial Completion.
B. Repair, or remove and replace, defective construction. Repairing includes replacing defective parts, refinishi ng damaged surfaces, touching up with matching materials, and properly adjusting operating equipment. Where dama ged or worn items cannot be repaired or restored, provide replacements. Remove and replace operating components that cannot be repaired. Restore damaged construction and permanent facilities used during construction to specified condition.
1. Remove and repla ce chipped, scratched, and broken glass, reflective surfaces, and other damaged transparent materials.
2. Touch up and repair and restore marred or exposed finishes and surfaces.
Replace finishes and surfaces that already show evidence of repair.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
CLOSEOUT PROCEDURES - 017700 - 6
a. Do not paint over "UL" and other required labels and identification, including mechanical & electrical. Remove paint applied to labels.
3. Replace parts subjec t to operating conditions du ring construction that may impede operation or reduce longevity.
4. Replace burned -out bulbs, bulbs dimmed by use, and defective and noisy fixtures to comply with requirements.
3.3 NOTE: SAMPLE WARRANTY FORM IS INCLUDED DIRECTLY FOLLO WING THIS SECTION.
END OF SECTION 017700
WARRANTY AND GUARANTEE FORM
1._________________________________________________________________ ("Contractor") hereby agrees that the___________________________________________ (“Work” of Contractor) which Contractor has installed for the CITY OF SACRAMENTO ("City") for the following project:
EV BLUEPRINT- SITE _____________________
C15210050 (“Project” or “Contract”)
was performed in accordance with the requirements of the Contract Documents and that the Work as installed fulfills the requirements of the Contract Documents.
2. Contractor agrees to repair or replace all of the Work that may prove to be defective in workmanship or material and any other adjacent Work that may be displaced in connection with such replacement within a period of ____ YEAR(S) from the date of Completion as defined in the Contract, ordinary wear and tear and unusual abuse or neglect excepted. The date of completion is .
3. In the event Contractor fails to comply with the above-mentioned conditions within a reasonable period of time, as determined by City, but not later than TEN (10) calendar days after being notified in writing by City, Contractor authorizes City to proceed to repair or replace the defective Work at the expense of Contractor. Contractor shall pay the costs and charges therefor upon demand.
4. Representatives to be contacted for service subject to the terms of Contract:
NAME:___________________________________________________________ ADDRESS:_________________________________________________________ PHONE NO.:_______________________________________________________ EMAIL:___________________________________________________________ Date:_____________________________________________________________ Proper Name of Contractor:__________________________________________ Signature:________________________________________________________ Print Name:_______________________________________________________ Title:_____________________________________________________________
END OF DOCUMENT
CITY OF SACRAMENTO
EV BLUEPRINT
SECTION 01 77 10
CERTIFICATION OF COMPLIANCE- SITE #__________________
T
he Contractor does hereby certify that all work has been performed and materials supplied in accordance with the drawings, specifications and Contract Documents for the above Work, and that:
No less than the prev ailing rates of wages as ascertained by the governing body of the Contracting agency has been paid to laborers, workmen and mechanics employed on this Work;
There have been no unauthorized substitutes of Subcontractors; nor have any subcontractors been entered into without the names of the Subcontractors having been submitted to the Owner prior to the start of such subcontracted work;
No subcontract was assigned or transferred or performed by any Subcontractor other than the original Subcontractor, without prior notice having been submitted to the Owner together with the names of all Subcontractors;
All claims for material and labor and other service performed in connection with these specifications have been paid;
I
n WITNESS WHEREOF, the undersigned has signed and sealed this instrument this day , 2 .
F
irm Name
S
ignature
T
itle
(Attest)
(SEAL IF BIDDER IS A CORPORATION)
As determi ned necessary, evidenc e of complianc e may be requir ed t o be submitted with and made a part of this Certificate of Compliance.
CERTIFICATE OF COMPLIANCE – 01 77 10 – PAGE 1
CITY OF SACRAMENTO
EV BLUEPRINT
CERTIFICATION OF COMPLIANCE – 01 77 10 – PAGE 2
SECTION 01 77 10
CE
RTIFICATION OF COMPLIANCE
PART
1 GENERAL
1. No final payment shall be made until the Contractor files with the Owner, prior to acceptance of the Work, a notarized Certification of Compliance in the following form.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION 01 77 10
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
OPERATION AND MAINTENANCE DATA - 017823 - 1
SECTION 017823 - OPERATION AND MAINTENANCE DATA
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for preparing operation and maintenance manuals, including the following:
1. Operation and maintenance documentation directory manuals.
2. Systems and equipment operation manuals.
3. Systems and equipment maintenance manuals.
4. Product maintenance manuals.
B. Related Requirements:
1. Section 013300 "Submittal Procedures" for sub mitting copies of submittals for operation and maintenance manuals.
2. Section 017700 "Closeout Procedures" for schedule for submitting operation and maintenance documentation.
1.3 DEFINITIONS
A. System: An organized collection of parts, equipment, or subsystems united by regular interaction.
B. Subsystem: A portion of a system with characteristics similar to a system.
1.4 CLOSEOUT SUBMITTALS
A. Submit operation and maintenance manuals indicated. Provid e content for each manual as specified in individual Specification Sections, and as reviewed and approved at the time of Section submittals. Submit reviewed manual content formatted and organized as required by this Section.
1. Owner will comment on whether c ontent of operation and maintenance submittals is acceptable.
2. Where applicable, clarify and update reviewed manual content to correspond to revisions and field conditions.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
OPERATION AND MAINTENANCE DATA - 017823 - 2
B. Format: Submit operation and maintenance manuals in the following format:
1. Submit PDF documents via email to Owner. Enable reviewer comments on draft submittals.
2. Submit PDF documents on a USB flash drive and deliver to City PM.
C. Initial Manual Submittal: Submit draft copy of each manual at least thirty [30] days before commencing demonstration and training. Owner will comment on whether general scope and content of manual are acceptable.
D. Final Manual Submittal: Submit each manual in final form prior to requesting inspection for Substantial Completion and at least fifteen [15] days before commencing demonstration and training. Owner will return copy with comments in a digital format.
1. Correct or revise each manual to comply with Owner’s comments. Submit digital copies of each corrected manual within fifteen [15] days of receipt of Owner’s comments and prior to commencing demonstration and training.
E. Comply with Section 017700 "Closeout Procedures" for schedule for submitting operation and maintenance documentation.
1.5 FORMAT OF OPERATION AND MAINTENANCE MANUALS
A. Manuals, Electronic Files: Submit manuals in the form of a multiple file composite electronic PDF file for each manual type required. Provide a USB flash drive with all files sorted by O&M manual sections and renamed appropriately.
1. Electronic Files: Use electronic files prepared by manufacturer where available.
Scanning of paper documents is required, configure scanned file for minimum readable file size.
2. File Names and Bookmarks: Bookmark individual documents based on file names. Name document files to correspond to system, subsystem, and equipment names used in manual directory and table of contents. Group documents for each system and subsystem into individual composite bookmarked files, then create composite manual, so that resulting bookmarks reflect the system, subsystem, and equipment names in a readily nav igated file tree. Configure electronic manual to display bookmark panel on opening file.
1.6 REQUIREMENTS FOR EMERGENCY, OPERATION, AND MAI NTENANCE
MANUALS
A. Organization of Manuals: Unless otherwise indicated, organize each manual into a separate section for each system and subsystem, and a separate section for each piece of equipment not part of a system. Each manual shall contain the followi ng materials, in the order listed:
1. Title page.
2. Table of contents.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
OPERATION AND MAINTENANCE DATA - 017823 - 3
3. Manual contents.
B. Title Page: Include the following information:
1. Subject matter included in manual.
2. Name and address of Project.
3. Name and address of Owner.
4. Date of submittal.
5. Name and contact information for Contractor.
6. Name and contact information for Construction Manager.
7. Name and contact information for Owner.
8. Name and contact information for Architect.
9. Cross-reference to related systems in other operation and maintenance manuals.
C. Table of Contents: List each product included in manual, identified by product name, indexed to the content of the volume, and cross -referenced to Specification Section number in Project Manual.
D. Manual Contents: Organize into sets of manageable size. Arrange contents alphabetically by system, subsystem, and equipment. If possible, assemble instructions for subsystems, equipment, and components of one system into a digital file.
E. Identification: In the documentation directory and in each operation and maintenance manual, identify each sy stem, subsystem, and piece of equipment with same designation used in the Contract Documents. If no designation exists, assign a designation according to ASHRAE Guideline 4, "Preparation of Operating and Maintenance Documentation for Building Systems."
1.7 OPERATION AND MAINTENANCE DOCUMENTATION DIRECTORY MANUAL A. Operation and Maintenance Documentation Directory: Prepare a separate manual that provides an organized reference to emergency, operation, and maintenance manuals.
List items and their location to facilitate ready access to desired information. Include the following:
1. List of Systems and Subsystems: List systems alphabetically. Include references to operation and maintenance manuals that contain information a bout each system.
2. List of Equipment: List equipment for each system, organized alphabetically by system. For pieces of equipment not part of system, list alphabetically in a separate list.
3. Tables of Contents: Include a table of contents for each emergency, operation, and maintenance manual.
1.8 SYSTEMS AND EQUIPMENT OPERATION MANUALS
A. Systems and Equipment Operation Manual: Assemble a complete set of data indicating operation of each system, subsystem, and piece of equipment not part of a EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
OPERATION AND MAINTENANCE DATA - 017823 - 4
system. Include information required for daily operation and management, operating standards, and routine and special operating procedures.
1. Engage a factory -authorized servic e representative to assemble and prepare information for each system, subsystem, and piece of equipment not part of a system.
2. Prepare a separate manual for each system and subsystem, in the form of an instructional manual for use by Owner's operating personnel.
B. Content: In addition to requirements in this Section, include operation data required in individual Specification Sections and the following information:
1. System, subsystem, and equipment descriptions. Use designations for systems and equipment indicated on Contract Documents.
2. Performance and design criteria if Contractor has delegated design responsibility.
3. Operating standards.
4. Operating procedures.
5. Wiring diagrams.
6. Precautions against improper use.
7. License requirements including inspection and renewal dates.
C. Descriptions: Include the following:
1. Product name and model number. Use designations for products indicated on Contract Documents.
2. Manufacturer's name.
3. Equipment identification with serial number of each component.
4. Equipment function.
5. Operating characteristics.
6. Limiting conditions.
7. Performance curves.
8. Engineering data.
9. Complete nomenclature and number of replacement parts.
D. Operating Procedures: Include the following, as applicable:
1. Startup procedures.
2. Routine and normal operating instructions.
3. Normal shutdown instructions.
1.9 SYSTEMS AND EQUIPMENT MAINTENANCE MANUALS
A. Systems and Equipment Maintenance Manuals: Assemble a complete set of data indicating maintenance of each system, subsystem, and piece of equipment not part of a system. Include manufactur ers' maintenance documentation, preventive maintenance procedures and frequency, repair procedures, wiring and systems diagrams, lists of spare parts, and warranty information.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
OPERATION AND MAINTENANCE DATA - 017823 - 5
1. Engage a factory -authorized service representative to assemble and prepare information for each system, subsystem, and piece of equipment not part of a system.
2. Prepare a separate manual for each system and subsystem, in the form of an instructional manual for use by Owner's operating personnel.
B. Content: For each system, subsystem, an d piece of equipment not part of a system, include source information, manufacturers' maintenance documentation, maintenance procedures, maintenance and service schedules, spare parts list and source information, maintenance service contracts, and warranti es and bonds as described below.
C. Source Information: List each system, subsystem, and piece of equipm ent included in manual, identified by product name and arranged to match manual's table of contents.
For each product, list name, address, and telephone number of Installer or supplier and maintenance service agent, and cross-reference Specification Section number and title in Project Manual and drawing or schedule designation or identifier where applicable.
D. Manufacturers' Maintenance Documentation: Include the following information for each component part or piece of equipment:
1. Standard maintenance instructions and bulletins; include only sheets pertinent to product or component installed. Mark each sheet to identify each product or component incorporated into the Work. If data include s more than one item in a tabular format, identify each item using approp riate references from the Contract Documents. Identify data applicable to the Work and delete references to information not applicable.
a. Prepare supplementary text if manufacturers' standard printed data are not available and where the information is necess ary for proper operation and maintenance of equipment or systems.
2. Drawings, diagrams, and instructions required for maintenance, including disassembly and component removal, replacement, and assembly.
3. Identification and nomenclature of parts and components.
4. List of items recommended to be stocked as spare parts.
E. Maintenance Procedures: Include the following information and items that detail essential maintenance procedures:
1. Test and inspection instructions.
2. Troubleshooting guide.
3. Precautions against improper maintenance.
4. Disassembly; component removal, repair, and replacement; and reassembly instructions.
5. Aligning, adjusting, and checking instructions.
6. Demonstration and training video recording, if available.
F. Maintenance and Service Schedules: Include servic e and lubrication requirements, list of required lubricants for equipment, and separate schedules for preventive and routine maintenance and service with standard time allotment.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
OPERATION AND MAINTENANCE DATA - 017823 - 6
1. Scheduled Maintenance and Service: Tabulate actions for daily, weekly, monthly, quarterly, semiannual, and annual frequencies.
2. Maintenance and Service Record: Include manufacturers' forms for recording maintenance.
3. In no way shall lack of mainte nance void the warranty on any products nor services warranted for the first year of service. If any service of systems is required to maintain the warran ty, then that shall be i ncluded to ensure th e 1 - year warranty is valid and active.
G. Spare Parts List and Source Information: Include lists of replacement and repair parts, with parts identified and cros s-referenced to manufacturers' maintenance documentation and local sources of maintenance materials and related services.
H. Maintenance Service Contracts: Include copies of maintenance agreements with name and telephone number of service agent.
I. Warranties and Bonds: Include copies of warranties and bonds and lists of circumstances and conditions that would affect validity of warranties or bonds.
1. Include procedures to follow and required notifications for warranty claims.
J. Drawings: Prepare drawings supplementing manufacturers' printed data to illustrate the relationship of component parts of equipment and systems and to illustrate control sequence and flow diagrams. Coordinate these drawings with information contained in record Drawings to ensure correct illustration of completed installation.
1. Do not use original project record documents as part of maintenance manuals.
1.10 PRODUCT MAINTENANCE MANUALS
A. Maintenance Procedures: Include manufacturer's written recommendations and the following:
1. Inspection procedures.
2. Repair instructions.
B. Repair Materials and Sources: Include lists of materials and local sources of materials and related services.
C. Warranties and Bonds: Include copies of warranties and bonds and lists of circumstances and conditions that would affect validity of warranties or bonds.
1. Include procedures to follow and required notifications for warranty claims.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 017823
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
PROJECT RECORD DOCUMENTS - 017839 - 1
SECTION 017839 - PROJECT RECORD DOCUMENTS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for project record documents, including the following:
1. Record Drawings.
2. Record Specifications.
3. Record Product Data.
4. Miscellaneous record submittals.
B. Related Requirements:
1. Section 013100 "Project Management and Coordination" for requirements related to use of Architect's digital data files.
2. Section 017300 "Execution" for final property survey.
3. Section 017700 "Closeout Procedures" for general closeout procedures.
4. Section 017823 "Operation and Maintenance Data" for operat ion and maintenance manual requirements.
1.3 CLOSEOUT SUBMITTALS
A. Record Drawings: Comply with the following:
1. Number of Copies: Submit one set of marked-up record prints.
2. Number of Copies: Submit copies of record Drawings as follows:
a. Initial Submittal:
1) Submit PDF electronic files of scanned record prints and one set of file prints.
2) Owner will indicate whether general scope of changes, additional information recorded, and quality of drafting are acceptable. b. Final Submittal:
1) Submit PDF electronic files of scanned record prints and one set of prints.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
PROJECT RECORD DOCUMENTS - 017839 - 2
2) Print each drawing, whether or not changes and additional information were recorded.
B. Record Specifications: Submit annotated PDF electronic files of Project's Specifications, including addenda and contract modifications.
C. Record Product Data: Submit annotated PDF electronic files and directories of each submittal.
1. Submit scans of marked-up Product Data as a component of manual.
D. Miscellaneous Record Submittals: See other Specification Sections for miscellaneous record-keeping requirements and submittals in connection with various construction activities. Submit annotated PDF electronic files and directories of each submittal.
E. Reports: Submit written report monthly indicating items incorporated into project record documents concurrent with progress of the Work, including revisions, concealed conditions, field changes, product selections, and other notations incorporated.
1.4 RECORD DRAWINGS
A. Record Prints: Maintain one set of marked -up paper copies of the Contract Drawings and Shop Drawings, in corporating new and revised drawings as modifications are issued.
1. Preparation: Mark record prints to show the actual installation where installation varies from that shown originally. Require individual or entity who obtained record data, whether individual or entity is Installer, subcontractor, or similar entity, to provide information for preparation of corresponding marked-up record prints. a. Give particular attention to information on concealed elements that would be difficult to identify or measure and record later.
b. Accurately record information in an acceptable drawing technique. c. Record data as soon as possible after obtaining it.
d. Record and check the markup before enclosing concealed installations. e. Cross-reference record prints to corresponding photographic documentation.
2. Content: Types of items requiring marking include, but are not limited to, the following:
a. Dimensional changes to Drawings.
b. Revisions to details shown on Drawings.
c. Revisions to routing of piping and conduits.
d. Revisions to electrical circuitry.
e. Actual equipment locations.
f. Duct size and routing.
g. Locations of concealed internal utilities.
h. Changes made by Change Order or Construction Change Directive (CCD). i. Changes made following Owner’s written orders.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
PROJECT RECORD DOCUMENTS - 017839 - 3
j. Details not on the original Contract Drawings.
k. Field records for variable and concealed conditions. l. Record information on the Work that is shown only schematically.
3. Mark the Contract Drawings and Shop Drawings compl etely and accurately. Use personnel proficient at recording graphic information in production of marked- up record prints.
4. Mark record sets with erasable, red- colored pencil. Use other colors to distinguish between changes for different categories of the Work at same location.
5. Mark important additional information that was either shown schematically or omitted from original Drawings.
6. Note Construction Change Directive numbers, alternate numbers, Change Order numbers, and similar identification, where applicable.
B. Record Digital Data Files: Immediately before inspection for Certificate of Substantial Completion, review marked- up record prints with Owner. When authorized, prepare a full set of corrected digital data files of the Contract Drawings, as follows:
1. Format: Same digital data software program, version, and operating system as the original Contract Drawings.
2. Format: DWG Version 2015 or previous, Microsoft Windows operating system.
3. Format: Annotated PDF electronic file with comment function enabled.
4. Incorporate changes and additional information previously marked on record prints. Delete, redraw, and add details and notations where applicable.
5. Refer instances of uncertainty to Owner for resolution.
6. Owner will furnish Contractor with one set of digital data files of the Contract Drawings for use in recording information.
a. See Section 013100 "Project Management and Coordination" for requirements related to use of Architect's digital data files. b. Architect/Owner will provide data file layer information. Record markups in separate layers.
C. Format: Identify and date each record Drawing; include the designation "PROJECT RECORD DRAWING" in a prominent location.
1. Record Prints: Organize record prints into manageable sets. Bind each set with durable paper cover sheets. Include identification on cover sheets.
2. Format: Annotated PDF electronic file with comment function enabled.
3. Record Digital Data Files: Organize digital data information into separate electronic files that correspond to each sheet of the Contract Drawings. Name each file with the sheet identification. Include identification in each digital data file.
4. Identification: As follows:
a. Project name.
b. Date.
c. Designation "PROJECT RECORD DRAWINGS."
d. Name of Architect and Owner.
e. Name of Contractor.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
PROJECT RECORD DOCUMENTS - 017839 - 4
1.5 RECORD SPECIFICATIONS
A. Preparation: Mark Specifications to indicate the actual product installation where installation varies from that indicated in Specifications, addenda, and contract modifications.
1. Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later.
2. Mark copy with the proprietary name and model number of products, materials, and equipment furnished, including substitutions and product options selected.
3. Record the name of manufacturer, supplier, Installer, and other information necessary to provide a record of selections made.
4. For each principal product, indicate whether record Product Data has been submitted in operation and maintenance manuals instead of submitted as record Product Data.
5. Note related Change Orders and record Drawings where applicable.
B. Format: Submit record Specifications as annotated PDF electronic file or scanned PDF electronic file(s) of marked-up paper copy of Specifications.
1.6 RECORD PRODUCT DATA
A. Recording: Maintain one copy of each submittal during the construction period for project record document purposes. Post changes and revisions to project record documents as they occur; do not wait until end of Project.
B. Preparation: Mark Product Data to indicate the actual product installation where installation varies substantially from that indicated in Product Data submittal.
1. Give particular attention to information on concealed produc ts and installations that cannot be readily identified and recorded later.
2. Include significant changes in the product delivered to Project site and changes in manufacturer's written instructions for installation.
3. Note related Change Orders , record Specifications, and record Drawings where applicable.
C. Format: Submit record Product Data as scanned PDF electronic fi le(s) of marked -up paper copy of Product Data.
1. Include record Product Data directory organized by Specification Section number and title, electronically linked to each item of record Product Data.
1.7 MISCELLANEOUS RECORD SUBMITTALS
A. Assemble miscellaneous records required by other Specification Sections for miscellaneous record keeping and submittal in connection with actual performance of the Work. Bind or file miscellaneous records and identify each, ready for continued use and reference.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
PROJECT RECORD DOCUMENTS - 017839 - 5
B. Format: Submit miscellaneous record submittals as PDF electronic file.
1. Include miscellaneous record submittals directory organized by Specification Section number and title, electronically l inked to each item of miscellaneous record submittals.
1.8 MAINTENANCE OF RECORD DOCUMENTS
A. Maintenance of Record Documents: Store record documents in the field office apart from the Contract Documents used for construction. Do not use project record documents for construction purposes. Maintain record documents in good order and in a clean, dry, legible condition, protected from deterioration and loss. Provide access to project record documents for Owner’s reference during normal working hours.
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 017839
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
PROJECT RECORD DOCUMENTS - 017839 - 6
(THIS PAGE INTENTIONALLY LEFT BLANK)
EV Blueprint Grant Project
SECTION 26 05 00
ELECTRICAL MATERIALS AND METHODS
1 PART 1 - GENERAL
1.1 SUMMARY
A. The work under this section is subject to the requirements of the Contract Documents including the GENERAL CONDITIONS, SUPPLEMENTARY CONDITIONS, and sections under Division 1 GENERAL REQUIREMENTS.
B. The requirements of this section apply to all work of Division 16 as applicable.
1.2 SUBMITTALS
A. Product Data: Provide product data for all equipment under this section.
B. Shop Drawings: Provide shop drawings for panelboards, switchgear, circuit breakers, transformers, wiring devices, light fixtures, lighting control devices.
C. Provide six copies of each type of submittal.
1.3 QUALITY ASSURANCE
A. All work must comply with NEC, IEC, all local, City, County, State & federal Codes.
B. All equipment must bear UL, CSA, ETRL or other City of Sacramento accepted listing age ncy or testing agency label.
PART 2 - PRODUCTS
2.1 MATERIALS
A. All material and equipment used for this project shall be new and free of manufacturing defects.
2.2 MANUFACTURERS
A. Manufacturers of each type of product shall have been in business manufacturing the type of product provided for at least the last three consecutive years.
2.3 PRODUCTS
A. Anchors and Fasteners
1. Materials and Finishes: Corrosion resistant
B. Formed Steel Channel
1. Manufacturers: B-Line or Unistrut
2. Channel shall be Galvanized
C. Sealing and Fireproofing
1. Fire and / or Smoke rated Surfaces
EV Blueprint Grant Project
SECTION 26 05 00
ELECTRICAL MATERIALS AND METHODS
2 a. 3M CP 25N/S or CP25S/L caulk, 3M FS 195 wrap/strip with restricting collar, 3M CS 195 composite sheet, Pipe Shields Inc. series F fire barrier kits, Proset systems fire rated floor and wall penetrations; Insta-Foam Products Insta-Fire seal Firestop Foam, Dow Corning Fire Stop System, or an approved equal. b. All products must be UL listed or tested by an independent testing laboratory.
Use a product that has a rating not less than the rating of the wall or floor being penetrated.
2. Non-Rated Surfaces
a. Use stamped steel 'chrome plated, hinged, split ring escutcheons or floor/ceiling plates for covering openings in occupied areas where conduit is exposed. b. In exterior wall openings below grade, use a modular mechanical type seal consisting of interlocking synthetic rubber links shaped. To continuously fill the annular space between the conduit and the cored opening or a water-stop type wall sleeve.
c. At interior wall or floor openings use Tremco Dymonic, Sika Corp. Sikaflex la, Sonneborn Sonolastic NPI, or Mameco Vilken 116 urethane caulk or approved equal to affect the seal.
D. Electrical Identification
1. Nameplates shall have 1/2" high lettering, except where space is limited; letters may be 1/4" high. Face of nameplate to be black and letters to be white, except emergency power equipment nameplates are to have white face with red letters. Fasteners shall be small metal screws, pop rivets or contact-type with permanent adhesive.
2. Engraved plastic nameplates shall be securely attached to: Panelboards, switchboards, motor control centers, motor starters, disconnects an individually mounted circuit breakers.
3. 4" round, 4" square and 4-11/16" junction boxes concealed above ceilings may be identified with neat lettering on cover with permanent type black marking pen.
4. Nameplates shall identify equipment or load controlled and/or function and shall be same as indicated on contract documents. Voltages shall be shown on panelboard nameplates.
E. Raceway
1. Rigid Steel Conduit (GRC)
a. Hot Dipped Galvanized after threading. Uniform finish coat with chromate for added protection. Manufacture in conformance with ANSI C-80.1 and Federal Specification WW-C-5810D.
2. Intermediate Metal Conduit (IMC)
a. Hot Dipped Galvanized after threading. Manufacture in conformance with Federal Specification WW-C-5810D.
EV Blueprint Grant Project
SECTION 26 05 00
ELECTRICAL MATERIALS AND METHODS
3 3. Electrical Metallic Tubing (EMT)
a. Hot Dipped Galvanized chromate coated. Manufacture in conformance with ANSI C-80.3 and Federal Specification WW-C-563.
4. Rigid Nonmetallic Conduit (PVC)
a. Heavy wall rigid PVC, type class 40, listed for underground encased and aboveground applications. Rated for use with 90 C conductors. Manufacture in conformance with NEMA TC-2 and Federal Specification WC1094A.
5. Flexible Metal Conduit
a. Electro-galvanized single strip steel. Manufacture in conformance with Federal Specification WWC-566. Aluminum prohibited.
6. Liquid Tight Flexible Metal Conduit
a. Electro-galvanized single strip steel with PVC coating. Aluminum prohibited.
7. Metal Clad Cable (MC)
a. Prohibited.
F. Conduit Fittings
1. Bushings
a. Insulated type for threaded GRC, IMC or raceway connectors without factor installed plastic throat conductor protection.
b. Insulated grounding type for threaded GRC and IMC.
c. Plastic snap-in bushings are prohibited.
d. Provide metallic threaded bushings at #4 and larger conductors.
2. Connectors and couplings
a. All conduit fittings to be steel, compression or set screw type. b. Die cast fitting are prohibited.
G. Conductors and Cable
1. All conductors shall be stranded copper UON.
2. Single conductor stranded, soft drawn copper wire having conductivity of not less than 98 percent of that of pure copper, with insulation rated at 600 volts AC, type THWN, THHN and XHHW.
3. Aluminum conductors are prohibited.
EV Blueprint Grant Project
SECTION 26 05 00
ELECTRICAL MATERIALS AND METHODS
4 4. Minimum insulation for branch circuits shall be 90 C., and 75 C. for conductors 3 AWG and larger.
H. Wiring Devices
1. Wall Switches
a. Toggle type, quiet acting, 20 ampere, 120/277 volt rated, UL listed for motor loads up to 80 percent of rated ampacity. Acceptable manufacturers and types:
Arrow-Hart 1221, Leviton 1221, Pass and Seymour 20AC1, Bryant 4901, Hubbell 1221, Eagle 1201.
2. Receptacles
a. Straight Parallel blade 20 ampere, 125 VAC, 2 pole, 3 wire grounding.
Acceptable manufacturers and types: Arrow-Hart 5352, Leviton 5352, Pass and Seymour 5352, Bryant 5352, Hubbell 5352, Eagle 5362.
b. Ground Fault Interrupter: Feed through type, 20 ampere, 125 VAC, specification grade. Acceptable manufacturers and types: Arrow-Hart GF-5342 or Hubbell GF- 5362GY.
c. Special-purpose or heavy duty receptacles shall be of type and of rating and number of poles indicated or required for the purpose.
3. Plates
a. Specification grade nylon cover plates, Leviton 807 Series. b. Type 302 stainless steel, smooth satin finish metal. 18 percent chrome, 8 percent nickel. Hubbell S series.
c. Die-cast copper-free aluminum gasketed raintight cover for outdoor use or as indicated.
4. Wiring device and plate color.
a. As selected by the Architect.
I. Circuit and Motor Disconnects
1. Toggle type disconnect switches: 120 volt rating, 20 ampere single pole, 1 HP maximum.
2. Manual Motor Starters: Quick-make quick-break, thermal overload protection, Square D, Class 2510.
3. Safety Switches: Heavy duty, fused type, dual rated, quick-make quick-break with fuse rejection feature for use with class R fuses only, unless other fuse type is specifically noted.
4. Combination Starter Disconnect: Heavy duty, fused type, dual rated, quick-make quick- break with fuse rejection feature for use with class R fuses only, unless other fuse type is specifically noted. Provide coil voltage coordinated with control requirements.
EV Blueprint Grant Project
SECTION 26 05 00
ELECTRICAL MATERIALS AND METHODS
5 Provide hand-off-auto switch, thermal overloads and one N.O. and one N.C. auxiliary contact.
J. Supports
1. Safety factor of 4 required for every fastening device or support for electrical equipment installed. Support to withstand four times weight of equipment it supports. Bracing to comply with Seismic Zone 3 requirements.
2. Conduit supports for horizontal or vertical single runs: Hot dipped galvanized heavy duty sheet steel straps, mineralac clamps or channel system with appropriate components. Spring type pressure clamps may be used with conduit through 3/4".
3. Conduit supports for horizontal and vertical multiple runs: Channel systems with appropriate components. Horizontal runs to be supported with appropriate sized rods and vertical runs anchored to structure. Spring type pressure clamps may be used with conduit through 3/4".
4. Vertical conduit runs 1-1/4" and larger passing through floors shall be supported at each floor with conduit riser grips.
K. Outlet and Junction Boxes
1. Galvanized steel or cast type outlet boxes to accommodate device indicated by symbol, in conformance with code requirements, number and size of conductors and splices and consistent with type of construction.
2. Surface mounted boxes shall have the appropriate cover, raised device covers on 4" square and 4-11/16" boxes. Boxes in block shall have device covers that are square drawn or square cut. Boxes in tile shall have tile covers. Use round drawn device covers on boxes in lath and plaster walls or dry wall only.
3. Device Outlet: Minimum of 4” square, use deep boxes where they will fit in the wall, minimum of 1-1/2” where deep boxes will not fit.
4. Gangable type boxes are not allowed. Box ears with tapped holes must turn into the box opening.
5. Junction or pull boxes and covers: Code gauge steel with galvanized or sheradized finish with covers secured by galvanized machine screws. Boxes shall be large enough so that code required minimum cable bending radii can be rolled and constructed.
Knock out punches shall be used for required holes.
L. Switchboards
1. Secondary voltage switchboards shall be completely metal enclosed assemblies constructed in accordance with applicable NEMA, USASI and IEEE standards.
Switchboard assemblies shall be constructed and assembled to permit lifting or rolling as single unit.
2. Switchboard shall be service entrance rated.
3. Outdoor equipment shall be enclosed to provide NEMA 3R non-walk-in-housing.
Outdoor equipment shall include full height door in front of each switchboard vertical EV Blueprint Grant Project
SECTION 26 05 00
ELECTRICAL MATERIALS AND METHODS
6 section, hinged and closed with rugged heavy-duty lockable door handle with 3-point latch. External roof of enclosure shall provide protected openings for ventilation. Floor sills shall be heavy duty 4" x 1-1/2" steel channel. Opening rainproof exterior door shall not expose live parts. Switchboard shall be dead-front behind exterior doors.
4. Arrange switchboards as indicated on drawings. Dimensions indicated on drawings are maximum allowed
5. Switchboard shall be free standing, front access only.
6. Common bases and frame structures shall be one-piece welded, structural steel forms in gage required, complete with lifting lugs. Where shipping splits are required, bases and frames shall be bolted at job site.
7. Switchboard compartments shall be totally enclosed, stretcher leveled, steel, not less than 12 gauge, bolted to base, with side, front and rear panels of one piece welded construction. Compartments shall have ventilation louvers in top and bottom sections of front and rear panels.
8. Bus shall meet UL 891 requirements.
9. Provide neutral bus at same ampere capacity as phase buses.
10. Provide 1/4" x 4" copper ground bus with assemblies arranged for ground continuity between grounding bus, base, framework and enclosing panels, with unfinished exposed bar metal surfaces between contacts.
11. Bus shall be solid tin or silver plated copper, minimum 98% conductivity, sized to maximum current density of 1000 amp per square inch of cross sectional area.
12. Switchboard shall be designed for both bottom and top exit of branch and feeder conduits.
13. Branch feeder overcurrent devices shall consist of stationary mounted molded case circuit breakers with continuous current ratings, interrupting capacity and frame size as indicated on drawings.
14. Switchboard enclosures, inside and out, shall be cleaned, phosphatized, and given one coat of red oxide primer, then painted inside and out with 2 coats of standard enamel over suitably prepared metal. Surfaces damaged during shipping or installation shall be refinished by Owner's contractor. Provide Owner with one can of touch up paint.
M. Panelboards
1. Provide Lighting Appliance and Power Distribution panelboards as indicated on drawings and as scheduled. Panelboards shall be factory assembled, constructed in accordance with latest NEMA, UL, Federal and NEC requirements, and shall bear UL label. Panelboard cabinets including boxes and fronts shall be code gage galvanized steel.
2. Paint interior and exterior surfaces. Medium light gray finish, applied by electro- deposition process over an iron phosphate pretreatment.
EV Blueprint Grant Project
SECTION 26 05 00
ELECTRICAL MATERIALS AND METHODS
7 3. Panelboards to be fully rated. The AIC of each panelboard shall be greater than the available fault current. Series rating of panelboards and equipment is prohibited .
4. All panelboard bussing shall be copper. Not less than 98 percent of that of pure copper. Aluminum bussing is prohibited.
5. Panelboards shall have full ampacity bussing throughout and shall be full size in regard to number of possible pole spaces. Lighting and Appliance panels shall have 42 poles per section except where shown to be less. Power Distribution panels shall have number of poles as scheduled. Panelboards shall be identified with phases reading left to right, and circuits alternately numbered left to right - odd number on left, even on right.
6. Panel boards shall have neutral bussing rated at 100% and ground bussing rated at 50%.
7. Where required panelboards shall be labeled as suitable for use as service entrance equipment.
8. Panelboards covers shall be hinged door-in-door construction, flush lift latch and lock, two keys per panel. Key all panels alike.
9. Circuit breakers shall be bolt on type only.
N. Circuit Breakers
1. Molded Case Circuit breakers: One, two or three pole with single common trip handle.
2. 600 volt or 250 volt minimum, see plans for required voltage.
3. Circuit breakers to be fully rated for the system, series rating is prohibited.
O. Lighting
1. Refer to the lighting fixture schedule for manufacturer, model number and descriptions of each type of Luminaire. Where the model number and description do not match, the description shall take precedence.
2. Provide proper trim type for recessed luminaries. Trim type to be compatible with the type of ceiling. Provide flanged luminaries, slope ceiling adaptors, etc. as required.
Review the architectural ceiling plans to verify.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Fire Rated Surface
1. When the opening is through a fire rated wall floor, ceiling or roof the opening must be sealed by installing a steel sleeve, minimum 12 ga., through the opening and extending beyond a minimum of 1 inch. Further, the sleeve shall be large enough to allow a minimum of a 1 inch void between the sleeve and the item of penetration. The void shall be packed with an approved packing material and the ends of the sleeve sealed with EV Blueprint Grant Project
SECTION 26 05 00
ELECTRICAL MATERIALS AND METHODS
8 minimum of 1 inch of a listed fire-resistive silicone compound to a depth required to meet the fire rating of the structure penetrated.
2. Install approved product in accordance with, manufacturer's instructions where, a p pipe (i.e. cable tray, bus, cable bus, conduit, wireway, trough, etc.) penetrates a fire rated surface.
B. Non-Rated Surfaces
1. When the opening is through a non-fire rated floor, ceiling or roof the opening must be using an approve type of material.
2. Use galvanized sheet metal sleeves in hollow wall penetrations to provide a backing for the sealant. Grout area around sleeve in masonry construction.
3. Install escutcheons or floor/ceiling plates where pipe, penetrates non-fire rated surfaces in occupied spaces. Occupied spaces for this paragraph include only those rooms with finished ceilings and the penetration occurs below the ceiling.
4. In exterior wall openings below grade, assemble rubber links of mechanical seal to the proper size for the pipe and tighten in place, in accordance with the manufacturer's instructions.
5. At interior partitions, pipe penetrations are required to be sealed for all clean rooms, laboratories, most hospital spaces, computer rooms, tele/data/com rooms and similar spaces where the room pressure or odor transmission must be controlled. Apply sealant to both sides of the penetration in such a manner that the annular space between the pipe sleeve and the pipe is completely filled.
C. Identification
1. Engraved plastic nameplates shall be securely attached to each panelboard, generator, automatic transfer switch, separately mounted circuit breaker, and disconnect switchs.
2. 4" round, 4" square and 4-11/16" junction boxes concealed above ceilings may be identified with neat lettering on cover with permanent type black marking pen.
3. Nameplates shall identify equipment or load controlled and/or function and shall be same as indicated on contract documents. Voltages shall be shown on panelboard nameplates.
4. Group conductors as to circuits and arrange in neat manner in pull boxes, cabinets and panelboards. Group, bind together with nylon ties and identify conductors as to feeder or branch circuit. Phase identification shall be consistent throughout system.
5. Identify each conductor of all systems at each panel, pull box and at each outlet with permanently attached, wrap around, adhesive markers.
6. Identification of junction boxes and conductors shall include panelboard, switchboard or motor control center, circuit number, phase, control circuit number or other appropriate number or letter that will expedite future tracing and trouble shooting.
EV Blueprint Grant Project
SECTION 26 05 00
ELECTRICAL MATERIALS AND METHODS
9 D. Raceway
1. Conceal all conduits. Exposed conduits are only permitted in mechanical rooms, electrical rooms, or where walls and ceilings will not be covered with a finish material.
Where exposed conduit are permitted install parallel to building lines and as tight to structure as possible.
2. Do not install conduits on surface of building, across the roof or parapet, unless specifically shown on drawings.
3. Below grade conduits: Place a minimum of 3” sand or clean earth fill cover over conduits. Install in a level trench bed so conduit is in contact with the earth the entire length. Where three or more conduits are in a trench, use conduit spacers located 5’ on center, maintain a 3” separation between conduits.
4. Underground conduits to have a minimum of 32” cover or as required by code, whichever is more stringent.
5. Minimum conduit size: 3/4", except as noted.
6. Exterior exposed conduits, above grade to be rigid steel UON. When routed on exterior building walls, conduit shall be painted to match the building.
7. Minimum size for flexible metal conduit is 1/2" except 3/8" for lighting fixtures.
8. Ream conduit smooth at ends, cap upon installation, rigidly attach to structural parts of building and securely fasten to outlet boxes, panel cabinets, junction boxes, pull boxes, splicing chambers, safety switches and other components of the raceway system.
9. Independently support or attach raceway system to structural parts of construction in accordance with good industry practice. Suspended ceiling systems shall not be considered as structural parts of the construction for conduit support. Conduit, conduit systems or boxes shall not be supported or secured by wire, but shall be supported by devices manufactured specifically for this purpose. Plastic tie-wrap is not permitted.
10. Conduits supported on channel systems shall be secured on each channel with appropriate clamps.
11. Conduit installed in metal stud walls must be secured to prevent rattling.
12. Provide spare capped conduits for flush-mounted panelboards consisting of three 3/4" conduits to the ceiling space above, and three 3/4" conduit to the ceiling space below floor slab.
13. Homerun conduits to contain no more than three branch circuits.
14. Underground conduits and raceways shall be swabbed prior to pulling conduits.
15. Mandrel all underground service lateral and feeder raceways prior to pulling wire.
16. Install a code sized copper equipment grounding conductor in all conduits.
17. No more than three 90 degree bends or a total of 270 degree combined bends between pull boxes. Provide pull boxes as required, size pull boxes per the NEC.
EV Blueprint Grant Project
SECTION 26 05 00
ELECTRICAL MATERIALS AND METHODS
10 18. Rigid Steel Conduit (GRC)
a. May be used in all locations, concealed or exposed, except where flex is required.
b. Where conduits transition from underground to above grade, use rigid steel elbows and risers.
c. Where installed in contact with earth or fill material, conduit shall be wrapped with net one (1) layers of Scotchwrap #50, Johns-Manville VID-10, or equal, or PVC coated rigid steel.
19. Intermediate Metal Conduit (IMC)
a. IMC may be installed in the same locations as GRC except, IMC may not be installed underground or in contact with the earth.
b. Connections shall be made with double locknuts and bushings. Bushings to be steel with integral insulator except conduits 2" and below may have high impact thermoset Phenolic insulating bushings.
20. Electrical Metallic Tubing (EMT)
a. Electrical metallic tubing may be used in exposed interior locations and in furred spaces. Connectors to outlets, boxes and panels shall be with plastic insulator.
21. Rigid Nonmetallic conduit (PVC)
a. Use for underground applications.
b. All stub ups to transition to rigid steel elbows and risers.
22. Flexible Metal Conduit
a. Max length of 6 feet. Use for connections in dry locations to equipment, light fixtures and vibrating equipment.
23. Liquid tight Flexible Metallic Tubing
a. Max length of 6 feet. Use for connections in damp or wet locations to equipment, light fixtures and vibrating equipment.
24. Metal Clad Cable (MC)
a. Prohibited.
E. Conductors and Cable
1. Color code power wiring as follows:
a. 120/208 volt, 3 phase, 4 wire: phase A-black, phase B-red, phase C-blue, neutral-white; ground conductor-green.
EV Blueprint Grant Project
SECTION 26 05 00
ELECTRICAL MATERIALS AND METHODS
11 b. 277/480 volt, 3 phase, 4 wire: phase A-brown, phase B-orange, phase C-yellow, neutral-gray; ground conductor-green.
c. Pull wire and cables into conduits and raceways in such manner that insulation will not be damaged or undue strain placed on conductors. Lubricants shall be UL listed.
F. Wiring devices
1. Install devices plumb, level with finished surfaces and free from blemishes.
2. Install devices at heights scheduled, and as indicated on drawings. Install duplex wall receptacles vertically with ground contacts down except where shown otherwise or where space problem occurs. Install lighting switches vertically on latch side of door within 6" of frame edge.
3. Install devices above counters 2" to bottom above countertop or backsplash. Install at same height all devices above any one counter or fixed cabinet. Verify locations prior to rough-in.
4. Plates to be stainless steel in all public spaces, U.O.N.
G. Circuit and Motor Disconnects
1. Provide disconnect switches in sight of each motor location unless otherwise noted.
2. Coordinate fuse ampere rating with the nameplate of the installed equipment.
H. Supports
1. Provide all electrical equipment supports.
2. Verify mounting height of all luminaries equipment and items prior to installation.
3. Provide independent supports to structural member for luminaries, material or equipment. Do not use other trade supports for a means of fastening electrical equipment or materials.
4. Support conduit within 18” of outlet boxes, panels, cabinets and deflections.
5. Maximum distance between supports not to exceed 8 foot spacing.
6. Provide seismic bracing per UBC requirements.
I. Outlet and Junction boxes
1. Set outlet boxes parallel to construction and independently attached to same. Adjust flush type boxes to set level with finished surface. Back to back and through-the-wall boxes are not acceptable. Ganged sectional type boxes are not acceptable.
2. Box Support: Mount boxes straight. In stud walls provide horizontal bracing at top or bottom of box for 3 or more gang device boxes. For up to 2 gang device boxes, provide stud support one side, with short piece of stud of support on opposite side as shown in EV Blueprint Grant Project
SECTION 26 05 00
ELECTRICAL MATERIALS AND METHODS
12 details. In masonry walls boxes shall be solidly mortared in. Tie wire supported boxes are not acceptable.
3. Provide multi-ganged boxes where 2 or more devices are in same location, except where otherwise noted. Provide partitions in multi-ganged boxes where different types of devices are installed, or devices installed operate at different voltages.
4. Identify circuit number and voltage on all junction boxes covers.
5. Paint fire and telephone box covers for identification. Red covers for fire, blue for telephone.
J. Switchboards
1. Install equipment per manufacturer's recommendations and as indicated. Coordinate final locations of equipment with General Contractor, and review final locations with Architect prior to setting equipment.
2. Protect equipment during installation to prevent twisting or deformations, exposure to potentially damaging environments, and work of other trades. Maintain protection until completion of construction.
K. Panelboards
1. Final locations, sizes and mounting of panelboards shall be reviewed with Architect prior to installation.
2. Install panelboards and enclosures as indicated, in accordance with manufacturer's written instructions, applicable requirements of NEC standards, NECA's "Standards of Installation", and in compliance with recognized industry practices to ensure that products fulfill requirements.
3. Where flush panels are installed, verify available recessing depth and coordinate wall framing with other divisions.
4. Fasten enclosures firmly to walls and structural surfaces, ensuring they are permanently and mechanically anchored.
5. Top breaker handle: Maximum of 6 ft above finished floor.
6. Tighten connectors and terminals, including screws and bolts, in accordance with equipment manufacturer's published torque tightening values for equipment connectors.
Where manufacturer's torquing requirements are not indicated, tighten connectors and terminals to comply with tightening torques specified in UL Standards 486A and B.
7. Prior to energization of panelboards, check with ground resistance tester phase-to-phase and phase-to-ground insulation resistance levels.
8. Prior to energization, check panelboards for electrical continuity of circuits and for short-circuits.
9. Balance load on panelboards so phases are balanced to 10% of each other.
Reconnect or redistribute circuits and/or circuit breakers to achieve balanced condition.
EV Blueprint Grant Project
SECTION 26 05 00
ELECTRICAL MATERIALS AND METHODS
13 Submit ammeter readings for all panelboard feeders indicating normal operating load and phase balance.
10. Each panelboard shall have typewritten circuit schedule installed inside cover of each panelboard. Schedule shall be covered with clear plastic and shall include description of connected loads, room numbers, room name, area or item served for each branch circuit. Label spare circuits as "SPARE". Room numbers used shall be those used by Owner except as otherwise directed by Architect.
11. Flush panels in finished areas shall have factory applied primer coat painted trim for finish painting by others.
12. Where panels are installed flush, provide (3) ¾” spare conduits from panel to accessible space above and/or below the panel.
L. Circuit breakers
1. Provide device on handle to lock breaker in “ON” position for breakers feeding fire alarm, time switches, nightlights and similar circuits required to be continuously energized.
M. Grounding
1. Ground fittings shall be an approved manufactured type, installed and connected to conform with Code requirement; UL 467.
2. Ground neutral bus and non-current-carrying parts of equipment at each installation in accordance with applicable Codes. Ground conductor shall be copper having a current capacity in accordance with N.E.C. and Electrical Safety Orders.
3. Completely ground all equipment cases, motor frames, and other items to be grounded to satisfy requirements of N.E.C. Install bond wire in flexible conduit. Install copper bond wire, sized in accordance with N.E.C., in all nonmetallic raceways and bond to all metallic parts using approved fittings. Bond wire shall be copper.
4. Connect service ground conductor to metallic cold water pipe (pipe must be in contact with earth for 10 feet or more and electrically continuous to point of connection of ground electrode conductor). Additional ground electrode shall supplement the water pipe ground. The supplemental ground electrode shall be a concrete encased ground "Ufer". Bond building steel to ground system.
3.2 Project Closeout
A. Operation and Maintenance Manuals
1. Provide three hard copies and one electronic PDF of operation and maintenance manuals. O & M’s shall include the following: Panelboards, switchgear, transformers, light fixtures, and lighting control devices.
B. Testing and Commissioning
1. Receptacle Polarity Test: Spot check receptacles installed or reconnected with a circuit polarity tester. Tester shall test for open ground, open hot, open neutral, reverse polarity, hot and ground reversed, hot and neutral reversed.
EV Blueprint Grant Project
SECTION 26 05 00
ELECTRICAL MATERIALS AND METHODS
14 2. Ground-Fault Receptacle Circuit Interrupter Test: Test each receptacle or branch circuit breaker having ground-fault circuit protection to assure that the ground-fault circuit interrupter will not operate when subjected to a ground fault current of less than 4 milliamperes and will operate when subjected to a ground fault current exceeding 6 milliamperes. Perform testing using an instrument specifically designed for testing ground fault interrupters. Pushing the test button is not acceptable. Replace receptacles that do not interrupt power with 5/1000 of an ampere within 1/40th of a second. Correct deficiencies and submit test report.
3. Check the lighting system after start up and ensure that all lamps are operating and all light fixtures are clean.
4. Check the locations and settings on all occupancy sensors and verify they are operating correctly. Check for false on or off in coverage areas. Verify walking by open doors or windows does not activate an occupancy sensor within a private office, support area or conference room. Adjust and correct any deficiencies. Provide a room by room report.
5. Lighting Control Panel: Program the lighting control panel as directed by the engineer.
Verify all zones are operating correctly. Provide a written schedule to the City of Sacramento.
END OF SECTION 26 05 00
EV Blueprint Grant Project
SECTION 26 05 26
GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 260526 - 1 SECTION 260526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General an d Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes grounding and bonding systems and equipment.
1.3 ACTION SUBMITTALS
A. Product Data: For each type of product indicated.
1.4 INFORMATIONAL SUBMITTALS
A. Coordination Drawings: Plans showing dimensioned locations of grounding features specified in "Field Quality Control" Article, including the following:
1. Ground rods.
2. Grounding arrangements and connections for separately derived systems.
B. Qualification Data: For testing agency and testing agency's field supervisor.
C. Field quality-control reports.
1.5 CLOSEOUT SUBMITTALS
A. Operation and Maintenance Data: For grounding to include in emergency, operation, and maintenance manuals.
1. In addition to items specified in Section 017823 "Operation and Maintenance Data," include the following:
a. Plans showing as-built, dimensioned locations of grounding features specified in "Field Quality Control" Article, including the following:
1) Ground rods.
2) Grounding arrangements and connections for separately derived systems.
EV Blueprint Grant Project
SECTION 26 05 26
GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 260526 - 2
1.6 QUALITY ASSURANCE
A. Testing Agency Qualifications: Certified by NETA.
PART 2 - PRODUCTS
2.1 SYSTEM DESCRIPTION
A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.
B. Comply with UL 467 for grounding and bonding materials and equipment.
2.2 MANUFACTURERS
2.3 CONDUCTORS
A. Insulated Conductors: Copper wire or cable insulated for 600 V unless otherwise required by applicable Code or authorities having jurisdiction.
B. Bare Copper Conductors:
1. Solid Conductors: ASTM B 3.
2. Stranded Conductors: ASTM B 8.
3. Bonding Cable: 28 kcmil, 14 strands of No. 17 AWG conductor, 1/4 inch in diameter.
4. Bonding Conductor: No. 4 or No. 6 AWG, stranded conductor.
5. Bonding Jumper: Copper tape, braided conductors t erminated with copper ferrules; 1-5/8 inches wide and 1/16 inch thick.
6. Tinned Bonding Jumper: Tinned-copper tape, braided conductors terminated with copper ferrules; 1-5/8 inches wide and 1/16 inch thick.
C. Grounding Bus: Predrilled rectangular bars of annealed copper, 1/4 by 4 inches in cross section, with 9/32-inch holes spaced 1-1/8 inches apart. Stand-off insulators for mounting shall comply with UL 891 for use in switchboards, 600 V and shall be Lexan or PVC, impulse tested at 5000 V.
2.4 CONNECTORS
A. Listed and labeled by an NRTL acceptable to authorities having jurisdiction for applications in which used and for specific types, sizes, and combinations of conductors and other items connected.
B. Welded Connectors: Exothermic -welding kits of types recommended by kit manufacturer for materials being joined and installation conditions.
C. Bus-Bar Connectors: Compression type, copper or copper alloy, with two wire terminals.
EV Blueprint Grant Project
SECTION 26 05 26
GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 260526 - 3 D. Beam Clamps: Mechanical type, terminal, ground wire access from four directions, with dual, tin-plated or silicon bronze bolts.
E. Cable-to-Cable Connectors: Compression type, copper or copper alloy.
F. Cable Tray Ground Clamp: Mechanical type, zinc-plated malleable iron.
G. Conduit Hubs: Mechanical type, terminal with threaded hub.
H. Ground Rod Clamps: Mechanical type, copper or copper alloy, terminal with hex head bolt I. Ground Rod Clamps: Mechanical type, copper or copper alloy, terminal with hex head bolt.
J. Lay-in Lug Connector: Mechanical type, copper rated for direct burial terminal with set screw.
K. Service Post Connectors: Mechanical type, bronze alloy terminal, in short - and long -stud lengths, capable of single and double conductor connections.
L. Signal Reference Grid Clamp: Mechanical type, stamped-steel terminal with hex head screw.
M. Straps: Solid copper, copper lugs. Rated for 600 A.
N. Tower Ground Clamps: Mechanical type, copper or copper alloy, terminal one-piece clamp.
O. U-Bolt Clamps: Mechanical type, copper or copper alloy, terminal listed for direct burial.
P. Water Pipe Clamps:
1. Mechanical type, two pieces with stainless-steel bolts. a. Material: Tin-plated aluminum
b. Listed for direct burial.
2. U-bolt type with malleable -iron clamp and copper ground connector rated for direct burial.
2.5 GROUNDING ELECTRODES
A. Ground Rods: Copper-clad steel feet5/8 inch by 96 inches B. Concrete Encased Electrode: Bare Copper, #4 AWG Minimum.
PART 3 - EXECUTION
3.1 APPLICATIONS
A. Conductors: Install solid conductor for No. 8AWG and smaller, a nd stranded conductors for No. 6 AWG and larger unless otherwise indicated.
EV Blueprint Grant Project
SECTION 26 05 26
GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 260526 - 4 B. Underground Grounding Conductors: Install bare copper conductor, No. 2/0 AWG minimum.
1. Bury at least 24 inches below grade.
C. Isolated Grounding Conductors: Green -colored insulation with continuous yellow stripe. O n feeders with isolated ground, identify grounding conductor where visible to normal inspection, with alternating bands of green and yellow tape, with at least three bands of green and two bands of yellow.
D. Grounding Bus: Install in electrical equipment rooms, in rooms housing service equipment, and elsewhere as indicated.
1. Install bus horizontally, o n insulated spacers 2 inches minimum from wall, 6 inches above finished floor unless otherwise indicated.
2. Where indicated on both sides of doorways, route bus up to top of door frame, across top of doorway, and down; connect to horizontal bus.
E. Conductor Terminations and Connections:
1. Pipe and Equipment Grounding Conductor Terminations: Bolted connectors.
2. Underground Connections: Welded connectors except at test wells and as otherwise indicated.
3. Connections to Ground Rods at Test Wells: Bolted connectors.
4. Connections to Structural Steel: Welded connectors.
5. Connections to Concrete encased electrode : exothermic welding, listed lugs, listed pressure connectors, listed clamps or other listed means.
3.2 GROUNDING AT THE SERVICE
A. Equipment grounding conductors and grounding electrode conductors shall be connected to the ground bus. Install a main bonding jumper between the neutral and ground buses.
3.3 GROUNDING SEPARATELY DERIVED SYSTEMS
A. Generator: Install grounding electrode(s) at the generator location. The electrode shall be connected to the equipment grounding conductor and to the frame of the generator.
3.4 GROUNDING UNDERGROUND DISTRIBUTION SYSTEM COMPONENTS A. Comply with IEEE C2 grounding requirements.
B. Pad-Mounted Transformers and Switches: Install two ground rods and ground ring around the pad. Ground pad -mounted equipment and n oncurrent-carrying metal items associated with substations by connecting them to underground cable and grounding electrodes. Install tinned - copper conductor not less than No. 2 AWG for ground ring and for taps to equipment grounding terminals. Bury ground ring not less than 6 inches from the foundation.
EV Blueprint Grant Project
SECTION 26 05 26
GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 260526 - 5
3.5 EQUIPMENT GROUNDING
A. Install insulated equipment grounding conductors with all feeders and branch circuits.
B. Install insulated equipment grounding conductors with the following items, in addition to those required by NFPA 70:
1. Feeders and branch circuits.
2. Electric Vehicle Charger circuits.
3. Receptacle circuits.
4. Single-phase motor and appliance branch circuits.
5. Three-phase motor and appliance branch circuits.
6. Flexible raceway runs.
7. Armored and metal-clad cable runs.
8. Busway Suppl y Circuits: Install insulated equipment grounding conductor from grounding bus in the switchgear, switchboard, or distribution panel to equipment grounding bar terminal on busway.
C. Isolated Grounding Receptacle Circuits: Install an insulated equipment groun ding conductor connected to the receptacle grounding terminal. Isolate conductor from raceway and f rom panelboard grounding terminals. Terminate at equipment grounding conductor terminal of the applicable derived system or service unless otherwise indicated.
D. Isolated Equipment Enclosure Circuits: For designated equipment supplied by a branch circuit or feeder, isolate equipment enclosure from supply circuit raceway with a nonmetallic raceway fitting listed for the purpose. Install fitting where raceway ente rs enclosure, and install a separate insulated equipment grounding conductor. Isolate conductor fro m raceway and from panelboard grounding terminals. Terminate at equipment grounding conductor terminal of the applicable derived system or service unless otherwise indicated.
E. Poles Supporting Outdoor Lighting Fixtures: Install grounding electrode and a separate insulated equipment grounding conductor in addit ion to grounding conductor installed with branch-circuit conductors.
F. Metallic Fences: Comply with requirements of IEEE C2.
1. Grounding Conductor: Barecopper, not less than No. 8 AWG.
2. Gates: Shall be bonded to the grounding conductor with a flexible bonding jumper.
3.6 INSTALLATION
A. Grounding Conductors: Route along shortest and straightest paths possible unless ot herwise indicated or required by Code. Avoid obstructing access or placing c onductors where they may be subjected to strain, impact, or damage.
B. Ground Bonding Common with Lightning Protection System: Comply with NFPA 780 and UL 96 when interconnecting with lightning protection system. Bond electrical power system ground directly to lightning protection system grounding conductor at closest point to electrical EV Blueprint Grant Project
SECTION 26 05 26
GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 260526 - 6 service grounding electrode. Use bonding conductor sized same as system grounding electrode conductor, and install in conduit.
C. Ground Rods: Drive rods until tops are 2 inches below finished floor or final grade unless otherwise indicated.
1. Interconnect ground rods with grounding electrode conductor below grade and as otherwise indicated. Make connections without exposing steel or damaging coating if any.
2. Use exothermic welds for all below-grade connections.
D. Concrete-Encased Grounding Electrode (Ufer Gro und): Fabricate according to NFPA 70; use a minimum of 20 feet of bare copper conductor not smaller than No. 4AWG.
1. If concre te foundation is less than 20 feet long, coil excess conduc tor within base of foundation.
2. Bond grounding conductor to reinforcing steel in at least four locations and to anchor bolts. Extend grounding conductor below grade and connect to building's groundi ng grid or to grounding electrode external to concrete.
E. Concrete-Encased Grounding Electrode (Ufer Ground): Fabricate according to NFPA 70; using electrically conductive coated steel reinforcing bars or rods, at least 20 feet long. If reinforcing is in mul tiple pieces, connect together by the usual steel t ie wires or exothermic welding to create the required length.
F. Connections: Make connections so possibility of galvanic action or electrolysis is minimized.
Select connectors, connection hardware, conductors, and connection methods so metals in direct contact are galvanically compatible.
1. Use electroplated or hot -tin-coated materials to ensure high conductivity and to make contact points closer in order of galvanic series.
2. Make connections with clean, bare metal at points of contact.
3. Make aluminum -to-steel co nnections with stainless -steel separators and mechanical clamps.
4. Make aluminum -to-galvanized-steel connections with tin -plated copper jumpers and mechanical clamps.
5. Coat and seal connections having dissimi lar metals with inert material to prevent future penetration of moisture to contact surfaces.
3.7 FIELD QUALITY CONTROL
A. Testing Agency: Engage a qualified testing agency to perform tests and inspections.
B. Manufacturer's Field Service: Engage a factory -authorized service representative to test and inspect components, assemblies, and equipment installations, including connections.
C. Perform tests and inspections with the assistance of a factory-authorized service representative.
D. Tests and Inspections:
EV Blueprint Grant Project
SECTION 26 05 26
GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 260526 - 7
1. After installi ng grounding system but bef ore permanent electrical circuits have been energized, test for compliance with requirements.
2. Inspect physical and mechanical condition. Verify tightness of accessible, bolted, electrical connections with a calibrated torque wren ch according to manufacture r's written instructions.
3. Test completed grounding system at each location where a maximum ground -resistance level is specified, at service disconnect enclosure grounding terminal and at individual ground rods. Make tests at ground rods before any conductors are connected. a. Measure ground resistance no fewer than two full days after last trace of precipitation and without soil being moistened by any means other than natural drainage or seepage and without chemical treatment or othe r artificial means of reducing natural ground resistance.
b. Perform tests by fall-of-potential method according to IEEE 81.
4. Prepare dimensioned Drawings locating e ach test well, ground rod and ground -rod assembly, and other grounding electrodes. Identify eac h by letter in alphabetical order, and key to the record of tests and observations. Include the number of rods driven and their depth at each location, and inclu de observations of weather and other phenomena that may affect test results. Describe measures taken to improve test results.
E. Grounding system will be considered defective if it does not pass tests and inspections.
F. Prepare test and inspection reports.
G. Report measured ground resistances that exceed the following values:
1. Power Distribution Units or Panelboards Serving Electronic Equipment: 1 ohm(s).
2. Substations and Pad-Mounted Equipment: 5Insert value ohms.
H. Excessive Ground Resistance: If resistance to ground exceeds specified values, notify Architect promptly and include recommendations to reduce ground resistance.
END OF SECTION 260526
EV Blueprint Grant Project
SECTION 26 05 26
GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 260526 - 8
This page intentionally left blank.
CITY OF SACRAMENTO EV BLUEPRINT
MULTIPLE PROJECT SITES
ELECTRIC VEHICLE CHARGING EQUIPMENT - LEVEL 2 26 26 53- 1
SECTION 26 26 53 - ELECTRIC VEHICLE CHARGING EQUIPMENT - LEVEL 2 PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes EV charging equipment that provides Level 2 EV charging.
1.3 DEFINITIONS
A. EV: Electric Vehicle.
B. EV Cable: The off -board cable containing the conductor (s) to connect the EV power controller to the EV that provides both power and communications during energy transfer.
C. EV Capable: Parking spaces that include nearby termination of raceway (conduit) to a power source with sufficient electrical panel capacity designed for simultaneous charging of electric vehicles in all planned EV parking spaces. Electrical wiring need not be pulled through raceway (conduit) until charging station is installed.
D. EV Charger or EV Charging Equipment: See "EVSE".
E. EV Connector: A conductive device that, when electrically coupled to an EV inlet, establishes an electrical connection to the EV for the purpose of power transfer and information exchange.
This device is part of the EV coupler.
F. EV Coupler: A mating EV inlet and connector set.
G. EV Inlet: The device in the vehicle into which the EV connector is inserted, and a conductive connection is made for the transfer of power and communication. This device is part of the EV coupler.
H. EV Make Ready: P arking spaces that include nearby termination of raceway (conduit) and electrical wiring pulled to a power source with sufficient electrical panel capacity for simultaneous charging of electric vehicles in all EV parking spaces.
I. EVSE: Electric Vehicle S upply Equipment. It includes the EV charging equipment and conductors, including the ungrounded, grounded, and equipment grounding conductors and EV cables, attachment plugs, and all other fittings, devices, power outle ts, or apparatus installed specifically for transferring energy between the premise wiring and the EV.
CITY OF SACRAMENTO EV BLUEPRINT
MULTIPLE PROJECT SITES
ELECTRIC VEHICLE CHARGING EQUIPMENT - LEVEL 2 26 26 53- 2
1.4 PREINSTALLATION MEETINGS
A. Preinstallation Conference: Conduct conference at VARIOUS PROJECT SITES , refer to Section 01 10 00- Summary for locations.
1.5 ACTION SUBMITTALS
A. Product Data: For each type of product.
1. Include construction details, material descriptions, dimensions of individual components and profiles, and finishes for EV charging equipment.
2. Include rated capacities, operating characteristics, electrical characteristics, and furnished specialties and accessories.
B. Sustainable Design Submittals:
1. Plan showing location and number of EV charging units, and distance from building.
2. Plan showing "reasonable accessibility" to EV charging units.
3. Plan showing location and number of EV charging units, charging levels and connectors, and ability of EV charging units to participate in a demand -response or time -of-use pricing program, as well as a power load management system that allows for an increased number of charging stations than would otherwise be feasible without power load management.
C. Shop Drawings: For EV charging equipment.
1. Include plans, elevations, sections, and mounting details.
2. Include details of equipment assemblies. Indicate dimensions, weights, loads, required clearances, method of field assembly, components, and location and size of each field connection.
3. Detail fabrication and assembly of mounting assemblies for EV charging equipment.
4. Include diagrams for power, signal, and control wiring.
5. Include verification of wireless communications service at each location of EV charging equipment.
D. Product Schedule: For EV charging equipment. Use designations indicated on Drawings.
1.6 INFORMATIONAL SUBMITTALS
A. Coordination Drawings: Area plans and detai ls, drawn to scale, on which the following items are shown and coordinated with each other, using input from installers of the items involved:
1. Concrete foundation to which equipment will be attached.
2. Electrical service.
3. Communications service, including wireless communications equipment.
B. Qualification Data: For Installer.
1. Installer must provide EVITP Certification and number identifying a cer tified electrician and any additional qualification documentation required by manufacturer.
CITY OF SACRAMENTO EV BLUEPRINT
MULTIPLE PROJECT SITES
ELECTRIC VEHICLE CHARGING EQUIPMENT - LEVEL 2 26 26 53- 3
C. Seismic Qualification Certific ates: For all Chargepoint equipment and accessories, and components, from manufacturer. Refer to plans for concrete foundation scope.
1. Basis for Certification: Indicate whether withstand certification is based on actual test of assembled components or on calculation.
2. Dimensioned Outline Drawings of Equipment Uni t: Identify center of gravity and locate and describe mounting and anchorage provisions.
3. Detailed description of equipment anchorage devices on which the certification is based and their installation requirements.
D. Field quality-control reports.
E. Sample Warranty: For manufacturer's warranty.
1. Minimum of extended 5-year extended warranty is required as part of this project.
1.7 CLOSEOUT SUBMITTALS
A. Operation and Maintenance Data: For EV charging equipment to include in operation and maintenance manuals.
B. Software and Firmware Operational Documentation:
1. Online training and help documentation.
2. Station activation sticker.
1.8 QUALITY ASSURANCE
A. Installer Qualifications: An authorized representative who is trained and approved by the manufacturer. Installer must also have current EVITP Certification and be a licensed electrician in the State of California.
B. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and use.
C. Comply with UL 2231-1. UL 2231-2, UL 2594, and NEC Article 625.
D. Comply with SAE J1772.
E. Comply with FCC Part 15 Class A.
1.9 FIELD CONDITIONS
A. Wireless Survey: Complete wireless survey to determine if wireless provider signals meet or exceed manufacturer's recommended minimum values.
B. Rate equipment for continuous operation under the following conditions unless otherwise indicated:
CITY OF SACRAMENTO EV BLUEPRINT
MULTIPLE PROJECT SITES
ELECTRIC VEHICLE CHARGING EQUIPMENT - LEVEL 2 26 26 53- 4
1. Ambient Temperature: Not below 0 deg. F or over 122 deg F.
2. Altitude: Not exceeding 1,000 feet . Note: The average elevation of Sacramento is 26 feet, this will not be an issue.
C. Interruption of Existing Electric Service: Do not interrupt electric service to facilities occupied by Owner or others unless permitted un der the following conditions and then only after arranging to provide temporary electric service according to requirements indicated:
1. Notify Owner’s Representative no fewer than three days in advance of proposed interruption of electric service.
2. Do not proceed with interruption of electric service without Owner’s Representative written permission.
1.10 WARRANTY
A. Manufacturer's Warranty: Manufacturer and Installer agree to repair or replace components of EV charging units that fail(s) in materials or workmanship within specified warranty period.
1. Standard Warranty Period: One year from date of Substantial Completion.
2. Extended Warranty Period: Five years from date of Substantial Completion is required for all equi pment. Provide Chargepoint Assure Plan for 5 years o r as approved. Provide 5-year commercial cloud plan pre-paid as part of this project.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Basis-of-Design Product: Provide ChargePoint CP6000-series EV charging stations, ref. plans.
B. Source Limitations: EV charging equipment shall be from a single manufacturer. Substitutions are not acceptable without written approvals through the Submittal and Substitution process.
2.2 EV CHARGING EQUIPMENT DESCRIPTION
A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and use.
B. Comply with NFPA 70.
C. ADA compliant, including reach ranges and clear floor area.
D. Metering: +/- 2 percent from 2 percent to full scale of output (30 A).
E. EV Charging Equipment Mounting: Pedestal mount to concrete foundation.
F. Enclosures:
CITY OF SACRAMENTO EV BLUEPRINT
MULTIPLE PROJECT SITES
ELECTRIC VEHICLE CHARGING EQUIPMENT - LEVEL 2 26 26 53- 5
1. Rated for environmental conditions at installed location. a. Outdoor Locations: NEMA 250, Type 3R.
b. Aluminum and UV-resistant plastic.
c. Paint and Anodized.
d. Charging components protected by security screws.
e. Charging connectors in locking holsters.
f. Meter, modem, and CPU, tamper resistant.
G. EV Cable and Connectors:
1. SAE J1772 connector.
2. One or Two connectors with locking holster, depending on location. Verify on plans.
3. 18-foot cable with cable management system.
H. Status Indicators:
1. LEDs to indicate power , vehicle charging, charging complete, system status, faults, and service, as well as authorization.
I. Display Screen:
1. VGA-resolution, daylight -viewable LCD screen with UV protection. Daylight readable and fingerprint resistant.
2. Displays power, charging, charging complete, remote control, system status, faults, payment and pricing details, and service.
J. Networking:
1. WAN Communications: Cellular GSM/GPRS and CDMA.
2. LAN Communications: 2.4 GHz Wi-Fi 802.11b/g/n.
3. Capable of remote configuration, diagnostics and reporting.
4. Capable of remote software updates (future proof).
K. Payment System:
1. RFID (ISO 15693, ISO 14443), NFC, Contactless credit card reader.
2. PCI (Payment Card Industry) compliant.
3. Capable of remote control and authorization including mobile phone application or toll free phone number.
L. Charging Network: Compatible with the ChargePoint EV charging network or an approved open charge point protocol (OCPP).
1. Multiple units shall independently connect to charging network.
2. Multiple units shall have one unit designated a s a master unit that is configured as a gateway unit between the EV charging equipment and the charging network.
3. Individual units shall be capable of indicating station status and availability providing or connecting user to customer support and remote control.
2.3 PERFORMANCE REQUIREMENTS
CITY OF SACRAMENTO EV BLUEPRINT
MULTIPLE PROJECT SITES
ELECTRIC VEHICLE CHARGING EQUIPMENT - LEVEL 2 26 26 53- 6
A. Thermal Movements: Allow for thermal movements from ambient and surface temperature changes.
B. Surge Withstand: 6 kV at 3,000 A.
C. Integral GFCI.
D. Auto-GFCI fault retry.
E. Input Power:
1. 40 Amp, 2P Breaker with 32 Amp dedicated for each handle . 208/240-V ac, 60 Hz, per charger with EMV Chip Reader (Note: Each charger handle is assigned a 40A, 2P breaker- refer to plans for specific requirements).
2. Dual-circuits provided to a single pedestal need to be interlocked.
F. EV Charging Levels, Verify with Plans:
1. Single vehicle: AC Level 2 at up to 6.6 kW (CP6000) per vehicle.
2. Dual vehicles, AC Level 2 at up to 11.5 kW (CP6000) or up to 6.6 kW per vehicle.
3. Multiple vehicles simultaneously charging at a site using Automatic Power Load Management may be charged up to 11.5 kW (CP6000) or up to 6.6 kW per vehicle.
2.4 GENERAL FINISH REQUIREMENTS
A. Protect mechanical finishes on exposed surfaces from damage by applying a strippable, temporary protective covering before shipping.
B. Appearance of Finished Work: Noticeable variations in same piece are not acceptable.
Variations in appearance of adjoining components are acceptable if they are within the range of approved Samples and are assembled or installed to minimize contrast.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine areas and conditions, with Installer present, for compliance with requirements for installation tolerances and other conditions affecting performance of the Work.
B. Examine roughing-in for EV charging equipment electrical conduit to verify actual locations of conduit connections before equipment installation.
C. Examine suitable conditions where EV charging equipment will be installed.
D. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
CITY OF SACRAMENTO EV BLUEPRINT
MULTIPLE PROJECT SITES
ELECTRIC VEHICLE CHARGING EQUIPMENT - LEVEL 2 26 26 53- 7
A. Comply with NECA 1 and NECA 413.
B. Concrete Base Mounting:
1. Install EV charging equipment on concrete foundation, per plans . Comply with requirements for concrete base specified in plans and details. a. Place and secure anchorage devices. Use setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded. b. Install anchor bolts to elevations required for proper attachment to supported equipment.
c. Secure EV charging equipment to concrete base according to manufacturer's written instructions.
C. Comply with mounting and anchoring requirements required for all California Building C ode (CBC) and local code-related requirements for: Seismic Controls for Electrical Systems.
D. Wiring Method: Install low-voltage cables in raceways / cable trays. Conceal raceway & cables.
1. Comply with requirements for raceways and boxes specified in plans and details.
2. Comply with requirements for underground raceways and enclosures specified in plans.
E. Wiring Method: Conceal conductors and cables where possible.
F. Wiring within Enclosures: Bundle, lace, and train conductors to terminal points with no excess and without exceeding manufacturer's limitations on bending radii. Install lacing bars and distribution spools.
G. Circuit Breakers: Comply with plans and details.
H. Secure covers to enclosure.
3.3 CONNECTIONS
A. Connect wiring according to plans and details.
B. Comply with grounding requirements in plans and details.
C. Comply with requirements for installation of conduit in plans and de tails. Drawings indicate general arrangement of conduit, fittings, and specialties.
D. Tighten electrical connectors and terminals according to manufacturer's published torque - tightening values. If manufacturer's torque values are not indicated, use those specified in UL 486A-486B.
3.4 IDENTIFICATION
A. Identify system components, wiring, cabling, and terminals. Comply with requirements for identification specified in plans and details.
CITY OF SACRAMENTO EV BLUEPRINT
MULTIPLE PROJECT SITES
ELECTRIC VEHICLE CHARGING EQUIPMENT - LEVEL 2 26 26 53- 8
3.5 FIELD QUALITY CONTROL
A. Field Service: Electrician is to be factory-authorized to test and inspect all components.
B. Perform tests and permit inspections through City of Sacramento. Work with City of Sacramento staff to integrate all equipment into the Chargepoint Dashboard, or as approved.
C. Tests and Inspections:
1. For each unit of EV charging equipment, perform the following tests and inspections:
a. Unit self-test.
b. Operation test with load bank.
c. Operation test with EV.
d. Network communications test.
D. EV charging equipment will be considered defective if it does not pass tests and inspections.
E. Prepare test and inspection reports.
3.6 STARTUP SERVICE
A. Perform startup service.
1. Complete installation and startup checks according to manufacturer's written instructions.
3.7 ONGOING MANAGEMENT SERVICES
A. Engage a station manufacturer that offers a service to manage the administration and policies of the electric vehicle charging stations on an ongoing basis.
3.8 SOFTWARE SERVICE AGREEMENT
A. Technical Support: Beginning at Substantial Completion, service agreement shall include software support for the duration of an active ChargePoint Network Service Plan for 5 years.
B. Upgrade Service: At Substantial Completion, remotely update software to latest version. Install and program software upgrades that become available while an active ChargePoint Network Service Plan is maintained. Upgrading software shall include operating system and new or revised licenses for using software.
3.9 OPERATIONS AND MAINTENANCE (O&M)
A. Utilize ChargePoint Station Management Services and ChargePoint Assure Services . Provide Owner's maintenance manual (O&M) to allow adjustment, operation, and maintenance.
END OF SECTION 26 26 53
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 1 of 45
TABLE OF CONTENTS
ARTICLE Page
00100 DEFINITIONS ............................................................................................................................. 3 00101 PRE-BID INTERPRETATION OF CONTRACT DOCUMENTS....................................................... 7 00102 THRU 00199 NOT USED .............................................................................................................. 7 00200 SCOPE ........................................................................................................................................ 7 00201 AUTHORITY OF THE CITY PROJECT MANAGER AND INSPECTOR .................................... 8 00202 INTENT OF CONTRACT DOCUMENTS .................................................................................... 8 00203 STANDARD SPECIFICATIONS ................................................................................................. 8 00204 PLANS AND SPECIFICATIONS ................................................................................................. 9 00205 PRECEDENCE OF CONTRACT DOCUMENTS ........................................................................ 9 00206 ACCURACY OF PLANS AND SPECIFICATIONS ................................................................... 10 00207 EXAMINATION OF COVERED WORK .................................................................................... 10 00208 UNNOTICED DEFECTS ........................................................................................................... 10 00209 CODES AND REGULATIONS .................................................................................................. 10 00210 LENGTH OF WORKDAY AND WORK WEEK ......................................................................... 11 00211 PAYMENT OF EMPLOYEES ................................................................................................... 11 00212 CONVICT-MADE MATERIALS ................................................................................................. 11 00213 SALES OR USE TAX / EXEMPTION FROM FEDERAL EXCISE TAX .................................... 11 00214 NONDISCRIMINATION IN EMPLOYMENT ............................................................................. 12 00215 APPRENTICE UTILIZATION .................................................................................................... 12 00216 LAWS AND REGULATIONS .................................................................................................... 12 00217 PERMITS AND CONSTRUCTION EASEMENTS .................................................................... 12 00218 PARTIES EXCLUDED FROM FEDERAL PROCUREMENT AND NON PROCUREMENT PROGRAMS ............................................................................................................................. 13 00219 BUSINESS TAX REGISTRATION CERTIFICATES ................................................................. 13 00220 CONTRACTOR PROPOSED ALTERNATES AND OREQUALS ............................................. 13 00221 THRU 00299 NOT USED ............................................................................................................ 14 0030
0 FINANCIAL LIABILITY .............................................................................................................. 14 00301 CONTRACTOR’S OBLIGATIONS ............................................................................................ 14 00302 CONTRACTOR’S REPRESENTATIVE AT THE SITE ............................................................. 14 00303 FAMILIARITY WITH PLANS AND SPECIFICATIONS ............................................................. 15 00304 JOB CONDITIONS .................................................................................................................... 16 00305 JOB BULLETIN BOARD ........................................................................................................... 16 00306 RESPONSIBILITY FOR SITE ................................................................................................... 17 00307 WORKMANSHIP AND MATERIALS ........................................................................................ 17 EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 2 of 45
00308 INJURY AND ILLNESS PREVENTION - SAFETY MEASURES .............................................. 17 00309 PROTECTION OF PERSONS AND PROPERTY AND RESTORATION OF EXISTING IMPROVEMENTS ..................................................................................................................... 18 00310 NON-CONFORMING WORK .................................................................................................... 20 00311 SUBCONTRACTORS AND SUB-SUBCONTRACTORS ......................................................... 21 00312 RESPONSIBILITY OF CONTRACTOR TO ACT IN EMERGENCY ......................................... 25 00313 ASSIGNMENT .......................................................................................................................... 25 00314 NOTIFICATION OF HAZARDOUS SUBSTANCES ................................................................. 25 00315 INDEPENDENT CONTRACTOR .............................................................................................. 26 00316 INDEMNIFICATION .................................................................................................................. 26 00317 INSURANCE ............................................................................................................................. 27 00318 SERVICE OF NOTICE .............................................................................................................. 31 00319 AGENT TO ACCEPT SERVICE ............................................................................................... 32 00320 THRU 00399 NOT USED ............................................................................................................ 32 00400 TEMPORARY SUSPENSION OF WORK ................................................................................ 32 00401 UNAVOIDABLE DELAY ............................................................................................................ 33 00402 ARCHAEOLOGICAL AND PALEONTOLOGICAL DISCOVERIES .......................................... 33 00403 COORDINATION WITH OTHER CONTRACTS ....................................................................... 33 00404 TERMINATION OF CONTRACT BY CITY (CONTRACTOR NOT AT FAULT) ....................... 34 00405 TERMINATION OF CONTRACT BY CITY (CONTRACTOR DEFAULT) ................................. 36 00406 PARTIAL ACCEPTANCE ......................................................................................................... 37 00407 FINAL ACCEPTANCE .............................................................................................................. 38 00408 LIQUIDATED DAMAGES ......................................................................................................... 38 00409 COMPENSATION FOR DELAY, DISRUPTION, UNANTICIPATED OVERHEAD ................... 38 00410 THRU 00499 NOT USED ............................................................................................................ 39 00500 CHANGES AND EXTRA WORK .............................................................................................. 39 00501 DIFFERING SITE CONDITIONS .............................................................................................. 41 00502 THRU 00599 NOT USED ............................................................................................................ 41 00600 CLAIMS AND PROTESTS ........................................................................................................ 41 00601 COMMENCEMENT OF STATUTE OF LIMITATIONS ............................................................. 43 00602 GOVERNING LAW ................................................................................................................... 43 00603 VENUE ...................................................................................................................................... 44 00604 NO WAIVER OF RIGHTS ......................................................................................................... 44 00605 ACCEPTANCE OF FINAL PAYMENT CONSTITUTES RELEASE ......................................... 44 00606 PATENTS AND COPYRIGHTS ................................................................................................ 44 00607 PUBLIC RECORDS ACT ........................................................................................................... 45
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 3 of 45
00100 DEFINITIONS
Unless otherwise stated, the words "directed, required, permitted, ordered, instructed, designated, considered necessary, prescribed, approved, acceptable, satisfactory," or words of like meaning, refer to actions, statements, judgements, conclusions, and decisions within the responsibility of the Project Manager or the Inspector.
Addenda: Written documents issued during the Bidding Period which modify, supersede, or supplement the original Contract Documents.
“as shown”, “as indicated”, or “as specified”: These words are understood to be followed by the phrase "in the Contract Documents."
Beneficial Use: Use of a building, system, structure, or facility by the City.
Bid: The offer of the Bidder submitted on the prescribed forms setting forth the price(s) for the Work.
Bid Notice: The notice that informs prospective Bidders of the opportunity to submit a Bid, bidding procedures and other requirements.
Bid Guaranty: The certified check or Bidder’s Surety Bond accompanying the Bid as a guaranty that the Bidder will enter into a contract with the City for the performance of the Work.
Bidder: The person or persons, partnership, firm or corporation submitting a Bid or proposal for the Work defined in the Contract Documents.
Bidding Period: The time period allocated to the Bidder to enable preparation of a Bid.
Bond: Bid bond, performance and payment bond or other instrument of security.
Calendar day: Except as follows, all days beginning with the Notice to Proceed and ending with the date the City acknowledges in writing that all Contract Work is complete.
1) Any day the Contractor is prevented from working for cause as established by “Unavoidable Delay” of these General Conditions; and
2) Any day the Contractor is prevented from working during the first five (5) hours of the workday with at least sixty percent (60%) of the normal Work force for cause as established by “Unavoidable Delay” of these General Conditions.
Change Order: A written order to the Contractor signed by the City Manager directing an addition, deletion or revision in the Work, or an adjustment in the Contract Price or time which is issued after the effective date of the Contract and effects less modification than is effected by a Supplemental Agreement. A Change Order may or may not also be signed by the Contractor.
City: The City of Sacramento, a municipal corporation.
Claim: A written demand or assertion by one of the parties seeking, as a matter of right, an interpretation of the Contract Documents, payment of money, extension of time or other relief. The party asserting the Claim must set forth the facts and circ umstances for which the other party is responsible.
Code: Codes of the State of California as well as any other Federal or local law, statute, ordinance, rule or regulation.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 4 of 45
Contract: The agreement between the City and the Contractor for the Work described in the Contract Documents.
Contract Documents: Includes, but is not limited to, the Notice Inviting Bids, Bid Proposal, Notice(s) to Bidders, Contractor’s Bid, Performance bond, Payment bond, General and Supplementary Conditions, Special Provisions, General Requirements, Federal and State Requirements, Standard and Reference Specifications, Technical and Nontechnical Specifications, Soil Reports and Subsurface Investigation Reports, Standard Plans, Plans, and Addenda, Plan Clarifications, Request for Information, Supplemental Agreements, Change Orders issued after Contract award and other documents designated by the Project Manager.
Contract Price: The total amount of money for which the Contract is awarded.
Contract Unit Price: The amount stated in the Bid for a single unit of an item of Work.
Contractor: A person or persons, partnership, firm or corporation licensed by the State of California as a general contractor. The terms “Prime Contractor” and Contractor are synonymous.
Contractor’s Representative: A representative of the Contractor present at the site to supervise, organize, coordinate and direct daily construction activities and who is authorized to receive and fulfill instructions from the Project Manager or Inspector.
“days”: Consecutive calendar days unless otherwise specifically stated.
Drawings: See Plans.
“easement”: Permission to access or utilize property not owned by the City.
Equal: See "or equal”.
General Conditions: Instructions to the Contractor setting forth its responsibilities and the City’s responsibilities for proper execution of the Work indicated herein.
General Requirements: Division 1 of the Specifications.
Geotechnical Report: This report contains factual information gathered during exploration and design. It may include logs of exploratory borings, laboratory test data, geologic, seismic or environmental data.
“holiday”: In reference to days, the holidays and dates as observed by the City. A list of such holidays is available from the City Clerk’s office.
Illegal Subcontractor Substitution: Anyone other than the Bid- listed or approved subcontractor(s) performing any portion of the Work designated to be performed by said subcontractor without prior approval of the Inspector.
“immediately notify”: The obligation to cause verbal notification of Project Manager and Inspector of some condition or event as soon as possible upon discovery or knowledge of the condition or event and in all instances, no more than two (2) hours.
Inspector: The Inspector of Public Works, or an authorized representative designated by the City Department of Public Works, Project Delivery.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 5 of 45
“jobsite”: The area upon or in which the Contractor’s operations are carried on and such other areas adjacent thereto as may be designated as such by the Contract Documents.
“law”: Any Federal, State or local law, statute, ordinance, rule, regulation or Code.
“liquidated damages”: The amount the Contractor shall pay to the City, as determined by rates and amounts as f ixed in the Contract Documents, due to the Contractor’s failure to complete the Work within the time specified.
“non-conforming work”: Unapproved construction, defective work or damaged materials that does not fully comply with the Contract Documents.
Notice to Proceed: The written notice by the City to the successful Bidder stating that the Work or portions of the Work shall commence. The Notice to Proceed will be issued upon the successful execution of the contractor ’s contract, bonds, certificate of insurance and participation goals.
Notice to Withhold: The written notice by the City to the Contractor advising that certain payments shall be withheld due to unacceptable execution of the Work by the Contractor.
“or equal”: In reference to products, equipment, or materials proposed by the Contractor for use in the Work. The contractor is solely responsible for proving to the Project Manager the proposed materials are equal or better in all respects to the materials specified. The Project Manager for the City has the final determination as to equivalency.
Partial Acceptance: Any portion of the Work which has been completed in accordance with the plans and specifications and has been accepted in writing by the Inspector.
“person”: Any indi vidual, firm, association, partnership, corporation, trust, joint venture, or other legal entity.
Plans: The drawings, profiles, cross sections, shop drawings, and supplemental drawings, or reproductions thereof, issued or approved by the Project Manager, which show the location, character, dimensions or details of the Work.
Private Contract: Work subject to City inspection, control, and approval, involving private funds, not administered by the City.
Project: The Work and/or construction operations executed through the performance of this Contract.
Project Completion Date: The date of Final Field Acceptance of the Project as evidenced by the issuance of a “Notice of Completion” by the Inspector.
Project Manager: The City Project Manager, responsible for the management of the project and the authorized representative for the City.
Project Manual: See Contract Documents.
Protest: See Claim.
Reference Specifications: Those bulletins, standards, rules, methods of analysis or test, codes, and specifications of other agencies, engineering societies, or industrial associations referred to in the Contract Documents. These refer to the edition, including amendments in effect and published at the time of advertising the project, adopted by the Ci ty, if applicable, unless specifically referred to by edition, volume, or date.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 6 of 45
“right of entry”: Written permission from an owner of a facility or property to access the facility or property for a specific purpose.
Special Provisions: Any provision which supplements or modifies the Specifications.
Specifications: Written requirements describing the commercial, legal, technical and nontechnical aspects of the project. Specifications include but are not limited to Terms, Provisions, General Conditions, G eneral Requirements, Technical Specifications, Equipment Schedules, and all revisions made to the specifications in Addenda, and Change Orders.
Standard Plans or “Std. Plan”: Details of standard structures, devices or instructions referred to on the Plans or in the Specifications by title or number.
Standard Specifications: Parts 2 through 6 of “Standard Specifications for Public Works Construction” published by Public Works Standards, Inc., latest edition and supplements adopted by the Board of Public Works and as modified by the corresponding edition of the Additions and Amendments to the SSPWC or Standard Plan S-610.
State: The State of California.
Subcontractor: Any individual, firm, or corporation, other than an employee of the Contractor, having a direct contract with the Contractor or with any other subcontractor for the performance of the Work. A Subcontractor is a contractor who is licensed pursuant to California Business and Professions Code, Section 7000 et. seq. A Subcontr actor does not have any direct contract with the City related to the project.
Subcontractor Substitution: Anyone other than the Bid- listed or approved subcontractor(s), including the Contractor, performing any portion of the Work designated to be performed by said subcontractor.
Sub-subcontractor: A "Sub-Subcontractor" is a Subcontractor, within the definition of that term, who has a contract with a Subcontractor and has no Contract with the City related to the project.
Supervision: With reference to supervision by the Project Manager, the performance of obligations, and the exercise of rights, specifically imposed upon and granted to the City in becoming a party to the Contract. Except as specifically stated herein, supervision by the City shall not mean active and direct superintendence of details of the Work.
Supplemental Agreement: A written amendment of the Contract Documents, signed by the Contractor and City.
Supplier: An individual, organization, or firm who may not be required for the purposes of the Work to be licensed pursuant to California Business and Professions Code as a contractor, or subcontractor, within the meanings of those terms as defined herein above, who provides equipment and/or materials for the Work, to the Contractor, a Subcontractor, or a Sub- Subcontractor, including that fabricated to a special design, but who does not perform labor at the site except for labor or labor supervision required by some manufacturers as part of their equipment installation for warranty or other purposes. The term "supplier" also includes fabricator, manufacturer, or vendor.
Surety: Any individual, firm or corporation bound with and for the Contractor for the acceptable performance, execution and completion of the Work, and for the satisfaction of all obligations incurred.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 7 of 45
Unauthorized Subcontractor Substitution: Any reduction, increase, or other change to any Subcontractor dollar amount without written approval by the Project Manager and Inspector.
Unavoidable Delay: Delay arising from causes beyond the control and without the fault or negligence of the Contractor and its Subcontractors at all tiers.
Work: Includes all material, labor, utility services, tools, expendable equipment, and all appliances, machinery, transportation, appurtenances and specified services necessary to perform and complete the Contract; and such additional items not specifically indicated or described that can be reasonably inferred as belonging to the item described or indicated and as required by good practice to provid e a complete and operable satisfactory system or structure. As used herein, "provide" shall be understood to mean "furnish and install, complete in place."
Workday: Except as follows, all days beginning with the Notice to Proceed and ending with the date the City acknowledges in writing that all Contract Work is complete.
1) Saturday,
2) Sunday,
3) any day designated as a holiday by the City,
4) any day designated as a holiday in a Master Labor Agreement binding the Contractor,
5) any day the Contractor is prevented from working for cause as established by “Unavoidable Delay” of these General Conditions; and
6) any day the Contractor is prevented from working during the first five (5) hours of the workday with at least sixty percent (60%) of the normal Work force for cause as established by “Unavoidable Delay” of these General Conditions.
Worksite: See "jobsite."
00101 PRE-BID INTERPRETATION OF CONTRACT DOCUMENTS
No oral representations or interpretation will be made to any bidder as to the meaning of the contract documents. Requests for interpretation shall be made in writing and delivered to the City as least seven (7) days before the time announced for opening the proposals. Interpretation, where necessary, will be made by the City in the form of an addendum to the contract documents and, when issued, will be sent as promptly as is practicable to all parties to whom the bid documents have been issued. All such addenda shall become part of the contract.
It shall also be the Bidder’s responsibility to call to the attention of the Project Manager any missing pages or drawings in the contract documents including the addenda. These items shall be brought to the attention of the Project Manager at least seven (7) days before the time announced for opening the proposals .
00102 THRU 00199 NOT USED
00200 SCOPE
The work to be performed under this Contract shall consist of furnishing all tools, equipment, materials, supplies and manufactured articles, all transportation, services, including fuel, power and water, and essential communications, and the performance of all labor, Work, required calculations testing, inspections EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 8 of 45
or operations, or operations required for the fulfillment of the Contract, in strict accordance with the specifications, schedules, and Plans, all of which are made a part hereof, and including such detail sketches as may be furnished by the Project Manager from time to time during the construction in explanation of said Plans. The Work shall be complete and all material, and services incidentals, quality or not specifically called for quality and conditions noted, in the Specifications, or not shown on the Plans, which may be necessary for complete and proper construction to carry out the Contract in good faith and a satisfactory manner shall be performed, furnished, and installed by the Contractor at no increase in cost to the City.
00201 AUTHORITY OF THE CITY PROJECT MANAGER, AND INSPECTOR
The City Project Manager (the Project Manager) is responsible for management of the contract and has the final authority in all matters affecting the Work. The Contractor shall promptly comply with instructions from the Project Manager or the Inspector.
The Project Manager is authorized to require performance of the Work consistent wit h the meaning of the Plans and the Contract Documents. On all questions related to the interpretation of Plans or Specifications, the decision of the Project Manager is final and binding. As authorized by the City Council, the Project Manager may recommend Change Orders to the City Manager or City Council to increase, decrease or modify the scope of work.
The Inspector is authorized to enforce compliance with the Contract Documents, to determine the acceptability, quality and quantity of materials and work manship, administer requirements with respect to subcontracts, and to review and process progress payment estimates. Unless otherwise ordered by the Project Manager, the Inspector’s determination of satisfactory performance is a condition precedent to payment under this Contract. For such matters, the decision of the Inspector is final and binding. In the event of a dispute between the Contractor and the Inspector, the latter is authorized to reject materials or suspend the Work until any questions at issue can be referred to and decided by the Project Manager or, in engineering matters, by the Project Manager.
The Inspector is authorized to sample and test all materials to be incorporated into the Work. The Inspector may delegate this authority to sample m aterials and perform tests to an independent testing company contracted through the City.
The Project Manager may delegate street lighting matters to the Transportation Division of the City of Sacramento.
00202 INTENT OF CONTRACT DOCUMENTS
The Contract Documents are complementary, and what is called for by one part shall be as binding as if called for by all. The intent of the Documents is to include all Work consistent therewith and reasonably inferable therefrom as being necessary for completion of the contract. Materials or Work described in words that indicate the proper execution and a well-known technical or trade designation shall be held to refer to such recognized standards.
It is understood and agreed that the written terms and provisions of the Contract Documents represent the entire and integrated agreement between the parties hereto and supersede all prior negotiations, representations, or agreements, either written or oral. The Contract Documents shall not be construed to create any c ontractual relationship of any kind between the Project Manager (or the Inspector) and the Contractor.
00203 STANDARD SPECIFICATIONS
Unless otherwise noted, Divisions 1 through 16 of the Standard Specifications are included in the Contract Documents.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 9 of 45
The work to be performed under this contract shall be in accordance with the Technical Specifications contained herein. In these Technical Specifications, reference is made to the Standard S pecifications of the City of Sacramento, adopted June 2007, with Addendums 1 and 2, referred to herein as “Standard Specifications.” The General Requirements of this contract shall be governed by these General Requirements first, followed by Section 1 thr ough 8 of the Standard Specifications. Other standards or specifications specified in these Technical Specifications govern only the applicable technical specifications.
Please note the following items with respect to the Standard Specifications:
Wherever reference is made to City Manager, Director of Public Works, Engineer, Finance Director, Inspector, Landscape Architect, or other specifically identified individuals, it shall include their designated representative.
Replace the last paragraph of Section 2-9 SUBCONTRACTORS with the following:
• In addition to the above requirements, Contractor shall perform with his own organization and with the assistance of workers under his immediate superintendence, work of a value not less than twenty percent (20%) of the value of all Work in the Contract. The dollar amount of subcontracted work that is specifically indicated by the Bidder on the form provided by the City shall be used to determine the value of work being subcontracted, as well as the value of LBE S ubcontractor participation for purposes of determining compliance with LBE participation requirements, unless the Engineer determines such value to be significantly misstated. The Bidder shall provide such bidding information as may be requested by the Engineer to make this determination.
Add the following after the last paragraph of Section 5-4 COOPERATION OF CONTRACTOR:
• Contractor shall give the work the constant attention necessary to facilitate the progress thereof. Contractor shall cooperate with the Engineer, inspectors and with other Contractors in every way possible. The Engineer shall allocate the Work and designate sequence of construction in case of controversy between Contractors.
00204 PLANS AND SPECIFICATIONS
As shown on the Plans or described in the Specifications, each element of the Work must be furnished complete, finished and functional. Whether shown or not, include all materials and ancillary equipment necessary to provide a complete installation. The Plans, Specifications and other Contract Documents are intended to be complementary and cooperative to describe and provide for a complete project. Anything in the Specifications and not on the Plans, or on the Plans and not in the Specifications, shall be as though shown or mentioned in both. Details shown for an item of Work are typical and shall apply to similar items of Work.
Do not deviate from the Plans and Specifications without written authorization from the Project Manager.
The Project Manager does not warrant the accuracy of scaled dimensions. Dimensions indicated by figures or numerals shall govern. Larger scale drawings shall take precedence over smaller scale drawings.
The Project Manager may furnish additional details pertaining to the Work and the same shall be considered part of the Contract.
References made to other specifications and codes refer to the edition including amendments in effect and published at the time of advertising the project, unless specifically referred to by edition, volume, or date as noted in the Contract Documents.
00205 PRECEDENCE OF CONTRACT DOCUMENTS
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 10 of 45
In resolving inconsistencies or ambiguities among two (2) or more components of the Contract Documents, the document highest in precedence shall control. The precedence shall be:
1) Permits from other agencies as may be required by law. 2) Bid Proposal
3) General Conditions
4) General Requirements
5) Technical Specifications
6) Plans
7) Geotechnical Report
8) Standard Plans
9) Standard Specifications
10) Reference Specifications
11) Reference Plans
Supplemental Agreements, Change Orders, Project Manager’s written interpretations and clarifications, and Addenda, will take precedence over all other components of the Contract Documents. Shown dimensions take precedence over scaled dimensions. Detailed drawings will take precedence over general drawings.
00206 ACCURACY OF PLANS AND SPECIFICATIONS
Omissions fr om the Plans and Specifications shall not relieve the Contractor from the responsibility of furnishing, making, or installing all items required by law or usually furnished, made, or installed in a project of the scope and character indicated by the Plans and Specifications.
The Plans show conditions as they are supposed or believed by the Project Manager to exist, but it is not intended or to be inferred that the conditions as shown thereon constitute a representation or warranty, expressed or implied, by the City or its officers, that such conditions are actually existent, nor shall the City, or any of its officers, be liable for any loss sustained by the Contractor as a result of any variance between conditions as shown on the Plans, and the actual condi tions revealed during progress of the Work or otherwise, except as indicated in “Differing Site Conditions” of these General Conditions.
00207 EXAMINATION OF COVERED WORK
If any Work is covered w ithout inspection, approval or consent of the Inspector, an examination may be required by the Inspector. The cost for uncovering the work, inspection, testing required by the Inspector, remedial work and restoring the work is at the Contractor’s expense.
00208 UNNOTICED DEFECTS
The Contractor is responsible for ensuring that all Work complies with the Contract Documents. Upon discovery, all defective or noncompliant Work must be immediately repaired or replaced by the Contractor.
Failure by the Project Manager or the Inspector to condemn or reject non- conforming Work shall not constitute acceptance or implied acceptance of such Work.
00209 CODES AND REGULATIONS
The Contractor shall perform the Work in accordance with all applicable regulations, laws, and ordinances, even though such requirements may not be specifically mentioned in the Specifications or shown on the Plans.
It is not the responsibility of the Contractor to ensure that the Contract Documents comply with applicable laws, statutes, codes and regulations. If the Contractor believes that any part of the Contract Documents City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 11 of 45
does not comply, the Contractor shall pro mptly notify the Project Manager in writing. Do not proceed with those affected Work items until the Project Manager issues written instructions to the Contractor.
If the Contractor proceeds with those Work items without written instruction from the Project Manager, the Contractor will bear the costs and impacts of any corrective work.
00210 LENGTH OF WORKDAY AND WORK WEEK
Eight (8) hours of labor shall constitute a calendar day's work for employees of the Contractor under this Contract. Said employees shall be paid not less than the prevailing wage rate for the first eight (8) hours work of each day.
A working day shall be Monday through Friday, and work shall be between 7:00 a.m. and 4:00 p.m., unless otherwise approved by the Project Manager or revised by City Ordinance.
When work in excess of eight (8) hours per day, or forty (40) hours during any one (1) week is performed, wages for all hours over eight (8) hours in any day or over forty (40) hours during any one (1) week shall be paid at the prevailing wage rate, as required by City, state and federal requirements.
00211 PAYMENT OF EMPLOYEES
The Contractor and each Subcontractor shall pay each employee engaged in Work on the project under this Contract in compliance with the Federal and State wage provisions indicated on the appropriate page of the Bid Proposal (General Instruction and Information for Bidders), and “Length of Workday and Work Week” of these General Conditions.
The certified payroll and a signed Statement of Compliance shall be submitted to Public Works by the Contractor and all Subcontractors performing Work on the project, regardless of dollar amount or type of contract.
If there is a difference between the Federal and State minimum wage rates for similar classifications of labor, the Contractor and its Subcontractors shall pay not less than the higher wage rate.
When the Contractor intends to use a craft or c lassification not shown on the general prevailing wage determinations, it will be required to pay the wage rate of that craft or classification most closely related to it as shown in the general prevailing wage determinations. In case of disagreement between the Contractor and the City. Contract Services shall make the final determination as to the prevailing wages for the Work.
00212 CONVICT-MADE MATERIALS
Unless otherwise noted, no materials manufac tured or produced in a penal or correctional institution shall be incorporated in the project under this Contract.
00213 SALES OR USE TAX / EXEMPTION FROM FEDERAL EXCISE TAX
Purchases of materials and equipment which will be incorporated or installed permanently in the Work, or which will be used in the operation of the Contractor or Subcontractors, and not incorporated in the Work, are not exempt from City of Sacramento and California State Sales or Use Taxes as applicable.
Purchase of materials and equipment which will be incorporated or installed permanently in the Work are exempt from Federal excise tax in effect at the time of purchase, as applicable. Prices included in the Contract amount shall reflect such exemptions. A Federal Tax Exemption Certificate will be furnished by the City, on request, as acknowledgment that materials and equipment for which exemption is requested by the Contractor, is valid where provided for the exclusive use of the City. Lists of exempt articles provided by the Contractor and Subcontractor shall be submitted to the City by the Contractor. Purchases of EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 12 of 45
materials and equipment which will be used in the operations of the Contractor or Subcontractors and not incorporated in the Work are not exempt from excise tax.
00214 NONDISCRIMINATION IN EMPLOYMENT
The Contractor shall comply with all of the provisions of the Sacramento City Code, Mandatory Provision Pertaining to Nondiscrimination in Employment.
Nondiscrimination Clause: "The Contractor shall not discriminate during the performance of this Contract against any employee or applicant for employment because of employee's or applicant's race, religion, national origin, ancestry, sex, age, sexual orientation or physical handicap." The Contractor shall include the same Nondiscrimination Clause in all subcontracts awarded under this Contract.
If conflicts exist between these provisions and the Federal Rules and Regulations governing the same, the more stringent requirements shall prevail.
00215 APPRENTICE UTILIZATION
Any Contract awarded hereunder will require the Contractor to comply with the provisions of the California Labor Code relating to apprentice employment and training; and will require the Contractor to assume full responsibility for compliance with said section with respect to all Apprenticing Occupations involved in the Project. (Compliance with said Apprentice Utilization provisions of the Labor Code is not required for Public Works contracts involving less than $25,000 or less).
00216 LAWS AND REGULATIONS
The Contractor shall observe and comply with all Federal, State, and local laws, ordinances, Codes, orders, and regulations which in any manner affect those engaged or employed on the Work, the materials used in the Work, or the conduct of the Work. If any discrepancy or inconsistency should be discovered in th is Contract in relation to any such law, ordinance, Code, order, or regulation, the Contractor shall report the same in writing to the Project Manager. The Contractor shall indemnify and save harmless the City, and its officers, agents, and employees, against all claims or liability arising from violation of any such law, ordinance, Code, order, or regulation, whether by itself or by its employees or Subcontractors as stated in these Contract Documents. Any particular law or regulation specified or referr ed to elsewhere in these specifications shall not in any way limit the obligation of the Contractor to comply with all other provisions of Federal, State, and local laws and regulations.
00217 PERMITS AND CONSTRUCTION EASEMENTS
The Contractor shall obtain and pay for all permits necessary for performance of the Work, unless otherwise identified herein. The Contractor shall pay for and obtain permits required for contractor designed items, annual permits, temporary construction or general permits that are usable for other projects, and utility tap fees. Within thirty (30) calendar days after the Notice to Proceed, the Contractor shall obtain and pay all costs incurred and submit to the Project Manager copies of all permits required for the construction and installation of all Work called for on this project.
The City shall provide the following permit:
1) City of Sacramento Community Development Department Building Permit
The Contractor’s responsibility shall include, but is not limited to, the following:
1) Night Work, encroachment, overload, grading, excavation, demolition, foundation, and other building permits.
2) Electrical permits.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 13 of 45
3) Mechanical permits.
4) Plumbing permits.
5) Fire sprinkler permit.
6) All Federal, State, County and City issued permits.
7) Rights of ways, easements, or rights of entry for the Work will be provided by the City. The Contractor shall make arrangements, pay for, and assume all responsibility for acquir ing, using, and disposing of Work areas and facilities temporarily required which are necessary in addition to those provided by the City. The Contractor shall indemnify and hold the City harmless for all claims for damages caused by such actions.
00218 PARTIES EXCLUDED F ROM FEDERAL PROCUREMENT AND NON- PROCUREMENT
PROGRAMS
A list of individuals, firms and organizations which have been debarred, suspended or have voluntarily excluded themselves f rom Federal Procurement and Non- Procurement Program is maintained by US General Services Administration. A copy can be obtained from Superintendent of Documents, US Government Printing Office, Washington, DC 20402, Tel: (202) 783-3238.
The City will not conduct business with an individual, firm or organization, and the Contractor shall not employ or otherwise utilize any Subcontractor, supplier or equipment vendor at any tier which is on the U.S.
General Services Administration "List of Parties Excluded from Federal Procurement and Non-Procurement Programs."
00219 BUSINESS TAX REGISTRATION CERTIFICATES
The Contractor represents that it has, or will obtain upon award, the Business Tax Registration Certificate(s) required by the Sacramento City Business Tax Ordinance. The Contractor shall maintain, or obtain as necessary, all such Certificates required of it under said Ordinance and shall not cause or allow any such Certificate to be revoked or suspended.
The City requires all firms that have business activity within the City of Sacramento to pay City business taxes.
Payments for goods or services will be withheld unless proof of tax compliance is provided to the City. All firms and individuals that do business with the City will be required to provide a Business Tax Registration Certificate number or an exemption number as proof of compliance with Sacramento City business tax requirements in order to receive payment for goods or services.
The Tax and Permit Division has the sole authority to determine whether a firm is covered by business tax requirements.
00220 CONTRACTOR PROPOSED ALTERNATES AND “OR EQUALS”
Unless otherwise noted, the Contractor may propose products, equipment, or materials to be an “or equal” to those specified in the Contract. These proposals must be submitted within thirty (30) days after Notic e to Proceed along with sufficient substantiating data for the Project Manager to determine equivalence. The substantiating data must demonstrate equivalence in terms of function, performance, reliability, quality, and general configuration to the items specified in the Contract Documents. The contractor shall provide complete documentation on the total impact of the substitution has on the other parts of the project including all modifications and equipment changes. The Project Manager will be the sole arbiter of equivalence.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 14 of 45
Proposals that are submitted late or with incomplete substantiation are “Not Equal” and subject to summary rejection.
Contractor-proposed “or equals” that are accepted by the Project Manager shall be coordinated with other items of Work and incorporated into the Work without time extensions and at no additional cost to the City.
00221 THRU 00299 NOT USED
00300 FINANCIAL LIABILITY
The City’s liability under this Contract shall not exceed the City’s appropriation to fund the Contract at the time of Contract award. However, if the City shall appropriate funds for any successive years, the City’s maximum liability shall not exceed the extent of such appropriation, subject to the terms and conditions of this Contract.
00301 CONTRACTOR’S OBLIGATIONS
Only competent workers shall be employed on the Work.
Any person employed who is found by the Inspector to be incompetent, disorderly or otherwise objectionable, or who fails or refuses to perform Work properly, acceptably and as directed shall be immediately removed from the Work by the Contractor and not be reemployed on the Work.
The Contractor, at its sole cost and expense, shall perform all labor and services and furnish all the materials, tools, and appliances, except as hereinafter otherwise definitely provided, necessary or proper for performing and completing the Work required, i n the manner and within the time stipulated in these specifications. The Contractor shall furnish, erect, maintain, and remove the construction plant and such temporary works as may be required. If, at any time before the commencement or during the progress of the Work or any part of it, the Contractor’s methods or appliances appear to the Project Manager or the Inspector to be unsafe, inefficient, or inadequate for securing the safety of the workers, the quality of the Work required, or the rate of progress stipulated, the Project Manager or the Inspector may order the Contractor to increase their safety and efficiency or to improve their character, and the Contractor shall comply with such orders at its own expense. Neither the making of such demands by the Project Manager nor the failure to make such demands shall relieve the Contractor of its obligation to secure the safe conduct of the Work, the quality of Work required, and the rate of progress stipulated in the Contract. The Contractor shall be fully responsible for the safety, efficiency, and adequacy of its plant, appliances, and methods, and for any damage which may result from their failure or their improper construction, maintenance, or operation.
All of the labor shall be performed and material s furnished pursuant to and in strict conformance with the Contract Documents, and in accordance with approved shop drawings. The Contractor shall complete the entire Work to the satisfaction of the Inspector and in accordance with the Specifications and P lans herein mentioned, at the prices fixed in the Contract.
Where articles or materials are especially manufactured, or fabricated for delivery under these specifications, the Contractor shall at all times employ such workforce, plant, materials, and tools as will be sufficient to complete the performance of the Contract and every part thereof within the time limits stipulated herein. If the Contractor fails to employ sufficient workforce, plant, materials, tools, or to maintain adequate progress, the Project Manager may require an increase in progress at any point or points or a modification of Plans and procedure in such a manner as to accelerate the Work. Failure to adequately staff the project shall be just cause for the City to terminate the Contract.
00302 CONTRACTOR’S REPRESENTATIVE AT THE SITE
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 15 of 45
A technically qualified and English- speaking project representative shall be designated in writing as the Contractor’s Representative at the job site, who shall supervise the Work and shall provide competent supervision of the Work until its completion. The Contractor’s Representative shall be assigned full time and exclusively to this project. Alternate representatives with qualifications equal to or better than the previous representative may be designated. The Contractor’s Representatives shall have at least five (5) years of verifiable experience as the person primarily responsible for supervision of the Work on projects of the same or similar size and nature as this project. Within five (5) days after the Notice of Award the Contractor shall provide a statement to the Project Manager and the Inspector with the following:
1) Identification and resume, showing the qualifications and experience of the Contractor’s Representative and the alternate appointed to act in the place of the Contractor’s Representative.
2) References of not less than two (2) previous projects on which the Contractor’s Representative and the alternate had supervisory responsibility on a project of a similar nature and at least one- half or more of the cost of this project. Such references shall include names, addresses, and telephone numbers of owner representatives who worked on the project as well as project information such as project type, size, location and duration.
The Project Manager and the Inspector reserve the right to disapprove any candidate named as the Contractor’s Representative or alternate who fails to meet the provisions set forth herein. The Project Manager and the Inspector reserve the right to remove, without any right to work on the project, either the Contractor’s Representative or alternate, who in the sole opinion of the Project Manager or the Inspector, has demonstrated incompetence, lack of ability, or other unsuitability to perform supervision of the Work.
If the Contractor’s Representative or alternate leave the employ of the Contractor, the Contractor will be required to replace the individual(s) and fulfill the requirements of this Article within fifteen (15) calendar days. In no event shall any Work proceed in the absence of an approved representative.
The Contractor’s Representative or alternate shall have full authority to act on behalf of the Contractor, including, but not limited to final approval of Change Orders and Supplemental Agreements. All directions given by the Project Manager or the Inspector to said representative or alternate shall be considered as having been given to the Contractor. Such instructions given by the Project Manager or the Inspector to the Contractor’s Representative or alternate will be confirmed in writing. All instructions and directions given by the Project Manager or the Inspector will be limited to matters properly falling within the Project Manager’s or the Inspector’s authority as specified in “Authority of the Project Manager and Inspector” of these General Conditions.
The Contractor’s Representative or alternate shall be present at the worksite at all times while Work is in progress. Failure to observe this requirement constitutes a suspension of the Work by the Contractor, until such time the Contractor’s Representative or alternate is again present at the worksite. All Work performed while the Contractor’s Representative or alternate is absent from the worksite is ineligible for payment.
Work performed in violation of these provisions shall be removed and reconstructed, refabricated, or reinstalled under the required supervision. The Contractor is ineligible for time extensions or additional payment for costs or impact that directly or indirectly are caused by said suspension. Those ineligible costs and impacts include what the Contractor may incur for slowdown, delays, idled equipment, removals, reconstruction, refabricating, reinstalling and other. During such periods of noncompliance when the Contractor’s Representative is not on site, written instructions issued by the Project Manager or the Inspector to any employee of the Contractor is considered adequate notice to the Contractor .
Whenever the Work is defined as being suspended under the provisions of this Article, any such suspension in excess of ten (10) calendar days shall constitute just cause for the City to terminate the Contract under the provisions of “Termination of Contract by City (Contractor Default)” of these General Conditions.
00303 FAMILIARITY WITH PLANS AND SPECIFICATIONS
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 16 of 45
It shall be the responsibility of the Contractor to be thoroughly familiar with all details of the Project, including the work of the Contractor’s forces and all Subcontractors. The Contractor shall call the following to the attention of both the Project Manager and the Inspector in writing within twenty-four (24) hours of discovery, before any Work is performed:
1) Errors and omissions in the Plans and Specifications;
2) Work on the Plans or in the Specifications which, if so constructed, would result in a conflict or interference with other Work or the Work of other trades, including the location of fixtures and equipment;
3) Existing improvements visible at the job site, f or which no existing disposition is made on the Plans or in the Specifications but which could reasonably be assumed to interfere with the satisfactory completion of the improvements contemplated by the Plans and Specifications.
4) Failure to notify shall co nstitute a waiver by the Contractor of any claim for delay or other damages occasioned by such defect. If the Contractor proceeds with the Work without instructions from the Project Manager, the incorrect Work shall be removed and corrections made to comp ly with the Project Manager ’s instructions, at no cost to the City. The requirements of this Article are applicable to typographical errors in the Specifications and notational errors on the Plans where ambiguity or inadequate description exists.
00304 JOB CONDITIONS
The Contractor shall determine the nature and types of work to be performed, ascertain all conditions affecting construction procedure and sequencing of Work operations in the execution of the Work, including condition of available roads and streets, or clearances, restrictions and other limitations affecting transportation and ingress and egress to the job site. This determination must be made during the Bidding Period with any costs and impact included within the Bid.
The Contractor shall observe any “Site Security” restrictions described in the General Requirements or the Plans.
Whenever the Work requires entry into an operating plant, occupied building, working facility or other secured location, observe the following unless otherwise noted:
1) No vehicles are allowed except delivery trucks and Contractor’s identified vehicles and equipment.
2) It shall be the Contractor’s sole responsibility to arrange and pay for offsite empl oyee parking and to provide transportation from the parking area to the Work site.
3) The Contractor shall fully cooperate with all authorities on the job site and other contractors not related to the Work of this Contract who might be at the job site.
4) Fully comply with all regulations in force at the job site.
00305 JOB BULLETIN BOARD
When a Field Office is required, the Contractor shall provide and mount a Job Bulletin Board at the field office in a location where it can be readily seen by all of the Contractor employees. The bulletin board shall be substantially built to a minimum size of 900 mm high x 1200 mm wide (3' x 4') shall be fitted with a framed safety glass door and lock. The glass on the outside shall be protected with a 12 mm x 12 mm (½” City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 17 of 45
x ½”) galvanized wire mesh screen permanently attached to the frame. The bulletin board shall be finished inside and outside with two (2) coats of an exterior paint.
00306 RESPONSIBILITY FOR SITE
The Contractor is in full charge of and responsible for the job site and the Work. The “Interface/ Coordination Requirements” of the General Requirements describe interfaces w ith other contractors working on the job site. No other operations of any nature shall be performed except as specifically authorized in the Contract Documents or as authorized by the Project Manager.
The Contractor shall exercise care not to damage impr ovements and adjacent land. The Contractor shall correct any damage caused within seventy -two (72) hours by restoring the land and improvements damaged to their original condition and shall indemnify and hold the City harmless for any such damage as specified in “Indemnification” of these General Conditions.
00307 WORKMANSHIP AND MATERIALS
All materials, parts and equipment furnished by the Contractor for the Work shall be new, high grade and free from defects. Materials and work quality shall be subject to the Inspector’s approval.
00308 INJURY AND ILLNESS PREVENTION - SAFETY MEASURES
Safety is the responsibility of the Contractor. The Contractor shall observe and comply with the safety provisions of all applicable laws, building and construction Codes, safety and health regulations of the California Code of Regulations, and with applicable City Safety Policies.
Every employer (Prime Contractor and / or Subcontractor) employed on the Project shall establish, implement, and maintain an effective Injury and Illness Prevention Program in accordance with Section 3203 of the General Industry Safety Orders.
Contractor shall provide two (2) copies of company safety manual to the project manager for City records.
The contractor is solely responsible for the content of this manual and providing the City with updates during this contract.
Each Contractor / Subcontractor shal l make the applicable Injury and Illness Prevention Program specific for site conditions and type of Work to be performed on the Project.
Each prime Contractor and Subcontractor working on the Project shall make its Injury and Illness Prevention Program available to the Inspector and the Engineer prior to beginning any Work on the Project.
If a work procedure or site condition exists that violates the Contractor’s / Subcontractor’s Injury and Illness Prevention Program or any other safety standard, the Pr oject Manager or Inspector may order the Contractor to immediately comply with said safety provisions, and the Contractor shall comply with such orders at its own expense. If the Contractor fails to act promptly, the Project Manager or Inspector is authorized to suspend the Work. Failure of the Project Manager or the Inspector to make such demands shall not relieve the Contractor of its obligations to secure the safe conduct of the Work.
If a work procedure or site condition creates an immediate hazard to the health or safety of the public, City employees, property, or a licensee, the City may suspend all work on the project. Without prior notice, the City may also correct such hazardous conditions using other forces or contractors, at the Contractor’s sole expense. Any delays or impacts arising on the Work as a result of such an emergency shall be at the sole expense of the Contractor with no time extension, additional reimbursement for extended overhead, or interest on monies due, allowed for the Contractor.
First aid facilities and supplies shall be kept and maintained by the Contractor at the site of the Work.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 18 of 45
The Contractor shall cause all persons within the construction area to wear protective helmets. In addition, all employees of the Contractor and its Subcontractors shall be provided with, and required to use, personal protective and life-saving equipment set forth in California Construction Safety Orders and the OSHA Safety and Health Standards for Construction.
The Contractor shall pr ovide safety equipment, material, and assistance to City personnel to properly inspect all phases of the Work, including final inspection. Such equipment, material and assistance shall include, but not be limited to testing for the presence of explosive or toxic gases and oxygen deficiency in confined spaces, blowers, ventilators, first aid supplies and equipment, ladders, scaffolds, shoring, harnesses, self-contained breathing apparatus, and personnel for standby assistance as required. When the Work requires specialized safety equipment, the Contractor shall provide new sets of such equipment, the training deemed necessary by the Inspector and maintenance of such equipment. When asbestos is being removed, the requirements of the CCR, Title 8, Div. 1, Chapter 4, Subchapter 4, “Construction Safety Orders,” and Subchapter 7, “General Industry Safety Orders,” shall be implemented.
In cases involving exposure of City personnel to toxic/hazardous materials and/or elements, the City’s Occupational Safety Office, shall have field review authority over the Contractor’s operations.
For additional requirements, refer to “Safety and Preconstruction Safety Conference” of the General Requirements.
00309 PROTECTION OF PERSONS AND PROPERTY AND RESTORATION OF EXISTING
IMPROVEMENTS
The Contractor shall not destroy, remove, or otherwise disturb any existing survey monuments or reference points without authorization fr om the Project Manager. No pavement breaking or excavation shall be started until all survey monuments or other reference points that will be disturbed by the construction operations have been properly referenced by the Project Manager. It shall be the Contractor’s responsibility to notify the Project Manager and the Inspector of the time and location that Work will be done. Such notification shall be sufficiently in advance of construction so that there will be no delay due to waiting for survey points to be satisfactorily referenced for restoration. All survey monuments or reference points disturbed, without authorization by the Project Manager, shall be accurately restored by the City at the Contractor’s sole expense after all street or roadway resurfacing has been completed.
Unless otherwise noted, all construction operations shall preserve existing drainage paths, vehicular and pedestrian access. The Contractor shall also regularly attend to dust, mud, trash, noise, debris, and etcetera’s, caused by their construction operations to prevent a public nuisance.
All paved areas including asphalt concrete berms cut or damaged as a result of construction shall be replaced with similar materials and of equal thickness to match the existing adjacent undisturbed areas, except where specific resurfacing requirements have been called for in the Contract Documents or in the requirements of the agency issuing the permit. All temporary and permanent pavement shall conform to the requirements of the affected pavement owner. All pavement which is subject to partial removal shall be neatly saw cut in straight lines.
In order to obtain a satisfactory junction with adjacent surfaces, the Contractor shall saw cut back and trim the edge so as to provide a clean, sound, vertical joint before permanent replacement of an excavated or damaged portion of pavement. Damaged edges of pavement along excavations and elsewhere shall be trimmed back by saw cutting in straight lines. All pavement restoration and other facilities restoration shall be constructed to finish grades compatible with adjacent undisturbed pavement.
Where sidewalks have been removed for purposes of construction, the Contractor shall place suitable temporary sidewalks, properly protected, promptly af ter backfilling and shall maintain them in satisfactory condition until the final restoration thereof has been made.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 19 of 45
When existing planted areas are regraded, or removed and replaced because of the Contractor’s operations, the soil in these areas shall be prepared and the area replanted-in-kind. All landscape materials shall conform to the requirements of the owner of the affected planted area.
All utilities encountered along the line of the Work shall be maintained continuously in service during all the operations under the Contract, unless other arrangements satisfactory to the Project Manager are made.
Utilities shall include, but not be limi ted to, all above or below -ground conduit, pipes, ducts, cables, and appurtenances associated with oil, gas, water, steam, irrigation, process, sewer, storm drain, wastewater, air, electrical, power, instrumentation, communication, telephone, cable, TV, and lighting systems, whether or not owned by the City.
The Contractor shall protect all existing utilities and improvements not designated for removal. Potholing shall be accomplished at the Contractor’s expense. The Contractor shall determine the exact locations and depths of all utilities indicated on the Drawings. The Contractor shall make exploratory excavations of all utilities. The Contractor in conformance with City Ordinance shall pothole existing subsurface installations carrying unstable substances to determine their locations and elevations before commencing excavation.
All such exploratory excavations shall be performed as soon as practicable after award of the Contract and in any event, a sufficient time in advance of construction to avoid possible delays to the Contractor’s Work.
When such exploratory excavations show the utility location as indicated on the Drawings to be in error, the Contractor shall so notify the Inspector and the Project Manager. The Contractor should not rely upon plan designation of location of underground utilities. The number of exploratory excavations and extent of potholing required shall be that number which is sufficient to determine the alignment and grade of the utility. These costs are a part of the Bid.
Prior to any excavation in the vicinity of any existing underground facilities, the Contractor shall notify the Inspector and the Project Manager, and the respective authorities representing the owners or agencies responsible for such facilities, not less than three (3) Workdays, nor more than five (5) Workdays, of their intention to begin excavation. The Contractor shall make arrangements for and provide access such that a representative of said owners or agencies may be present during such Work.
Before commencing any excavation, the Contractor shall obtain an Underground Service Alert (USA) inquiry I.D. number. Two workdays, shall be allowed after the I.D. number is obtained and before the excavation work is started so that utility owners can be notified. If the utility owner is the City, a confirmation number indicating the City has been notified shall be obtained by USA and/or the Contractor from the appropriate City department. The I.D. number together with the date acquired shall be reported to the Inspector when calling for inspection. I.D. numbers will not be given more than ten (10) Workdays before starting excavation work.
Unless otherwise indicated on the Plans or Specifications, where the proper completion of the Work requires the temporary or permanent removal and/or relocation of an existing utility or other improvement, which is shown on the Plans, the Contractor shall, at its own expense, remove and, without unnecessary delay, temporarily replace or relocate such utility or improvement to a place and in a manner as directed by the Project Manager, and the owner of the facility. In all cases of such temporary removal or relocation, restoration to former location shall be accomplished by the Contractor in a manner that will restore or replace the utility or improvement as nearly as possible to its former locations and to as good or better condition than found prior to removal. When utilities that are to be removed are encountered within the area of operations, the Contractor shall notify the Project Manager not less than fifteen (15) days in advance for necessary measures to be taken to prevent interruption of service.
The Contractor shall notify the Project Manager thirty (30) calendar days in advance of any proposed connection, and shall notify the Project Manager and the Inspector twenty-four (24) hours prior to the actual connection, to any existing utility.
Any utility or improvement which is damaged by the Contractor shall be immediately repaired at the Contractor’s expense, to a condition equal to, or better than, the condition it was in prior to such damage EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 20 of 45
or temporary relocation. If the Contractor fails or refuses to promptly repair the utility or improvement, the City may perform the necessary Work at the Contractor’s expense. The Contractor will also not be entitled to any time extension, additional reimbursement, extended overhead, or interest on monies due. The Contractor is not relieved of provisions of this Article even in the event such damage occurs after backfilling or is not discovered until after completion of backfilling.
All repairs to a damaged improvement shall be inspected and approved by the Inspector and an authorized representative of the improvement owner before being concealed by backfill or other Work. In case of damage, which in the opinion of the Project Manager or the Inspector, threatens the safety of persons or property, the Contractor shall immediately make all repairs necessary for removal of the hazard. Should the Contractor fail to promptly take all necessary action, the City has the option to remove any hazard resulting from damages caused by the Contractor at the Contractor’s expense without waiving any other rights the City may have. The Contractor will also not be entitled to any time extension, additional reimbursement, extended overhead, or interest on monies due.
In the event that the Contractor damages any existing utilities that are not shown on the Plans or the locations of which are not made known to the Contractor prior to excavation, the Contractor shall immediately notify the Inspector and take all measures necessary to prevent further damage. The Contractor shall then immediately make a written report to the Project Manager and shall make repairs as directed by the Project Manager.
Notwithstanding that an existing utility or substructure is not shown on the original Plans and Specifications, if the existence and location thereof was made known to the Contractor prior to excavation, the utility or substructure constitutes an existing known condition, and the Contractor is responsible for protecting the utility or substructure.
Damage to a utility known to the Contractor shall be repaired at the Contractor’s expense.
00310 NON-CONFORMING WORK
Except as set forth in this Article, all non-conforming Work and materials, in place or not, shall be removed immediately from the site or corrected to conform to all requirements of the Contract Documents, by the Contractor, at the sole expense of the Contractor.
If the Contractor fails to remove, replace or correct any non- conforming Work or materials within seventy - two (72) hours of discovery, the Inspector or the Project Manager may cause such Work or materials to be removed and replaced. Such removal and replacement shall be at the sole expense of the Contractor with no entitlement to time extensions, additional reimbursement, extended overhead, or interest on monies due. In addition, all such cost shall be deducted from any amounts that are due or may become due to the Contractor.
Failure of the Inspector or the Project Manager to notify the Contractor of any non -conforming Work shall not constitute acceptance of any non-conforming Work. The Contractor’s obligation to remove, replace or correct any non-conforming Work, whenever discovered, shall continue to the end of the guaranty-warranty period provided for in “Guaranty-Warranty” of the General Requirements. The City reserves and retains all rights and remedies at law against the Contractor and their Surety for correction of any and all latent defects discovered after the guaranty-warranty period.
Any delays or impacts arising on the Work as a result of construction, fabrication or delivery of non- conforming work or materials shall be at the Cont ractor’s sole expense, with no time extension, additional reimbursement for extended overhead, or interest on monies due allowed.
Examination of covered Work may be ordered by the Project Manager or the Inspector for any reason. The Work shall be uncovered by the Contractor and if such Work is found to be in accordance with the Contract Documents, the City will issue a Change Order authorizing payment for the cost of examination and City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 21 of 45
replacement. If such Work is found to be not in conformance with the Contr act Documents, the Contractor shall correct the non- conforming Work and the cost of examination and correction of the non- conforming Work shall be borne solely by the Contractor.
Failure of the Contractor to comply with the requirements of this Article shall constitute default of the Contract by the Contractor and the City may terminate the Contract as provided for in Termination of Contract by City (Contractor Default).
00311 SUBCONTRACTORS AND SUB-SUBCONTRACTORS
The Contractor shall perform on the site and with its own organization not less than twenty percent (20%) of the total Contract Price, unless a different percentage is designated in the Bid Proposal. Any items designated "specialty items" in the Bid Proposal may be performed by subcontract and the amount of all such "specialty items" may be deducted from the Contract Price before computing the amount of Work required to be performed by the Contractor with its own organization. The dollar value included in the percentage performed by the Contractor shall include the value of labor, materials and equipment to be incorporated or used in the Work and directly purchased by the Contractor and shall not include the value of Work, including labor, materials and equipment, incorporated or used in the Work, performed or provided by Subcontractors.
To be eligible for award of this Project, the Sacramento City Code requires Bidders to subcontract a minimum of its total Bid to qualified Subc ontractors, as discussed in the “ Local Business Enterprise (LBE) Requirements” of the Bid Proposal. Failure to list Subcontractors and the subcontracted dollar amounts on the applicable pages of the Bid Proposal to satisfy the LBE is cause for the Bid to be declared nonresponsive and rejected by City Council.
Bidders must list all Subcontractors in the Bid, regardless of the dollar amount of the work to be performed, if the Bidder wishes to have the Subcontract amount credited toward meeting both the LBE levels of participation of the Project. Subcontractors added to the project following acceptance of the Bid and award of the Project will not be credited toward meeting the required L levels of participation for this Project.
LBE credit will not be given to a joint venture partner listed as a Subcontractor by a joint venture.
The designated percentage of the total Contract Price the Contractor is to perform may not be reduced below that level by the addition of Subcontractor’s added after Award of the Project.
The Contracts person, will be responsible for approval of all Subcontractors, whether Bid-listed or not, and all Sub-subcontractors employed on the Project.
Each Subcontractor who will perform Work or render services in an amount in excess of one- half of 1 percent of the Contractor’s total Bid, must be listed in the original Bid.
Subletting or Subcontracting of any portion of the Work in excess of one-half of 1 percent of the Contractor’s original total Bid, for which no Subcontractor was designated in the original Bid shall only be permitted in cases of public emergency or necessity, and then only after a finding reduced to writing as a public record of the Inspector setting forth the facts constituting the emergency or necessity.
If the Contractor fails to specify a Subcontractor, or if the Contractor specifies more than one Subcontractor for the same portion of Work to be performed under the Contract in exc ess of one-half of 1 percent of the Contractor’s total original Bid, the Contractor agrees that it is fully qualified to perform that portion of Work itself, and that it shall perform that portion itself.
The Contractor shall set forth in its Bid the following: The name, location of the place of business, telephone number, California State Contractor’s License Number and dollar amount of each Subcontractor who will perform Work, labor, service, supply specifically fabricated materials or equipment in an amount in excess of one-half of 1 percent of the Contractor’s total Bid.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 22 of 45
The Contractor shall list only one Subcontractor for each portion of Work as defined by the Contractor in its Bid.
Acceptance by City Council of its Bid is dependent upon each Bid listed Subcontractor, and all subsequently approved additional Subcontractors, performing the dollar value of Work listed or approved. Any reduction, increase, or other change to any Subcontract amount without prior approval is considered an Unauthorized Subcontractor Substitution. A Subcontract dollar value increased or reduced as the result of a Change Order issued by the Project Manager to add or delete from the original scope of Work shall not be subject to a penalty for an Unauthorized Subcontract Substitution.
Acceptance by the City Council of its Bid shall not entitle Subcontractors to recognition for any direct or contractual relationship with the City, nor shall it constitute approval of the use of any materials other than those specified.
The Contractor shall be responsible for all acts of all Subcontractors at all tiers. The Contractor shall coordinate all interests of the City in performed by subcontractors.
All Subcontractors who will be working on the Project shall be approved in writing by the Inspector prior to beginning Work, regardless of the dollar amount of Work to be performed, and whether or not they were listed in the original Bid.
Requests for approval of all Subcontractors, or request for substitution of a Subcontractor, shall be made in writing to the Inspector, and said request shall contain the following information for each Subcontractor:
1) Project Name
2) Project Number
3) Subcontractor’s Name
4) Subcontractor’s Address
5) Subcontractor’s Phone Number
6) Subcontractor’s Status (WBE, MBE, SBE)
7) Subcontractor’s State of California Contractor License Number
8) Subcontractor’s City Business Tax Registration Certificate Number (BTRC)
9) Dollar amount of Subcontract work to be performed
10) Description of Subcontract work to be performed
Failure to provide any of the information listed will result in denial of approval until such time as the information is provided.
Failure to obtain approval of the Inspector prior to each Subcontractor performing Work on the Project may result in suspension of Work by that Subcontractor, removal of Work performed by unapproved Subcontractors, assessment of penalties, and possible sanctions against the Contractor.
Additional Subcontractors may be added after the time of original Bid. The value of W ork to be performed by additional Subcontractors may not be greater than one-half of 1 percent of the Contractor’s original total City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 23 of 45
Bid, unless the Subcontractor will be performing Work added by Change Order causing changes or deviations from the original Contract.
The Contractor shall provide the dollar amount of Work to be performed in all requests for additional Subcontractors. Failure to specify a dollar amount of Work to be performed will result in denial of additional Subcontractors until such time as the amount is provided.
A Contractor whose Bid is accepted may not:
1) Substitute any person as Subcontractor in place of a Subcontractor listed in the original Bid, except that the Inspector, acting on behalf of the City, may consent to the substitution of another Subcontractor for one of the following situations:
A) When the Subcontractor listed in the original Bid or proposal after having had a reasonable opportunity to do so fails or refuses to execute a written contract, when that written contract, based upon the general terms, conditions, plans and specifications for the project involved or the terms of that Subcontractor’s written bid, is presented to the subcontractor by the Contractor.
B) When the listed Subcontractor becomes bankrupt or insolvent.
C) When the listed Subcontractor fails or refuses to perform its subcontract.
D) When the listed Subcontractor fails or refuses to meet the bond requirements of the Contractor as set forth herein.
E) When the Contractor demonstrates to the Inspector’s satisfaction that the name of the Subcontractor was listed as a result of an inadvertent clerical error.
F) When the listed Subcontractor is not licensed pursuant to the State of California Contractor’s License Law.
G) When the listed Subcontractor refuses to obtain a City of Sacramento Business Tax Receipt Certificate (BTRC).
H) When the Inspector concurs with the Contractor that the Work being performed by the listed Subcontractor is unsatisfactory and not in substantial accordance with the Contract Documents, or the listed Subcontractor is delaying or disrupting the progress of the work.
I) When the listed Subcontractor fails to submit an Affirmative Action Plan acceptable to the Inspector.
J) When the City determines that a listed Subcontractor is not a responsible contractor.
2) Permit a Subcontract to be voluntarily assigned or transferred or allow it to be performed by anyone other than the original Subcontractor listed in the original Bid, without the consent of the Inspector.
3) Other than in the perform ance of Change Orders causing changes or deviations from the original Contract, sublet or Subcontract any portion of the Work in excess of one half of 1 percent of the Contractor’s total Bid as to which its original Bid did not designate a Subcontractor.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 24 of 45
4) Reduce the dollar amount of a Bid- listed Subcontract without the written approval of the Inspector.
A request for substitution of any Subcontractor, whether Bid- listed or not, must be made in writing to the Inspector and must include letter(s) of explanation as to the reason for the requested substitution.
It is considered a substitution if anyone other than the Bid- listed and/or approved Subcontractor(s), including the Contractor, performs any portion of the Work designated to be performed by sai d Subcontractor.
Failure to obtain approval for a Subcontractor substitution may result in rejection of the affected Work, penalties assessed for failure to obtain approval, and possible sanctions by the City.
All substitutions of Subcontractors, whether LBE or not, shall be approved in writing by the City prior to any Work being performed by the substituting Subcontractor.
The Contractor shall comply with the Local Business Enterprise requirements of the Bid Proposal prior to approval of any Subcontractor substitution. The contracts person from City of Sacramento Public Works shall approve any requested Subcontractor substitution, whether the Subcontractor was Bid listed or approved after the Award of the Project.
There shall be no decrease in dollar va lue of Work to be performed by Subcontractors approved as a substitute for a Bid- listed Subcontractor without a change in scope of the Work to be performed by the originally Bid-listed Subcontractor. Written evidence of a change of scope must be provided by the Project Manager prior to approval of a change in dollar value of a Bid-listed Subcontractor.
Prior to approval of the Contractor’s request for substitution, the Inspector shall give notice in writing to the Subcontractor affected by the Contractor’ s request to substitute and of the reasons for the request. The notice shall be served by certified or registered mail to the last known address of the Subcontractor. The listed Subcontractor who has been so notified shall have five (5) Workdays within w hich to submit written objections to the substitution. Failure to file these written objections within five (5) Workdays of notification shall constitute the listed Subcontractor’s consent to the substitution. Notification by the Inspector may be made by phone in lieu of written notification via certified or registered mail if agreed to by the listed Subcontractor and followed by written request. Upon notification by phone, the listed Subcontractor may file written objections within five (5) days of notification.
If written objections are filed, the Inspector shall give notice of at least five (5) Workdays to the listed Subcontractor of a hearing on the Contractor’s request for substitution.
The Contractor, as a condition to assert a claim of Inadvertent Clerical Error in the listing of a Subcontractor, shall within two Workdays after the time of the original Bid opening by the City Clerk give written notice to the Inspector and copies of such notice to both the Subcontractor he claims to have listed i n error and the intended Subcontractor who had bid to the Contractor prior to Bid opening.
Written notice of an Inadvertent Clerical Error shall be forwarded within two (2) days after the time of the original Bid opening by every Contractor claiming such an error, regardless if it is the potential low Bidder on the Project. Failure to forward such notice within the time prescribed shall make any such subsequent claim of Inadvertent Clerical Error invalid.
Any listed Subcontractor who has been notified by the Contractor of an Inadvertent Clerical Error shall be allowed six (6) Workdays from the time of the Bid opening to submit to the Inspector and to the Contractor written objection to the Contractor’s claim of Inadvertent Clerical Error. Failure of such listed Subcontractor to file such written notice within the six (6) Workdays shall constitute agreement that an advertent clerical error was made.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 25 of 45
The Project Manager shall, in the absence of compelling reasons to the contrary, consent to the requested substitution based on an Inadvertent Clerical Error if:
1) The Contractor, the Subcontractor listed in error, and the intended Subcontractor each submit an affidavit to the Project Manager along any additional information as the parties may wish to submit that an Inadvertent Clerical Error was in fact made, provided that the affidavits from each of the three parties are filed within eight (8) Workdays from the time of the original Bid opening, or
2) If such affidavits are filed by both the Contractor and the intended Subcontractor within eight days of the original Bi d opening but the Subcontractor whom the Contractor claims to have listed in error does not submit within six (6) Workdays, to the Inspector and to the Contractor, written objection to the Contractor’s claim of Inadvertent Clerical Error as provided in this article.
If such affidavits are filed by both the Contractor and the intended Subcontractor but the listed Subcontractor has, within six (6) Workdays from the time of the original Bid opening, submitted to the Project Manager and to the Contractor writt en objection to the Contractor’s claim of Inadvertent Clerical Error, the Project Manager shall investigate the claims of all parties and schedule a meeting to determine the validity of such claims. Any determination shall be based on the facts contained in the declarations submitted under penalty of perjury by all three parties and supported by testimony given to the Project Manager. The findings of the Project Manager shall be final.
00312 RESPONSIBILITY OF CONTRACTOR TO ACT IN EMERGENCY
When an emergency arises creating an imminent hazard to persons or threatening the loss or damage to property, the Contractor shall take prudent action without instruction from the City. T he Contractor shall immediately notify the Project Manager and the Inspector of any emergency action taken. During such emergencies, if the Contractor fails to act, the Project Manager or Inspector may instruct the Contractor to take action. Should the Contractor still fail to act, the Project Manager or Inspector may respond to the emergency with other forces or contractors at the Contractor’s sole expense. Claims for additional time, compensation or interest will be rejected if the Contractor’s actions or inaction created the emergency.
Similarly, any Claims will be offset by the amount that the Contractor’s actions or inaction aggravated the emergency.
00313 ASSIGNMENT
The Contractor shall not assign, transfer, convey or otherwise dispose of this Contract or any of the proceeds thereunder unless written consent of the City has been obtained. No right under this Contract or claim for any proceeds due or to become due her eunder shall be asserted against the City, or persons acting for the City, by reason of any so- called assignment, transfer or conveyance of this Contract or any part thereof unless such assignment, transfer or conveyance has been authorized by the written consent of the City. The instrument of assignment, transfer or conveyance shall contain a clause subordinating the claim of the assignee, transfer or conveyor to all prior liens for services rendered or materials supplied for the execution of the Work.
00314 NOTIFICATION OF HAZARDOUS SUBSTANCES
The existing facilities or Jobsite may contain asbestos, PCBs, corrosives, carcinogens, or other hazardous materials. Should the Contractor or any of its Subcontractors, while performing Work on or in the vicinity of existing facilities, unexpectedly encounter any material identified in the California Code of Regulations, Title 8, as a hazardous material not shown on the Plans or addressed in the specifications, or have reason to believe that any other material encountered may be a hazard to human health and safety and/or the environment, the Contractor shall stop the Work, cordon off the affected area to secure entry, and shall immediately notify the Inspector and the Project Manager. Removal and disposal of the hazardous material not shown on the Plans or addressed in the specifications, if the Project Manager deems it necessary, will EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 26 of 45
be done by and at the expense of the City. The City will provide the Contractor, upon request, with copies of Material Safety Data Sheets (MSDS) covering hazardous materials identified by the Contractor that are encountered in existing facilities during the course of the Work and that are not removed by the City.
In the event that the Contractor is delayed in the completion of the Contract solely because of such hazardous materials or conditions not previously identified in the Contract Documents, the Contractor shall be entitled to an extension of time in accordance with “Unavoidable Delay” of these General Conditions.
For new construction Work and for all Contractor furnished supplies and equipment that may contain hazardous materials, the Contractor shall develop and implement a written Hazard Communication Program for its employees in accordance with the California Code of Regulations. The Contractor’s basic written Hazard Communication Program shall be submitted to the Project Manager and the Inspector prior to the start of Work at the site, and shall be revised and kept current as required by the continuing progress of the Work. The Contractor’s Hazard Communication Program shall also include the MSDS for all hazardous materials the Contractor will be using at the facility. All provisions concerning MSDS for hazardous materials shall be met before the hazardous material is delivered to the site.
The Project Manager shall be provided with three (3) copies and the Inspector with four (4) copies of the Contractor’s written Hazard Communication Program, Contractor provided MSDS, and all revisions and modifications thereto.
The Contractor and Subcontractors shall comply with all State and Federal statutes and regulations on training, handling, storage, public notification, and disposal of hazardous materials and hazardous wastes.
In the event that the Contractor or its Subcontractors spills or releases hazardous materials, the Contractor shall immediately notify the Inspector and the Project Manager and any required agencies of the spill or release and the Contractor shall stop the Work, and cordon off the affected area to secure entry. Removal and disposal of the hazardous material, if the Project Manager deems it necessary, will be done by the City at the Contractor’s expense. Further, the Contractor shall notify the Project Manager and the Inspector when hazardous materials are brought on- site and when hazardous materials and hazardous wastes are removed from the site. Hazardous Materials brought on site shall be accompanied by four (4) copies of MSDS, which shall be provided to the Inspector before such materials are unloaded.
00315 INDEPENDENT CONTRACTOR
The Contractor represents that it is fully experienced and properly qualified to perf orm the class of Work required for the Contract and that it is properly licensed, equipped, organized and financed to perform the Work. The Contractor shall be an independent contractor. The Contractor is not an agent of the City in the performance of the Contract, and shall maintain complete control over its employees and its Subcontractors and Suppliers of any tier. Nothing contained in the Contract or any Subcontract awarded by the Contractor shall create any relationship between any Subcontractor and the City. The Contractor shall perform the Work in accordance with its own methods, in compliance with the terms of the Contract.
00316 INDEMNIFICATION
Except for the active negligence or willful misconduct of the City, the Contractor undertakes and agrees to defend, indemnify and hold harmless, through legal counsel acceptable to the City, the City, and any and all of the City Council, Officers, Agents, Employees, Assigns, and Successors in Interest from a nd against all suits and causes of action, claims, losses, demands and expenses, including, but not limited to, attorney's fees and cost of litigation, damage or liability of any nature whatsoever, arising out of or related to the performance or nonperfor mance by Contractor or its Subcontractors, Sub- Subcontractors, or Suppliers, of any tier, of any portion of the construction of the Project, including but not limited to Contractor’s negligent acts, errors, omissions, breach of contract, breach of warrant y (express or implied), or willful misconduct.
It is agreed that such defense and indemnity shall extend to the City’s Architect/Engineer or other Design Consultant providing services under written agreement with the City covering any portion of the P roject.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 27 of 45
Provided, however, that the Design Consultant shall be solely responsible for the enforcement of any request made by said Consultant for indemnification or defense by the Contractor. It is further provided that the City shall have no liability wh atsoever for any failure of the Contractor to comply with any request from the consultant for indemnity or defense.
It is further agreed that the defense and indemnity obligations of the Contractor under this Article shall not extend to the liability of t he Design Consultant or its agents, employees or subconsultants, arising as a result of such indemnitee's own active negligence, errors or omissions or from (1) the preparation or approval of maps, Plans, opinions, reports, surveys, change orders, designs or Specifications, or (2) the giving of or failure to give directions or instructions by the indemnitee provided that such giving or failure to give is the primary cause of the damage or injury.
00317 INSURANCE
These provisions apply unless otherwise noted in the General Requirements.
1) GENERAL
During the term of this Contract and without limiting the Contractor’s indemnification of the City, the Contractor shall provide and maintain at its own expense, insurance having the limits customarily carried and actually arranged by the Contractor but not less than the amounts and types listed on the Insurance Requirements Form in these Contract Documents, covering its operations hereunder subject to the following conditions as they may variously apply:
A) ADDITIONAL INSURED/ADDITIONAL INTEREST/LOSS PAYEE
The City Council, Officers, Agents, and Employees shall be included as:
1. Additional Insureds in all required General Liability and Additional Interests in all required Automobile Liability insurance.
2. Named Insureds in all required Owners and Contractors Protective Liability insurance policies.
3. Loss Payee As Its Interest May Appear in all required property, fidelity or Surety coverages.
The City and other listed above need not be named on Workers' Compensation/Employer's Liability, Professional Errors and Omissions and Second-party Legal Liability coverages (such as Garage Keepers' Legal).
B) INSURANCE APPROVAL
All insurance required hereunder shall conform to the City requirements established by Charter, ordinance or policy. Evidence of insurance shall be submitted to the Department's Risk Control Coordinator and approved by the City Attorney prior to commencement of any Work or tenancy under this Contract in accordance with the Sacramento City Code.
C) ALTERNATIVE PROGRAMS
Alternative Risk Financing mechanisms such as Risk Retention Groups, Risk Purchasing Groups, off-shore carriers and captive insurance programs are subject to review of their financial statements by the City before an approval can be granted by the City Attorney.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 28 of 45
D) ADMITTED CARRIER/LICENSED CALIFORNIA BROKER
Insurance shall be obtained from brokers or carriers authorized to transact insurance business in California. Surplus lines insurance from carr iers who are not admitted in California must be submitted through a California- licensed broker or agent.
Surplus lines coverage must also contain a Service of Suite provision whereby the underwriters will submit as necessary to any court of competent juri sdiction in California and agree that all matters arising thereunder will be determined in accordance with the law and practice of such court. It must further give the name and address of the underwriter's agent for service of process located within California or must nominate the California Insurance Commissioner as such agent.
E) PRIORITY OF COVERAGE
The Contractor’s insurance shall not call on the City’s program for contributions.
F) CANCELLATION/REDUCTION IN COVERAGE NOTICE
With respect to the interest of the City, if an insurance company elects to cancel insurance before the stated expiration date, or declines to renew in the case of a continuous policy, or materially reduces the coverage period by changing the retroactive date (if any), or the extended discovery period (if any), or reduces the stated limits other than by impairment of an aggregate limit, or materially reduces the scope of coverage which affects the City’s interest, the company will provide the City at least thirty (30) calendar days prior written of such election.
G) ACCEPTABLE EVIDENCE
The appropriate City Special Endorsement forms, contained in Volume 1 of these Contract Documents, are the preferred form of evidence of insurance.
Alternatively, the Cont ractor may submit two (2) certified copies of the policy or other evidence acceptable to the City Attorney containing language which complies with subparagraphs 1) through 6) above.
With respect to Professional Liability insurance, either a signed copy of the Policy Declarations Page or a letter from the Contractor’s insurance broker certifying coverage, together with a thirty (30) day cancellation notice endorsement in favor of the City as specified in subparagraph 6) will satisfy this requirement.
H) SEPARATION OF INSUREDS
Except with respect to the insurance company's limits of liability, each liability insurance policy shall apply separately to each insured against whom a claim or suit is brought. The inclusion of any person or organization as an insured shall not affect any right which such person or organization would have as a claimant if not so included.
I) RENEWAL
Once the insurance has been approved by City, evidence of renewal of an expiring policy may be submitted on a manually signed renewal endorsement or certificate City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 29 of 45
form. If the policy or carrier has changed, however, new evidence as specified in paragraphs 1) through 8) above, must be submitted.
2) AGGREGATE LIMITS/REDUCTION IN COVERAGE
If any of the required insurance coverages contain aggregate limits, or apply to other operations or tenancy of the Contractor not related to this Contract, the Contractor shall give the City prompt, written notice of any incident, occurrence, claim, settlement or judgement against such insurance which in the Contractor’s best judgement may diminish the protection such insurance affords the City. Further, the Contractor shall immediately take all reasonable and available steps to restore such aggregate limits or shall provide other insurance protection for such aggregate limits. The City may, at its option, specify a minimum acceptable aggregate for each line of coverage required.
The Contractor shall not make any substantial reductions in scope of coverage (e.g., elimination of contract ual liability or reduction of discovery period) which may affect the City’s protection without the City’s prior written consent.
3) SELF-INSURANCE AND SELF-INSURED RETENTIONS
Self-insurance programs and self -insured retention in insurance policies are su bject to separate approval by the City upon review of evidence of the Contractor’s financial capacity to respond. Additionally, such programs or retention must provide the City with at least the same protection from liability and defense of suits as would be afforded by first -dollar insurance.
4) MODIFICATION OF COVERAGE
The City reserves the right at any time during the term of this Contract to change the amounts and types of insurance required hereunder by giving the Contractor ninety (90) calendar day s advance written notice of such change. If such change should result in substantial additional cost to the Contractor, the City agrees to negotiate additional compensation.
5) FAILURE TO PROCURE INSURANCE
The required coverage and limits are subject to availability on the open market at reasonable cost as determined by the City. Non- availability or non- affordability must be documented by a letter from the Contractor’s insurance broker or agent indicating a good faith effort to procure the required insurance and showing, as a minimum, the names of the insurance carriers and the declinations or quotations received from each.
Within the foregoing constraints, the Contractor’s failure to procure or maintain required insurance or a self -insurance program during the entire term of this Contract shall constitute a material breach of this Contract under which the City may immediately suspend or terminate this Contract or, at its discretion, procure or renew such insurance to protect the City’s interests and pay any and all premiums in connection therewith, and recover all monies so paid from the Contractor.
6) UNDERLYING INSURANCE
The Contractor shall be responsible for requiring indemnification and insurance as it deems appropriate from its consultants, agent s and Subcontractors, if any, to protect the Contractor’s and the City’s interests, and for ensuring that such persons comply with any applicable insurance statutes. The Contractor is encouraged to seek professional advice in this regard.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 30 of 45
7) WORKERS' COMPENSATION
By signing this Contract, the Contractor hereby certifies that it is aware of the provisions of Section 3700 et seq., of the Labor Code which require every employer to be insured against liability for Workers' Compensation or to undertake self -insurance in accordance with the provisions of that Code, and that it will comply with such provisions at all such times as they may apply during the performance of the Work pursuant to this Contract.
A waiver of subrogation in favor of the City will be required when Work is performed on City premises under hazardous conditions.
8) ALL RISK BUILDER'S RISK/INSTALLATION FLOATER
During the course of construction, the Contractor shall secure and maintain an All Risk Builder's Risk Insurance policy covering loss, damage or destruction of property, including materials in transit and stored on and off site, in an amount equal to the value of the construction and materials on hand.
An Installation Risk or "Floater" Policy, written to cover only specific types of equipment during construction, may be provided to cover damage to Work or high valued equipment or materials.
Coverage shall remain in force until the Work is completed and accepted by the City.
Acceptable evidence of coverage shall be in the form of an endorsement to the policy which names the City as Loss Payee As Its Interest May Appear.
9) TYPICAL COVERAGES REQUIRED
The coverages required in A above shall be at least as broad as:
A) General Liability: Insurance Services Office Commercial General Liability coverage.
B) Automobile Liability: Insurance Services Office Form Number CA 00 01 covering Automobile Liability, code 1 (any auto).
C) Professional Liability: If applicable, errors and omissions liability appropriate to the consultant's profession, with a discovery period of not less than twelve (12) months after completion of Work or termination of Contract.
10) TYPICAL LIMITS OF LIABILITY
Unless otherwise specified, the Contractor shall maintain limits no less than:
A) General Liability: $1,000,000 per occurrence for bodily injury, personal injury and property damage. If Commercial General Liability or other form with a general aggregate limit is used, either the general aggregate shall apply separately to this project/location or the general aggregate limit shall be twice the required occurrence limit.
B) Automobile Liability: $1,000,000 per accident for bodily injury and property damage, combined or equivalent in split limits.
C) Employer's Liability: $1,000,000 per accident for bodily injury or disease.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 31 of 45
D) Professional Liability: $1,000,000 per occurrence.
11) CONTRACT BONDS
Before the execution of the Contract by the City Council, the Bidder shall file with the City bonds satisfactory to the City in the amounts and for purposes noted below. Bonds shall be duly executed by a responsible corporate Surety, authorized to issue such bonds in the State of California and secured through an authorized agent with an office in California.
Bonds shall be issued by a Surety who is listed in the latest revision of U.S. Department of Treasury Circular 570, is authorized to issue bonds in California, and whose bonding limitation shown in said circular is sufficient to provide Bonds in the amount required by the Contract. The Bidder shall pay all Bond premiums, costs, and incidentals.
Each Bond shall be signed by both the Bidder and the Surety, and the signature of the authorized agent of the Surety shall be notarized.
The Bidder shall provide two good and sufficient surety bonds. The "Payment Bond" (Material and Labor Bond) shall be for not less than one hundred percent (100%) of the Contract Price, to satisfy claims of material suppliers and of mechanics and laborers employed by it on the Work. The bond shall be maintained by the Contractor in full forc e and effect until the Work is accepted by the City, and until all claims for materials and labor are paid, and shall otherwise comply with the California Civil Code.
The "Performance Bond" shall be for one hundred percent (100%) of the Contract Price to guaranty faithful performance of all Work, within the time period prescribed, in a manner satisfactory to the City, and that all materials and Workmanship will be free from original or developed defects, and comply with requirements and guaranty specified in “Guaranty - Warranty” of the General Requirements.
Should any Surety at any time be unsatisfactory to the City, notice will be given the Contractor to that effect. No further payments shall be deemed due or will be made under the Contract until a new Surety shall qualify and be accepted by the City.
Changes in the Work, or extensions of time, made pursuant to the Contract, shall in no way release the Contractor or Surety from its obligations. Notice of such changes or extensions shall be waived by the Surety. In addition to the bonds detailed above, the Contractor shall provide a guarantee bond as detailed in “Guaranty -Warranty” of the General Requirements.
00318 SERVICE OF NOTICE
The delivering of any notice, instruction, claim or protest, or other written communication, personally to the Contractor or the Contractor’s Representative or to the Project Manager, the Inspector, or to the City Clerk shall constitute service therefore upon the Contractor, the Project Manager, the Inspector, or the City, respectively.
The depositing of a post -paid (Registered Mail) wrapper directed to the official address of the Contractor, the Engineer, the Inspector, or the City in any post office, of any notice, instruction, claim or protest, or written communication, shall be deemed sufficient service thereof upon the Contractor, the Engineer, the Inspector, or the City, respectively, and the date of said service shall be the day following the date of postmark.
The official address of the Contractor shall be the address given in the accepted Bid or such other address as the Contractor may subsequently designate in writing either to the Engineer or to the City. The official address of the Engineer, the Inspector, and the City will be supplied to the Contractor after the award.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 32 of 45
00319 AGENT TO ACCEPT SERVICE
The Contractor shall maintain within Sacramento County a duly authorized agent as identified in the Article entitled Service of Notice to accept service of legal process on its behalf, and shall keep the City advised of such agent's name and address during the duration of the Contract and for three (3) years after the Final Payment, or as long as the Contractor has warranty obligations under the Article entitled “Guaranty - Warranty” of General Requirements, whichever period terminates later. In the event that no such duly authorized agent is on file with the City, the Contractor agrees that the Sec retary of State of the State of California shall be the Contractor’s agent for service of legal process.
00320 THRU 00399 NOT USED
00400 TEMPORARY SUSPENSION OF WORK
If the Work of the Contract is suspended or delayed, the Contractor shall so notify the Project Manager within twenty-four (24) hours after the start thereof. If the Contractor is entitled to reimbursement for such suspension or delay, as specified hereinafter, the Contractor shall submit a completely detailed statement of the costs thereof, to the Project Manager, within twenty (20) calendar days after the termination thereof.
Failure to submit such statement of costs or notification within the time specified shall be deemed a waiver of any claims for delay or damages or both by the Contractor.
If the Work of the Contract is suspended or delayed through no fault of the City, all expenses and losses shall be borne by the Contractor with no time extension, additional reimbursement for extended overhead, or interest on monies due, allowed to the Contractor.
If the Work of the Contract is suspended or delayed by an act of the City, or by failure of the City to furnish required information, and the Contractor thereby incurs expenses or sustains losses which could not have been avoided by the judicious handling of forces and equipment, and if by a diligent prosecution of the Work the Contractor could not have completed the Work before such suspension, the Contractor will be paid such amount as the City may find to be a fair and reasonable compensation for such part of the Contractor’s actual loss. In no case, shall any compensation be made to cover any loss other than actual cash paid for wages, rental of equipment, and materials used in protection of the Work, all of which must be supported by satisfactory written evidence. Such wages shall not include the wages or salary of any individual not necessary for protection of the Work. The Contractor shall not be entitled to any mark -up for overhead or profit on damages or for extended duration or for interest on monies due for work satisfactorily completed prior to the suspension or delay.
The Contractor shall maintain complete and accurate daily records of all costs due to delay, clearly distinguishing them from the costs of other portions of the Work, and shall submit a detailed written report of such costs to the Project Manager and the Inspector within twenty (20) calendar days of incurring the delay. Failure to comply shall result in waiver by the Contractor to any claims for additional payment and schedule change. In addition, the Contractor shall submit evidence of any cause of delay specified herein if it has not already done so.
As soon as practicable, following receipt of such report and evidence, if required, the Project Manager will determine the nature and extent of such costs and will, if the Project Manager finds that payment is due, issue a Change Order therefor, subject to the provisions in “Change Orders” of the General Requirements.
If the Project Manager determines that payment is not due, the Contractor will be so advised in writing.
Should the Contractor disagree with such finding, Contractor may submit a notice of protest to the Project Manager as provided in Claims and Protests. The Contractor shall provide the Project Manager with access to its daily cost records or certified copies thereof as requested. All such records shall be retained by the Contractor and open to inspection and audit by the City and the Project Manager. Except for the additional compensation provided hereinbefore, the Contractor shall have no claim for damage or compensation for any delay or hindrance whether or not contemplated by the Contract.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 33 of 45
00401 UNAVOIDABLE DELAY
Should the Contractor be obstructed or delayed in the completion of the Work from causes beyond its control and without its fault or negligence, and solely due to acts of God, acts of government in its sovereign capacity, riots, insurrections, wars, fires, floods, earthquakes, tidal waves, epidemics, quarantine restrictions, industry-wide strikes, freight embargoes, or unusually severe weather, it shall be entitled to a non-compensable extension of time.
The Contractor shall only be entitled to a non-compensable extension of time for Unavoidable delay in the Work which negatively impacts the critical path of the approved project schedule, and causes the Work of the project to extend beyond the approved Contract Completion date.
The Contractor shall be entitled to a non-compensable time extension only if it notifies the Project Manager and the Inspector immediately at the time the Contractor is prevented from proceeding with the Work and follows with written notification of the causes of the delay within five (5) calendar days from the beginning of any delay. Also, the Contractor shall notify the Project Manager and the Inspector immediately at the end of the delay and follow up with written notification of the cessation of delay within five (5) calendar days from the end of the delay.
Any claim for a time extension shall be made in writing within twenty (20) calendar days after the conclusion of the delay. The Project Manager and the Inspector shall ascertain the facts and the extent of the delay and extend the time for completing the Work if, in their judgement, the findings of fact justify such an extension. The Project Manager’s decision shall be final and conclusive, subject only to appeal as provided by Claims and Protests.
00402 ARCHAEOLOGICAL AND PALEONTOLOGICAL DISCOVERIES
If items of archaeological or paleontological interest are discovered, the Contractor shall immediately cease excavation in the area of discovery and shall not continue until ordered by the Project Manager. When resumed, excavation operations within the area of discovery shall be as directed by the Project Manager.
Such discoveries include antiquated dwelling sites, stone implements or other artifacts, animal bones, human bones, fossils and the like. The Contractor shall be entitled to an extension of tim e and compensation in accordance with the provision of Temporary Suspension of Work.
00403 COORDINATION WITH OTHER CONTRACTS
The City may allow other work at the site by the City’s own forc es, utility owners or other direct contracts.
If such other work to be performed was not noted in the Contract Documents, written notice thereof will be given to the Contractor prior to starting any such other work; and, if the Contractor believes that such performance will involve additional expense to the Contractor or requires additional time and the parties are unable to agree as the extent thereof, the Contractor may make a claim therefor as provided under Claims and Protests.
Paving of roadway areas shall be withheld until planned utility changes or installations have been made under City permits and until verifications of completion of all such changes or installations have been received by the Inspector. The Contractor is responsible for assuring that verifications are submitted by the utilities. Underground final inspection and acceptance of sewer and storm drain installations shall precede paving operations.
The Contractor shall afford each utility owner and other contractor who is a party to s uch a direct contract (or the City, if the City is performing the additional work with City employees) proper and safe access to the site and a reasonable opportunity for the introduction and storage of materials and equipment and the execution of such wor k, and shall properly connect and coordinate the Work with theirs. The Contractor shall do all cutting, fitting and patching of the Work that may be required to make its several parts come EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 34 of 45
together properly and integrate with such other work. The Contractor shall not endanger any work of others by cutting, excavating or otherwise altering their work and will only cut or alter their work with the written consent of the Project Manager and the others whose work will be affected. The duties and responsibilities of the Contractor under this Article are for the benefit of such utility owners and other contractors to the extent that there are comparable provisions for the benefit of the Contractor in said direct contracts between the City and such utility owners and other contractors.
If any part of the Contractor’s work depends upon proper execution or results of the work of any such other contractor or utility owner or the City, the Contractor shall inspect and promptly report to the Project Manager in writing any delays, defects or deficiencies in such work that renders it unavailable or unsuitable for such proper execution and results. The Contractor’s failure to do so will constitute an acceptance of the other Work as fit and proper for integration w ith the Contractor’s Work. The exception is latent defects in the other work.
00404 TERMINATION OF CONTRACT BY CITY (CONTRACTOR NOT AT FAULT)
The Contract may be terminated, in whole or in part, at any time, by the City, at its sole discretion, without cause and for the City’s convenience. Such termination will be accomplished by delivery of a written “Notice of Termination” to the Contractor, specifying the extent to which performance of the Work under the Contract or portion of the Contract shall be terminated and the date upon which such termination shall become effective.
After receipt of a Notice of Termination, except as otherwise directed by the City the Contrac tor shall:
1) Stop Work under the Contract on the date and to the extent specified in the Notice of Termination.
2) Notify the City in writing of all outstanding orders, Subcontracts and contracts entered into by Contractor for performance of the Work, including the (I) name and address of the vendor, supplier or Subcontractor; (ii) a copy of the complete contract, order or Subcontract; (iii) an accounting of the Work performed and compensation earned by the vendor, supplier or Subcontractor, and (iv) such other information as the City may request to assist it in determining whether to terminate or accept assignment of the order, Subcontract or contract.
3) Upon written notice by City, terminate all Subcontracts, orders and contracts, of any tier, related to the performance of the Work that the City determines shall be terminated and not assigned. Place no further orders or Subcontracts for Goods or services, except as may be necessary for completion of that portion of the Work that has not been assigned.
4) Place no further orders or Subcontracts for Goods or services, except as may be necessary for completion of that portion of the Work that has not been terminated.
5) Settle outstanding liabilities and Claims arising out of such termination of orders and Subcontracts, with the Acceptance of the City if required (which Acceptance shall be final for the purposes of this Article).
6) Assign to the City in the manner, at the times, and to the extent directed by the City all of the rights, titles, and interests of the Cont ractor under such orders, contracts and Subcontracts so terminated
7) Transfer title and deliver to the City in the manner, at the times and to the extent directed by it, the fabricated or unfabricated parts, Work in process, completed Work, supplies, and other Goods procured as a part of, or acquired in connection with the performance of the Work terminated; and completed or partially completed plans, drawings, information and City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 35 of 45
other items that would have been required (per the Specifications) to be furnished to the City if the Contract had been completed.
8) Use its best efforts to sell the property of the types referred to above in the manner, at the times, to the extent, and at the price(s) directed or authorized by the City, providing that the:
A) Contractor is not required to extend credit to any purchaser;
B) Contractor may acquire any such property under the prescribed conditions; and/or proceeds of any such transfer or disposition are applied or otherwise credited to reduce payments made by the City to the Contractor under the Contract.
9) Take any action that may be necessary, or that the City may direct, for the protection and preservation of the property related to the Contract that is in the possession of the Contractor and in which the City has or may acquire an interest.
10) Complete performance of that portion of the Work that has not been terminated by the Notice of Termination, as applicable and in accordance with the Contract.
After receipt of a Notice of Termination for the City's convenience, the Contractor shall submit its termination Claim to the City requesting paym ent of such sums as are permitted under the terms of this Article, in the form and with the certification(s) prescribed by the City for Claims and Protests. Such Claim shall be submitted promptly but in no event later than thirty (30) days from the effect ive date of termination, unless one or more extensions are granted in writing by the City upon written request by the Contractor during such six-month period or authorized extension thereof. However, the City may receive and act upon any termination Claim at any time after the thirty (30) days period or any extension thereof, if it determines that the facts justify such action. Upon failure of the Contractor to submit its termination Claim within the time specified, the City will determine the amount due the Contractor, if any, on the basis of information available, and will pay the Contractor the amount so determined. Such determination shall be final and binding and payment shall be in full settlement for the Work performed under the Contract.
Subject to the provisions of this Article, the Contractor and the City may agree upon the total or partial amount to be paid to the Contractor by reason of the total of or partial termination pursuant to this Article.
The agreed upon amount shall under no circumst ances include any sum for lost profits on the terminated portion of the Work or for consequential damages, of any kind. If agreement is reached, the Contract will be amended by Modification accordingly and the Contractor will be paid the agreed upon amount.
In the event of failure of the Contractor and the City to agree on the total amount to be paid the Contractor by reason of the termination of Work pursuant to this Article, the City will pay the Contractor the amounts determined by the City as follows, exclusive of any amounts agreed upon in accordance with the preceding Paragraph:
The Contractor’s actual cost for the Work properly performed by the Contractor as of the date of termination, including a 5% allowance for profit on such costs; plus, the reasonable cost of preserving and protecting property; plus, other reasonable costs incidental to the termination of the Work under the Contract, including expense incurred to determine the amounts due; provided however, that the maximum payable or paid for any portion of the completed Work shall not exceed the values listed in the corresponding bid item of Schedule of Values.
The total sum to be payable or paid to the Contractor, exclusive of the settlement amounts described in the Paragraph immediately above, shall not exceed the total Contract Price less the:
1) Payments made previously by the City for the Work; plus
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 36 of 45
2) A prorated portion of the total Contract Price for the terminated portion of the Work as determined by the Project Manager.
Except for normal spoilage and to the extent that the City will have otherwise expressly assumed the risk of loss, the fair value (as determined by the City) of property that is destroyed, lost, stolen, or damaged (so as to become undeliverable to the City or other buyer as described above) shall be excluded from the amounts paid to the Contractor.
In arriving at the amount due the Contractor under this Article, a deduction shall be made for the following:
1) Any claim that the City may have against the Contractor in connection with the Contract; and
2) The agreed upon price for and/or proceeds from the sale of goods or other items acquired or sold by the Contractor that have not been otherwise recovered by or credited to the City.
Under such terms and conditions as it may prescribe and at its sole discretion, the City may make partial payments against costs incurred by the Contractor in connection with terminated portion of the Contract whenever the City decides that the aggregate of such payments is within the amount to which the Contractor is entitled hereunder. If the total of such payments is in excess of the amount finally agreed upon or determined to be due under this Article, such excess shall be payable by the Contractor or to the City upon demand together with interest at a rate equal to that set forth in California Code of Civil Procedure, Section 685.010.
Under no circumstances shall the Contractor be entitled to anticipatory or unearned profits or consequential damages as a result of a termination of partial termination under this Article, or for any other termination by the City. The payment to the Contractor determined in accordance with this Article shall constitute the exclusive remedy of the Contractor for termination hereunder.
Anything contained in the Contract to the contrary notwithstanding, a termination under this Article shall not waive any right or claim to damages that the City may have; the City may pursue any clause of action that it may have by law or under the Contract; and shall not relieve Contractor of its warranty obligations with respect to any Work performed prior to such termination.
If the termination hereunder is only for a part of the Work, the Contract Price shall be reduced by the amount of the Contract Price applicable to the portion of the Work which is terminated, including overhead and profit, on the basis of one or more of the following:
1) Unit prices stated in the Contract or agreed upon by the City and the Contractor.
2) A lump sum determined by the Project Manager, based on the estimate costs including overhead and profit of the terminated portions of the Work.
00405 TERMINATION OF CONTRACT BY CITY (CONTRACTOR DEFAULT)
In the event of conduct by the Contractor which is determined by the Project Manager or the Inspector to constitute default, the City may either suspend the Work under the provisions of Temporary Suspension of Work of these General Conditions or, upon ten (10) calendar days' written notice to the Contractor, terminate the Contract as provided herein. Default by the Contrac tor shall occur whenever it shall declare bankruptcy; become insolvent or assign its assets for the benefit of its creditors; fail to provide materials, equipment, or workmanship meeting the requirements of the Specifications; disregard or violate provisions of the Contract Documents or the Project Manager’s or the Inspector’s instructions; fail to prosecute the Work according to the approved progress schedule; or fail to provide a qualified representative, competent workers or Subcontractors. Upon request , the City will provide the Contractor a meeting to contest the recommendation of the Project Manager or the Inspector as to default by the Contractor.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 37 of 45
In the event the Contract is terminated pursuant to this Article, the City may take possession of the Work and of all materials, tools, equipment, and property of the Contractor, which have been provided in connection with the Work, and may complete the Work by whatever method or means the City may select.
The unpaid balance of the Contract cost for compl eting the Contract Work shall be used to complete the Work in accordance with the Contract Documents. If cost of completing the Work exceeds the unpaid balance, the Contractor shall pay the excess amount to the City. If such cost is less than the unpaid balance, the Contractor shall not have claim to the difference except to such extent as may be necessary, in the opinion of the Project Manager, to reimburse the Contractor or the Contractor’s sureties for any unpaid expense properly incurred for materials, tools, equipment, property, and labor devoted to the prosecution of the Work, or which the City shall have received the benefit. In computing such expenses, as it relates to equipment and property, the salvage value at completion of Work shall be deducted from the salvage value at the time the Contract was terminated, and the difference shall be considered as an expense. If after termination for failure of the Contractor to fulfill contractual obligations (Contractor Default), it is determined by a Court of competent jurisdiction that the Contractor had not failed to fulfill contractual obligations, the termination shall be deemed to have been for the convenience of the City. In such an event, adjustment of the Contract Price shall be made as provided in Termination of Contract by City (Contractor Not at Fault)”.
00406 PARTIAL ACCEPTANCE
The City shall have the right to utilize or place into service any item of equipment or other usable portion of the Work prior to completion of the entire project. The Project Manager will notify the Contractor in writing identifying the specific portion or portions of the Work to be so utilized or otherwise placed into service.
Following inspection by the Inspector and c ompletion of an Inspection Correction List, a “Statement of Partial Completion” will be issued.
It shall be understood by the Contractor that until a “Statement of Partial Completion” is issued, all responsibility for care and maintenance of all items or portions of the Work to be placed in use shall be borne by the Contractor. Upon issuance of a “Statement of Partial Completion”, the City will accept responsibility for the protection and maintenance of all such items or portions of the Work described in the written notice, and it is further understood that the manufacturer's warranties of any affected equipment will commence not later than the date for commencement of the warranties indicated on the “Statement of Partial Completion”. However, the Contractor shall retain full responsibility for satisfactory operation of the total project and the Contractor’s guarantee period shall commence only after the final acceptance of the Contract by the City. Such guarantee of total systems operation shall include t hat portion or portions previously placed into Beneficial Use by the City.
The issuance of a “Statement of Partial Completion” for any part of the Work shall not relieve the Contractor of its obligation to promptly remedy any omissions and latent or unnot iced defects in the Work covered by the “Statement of Partial Completion”. The City shall have the right to restrict the Contractor’s use of the occupied portion of the Work but shall allow the Contractor reasonable access to complete or correct items required by the Contract Documents.
The City may, if the Work is progressing satisfactorily, release part of the retention on portions of the Work for which a “Statement of Partial Completion” has been issued, provided that the following conditions have been met:
1) Final Inspection corrections have been completed to the satisfaction of the Inspector on the portions of work to be utilized or placed into service;
2) The Contractor submits a written request to the Inspector for release of retention which includes a verifiable valuation of the identified portions of the Work covered by the “Statement of Partial Completion”;
3) Impacted Subcontractors, major suppliers and the Contractor’s Surety all agree in writing to release of retention;
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 38 of 45
4) There are no Stop Notices on file with the City against the Contractor involving any portion of the affected Work; and
5) Both the Project Manager and Inspector agree that a portion of the retention should be released for the affected Work.
00407 FINAL ACCEPTANCE
When all Work has been completed to the satisfaction of the Inspector, the Contractor shall notify the Project Manager, and re quest in writing a Final Inspection be performed by the Inspector. The Final Inspection conducted by the Inspector may include the Contractor and major Subcontractors’ representatives. A Final Inspection Correction List will be provided to the Contractor at the completion of the Final Inspection. All corrections noted on the Final Inspection Correction List shall be completed within thirty (30) days of issuance of the Final Inspection Correction List. All corrections shall be inspected and accepted by the Inspector until all Work is complete. Failure to complete all corrections within thirty (30) days of issuance of the Final Inspection Correction List shall result in the Final Inspection being performed again.
Upon completion of all physical corrections the Inspector shall initiate release of final payment and retention monies due the Contractor after subtracting any disputed monies (outstanding administrative corrections, such as wage violations, illegal substitutions, or liquidated damages).
Upon completion of all items of Work and administrative requirements of the Project, the City shall implement the joint recommendation of the Inspector and the Project Manager that the Contract be accepted. Said action by the City shall establish the following:
1) Start date of the Contractor’s material and workmanship Guaranty -Warranty for the total Project.
2) Start date of any equipment or material warranties which had not previously been started.
3) Date the City assumes responsibility for maintenance, security, and safety of the Project.
00408 LIQUIDATED DAMAGES
Time is of the essence in completing the Work required by the Contract. If the Contractor fails or refuses to complete the Work or any part thereof within the time fixed by the terms of the Contract, or any approved extension thereof, the actual damage to the City due to the delay will be difficult or impossible to determine.
In lieu thereof, the Contractor shall pay to the City, as fixed and agreed, liquidated damages for each calendar day of delay in completion, the sum or sums as set forth in the Contract Documents. The Contractor shall be liable for the amount thereof. The City reserves the right, however, to terminate the Contractor’s completing the Work, charging against the Contractor and its sureties any excess cost occasioned the City thereby, together with liquidated damages accruing until such time as the City may reasonably complete the Work.
Permitting the Contractor to cont inue and complete the Work, or any portion thereof, after the time fixed herein for completion, or after the expiration of any extensions of said time, shall in no way operate as a waiver on the part of the City of any of its rights under the Contract.
00409 COMPENSATION FOR DELAY, DISRUPTION, UNANTICIPATED OVERHEAD
This Article establishes the Contractor’s sole and exclusive rights to compensation for costs, expenses or damages, of any kind, arising from or relating to (i) delay, disruption, hindrance, interference, schedule compression, and the impact, ripple or cumulative effect thereof; or (ii) additional supervision, administration, excess, extended or extraordinary overhead, loss of productivity, or similar costs, expenses City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 39 of 45
or damages incurred as a result of or related to extras, changes, additions or deletions in the Work, errors, omissions, conflicts or ambiguities in the Contract Documents, suspensions of the Work, acts or omissions of City or its representatives, agents, contractors or consultants, Differing Site Conditions, or other unforeseen circumstances, of any kind.
Contractor shall not be entitled to, and hereby conclusively waives, any right to recovery of compensation, costs, expenses or damages for delays, disruptions, hindrances or interferences (including without limitation interruption of schedules, extended, excess or extraordinary field and indirect overhead costs, loss of productivity and the impact, ripple or cumulative effect on other Work) that are the result of Unavoidable Delays or which are caused by the acts or omissions of Contractor or of its Subcontractors, of any tier.
Contractor’s rights to recovery of compensation, costs, expenses an d damages for delay, disruption, hindrance and interference (including without limitation interruption of schedules, extended, excess and extraordinary field and indirect overhead costs, loss of productivity and the impact, ripple or cumulative effect on other Work) that are the result of extras, changes, additions or deletions in the Work for which Contractor is entitled to an adjustment of the Contract Price as set forth in Changes and Extra Work shall be limited to the additional compensation set forth in “Change Orders” of the General Requirements, which shall constitute the sole, exclusive and complete compensation that the City is obligated to pay Contractor for all such costs, expenses and damages incurred by Contractor and its Subcontractors, of every tier.
If Contractor is entitled to an extension of time under the terms of the Contract Documents solely as a result of any cause other than Unavoidable Delay or extras, changes, additions or deletions in the Work for which Contractor is entitled to an adjustment of the Contract Price pursuant to Changes and Extra Work, then the Contract Price shall be increased by the sum of $ 500 per day for each day of such time extension; provided however, that such compensation shall be only be payable by City if and to the extent that (i) the Contractor is entitled to an extension of time under the Contract Documents on account of such delay, including without limitation that Contractor has strictly complied with all requirements regarding the timeliness and content of written notices and requests for extension of time; and (iii) the delay is not, in whole or in part, concurrent with an Unavoidable Delay, a delay due to extra work, changes, additions or deletions in the Work as set forth in “Changes and Extra Work”, or any other delay for which Contractor is not entitled to an extensions of time under the terms of the Contract Documents; and (iv) an adjustment to the Contract Price for the costs, expenses and damages incurred in connection with such extension of time is not provided for or excluded under any other provision of the Contract Documents. The daily rate of compensation provided for herein shall not be subject to further markups or additions for profit, overhead (direct or indirect), or impact and shall constitute the sole, exclusive and complete compensation that the City is obligated to pay for any costs, expenses and damages incurred by Contractor and its Subcontractors, of every tier, in connection with any delay, disruption, hindrance and interference (including without limitation interruption of schedules, extended, excess or extraordinary field and indirect overhead costs, loss of productivity and the impact, ripple or cumulative effect on other Work) related to such extension of time.
Notwithstanding the foregoing or any other provision of the Contract Documents to the contrary, Contractor shall in no event be entitled to receive the compensation set forth in this Article for the period of any delay or disruption that is concurrent wit h a delay or disruption that is caused by the acts or omissions of Contractor or its Subcontractors, of any tier, or that is the result of any breach by Contractor of any provision of the Contract Documents.
00410 THRU 00499 NOT USED
00500 CHANGES AND EXTRA WORK
The Project Manager may, at any time, without notice to the Sureties, by written order designated or indicated to be a Change Order, order performance of extra work or make any change, addition or deletion in the Work, including but not limited to changes in the Specifications including Plans and designs; in the time, method or manner of performance of the Work; in the City furnished facilities, equipmen t, materials, services, or site; or directing acceleration in the performance of the Work.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 40 of 45
Upon receipt of such Change Order, the Contractor shall promptly proceed with the Work covered thereby, which shall be performed in accordance with the provisions of the Contract Documents except as otherwise specifically provided.
In the event that Contractor receives any written order or direction by the Project Manager that is not so designated or indicated to be a Change Order, but which Contractor believes to constitute an extra, change, addition or deletion in the Work, then Contractor shall, prior to performance of any Work related thereto, give written notice to the Project Manager and Inspector confirming Contractor’s belief that such order or direction is believed to be a Change Order within one (1) working day of Contractor’s receipt of such order or direction.
Contractor conclusively waives any right to additional compensation, costs, expenses, damages or extension of time associated with an extra, change, addition or deletion to the Work that is performed by Contractor without either (i) a written order signed by the Project Manager designated or indicated to be a Change Order and any change, addition or deletion, or (ii) a written notice issued by Contractor in accordance with the provisions of this Article.
During the progress of the Work, it may be necessary for the Project Manager to issue written field orders in the form of an Emergency Change Authorization. Upon receipt, The Contractor shall immediately proceed with the Project Manager’s written directive to the limits described in Authority of the City Project Manager and Inspector.
Except as provided in this Article, no other order, statement, or conduct of the Project Manager shall be treated as a change under this Article or shall entitle the Contractor to an adjustment in the Contract Price or Contract Completion Date.
Except for claims based on defective Specifications, no Claim for any change under this Article shall be allowed for any costs incurred more than twenty (20) calendar days before the Contractor gives written notice as required. Except as otherwise provided in the Contract Documents, in the case of defective specifications for which the Project Manager is responsible, the adjustment shall include any increased cost the Contractor reasonably incurred in attempting to comply with those defective specifications.
If the Contractor intends to assert a Claim for an adjustment in the Contract Price under this Article, it must, within twe nty (20) calendar days after receipt of a written Change Order or the furnishing of a written confirmation notice as hereinbefore specified, submit a written statement to the Project Manager setting forth the general nature and monetary extent of such claim and all factual grounds therefor. The Contractor may include the statement of claim in the written notice as hereinbefore specified. Failure to comply with the twenty (20) calendar day notice requirement shall be deemed a waiver of Claims by the Contrac tor.
No adjustment shall be made under this Article for any suspension, delay, interruption, change or any other cause, to the extent that an adjustment is provided for or excluded under any other provision of the Contract.
Recovery of compensation, costs, expenses or damages resulting from delay, disruption, hindrance, or interference in the performance of the Work (including without limitation interruption of schedules, extended, excess or extraordinary field overhead and indirect overhead costs, loss of productivity and the impact, ripple or cumulative effect on other Work), shall not be permitted, and all rights thereto are conclusively waived by Contractor, except to the extent allowed by Compensation for Delay, Disruption and Unanticipated Overhead.
No Claim by the Contractor shall be allowed if the Claim is made after final payment under this Contract.
00501 DIFFERING SITE CONDITIONS
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 41 of 45
Upon discovery and before further disturbance of any differing site conditions, the Contractor shall immediately notify the Inspector and the Project Manager, followed by a written notice to the Project Manager within twenty -four (24) hours of subsurface or latent physical conditions at the site differing materially from those indicated in the Contract Documents; or unknown physical conditions at the site, of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in the Work of the character provided for in this Contract; or materially diff ering from that represented in the Contract Documents which the Contractor believes may be hazardous waste (as defined in the California Health and Safety Code and is required to be removed to a Class I, Class II or Class III disposal site in accordance with provisions of existing law).
The Project Manager will promptly investigate the conditions. If the Project Manager finds that conditions materially differ and will cause an increase or decrease in the Contractor’s cost or the time required to perform any part of the Work, the Project Manager will adjust the Contract by Change Order.
If the Contractor disagrees with the Project Manager’s determination the Contractor may request an adjustment to the Contract Price or Contract Completion Date. Within twenty (20) calendar days after it first discovered, or should have discovered in the exercise of diligence and extreme care, the existence of such Differing Site Condition, submit a written statement setting forth a detailed cost breakdown described in “Change Orders” of the General Requirements. The statement must include the Contractor’s basis and calculation of the costs saved or incurred, detailed information demonstrating the effect on the Contractor’s schedule of performance (in the same manner as requi red by the Contract Documents for requesting an extension of time), identification of the Bid Documents that formed the basis of the Contractor’s Bid to perform the Work affected by such conditions, and a complete and detailed explanation of the factual basis for the request.
Failure by Contractor to strictly comply with the requirements of this Article concerning the timing and content of any notice of Differing Site Conditions or of any request for adjustment in Contract Price or Contract Completion Date based on Differing Site Conditions shall be deemed waiver of any Claim by the Contractor for increase in the Contract Price or extension of the Contract Completion Date by reason of such conditions.
Contractor’s right to compensation for (I) delay, disruption, hindrance, interference, schedule compression, and the impact, ripple or cumulative effect thereof; or (ii) additional supervision, administration, excess, extended or extraordinary overhead, loss of productivity, or similar costs, expenses or damages incurred as a result of or related to any Claim based on Differing Site Conditions shall be limited to such sums as are allowable under Compensation for Delay, Disruption, Unanticipated Overhead.
No Claim by the Contractor for an adjustment hereunder s hall be allowed if asserted after final payment under this Contract.
00502 THRU 00599 NOT USED
00600 CLAIMS AND PROTESTS
A Claim that involves an extra, change, addition or deletion to the Work as set forth in Changes and Extra Work shall arise upon issuance of a final decision of the Project Manager denying, in whole or in part, a request for adjustment in the Contract Price or Contract Completion Date; provided however, that failure to comply with the requirements of the articles for Changes and Extra Work or Differing Site Conditions shall be conclusively deemed to constitute grounds to deny such Claim.
A Claim that does not involve an extra, change, addition or deletion to the Work may be asserted only if the Contractor shall immediately and prior to performing the Work affected thereby give written notice to the Project Manager and the Inspector of such circumstances and of Contractor’s intention to file a Claim based thereon. Unless otherwise directed by the Project Manager, the Contractor shall proceed without delay to perform the Work and to conform to any order, instruction, or decision of the Project Manager with respect thereto.
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 42 of 45
The Contractor shall, within twenty (20) calendar days after it first knew, or in the exercise of diligence and extreme care should have known, of the circumstances giving rise to the Claim, file a written Claim with the Project Manager, stating in detail all objections, grounds and reasons therefor. The Contractor shall, upon instruction by the Project Manager or the Inspector, provide, within ten (10) days or such other time as agreed to between the Project Manager, and the Contractor, any and all documents, records or other materials identified by the Project Manager or the Inspector as necessary for the resolution of the Contractor’s Claim.
Claims seeking time extensions shall be accompanied by such documentation as i s required by “Contractor’s Construction Schedule and Reports” of the General Requirements. Claims seeking recovery of compensation or adjustments to the Contract Price, whether based on extras, changes, additions or deletions to the Work, shall be in the form of Proposed Change Order prepared in accordance with and subject to all of the requirements of “Change Orders” of the General Requirements, including without limitation the prohibition on use of “total cost” and “modified total cost” methodologies.
Contractor waives all rights to assert any claims or seek any relief in the form of extensions of time or recovery of additional compensation, costs, expenses, damages from the City that are not presented as a Claim in the manner specified and within the t ime stated herein. Contractor further hereby agrees that in the interest of avoiding the additional expense and potential inequity of piecemeal resolution of Claims, all decisions by Project Manager shall be final and binding not only as to all matters asserted in the Claim, but also as to all matters (including without limitation all rights to extensions of time and recovery of extra compensation, costs, expenses and damages) not asserted in the Claim that were known to Contractor, or that could have been reasonably discovered by Contractor in the exercise of diligence and extreme care, at the time of submission of the Claim and that are in any way related to the subject matter of the Claim.
All orders, instructions and decisions of the Project Manager or the Inspector will be limited to matters properly falling within their respective authority as specified in Authority of the City Project Manager and Inspector.
The Contractor will be informed of the Project Manager’s or the Inspector’s decision within t hirty (30) days after the Contractor last submits data pertinent to the Claim previously mentioned. In the case of a Claim that involves an extra, change, addition or deletion to the Work as set forth in Changes and Extra Work, if the Contractor accepts the decision of the Engineer or Inspector, then the Contractor and City shall enter into a Change Order adjusting the Contract Price and Contract Completion Date in accordance with such decision. In case a Claim does not involve an extra, change, addition or deletion to the Work as set forth in Changes and Extra Work and the Contractor accepts the decision of the Project Manager or Inspector, then the Contractor and City shall enter into a Change Order setting forth the terms of the decision and, if appropriate, its effect on the Contract Price or Contract Completion Date. If the Contractor does not accept the decision of the Project Manager or Inspector, then further appeal may be made to the City Attorney’s Office (if provided for under the terms of the General Requirements). All determinations of the City Attorney with respect to Claims shall be final and binding.
In all matters concerning the validity, interpretation, performance, effect or otherwise of the Contract, the Federal regulations (if and to the extent expressly incorporated by reference in the Contract Documents), the laws of the State of California, and the Charter of the City of Sacramento shall govern and be applicable.
Pending final disposition of a Claim, the Contractor shall proceed diligently with the performance of the Contract and in accordance with the previously mentioned decision.
Any Claim, including without limitation any Claim filed on behalf of or having its source in a claim by Subcontractor, Sub-Subcontractor, or Supplier, at any tier, which the Contractor chooses to make to the City, shall be accompanied by the certification language set forth below signed by a responsible managing officer of the Contractor’s organization, who has the authority to sign Subcontracts or Purchase Orders on behalf of the Contractor, and who has personally investigated and confirmed the truth and accuracy of the matters set forth in such certification. Submission of certification in accordance herewith is a condition precedent to the City’s consideration of or decision on the Claim and to the filing and maintenance of any City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 43 of 45
legal action or proceeding to enforce or recover monies under such Claim. Failure to submit such a certification along with the Claim shall result in the Claim being returned to the Contractor without any decision, and shall waive the Contractor’s right to pursue the Claim either on its own behalf or on behalf of such Subcontractor or Supplier.
I hereby certify under penalty of perjury that I am a managing officer of (Contractor’s name) and that I have reviewed the Claim presented herewith on Contractor’s behalf and/or on behalf of (Subcontractor’s/Supplier's name(s)) and that the following statements are true and correct:
1) The facts alleged in or that form the basis for the Claim are true and accurate; and,
2) Contractor does not know of any facts or circumstances, not alleged in the Claim, that by reason of their not being alleged render any fact or statement alleged in the Claim materially misleading; and,
3) Contractor has, with respect to any request for money or damages alleged in or that forms the basis for the Claim, reviewed the job cost records (including those maintained by Contractor and by any Subcontractor or Supplier, of any tier, that is asserting all or any portion of the Claim) and confirmed with mathematical certainty that the losses or damages suffered by Contractor and /or such Subcontractor or Supplier were in fact suffered in the amounts and for the reasons alleged in the Claim; and,
4) Contractor has, with respect to any request for extension of time or claim of delay, disruption, hindrance or interference alleged in or that forms the basis for the Claim, reviewed the job schedules (including those maintained by Contractor and by any Subcontractor or Supplier, of any tier, that is asserting all or any portion of the Claim) and confirmed on an event-by-event basis that the delays or disruption suffered by Contractor and /or such Subcontractor or Supplier were in fact experienced for the durations, in the manner, and with the consequent effects on the time and/or sequence of performance of the Work, as alleged in the Claim; and,
5) Contractor has not received payment from City for, nor has Contractor previously released City from, any portion of the Claim.
Signature: ________________________________________
Name: ________________________________________
Title: ________________________________________
Company: ________________________________________
Date: ________________________________________
No Claim by the Contractor shall be allowed if made after final payment under this Contract.
00601 COMMENCEMENT OF STATUTE OF LIMITATIONS
Any applicable statute of limitations shall commence to run and any alleged cause of action by the Contractor against the City arising out of or related to the Project shall be deemed to have accrued in any and all events no later than 30 days after Contractor’s submittal of its last application for progress payment of Contract or Change Order Work satisfactorily performed.
00602 GOVERNING LAW
EV BLUEPRINT City of Sacramento
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 44 of 45
The terms and conditions of this Contract shall be construed and interpreted under, and all respective rights and duties shall be governed by, the laws of the State of California. Wherever applicable each provision of these Contract Documents shall be interpreted in such a manner as to be effective and valid under applicable law, but if any provision of these Contract Documents shall be prohibited by or invalid under applicable law, such provision shall be ineffective to the extent of such prohibition or invalidity, without invalidating the remainder of such provision or the remaining provisions of these Contract Documents.
Unless otherwise provided in this Contract, all claims, counterclaims, disputes and other matters in question between the City and the Contractor arising out of or relating to this Contract or the breach of it will be decided by a Court of competent jurisdiction. It is understood that this Contract is executed and to be performed within the City and County of Sacramento.
00603 VENUE
This Contract will be executed and performed within the City and County of Sacramento, California.
00604 NO WAIVER OF RIGHTS
Neither the inspection by the City, nor any order by the City for payment of money, nor any payment for or acceptance of the whole or any part of the Work by the City, nor any extension of time, nor any possession taken by the City, shall operate as a waiver of any provision of this Contract, or any power herein reserved to the City, or any right to damages herein provided, nor shall any waiver of any breach in this Contract be held to be a waiver of any other or subsequent breach.
00605 ACCEPTANCE OF FINAL PAYMENT CONSTITUTES RELEASE
The acceptance by the Contractor of final payment shall release the City, the Project Manager, the Inspector, their officers, agents, representatives, or employees, as representatives of the City, from all claims and all liability to the Contractor for all things done or furnished in connection with the Work and every act of the City relating to or arising out of the Work.
00606 PATENTS AND COPYRIGHTS
The Contractor shall include in its Bid the patent fees or royalties on any patented article or process which may be furnished or used in the Work. The Contractor shall indemnify and hold the City harmless from any legal action that may be brought for infringement of patents. The Contractor’s attention is directed to "Notice of Patents, Data, and Copyright Regulations" of the Federal Labor Standards.
The Contractor shall bear all costs arising from the use of patented goods and /or processes used on and/or incorporated into the Work. When use of these goods and/or processes are judged to be an infringement and their use is banned, the Contractor, at its own expense, shall, with concurrence of the Project Manager, do one of the following:
1) Secure for the City the right to continue using goods and/or processes by suspension of the injunction or by procuring a license(s);
2) Replace said goods and/or processes with non-infringing goods and /or processes;
3) Modify said goods and/or processes so that they become non-infringing; or
4) Remove said goods and/or processes and refund the sum paid therefor without prejudice to any other rights of the City.
The preceding shall not apply to any goods manufactured to the detailed design of the City contained in the Contract Documents.
City of Sacramento EV BLUEPRINT
MULTIPLE PROJECT SITES
GENERAL CONDITIONS - Page 45 of 45
00607 PUBLIC RECORDS ACT
All records, documents, Plans, specifications and all other information relating to the conduct of the City’s business, including information submitted by the Contractor, shall become the exclusive property of the City and except as provided by law shall be deemed public records. Said information shall be subject to the provisions of the California Public Records Act (Government Code Sections 6250 et seq.).
Under no circumstances will the City be responsible or liable to the Contractor, submitter or any other party for the disclosure of any records or information submitted to the City, regardless of whether such records or information are labeled "Trade Secret", "Confidential", or "Proprietary" (or words to similar effect) and regardless of whether the disclosure is required by law or a court order or occurs through inadvertence, mistake, or negligence on the part of the City or its officers, employees, and/or contractors.
The City will not advise as to the nature or content of documents entitled to protection from disclosure under the California Public Records Act", including interpretations of the Act or the definition of "Trade Secret".
The submitting party shall be solely responsible for all determinations made under the Act, and where appropriate for clearly and prominently mark ing each and every page or sheet of information with "Trade Secret", "Confidential", or "Proprietary". Each submitting party is advised to contact its own legal counsel concerning the California Public Records Act and its applicability to the submitting party's own circumstances.
In the event of litigation concerning the disclosure of any information submitted by the submitting party, the City’s sole involvement will be as a stakeholder, retaining the information until otherwise ordered by a court.
The submitting party, at its sole expense and risk, shall be responsible for any and all fees and costs for prosecuting or defending any action concerning the information, and shall indemnify and hold the City harmless from all costs and expenses including attorneys' fees, in connection with such action.
END OF SECTION