File ID: 2024-00389 2/13/2024 Consent Item 6.
Contract Award: Pavement Data Collection and Analysis (R15200800) File ID: 2024-00389
Location: Citywide
Recommendation: Pass a Motion: 1) authorizing the City Manager or City Manager’s designee to execute a two-year Professional Services Agreement for an amount not to exceed $432,400 with Nichols Consulting Engineers (NCE) to perform Pavement Data Collection and Analysis, for the City’s Pavement Analysis Program.
Contact: Josh Werner, Assistant Engineer, (916) 808-8158, [email protected]; Greg Smith, Senior Engineer, (916) 808-8364, [email protected]; Jose Sanchez, Streets Manager, (916) 808-2254, [email protected], Department of Public Works Presenter: None.
Attachments:
1-Description/Analysis
2-Professional Services Agreement - Nichols Consulting Engineers Description/Analysis
Issue Detail: The Department of Public Works’ Maintenance Services Division has an ongoing need to regularly update data regarding pavement conditions to accurately determine the schedule for resurfacing projects, pavement maintenance and upkeep of the City’s roadways, and to develop a budget for such activities. Staff recommends a professional services agreement be executed with Nichols Consulting Engineers (NCE) to collect and update this data.
Policy Considerations: The recommendations in this report are in accordance with the provisions of City Code Chapter 3.64 and Administrative Policy 4102, Professional Services, that require City Council approval of actions of $250,000 or more.
Economic Impacts: None.
Environmental Considerations:
File ID: 2024-00389 2/13/2024 Consent Item 6.
California Environmental Quality Act (CEQA): The subject of this report does not involve a project which may cause a direct or indirect change in the environment and is, therefore, exempt from CEQA, (Public Resources Code Section 21065).
Sustainability: Not applicable.
Commission/Committee Action: None.
Rationale for Recommendation: On August 23, 2023, Request for Proposals P24151621005 was issued for Pavement Condition Data Collection and Analysis. On September 27, 2023, the City received proposals from three consultants - Applied Research Associates, Inc. (ARA); HERE North America, LLC; and Nichols Consulting Engineers (NCE). The proposals were reviewed and evaluated by staff from the Department of Public Works. The reviewing panel determined that NCE had submitted the most responsive proposal and was most qualified to complete the scope of work required by this project. City Council approval is needed for the award of the consultant contract to proceed with the project.
Financial Considerations: The estimated total cost to complete the Pavement Data Collection and Analysis is approximately $432,400. The Pavement Management Application (R15200800) has a sufficient unobligated balance of New Measure A Maintenance funding (Fund 2026) to award the professional services agreement to Nichols Consulting Engineers for an amount not to exceed $432,400.
Local Business Enterprise (LBE): Nichols Consulting Engineers is an LBE.
Background: A Pavement Management System (PMS) is a planning tool to track the past, present and future pavement condition and street maintenance and rehabilitation projects in a central database, utilizing engineering software to forecast pavement maintenance needs and assist in budgeting for street maintenance. The PMS is used to ensure that the City is prioritizing roadway repairs to best serve the community in a cost-effective manner.
The City owns and maintains approximately 3,154 lane miles of streets. The Maintenance Services Division uses the PMS to plan future street resurfacing projects and determine the City’s annual Capital Improvement Project and Maintenance Budget, making the PMS very important to keep updated. For the system to remain a reliable planning tool and to determine the current and future condition of its pavement, every street must be inspected on a regular basis for its roughness and the severity of its pavement distress. The resulting data is then entered into the PMS, which uses a mathematical model to assign a Pavement Condition Index (PCI) number to each segment of every street. The PCI ranges from 0 to 100, with 100 indicating the highest quality.
File ID: 2024-00389 2/13/2024 Consent Item 6.
For the PMS to remain a reliable planning tool and reflect the latest street conditions, the PCI must be updated on a regular basis. Efficient pavement management is a matter of balancing expenditures between reconstructing severely deteriorated streets and assuring that other streets are maintained to the City standard, preventing further deferred maintenance.
Staff recommends the inspection of the City’s pavement in order to update the Pavement Condition Index measurements (roughness and severity of pavement distress). Updating this data will validate the system’s accuracy and allow continued use of this valuable planning tool.
Form Approved by City Attorney 9-1-2020 Page 1
CONTRACT #: PRC002668
CONTRACT NAME: Pavement Condition Data Collection and Analysis CONTRACT PROJECT #:
DEPARTMENT: Public Works
DIVISION: Maintenance Services
CITY OF SACRAMENTO
PROFESSIONAL SERVICES AGREEMENT
FOR ARCHITECTS, LANDSCAPE ARCHITECTS,
ENGINEERS, AND LAND SURVEYORS
THIS CONTRACT is made at Sacramento, California, by and between the CITY OF SACRAMENTO, a charter city and municipal corporation (“CITY”), and
Nichols Consulting Engineers (NCE)
1885 S. Arlington Ave. Suite 111
Reno, NV 89509
775-329-4955
(“CONTRACTOR”), as of the Effective Date, as defined below.
The City and Contractor agree as follows:
1. Effective Date. This Contract shall be effective beginning the date it is fully executed by the duly authorized parties.
2. Contract Documents. All exhibits and documents attached or referred to in this Contract are incorporated as if set forth herein, Including Exhibit A (titled “ Scope of Services”) and Exhibit B (titled “Payment”).
If there is a conflict between the terms and conditions of any document prepared or provided by the Contractor and made a part of this Contract and the other terms or conditions of the Contract, the other terms and conditions of the Contract control.
3. Services. Subject to the terms and conditions set forth in this Contract , CONTRACTOR shall provide to CITY the services described in Exhibit A (“Services”).
CONTRACTOR will not be compensated for services outside the scope of Exhibit A (“Additional Services”) unless, before providing Additional Services : (a) CONTRACTOR notifies CITY and CITY agrees that the Additional Services are outside the scope of Exhibit A; (b) CONTRACTOR estimates the additional compensation required for these A dditional Services; and (c) CITY, after notice, approves in writing a Supplemental Contract specifying the Additional Services and the amount of additional compensation to be paid Contractor.
CITY will have no obligations whatsoever under this Contract or any Supplemental Contract , unless and until this Contract or any Supplemental Contract is approved by the City as required Form Approved by City Attorney 9-1-2020 Page 2
by the Sacramento City Code. As used in this Contract, the term “Services” includes both Services and Additional Services as applicable.
4. Payment. CITY shall pay CONTRACTOR at the times and in the manner set forth in Exhibit B.
CONTRACTOR shall submit all invoices to CITY in the manner specified in Exhibit B.
5. Facilities and Equipment. Except as set forth below, CONTRACTOR shall, at its sole cost and expense, furnish all facilities and equipment required for CONTRACTOR to perform this Contract.
CITY shall furnish to CONTRACTOR only the facilities and equipment listed below, if any.
6. Insurance. Contractor shall, at its sole cost and expense, maintain the insurance coverage described in the attached Exhibit C.
7. General Conditions. Contractor shall comply with the terms and conditions set forth in the attached Exhibit D.
8. Additional Requirements for Surveying, Material Testing, and Inspection Services. If this Contract includes any land surveying, material testing, or inspection services provided for a City construction project, during the design, pre-construction, construction, or post- construction phases of the project, the Contractor and any subcontractor or subconsultant performing any such services shall comply with the provisions specified in Exhibit E.
9. Non-Discrimination in Employee Benefits. This Contract may be subject to Sacramento City Code chapter 3.54, Non- Discrimination in Employee Benefits by City Contractors. A summary of the requirements, entitled "Requirements of the Non-Discrimination in Employee Benefits Code (Equal Benefits Ordinance),” can be viewed at:
https://www.cityofsacramento.org/Finance/Procurement/Contract-Ordinances.
Contractor acknowledges and represents that Contractor has read and understands the requirements and shall fully comply with all applicable requirements of Sacramento City Code chapter 3.54. If requested by City, Contractor shall promptly provide any documents and information required by City to verify Contractor's compliance.
Contractor's violation of Sacramento City Code chapter 3.54 constitutes a material breach of this Contract, for which the City may terminate the Contract and pursue all available legal and equitable remedies.
10. Considering Criminal Conviction Information in the Employment Application Process. This Contract may be subject to the requirements of Sacramento City Code chapter 3.62, Procedures for Considering Criminal Conviction Information in the Employment Application Process . A summary of the requirements, entitled “Ban-The-Box Requirements,” can be viewed at:
https://www.cityofsacramento.org/Finance/Procurement/Contract-Ordinances.
Form Approved by City Attorney 9-1-2020 Page 3
The Ban-The-Box Requirements are applicable to certain contracts with the City in an amount of $250,000 or more (either initial value or total value after amendment) or if the total value of all Contractor's contracts with the City is $250,000 or more over a 12-month period.
Contractor acknowledges and represents that Contractor has read and understands these requirements and shall fully comply with all applicable requirements of Sacramento City Code chapter 3.62. If requested by City, Contractor shall promptly provide any documents and information required by City to verify Contractor's compliance. Contractor shall require applicable subcontractors to fully comply with all applicable requirements of Sacramento City Code chapter 3.62 and include these requirements in all subcontracts covered by Sacramento City Code chapter 3.62.
Contractor's violation of Sacramento City Code chapter 3.62 constitutes a material breach of this Contract, for which the City may terminate the Contract and pursue all available legal and equitable remedies.
11. Local Business Enterprise Program . The Local Business Enterprise Program Participation Requirements ("LBE Participation Requirements") may be applicable to this Contract. A summary of the requirements, entitled "LBE Participation Requirements," can be viewed at:
https://www.cityofsacramento.org/Finance/Procurement/Contract-Ordinances.
Contractor acknowledges and represents that Contractor has read and understands these requirements and shall fully comply with all applicable requirements of Sacramento City Code chapter 3.60. If requested by City, Contractor shall promptly provide any documents and information required by City to verify Contractor's compliance. Contractor shall require applicable subcontractors to fully comply with all applicable requirements of Sacramento City Code chapter 3.60 and include these requirements in all subcontracts covered by Sacramento City Code chapter 3.60.
Contractor's violation of Sacramento City Code chapter 3.60 constitutes a material breach of this Contract, for which the City may terminate the Contract and pursue all available legal and equitable remedies.
12. Authority. The person signing this Contract for CONTRACTOR represents and warrants that he or she has read, understands, and agrees to all the Contract terms and is fully authorized to sign this Contract on behalf of the CONTRACTOR and to bind the CONTRACTOR to the performance of the Contract’s obligations.
[Signature Pages Follow Exhibits]
Form Approved by City Attorney 9-1-2020 Exhibit A - Page 1
EXHIBIT A
SCOPE OF SERVICES
1. Representatives.
The CITY Representative for this Agreement is:
Josh Werner, Assistant Civil Engineer
918 Del Paso Road, Building 1
Sacramento, CA 95834
916-808-8158 / [email protected]
The CONTRACTOR Representative for this Agreement is:
Margot Yapp, Principal/Vice President
1885 S. Arlington Ave. Suite 111
Reno, NV 89509
775-329-4955 / [email protected]
Unless otherwise provided in this Contract, a ll Contractor questions and correspondence pertaining to this Contract must be addressed to the City Representative. All City questions and correspondence must be addressed to the Contractor Representative.
2. Scope of Services. Contractor shall provide Services to City as set forth in Attachment 1 to this Exhibit A.
3. Time of Performance. The Services described in this Contract shall be provided for a two year period, beginning on the date the contract is fully executed by the duly authorized parties , through June 30, 2026. Contractor shall provide the Services in accordance with any schedule in Attachment 1 to this Exhibit A. Contractor shall immediately notify the City if Contractor is unable to make delivery of Goods or perform Services in compliance with this Contract.
4. Conflict of Interest Requirements. The individual(s) who will provide Services pursuant to this Contract are “Consultants” within the meaning of the Political Reform Act and the City’s Conflict of Interest Code: ____ yes __X__ no [check one]
Contractor shall cause the following to occur within 30 days after execution of this Contract:
(A) Identify the individuals who will provide Services or perform Work under this Contract as "Consultants"; and
(B) Cause these individuals to file with the City Representative the "assuming office" statements of economic interests required by the City's Conflict of Interest Code.
Thereafter, throughout the term of the Contract, Contractor shall cause these individuals to file with the City Representative annual statements of economic interests and "leaving office" statements of economic interests, as required by the City's Conflict of Interest Code. The City
Form Approved by City Attorney 9-1-2020 Exhibit A - Page 2 may withhold all or a portion of any payment due under this Contract or impose fines on the individuals until all required statements are filed.
Form Approved by City Attorney 9-1-2020 Exhibit B - Page 1
EXHIBIT B
PAYMENT
1. CONTRACTOR’s Compensation. The total of all fees paid to the CONTRACTOR for the provision of Services as set forth in Exhibit A, including any authorized reimbursable expenses, shall not exceed the total sum of $ 432,400. The payments specified in this Exhibit B shall be the only payments made to Contractor unless the City approves a Supplemental Contract.
2. Billable Rates. Contractor shall be paid for the performance of Services on an hourly rate, daily rate, flat fee, lump sum, or other basis, as set forth in Exhibit A or Attachment 1 to this Exhibit B and any applicable special provisions included in the request for bids or proposals. If there is a conflict between Exhibit A or Exhibit B and the Special Provisions, Exhibit A or Exhibit B controls.
3. CONTRACTOR’s Reimbursable Expenses. “ Reimbursable Expenses ” are limited to actual expenditures of CONTRACTOR for expenses that are necessary for the proper satisfaction of the Contract and are only payable if specifically authorized in advance in writing by the City. No charges or markup will be allowed unless specified in the Contract, including charges for travel and transportation.
4. Payments to CONTRACTOR. Contractor is responsible for supplying all documentation necessary to verify invoices to the City’s satisfaction.
A. Payments to CONTRACTOR shall be made within a reasonable time after receipt of CONTRACTOR’s invoice, in proportion to services performed or as otherwise specified in Attachment 1 to Exhibit B. CONTRACTOR may request payment on a monthly basis.
CONTRACTOR shall be responsible for the cost of supplying all documentation necessary to verify the monthly billings to the satisfaction of CITY.
B. Invoices must be submitted to either of the addresses specified below. (1) Email. Submit email invoices and any attachments to:
[email protected]
(2) Postal Mail. If emailing is not an option, mail to:
A/P Processing Center
City of Sacramento
915 I Street, Floor 4
Sacramento, CA 95814-2608
C. All invoices submitted by CONTRACTOR must contain the following information:
(1) Job/Project Name
(2) CITY’s current Purchase Order Number
(3) CONTRACTOR’s Invoice Number
(4) Date of Invoice Issuance
(5) Work Order Number (if applicable)
(6) CITY representative identified on the Purchase Order
Form Approved by City Attorney 9-1-2020 Exhibit B - Page 2 (7) CONTRACTOR’s remit address
(8) Description of services billed under Invoice
(9) Amount of Invoice (itemize all authorized Reimbursable Expenses) (10) Total Billed to Date under Contract (if applicable)
D. Items must be separated into Services and Reimbursable Expenses. Invoices that do not conform to the format outlined above will be returned to CONTRACTOR for correction.
CITY is not responsible for delays in payment to CONTRACTOR resulting from CONTRACTOR’s failure to comply with the invoice format described above.
5. Additional Services. Additional Services shall be provided only when a Supplemental Contract authorizing the Additional Services is approved in writing by the City in accordance with the City’s contract amendment procedures. The City reserves the right to perform any Additional Services with its own staff or to retain other contractors to perform the Additional Services.
6. Accounting Records of CONTRACTOR. During performance of this Contract and for a period of three years after completion of performance, CONTRACTOR shall maintain all accounting and financial records related to this Contract , in accordance with generally accepted accounting practices, including records of Contractor’s costs for performance under this Contract and records of Contractor’s Reimbursable Expenses. Contractor shall keep and make records available for inspection and audit by representatives of the CITY upon reasonable written notice.
7. Tax Payments. CONTRACTOR shall pay, when and as due, any and all taxes incurred as a result of CONTRACTOR’s compensation hereunder, including estimated taxes, and shall provide CITY with proof of the payment upon request. CONTRACTOR hereby agrees to indemnify CITY for any claims, losses, costs, fees, liabilities, damages or injuries suffered by CITY arising out of CONTRACTOR’s breach of this section.
Form Approved by City Attorney 9-1-2020 Exhibit C - Page 1
EXHIBIT C
INSURANCE
1. Insurance Requirements. During the entire term of this Contract, Contractor shall maintain the insurance coverage described in the Insurance Terms below. Full compensation for all premiums that Contractor is required to pay for the insurance coverage described herein shall be included in the compensation specified under this Contract. No additional compensation will be provided for Contractor's insurance premiums. Any available insurance proceeds in excess of the specified minimum limits and coverages shall be available to the City.
Contractor's liability to the City is not in any way limited to or affected by the amount of insurance coverage required or carried by the Contractor in connection with this Contract.
2. General Liability Minimum Scope and Limits of Insurance Coverage. Commercial General Liability Insurance is required providing coverage at least as broad as ISO CGL Form 00 01 on an occurrence basis for bodily injury, including death, of one or more persons, property damage, and personal injury, arising out of activities performed by or on behalf of the Contractor and subcontractors, products and completed operations of Contractor and subcontractors, and premises owned, leased, or used by Contractor and subcontractors, with limits of not less than one million dollars ($1,000,000) per occurrence. The policy shall provide contractual liability and products and completed operations coverage for the term of the policy.
The City, its officials, employees and volunteers shall be covered by policy terms or endorsement as additional insureds as respects general liability arising out of: activities performed by or on behalf of Contractor and subcontractors; products and completed operations of Contractor and subcontractors; and premises owned, leased, or used by Contractor and subcontractors.
3. Automobile Liability Minimum Scope and Limits of Insurance Coverage. (Check the applicable provision.)
_X_ Automobile Liability Insurance is required providing coverage at least as broad as ISO Form CA 00 01 for bodily injury, including death, of one or more persons, property damage and personal injury, with limits of not less than one million dollars ($1,000,000) per occurrence. The policy shall provide coverage for owned, non-owned and/or hired autos as appropriate to the operations of the Contractor.
The City, its officials, employees and volunteers shall be covered by policy terms or endorsement as additional insureds as respects auto liability.
___ No automobile liability insurance is required , and by signing this Contract, C ontractor certifies as follows:
“Contractor certifies that a motor vehicle will not be used in the performance of any work or services under this agreement. If, however, Contractor does transport items under this Contract, or this Contract is amended to require any employees of Contractor to use a
Form Approved by City Attorney 9-1-2020 Exhibit C - Page 2 vehicle to perform services under the Contract, Contractor understands that it must maintain and provide evidence of Automobile Liability Insurance providing coverage at least as broad as ISO Form CA 00 01 for bodily injury, including death, of one or more persons, property damage and personal injury, with limits of not less than one million dollars ($1,000,000) per occurrence. The policy shall provide coverage for owned, non - owned and/or hired autos as appropriate to the operations of the Contractor.”
4. Excess Insurance . The minimum limits of insurance required above may be satisfied by a combination of primary and umbrella or excess insurance coverage, provided that any umbrella or excess insurance contains, or is endorsed to contain, a provision that it will apply on a primary basis for the benefit of the City, and any insurance or self-insurance maintained by City, its officials, employees, or volunteers will be in excess of Contractor's umbrella or excess coverage and will not contribute to it.
5. Workers’ Compensation Minimum Scope and Limits of Insurance Coverage. (Check the applicable provision.)
_X_ Workers’ Compensation Insurance is required with statutory limits and Employers' Liability Insurance with limits of not less than one million dollars ($1,000,000). The Workers' Compensation policy shall include a waiver of subrogation in favor of the City.
___ No work or services will be performed on or at CITY facilities or CITY Property, therefore a Workers’ Compensation waiver of subrogation in favor of the CITY is not required.
___ No Workers’ Compensation insurance is required, and by signing this Contract, Contractor certifies as follows:
“Contractor certifies that its business has no employees, and that it does not employ anyone, and is therefore exempt from the legal requirements to provide Workers' Compensation insurance. If, however, Contractor hires any employee during the term of this Contract, Contractor understands that Workers’ Compensation with statutory limits and Employer’s Liability Insurance with a limit of not less than one million dollars ($1,000,000) is required. The Workers’ Compensation policy will include a waiver of subrogation in favor of the City.”
6. Professional Liability Minimum Scope and Limits of Insurance Coverage. Professional Liability Insurance providing coverage on a claims-made basis for errors and omissions, or malpractice with limits of not less than one million dollars ($1,000,000):
Is _____ Is not __X___ [check one] required for this Agreement.
If required, such coverage must be continued for at least ____ year(s) following the completion of all Services under this Contract. The retroactive date must be prior to the date this Contract is approved or any Services are performed.
Form Approved by City Attorney 9-1-2020 Exhibit C - Page 3
7. Other Insurance Provisions. The policies must contain, or be endorsed to contain, the following provisions:
A. Contractor's insurance coverage, including excess insurance, shall be primary insurance as respects the City, its officials, employees and volunteers. Any insurance or self-insurance maintained by the City, its officials, employees or volunteers will be in excess of Contractor's insurance and will not contribute with it.
B. Any failure to comply with reporting provisions of the policies will not affect coverage provided to the City, its officials, employees or volunteers.
C. Coverage shall state that Contractor's insurance applies separately to each insured against whom claim is made or suit is brought, except with respect to the limits of the insurer's liability.
D. Contractor shall provide the City with 30 days written notice of cancellation or material change in the policy language or terms.
8. Acceptability of Insurance. Insurance must be placed with insurers with a Bests' rating of not less than A:VI. Self-insured retentions, policy terms or other variations that do not comply with the requirements of this Exhibit C must be declared to and approved by the City in writing before execution of this Contract.
9. Verification of Coverage.
A. Contractor shall furnish City with certificates and required endorsements evidencing the insurance required. Certificates of insurance must be signed by an authorized representative of the insurance carrier. Copies of policies shall be delivered to the City Representative on demand.
B. Contractor shall send all insurance certificates and endorsements, including policy renewals, during the term of this Contract directly to:
City of Sacramento
c/o Exigis LLC
PO Box 947
Murrieta, CA 92564
C. Certificate Holder must be listed as:
City of Sacramento
c/o Exigis LLC
PO Box 947
Murrieta, CA 92564
D. The City may withdraw its offer of Contract or cancel this Contract if the certificates of insurance and endorsements required have not been provided before execution of this Contract. The City may withhold payments to Contractor and/or cancel the Contract if the insurance is canceled or Contractor otherwise ceases to be insured as required herein.
Form Approved by City Attorney 9-1-2020 Exhibit C - Page 4
10. Subcontractor Insurance Coverage . Contractor shall require and verify that all subcontractors maintain insurance coverage that meets the minimum scope and limits of insurance coverage specified in this Exhibit C.
Form Approved by City Attorney 9-1-2020 Exhibit D - Page 1
EXHIBIT D
GENERAL CONDITIONS
1. Independent Contractor.
A. It is understood and agreed that CONTRACTOR (including CONTRACTOR’s employees) is an independent contractor and that no relationship of employer -employee exists between the parties hereto for any purpose whatsoever. Neither CONTRACTOR nor CONTRACTOR’s ass igned personnel wi ll be entitled to any benefits payable to CITY employees. CITY is not required to make any deductions or withholdings from the compensation payable to CONTRACTOR under the provisions of this Contract , and CONTRACTOR will be issued a Form 1099 for its services hereunder. As an independent contractor, CONTRACTOR hereby agrees to indemnify and hold CITY harmless from any and all claims that may be made against CITY based upon any contention by any of CONTRACTOR’s employees or by any third p arty, including any state or federal agency, that an employer -employee relationship or a substitute therefor exists for any purpose whatsoever by reason of this Contract or by reason of the nature and/or performance under this Contract.
B. It is further understood and agreed by the parties that CONTRACTOR, in the performance of its obligations, is subject to the City’s control and direction as to the designation of tasks to be performed and the results to be accomplished under this Contract, but not as to the means, methods, or sequence used by CONTRACTOR for accomplishing the results.
To the extent that CONTRACTOR obtains permission to, and does, use CITY facilities, space, equipment or support services in the performance of this Contract, this use will be at the CONTRACTOR’s sole discretion based on the CONTRACTOR’s determination that the use will promote CONTRACTOR’s efficiency and effectiveness. Except as may be specifically provided elsewhere in this Contract , the CITY does not require that CONTRACTOR use CITY facilities, equipment or support services or work in CITY locations in the performance of this Contract . As used in this Contract, "sole discretion" or "sole judgment" means that the party authorized to exercise its discretion or judgment may do so based on an unfettered assessment of its own interests, without considering how its decision affects the other party, and unconstrained by the implied covenant of good faith and fair dealing.
C. If, in the performance of this Contract, any third persons are employed by CONTRACTOR, such persons will be entirely and exclusively under the direction, supervision, and control of CONTRACTOR. Except as otherwise provided in this Contract, all terms of employment, including hours, wages, working conditions, discipline, hiring, and discharging, or any other terms of employment or requirements of law, shall be determined by CONTRACTOR. It is further understood and agreed that CONTRACTOR will issue W-2 or 1099 Forms for income and employment tax purposes for all CONTRACTOR’s assigned personnel and subcontractors.
D. The provisions of this s ection will survive any expiration or termination of this Contract .
Nothing in this Contract creates an exclusive relationship between CITY and CONTRACTOR. CONTRACTOR may represent, perform services for, or be employed by
Form Approved by City Attorney 9-1-2020 Exhibit D - Page 2 any additional persons or companies s o long as CONTRACTOR does not violate the provisions of Section 5, below.
2. Licenses; Permits, Etc. CONTRACTOR represents and warrants that CONTRACTOR has, and shall maintain at all times during the term of this Contract at its sole cost and expense, all licenses, permits, qualifications, and approvals of any nature that are legally required for CONTRACTOR to practice its profession or fulfill the terms of this Contract , including a City Business Operations Tax Certificate and any required certification issued by the California Secretary of State.
3. Time. Time is off the essence in the performance of this Contract. CONTRACTOR shall devote the necessary time and effort to its performance under this Contract. Neither party will be considered in default of this Contract, to the extent that party’s performance is prevented or delayed by any cause, present or future, that is beyond the reasonable control of that party.
4. CONTRACTOR Not Agent. Except as CITY may specify in writing, CONTRACTOR and CONTRACTOR’s personnel have no authority, express or implied, to act on behalf of CITY in any capacity whatsoever as an agent. CONTRACTOR and CONTRACTOR’s personnel shall have no authority, express or implied, to bind CITY to any obligations whatsoever.
5. Conflicts of Interest. CONTRACTOR covenants that neither it, nor any officer or principal of its firm, has or will acquire any interest, directly or indirectly, that would conflict in any manner with the CITY ’s interests or that would in any way hinder CONTRACTOR’s performance under this Contract. CONTRACTOR further covenants that in the performance of this Contrac t, no person having any such interest will be employed by it as an officer, employee, agent or subcontractor, without the City’s written consent.
CONTRACTOR agrees to avoid conflicts of interest or the appearance of any conflicts of interest with the City’s interests during the performance of this Contract. If CONTRACTOR is or employs a former officer or employee of the CITY, CONTRACTOR and any former City officer or employee shall comply with the provisions of Sacramento City Code Section 2.16.090 pertaining to appearances before the City Council or any CITY department, board, commission, or committee.
6. Hazardous Substances. "Hazardous Substances" means any substance, material, waste, or other pollutant or contaminant that is or becomes designated, classified, or regulated as hazardous or toxic under any law, regulation, rule, order, decree, or other governmental requirement now in effect or later enacted. If Contractor is shipping Hazardous Substances, Contractor must supply a Safety Data Sheet ("SDS") with the first shipment of Hazardous Substances to each City location receiving the Hazardous Substances. If the content of an SDS is revised, Contractor must provide a revised SDS to each City location receiving Hazardous Substances.
7. Confidentiality of CITY Information. During performance of this Contract , CONTRACTOR may gain access to and use CITY information regarding inventions, machinery, products, prices, apparatus, costs, discounts, future plans, business affairs, governmental affairs, processes, trade secrets, technical matters, systems, facilities, customer lists, product design, copyright, data, and other vital information (hereafter collectively referred to as “City Information”) that are valuable, special and unique assets of the CITY.
Form Approved by City Attorney 9-1-2020 Exhibit D - Page 3 CONTRACTOR agrees to protect all City Information and treat it as strictly confidential, and further agrees that CONTRACTOR shall not at any time, either directly or indirectly, divulge, disclose or communicate in any manner any City Information to any third party without the City’s prior written consent.
In addition, CONTRACTOR must comply with all CITY policies governing the use of the CITY network and technology systems, as set forth in applicable provisions of the City of Sacramento Administrative Policy Instructions # 30. A violation by CONTRACTOR of this s ection is a material violation of this Contract and shall justify legal and equitable relief.
8. CONTRACTOR Information.
A. CITY shall have full ownership and control, including ownership of any copyrights, of all information prepared, produced, or provided by CONTRACTOR under this Contract. In this Contract, the term “information” means and includes: any and all work product, submittals, reports, plans, specifications, and other deliverables consisting of documents, writings, handwritings, typewriting, printing, photostatting, photographing, computer models, and any other computerized data and every othe r means of recording any form of information, communications, or representation, including letters, works, pictures, drawings, sounds, or symbols, or any combination thereof. CONTRACTOR shall not be responsible for any unauthorized modification or use of such information for other than its intended purpose by CITY.
B. CONTRACTOR shall fully defend, indemnify and hold harmless CITY, its officers and employees, and each of them, from and against any and all claims, actions, lawsuits or other proceedings alleging that all or any part of the information prepared, produced, or provided by CONTRACTOR under this Contract infringes upon any third party’s trademark, trade name, copyright, patent or other intellectual property rights. CITY shall make reasonable efforts to notify CONTRACTOR not later than ten days after CITY is served with any such claim, action, lawsuit or other proceeding . However, City’s failure to provide notice within the ten- day period does not relieve CONTRACTOR of its obligations hereunder, which survive any termination or expiration of this Contract.
C. All proprietary and other information received from CONTRACTOR by CITY, whether received in connection with CONTRACTOR’s proposal to CITY or in connection with Contractor’s performance, will be disclosed upon receipt of a request for disclosure, in accordance with the California Public Records Act; provided, however, that, if any information is set apart and clearly marked “trade secret” when it is provided to CITY, CITY shall give notice to CONTRACTOR of any request for the disclosure of such information. The CONTRACTOR will then have five days from the date it receives notice to petition the court for a protective order to prevent the disclosure of the information.
The CONTRACTOR shall have sole responsibility for defense of the actual “trade secret” designation of such information.
D. The parties understand and agree that any failure by CONTRACTOR to respond to the notice provided by CITY and seek a protective order, in accordance with the provisions of subsection C, above, constitute s a complete waiver by CONTRACTOR of any rights regarding the information designated “trade secret” by CONTRACTOR, and the
Form Approved by City Attorney 9-1-2020 Exhibit D - Page 4 information will be disclosed by CITY in accordance with the Public Records Act.
9. Notification of Material Changes in Business. Contractor agrees that if it experiences any material changes in its business, including a reorganization, refinancing, restructuring, leveraged buyout, bankruptcy, name change, or loss of key personnel, it will immediately notify the City of the changes. Contractor also agrees to immediately notify the City of any condition that may jeopardize the scheduled delivery or fulfillment of Contractor's obligations to the City under this Contract.
10. Standard of Performance. CONTRACTOR shall perform in the manner and according to the standards currently observed by a competent practitioner of CONTRACTOR’s profession in California and in compliance with all requirements of this Contract . All products that CONTRACTOR delivers to CITY under this Contract must be prepared in a professional manner and conform to the standards of quality normally observed by a person currently practicing in CONTRACTOR’s profession.
CONTRACTOR shall assign only competent personnel to perform on its behalf under this Contract.
CONTRACTOR must notify the CITY in writing of any changes in CONTRACTOR’s staff assigned to perform under this Contract, before any performance by the new staff member . If the CITY, in its sole discretion, determines that any person assigned by the Contractor to perform under this Contract is not performing in accordance with the standards required herein, City shall provide notice to Contractor. CONTRACTOR shall immediately remove the assigned person upon receipt of the notice.
11. Performance or Different Terms and Conditions. The City's subsequent performance will not be construed as either acceptance of additional or different terms and conditions or a counteroffer by the Contractor, nor will the City's subsequent performance be viewed as acceptance of any provision of the Uniform Commercial Code, as adopted by any State, that is contrary to the terms and conditions contained herein. Contractor's performance shall conform to the applicable requirements of the Sacramento City Charter, Sacramento City Code, and all applicable State and Federal laws, and all the requirements of this Contract. The California Commercial Code will apply except as otherwise provided in the Contract.
12. Emergency/Declared Disaster Requirements. If an emergency is declared by the City Manager, or if any portion of the City is declared a disaster area by the county, state or federal government, this Contract may be subjected to increased usage. The Contractor shall serve the City during a declared emergency or disaster, subject to the same terms and conditions that apply during non- emergency / non-disaster conditions. The pricing set forth in this Contract will apply, without mark-up, regardless of the circumstances. If the Contractor is unable to fulfill the terms of the Contract because of a disruption in its chain of supply or service, then the Contractor shall provide proof of the disruption. Acceptable forms of proof will include a letter or notice from the Contractor's source stating the reason for the disruption
13. Term; Suspension; Termination.
A. This Contract is effective on the Effective Date and continues in effect until both parties have fully performed their respective obligations under this Contract, unless sooner terminated as provided herein.
Form Approved by City Attorney 9-1-2020 Exhibit D - Page 5
B. CITY shall have the right at any time to suspend CONTRACTOR’s performance hereunder, in whole or in part, by giving a written notice of suspension to CONTRACTOR. Upon receipt of such notice , CONTRACTOR shall immediately suspend its activities under this Contract, as specified in the notice.
C. The CITY shall have the right to terminate this Contract at any time by giving a written notice of termination to CONTRACTOR. Upon receipt of such notice , CONTRACTOR shall immediately cease performance under this Contract as specified in the notice. If the CITY terminates this Contract:
(1) CONTRACTOR shall, not later than five days after receipt of the notice, deliver all information prepared under this Contract to the City.
(2) The CITY shall pay CONTRACTOR the reasonable value of Goods or Services provided by CONTRACTOR before termination; provided, however, CITY shall not in any manner be liable for lost profits that might have been made by CONTRACTOR had the Contract not been terminated or had CONTRACTOR completed performance required by this Contract. CONTRACTOR shall furnish to the CITY any financial information requested by the City to determine the reasonable value of the Goods or Services provided by CONTRACTOR. The foregoing is cumulative and does not affect any right or remedy that CITY may have in law or equity.
14. Default by Contractor. In case of default by the Contractor, the City reserves the right to procure the Goods or Services from other sources and deduct from any monies due, or that may thereafter become due to the Contractor, the difference between the price named in this Contract and the actual cost to the City to procure from an alternate source. Prices paid by the City will be considered the prevailing market price at the time such purchase is made.
15. Indemnity.
A. Indemnity: Contractor shall defend, hold harmless, and indemnify City, its officers, and employees, and each and every one of them, to the fullest extent permitted under law, from and against all actions, damages, costs, liabilities, claims, demands, losses, judgments, penalties, and expenses of every type and description, whether arising on or off the site of the work or services performed under this Contract, including any fees and costs reasonably incurred by City’s staff attorneys or outside attorneys and any fees and expenses incurred in enforcing this provision (hereafter collectively referred to as “Claims”), including Claims for personal injury or death, damage to personal, real, or intellectual property, damage to the environment, contractual or other economic damages, or regulatory penalties, that arise out of, pertain to, or relate to any negligent act or omission, recklessness, or willful misconduct related in any way to the performance of or failure to perform this Contract by Contractor, any subcontractor (including lower-tier subcontractors) or agent of Contractor, their respective officers and employees, and anyone else for whose acts of omissions any of them may be liable, whether or not the Claims are litigated, settled, or reduced to judgment; provided that the foregoing indemnity does not apply to liability for damages for death or bodily injury
Form Approved by City Attorney 9-1-2020 Exhibit D - Page 6 to persons, injury to property, or other loss, damage, or expense, to the extent arising from the active negligence or willful misconduct of, or defects in design furnished by, City, its agents, servants, or independent contractors who are directly responsible to City, except when such agents, servants, or independent contractors are under the supervision and control of Contractor or any subcontractor (including lower-tier subcontractors) or agent of Contractor. While Contractor’s defense costs ordinarily cannot exceed Contractor’s proportionate percentage of fault, if one or more defendants is unable to pay its share of defense costs due to bankruptcy or dissolution, the Contractor shall meet and confer with the City and other parties regarding the unpaid defense costs.
B. Insurance Policies; Intellectual Property Claims: The existence or acceptance by City of any of the insurance policies or coverages described in this Contract will not affect or limit any of City’s rights under this Section, nor will the limits of any insurance limit the liability of Contractor hereunder. This Section will not apply to any intellectual property claims, actions, lawsuits or other proceedings subject to the provisions of the Contractor Information Section, above.
C. Survival. The provisions of this section will survive any expiration or termination of this Contract.
16. Funding Availability.
A. This Contract is subject to the budget and fiscal provisions of the Charter and the Sacramento City Code.
B. The City’s payment obligation under this Contract will not exceed the amount of funds appropriated and approved for this Contract by the Sacramento City Council.
C. This Section shall govern over any other contrary provision of the Contract.
17. Equal Employment Opportunity. During the performance of this Contrac t, CONTRACTOR, for itself, its assignees and successors in interest, agrees as follows:
A. Compliance With Regulations: CONTRACTOR shall comply with all state, local, and federal anti-discrimination laws and regulations, including the Executive Order 11246 entitled “Equal Opportunity in Federal Employment”, as amended by Executive Order 11375, 12086, and 13672, and as supplemented in Department of Labor regulations (41 CFR Chapter 60), referred to collectively as the “Regulations.”
B. Nondiscrimination: CONTRACTOR, with regards to the work performed by it after award and before completion of the work under this Contract, shall not discriminate on the ground of race, color, religion, sex, national origin, age, marital status, physical handicap or sexual orientation in selection and retention of subcontractors, including procurement of materials and leases of equipment. C ONTRACTOR shall not participate either directly or indirectly in discrimination prohibited by the Regulations.
C. Solicitations for Subcontractors, Including Procurement of Materials and Equipment: In
Form Approved by City Attorney 9-1-2020 Exhibit D - Page 7 all solicitations either by competitive bidding or negotiations made by CONTRACTOR for work to be performed under any subcontract, including all procurement of materials or equipment, each potential subcontractor or supplier shall be notified by CONTRACTOR of CONTRACTOR’s obligation under this Contract and the Regulations relative to nondiscrimination on the ground of race, color, religion, sex, national origin, age, marital status, physical handicap or sexual orientation.
D. Information and Reports: CONTRACTOR shall provide all information and reports required by the Regulations, or by any orders or instructions issued pursuant thereto, and shall permit access to its books, records, accounts, other sources of information and its facilities as may be determined by the CITY to be pertinent to ascertain compliance with the Regulations, orders and instructions. Where any information required of CONTRACTOR is in the exclusive possession of another who fails or refuses to furnish this information, CONTRACTOR shall so certify to the CITY, and shall set forth what efforts it has made to obtain the information.
E. Sanctions for Noncompliance: In the event of noncompliance by CONTRACTOR with the nondiscrimination provisions of this Contract, the CITY shall impose any sanctions it determines are appropriate including:
(1) Withholding of payments to CONTRACTOR under this Contract until CONTRACTOR complies;
(2) Cancellation, termination, or suspension of this Contract, in whole or in part.
F. Incorporation of Provisions: CONTRACTOR shall include the provisions of subsections A through E, above, in every subcontract, including procurement of materials and leases of equipment, unless exempted by the Regulations, or by any order or instructions issued pursuant thereto. The City may direct CONTRACTOR to take specific actions to enforce these provisions, including sanctions for noncompliance; provided, however, that if CONTRACTOR becomes involved in, or is threatened with, litigation with a subcontractor or supplier as a result of such direction, CONTRACTOR may request that the CITY join such litigation to protect the City’s interests.
18. Entire Agreement. This Contract, including all Exhibits and documents referenced herein, contains the entire agreement between the parties and supersedes whatever oral or written understanding they may have had before the execution of this Contract . No alteration to the terms of this Contract shall be valid unless approved in writing by CONTRACTOR, and by CITY, in accordance with applicable provisions of the Sacramento City Code.
19. Modification of Contract . The Contractor shall take no direction from any City employee that changes the executed terms and conditions of the Contract, including Exhibit A , or any change that impacts the cost, price, or schedule, before receiving a written, signed modification to the Contract.
20. Severability. If a court with jurisdiction rules that any portion of this Contract or its application to any person or circumstance is invalid or unenforceable, the remainder of this Contract will not be affected thereby and will remain valid and enforceable as written, to the greatest extent permitted by law.
Form Approved by City Attorney 9-1-2020 Exhibit D - Page 8
21. Waiver. Neither the CITY’s acceptance of, or payment for, any Goods or Services, nor any waiver by either party of any default, breach or condition precedent, will be construed as a waiver of any provision of this Contract, nor as a waiver of any other default, breach or condition precedent or any other right hereunder. No waiver will be effective unless it is in writing and signed by the waiving party.
22. Governing Law. This Contract shall be governed, construed and enforced in accordance with the laws of the State of California, except that the rule of interpretation in California Civil Code section 1654 will not apply. Venue of any litigation arising out of this Contract will lie exclusively in the state trial court or Federal District Court located in Sacramento County in the State of California, and the parties consent to jurisdiction over their persons and over the subject matter of any such litigation in such courts, and consent to service of process issued by such courts.
23. Assignment Prohibited. The expertise and experience of CONTRACTOR are material considerations for this Contract. CITY has a strong interest in the qualifications and capability of the persons and entities that will fulfill the obligations imposed on CONTRACTOR under this Agreement. In recognition of this interest, CONTRACTOR shall not assign any right or obligatio n pursuant to this Contract without the written consent of the CITY. Any attempted or purported assignment without CITY’s written consent shall be void and of no effect.
24. Binding Effect. This Contract is binding on the heirs, executors, administrators, successors and assigns of the parties, subject to the provisions of Section 23, above.
25. Compliance with Laws. The Contractor shall be responsible for strict compliance with all applicable laws, regulations, court orders and other legal requirements applicable to the work to be accomplished under the Contract, including the California Occupational Safety and Health Act and all applicable safety orders issued by the Division of Occupational Safety and Health, Department of Industrial Relations, State of California, and all applicable requirements of Underwriters Laboratories and the Federal Communication Commission.
26. Debarment Certification
A. Pursuant to 2 CFR, Part 200, and applicable Executive Orders, the City is restricted in its ability to contract with certain parties that are debarred, suspended, or otherwise excluded or ineligible for participating in Federal assistance programs or activities. By signing this Agreement, CONTRACTOR warrants and certifies under penalty of perjury under the laws of the State of California that Contractor, including any owner, partner, director, officer, or principal of the CONTRACTOR, or any person in a position with management responsibility or responsibility for the administration of federal funds:
(1) Is not presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from covered transactions by any federal or state department/agency;
(2) Has not within a three -year period preceding this certification been convicted of or had a civil judgment rendered against it for: commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public transaction or contract (federal, state, or local); violation of federal or state antitrust statutes; or
Form Approved by City Attorney 9-1-2020 Exhibit D - Page 9 commission of embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements, receiving stolen property, or other criminal felony;
(3) Is not presently indicted for or otherwise criminally or civilly charged by a governmental entity (federal, state, or local) with commission of any of the offenses enumerated in paragraph (b) above; or
(4) Has not, within a three -year period preceding this certification, had one or more public contracts (federal, state, or local) or transactions terminated for cause or default.
(5) Has not been notified, within a three-year period preceding this certification, been notified of any delinquent Federal taxes in an amount that exceeds $3,500 for which the liability remains unsatisfied. Federal taxes are considered delinquent if the tax liability has been finally determined and the taxpayer is delinquent in making payment, as defined in Section 52.209-5 of the Federal Acquisition Regulations.
B. CONTRACTOR further warrants and certifies that it shall not knowingly enter into any transaction with any subcontractor, material supplier, or vendor who is debarred, suspended, declared ineligible, or voluntarily excluded from covered transactions by any federal or state department/agency. Any exceptions to the warranties and certifications in this Section must be disclosed to the City.
C. Exceptions will not necessarily result in denial of recommendation for award, but will be considered in determining Contractor’s responsibility. Disclosures must indicate to whom exceptions apply, the initiating agency, and dates of action.
D. City will review the Federal Government’s System for Award Management Exclusions maintained by the General Services Administration for eligibility, prior to the execution of this Agreement. The CONTRACTOR shall provide immediate written notice to the City if, at any time prior to execution, the CONTRACTOR learns this certification is erroneous or has become erroneous by reason of changed circumstances. If it is later determined that the Contractor’s warranties and certification in this Section were erron eous, the City may terminate this Agreement for default.
Form Approved by City Attorney 9-1-2020 Exhibit E - Page 1
EXHIBIT E
ADDITIONAL REQUIREMENTS FOR SURVEYING, MATERIAL TESTING, AND INSPECTION SERVICES
The Services provided under this Contract include land surveying, material testing, or inspection services provided for a City construction project during the design, pre -construction, construction, or post- construction phases of the project. Therefore, the services include “Public Work” under the California Labor Code and is subject to the following requirements:
A. Payment of Prevailing Wages: Contractor and any subcontractor(s) performing any Public Work shall comply with the provisions of Sacramento City Code section 3.60.180 and applicable provisions of the California Labor Code, which require, among other things, that CONTRACTOR and all subcontractors pay not less than the prevailing rate of wages, as determined by the Director of the California Department of Industrial Relations (“DIR”) in accordance with California Labor Code section 1773. CONTRACTOR and every subcontractor shall maintain payroll records and submit certified payrolls and other labor compliance documentation electronically when and as required by CITY. In addition, Labor Code Section 1771.4 requires the CONTRACTOR and any subcontractor performing any Public Work to furnish electronic payroll records directly to the Labor Commissioner.
Contractor shall include these requirements in every subcontract.
This Agreement is subject to compliance monitoring and enforcement by the DIR, as specified in California Labor Code section 1771.4. The Contractor and any subcontractor will be subject to withholding and penalties for violation of prevailing wage requirements in accordance with applicable law, including Labor Code Sections 1726, 1741, 1771.5, and 1775, and City Code Section 3.60.180. Questions regarding the City’s Labor Compliance Program should be directed to the City Representative.
B. DIR Registration: California Labor Code Section 1725.5 requires the CONTRACTOR and all subcontractors performing Public Works services to be currently registered with the DIR, as specified in California Labor Code Section 1725.5. California Labor Code Section 1771.1 provides that a contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal (subject to the requirements of Section 4104 of the California Public Contract Code), or engage in the performance of any contract for P ublic Work, unless currently registered and qualified to perform Public Work in accordance with California Labor Code Section 1725.5.
Further information can be found on DIR’s website at http://www.dir.ca.gov/Public - Works/Contractors.html. The above summary is provided solely for informational purposes and does not in any way affect the CONTRACTOR’s and subcontractors’ obligation to com ply in all respects with all other applicable laws and regulations. The CONTRACTOR shall disseminate these provisions to all subcontractors.
Before the performance of work by Contractor or any subcontractor(s) under this Contract, Contractor shall furnish Contractor’s and any subcontractors’ current DIR
Form Approved by City Attorney 9-1-2020 Exhibit E - Page 2 registration number(s). The Contractor’s current DIR registration number and the current DIR registration number of all subcontractors will be listed on the Subcontractor and LBE Participation Verification Form, incorporated herein.
To be completed by the City Representative if this Agreement is for the performance of any Public Work:
Contractor DIR registration #: _________________________________________
C. Workers’ Compensation Certification. In accordance with California Labor Code Section 1861, by signing this Contract, Contractor acknowledges and represents that Contractor is aware of the provisions of section 3700 of the California Labor Code which requires every employer to be insured against liability for workers' compensation or to undertake self-insurance in accordance with the provisions of that code, and that Contractor will comply with the provisions of the Labor Code before commencing performance under this Contract.
D. Apprentices. If this Contract is for the performance of any Public Work, and the amount of the Contract is $30,000 or more, the Contractor and any subcontractors performing any Public Work under this Contract must comply with and be subject to enforcement under, the provisions of Sacramento City Code Section 3.60.190, Section 1777.5 et seq. of the California Labor Code, and implementing regulations set forth in Title 8 of the California Code of Regulations, governing the employment of apprentices. The Contractor and any subcontractors performing Public Work will be subject to penalties for apprenticeship violations in accordance with Labor Code Section 1777.7.
E. Working Hours. If this Contract is for the performance of any Public Work, Contractor and any subcontractors performing any Public Work under this Contract must comply with and be subject to enforcement under, the provisions of Sacramento City Code Section 3.60.180 and California Labor Code Section 1810 et seq., governing the working hours of employees performing Public Work.
F. Failure to Comply with Labor Compliance. If all applicable labor compliance requirements are not met, the City will have the right to withhold or reject a payment request and/or invoice, in whole or in part, without in any way relieving Contractor or its subcontractors of any obligations under this Contract.
G. Subcontractors. The Contractor shall include these provisions A through F in every subcontract or sub -agreement for any subcontractors performing work under this Contract.
Attachment 1 to Scope of Services Exhibit A & Payment Exhibit B City of Sacramento
Pavement Condition Data Collection and Analysis (RFP No P24151621005) Revised January 2, 2024
Page | 1
Work Plan, Project Schedule and Cost Estimate
Work Plan
NCE’s work plan includes the following tasks.
Task 1: Kickoff Meeting and Project Coordination
NCE will first meet with City staff to kick-off the project by reviewing the technical approach and any administrative matters that may be necessary. At a minimum, items to be discussed will include the following:
• Project goals
• Scope of work, project schedule, budget and invoicing requirements • Field work
o Scheduling and access requirements for field work
o Public safety concerns, requirements and procedures
o Quality Control Plan (QCP)
o Updated GIS map of publicly maintained streets if any o New roads, if any
• Maintenance and rehabilitation (M&R) practices, records, costs • Paving or maintenance budgets
• Budgeting scenarios
• Other optional tasks
Prior to the kick -off meeting, NCE will prepare a detailed agenda, which will be sent to City staff for review. Additional meetings may be held at appropriate milestones to review the work performed and to address any questions or issues that arise as the work progresses.
Deliverables
• Kickoff meeting agenda and summary.
Task 2: Pavement Condition Surveys
NCE will next perform pavement condition surveys on approximately 701 centerline miles of the City maintained streets, i.e., 122 miles of arterials, 85 miles of collectors, and 494 miles of residentials as requested in the RFP. Alleys and bikeway will not be surveyed unless requested. The distress collection protocols will be in accordance with ASTM D6433-20.
The “fuel” for any pavement management engine is the surface condition data. Pavement distress provides that important set of data in determining the costs to maintain the pavement network.
Automated procedures will be conducted with a 100% sampling rate with full width “curb- to-curb” pavement survey coverage to collect distress data. This is the similar technology utilized in 2017 to 2022 , but with upgrade d LiDAR Scanner s to capture high- resolution 3D pavement profile s and automatically determine surface damage areas and the type, severity, and quantity of distress to evaluate pavement conditions. The data collection
City of Sacramento
Pavement Condition Data Collection and Analysis (RFP No P24151621005) Revised January 2, 2024
Page | 2
system will be operated by the same MTC-certified technicians who worked in the City before, ensuring consistency and reliability in the collected data.
Any variation from the established procedures will be to accommodate unique local conditions, e.g., gap-graded texture of rubberized asphalt concrete overlays, bleeding, edge cracking, etc. These conditions typically exhibit unique distresses that may not be reflected in any distress manual, so special exceptions will need to be made.
Our team will be responsible for providing all equipment necessary for the performance of this task. Should City personnel wish to observe our field crews and testing vehicle during the inspection surveys, we will be more than happy to accommodate this. Individual City staff may also accompany NCE’s field crew for up to ½ day to gain hands-on training at no additional cost to the City. We have found that this is the most effective training method for agency staff, as they become part of the data collection crew, rather than just observers.
Please note that this scope of work and condition surveys do not address issues including, but not limited to traffic, safety and road hazards, geometric issues, road shoulders, sidewalks, curb and gutters, drainage issues or short -term maintenance that should be performed.
Deliverables
• Updated StreetSaver® database with pavement distress data.
Task 3: Data Entry and PCI Calculation
All data collected from the field will then be uploaded into the StreetSaver® database. There are specific rules and validations that must be followed in this task, so a successful upload depends on appropriate Quality Control (QC) as well as a solid familiarity with the StreetSaver® program.
This task will be performed at NCE’s office in order to provide Quality Control of all data entered into the system. NCE will then perform the pavement condition index (PCI) calculations, and correct any errors found. Finally, all PCI, database statistics and other reports will be prepared and will include the following:
• Pavement distribution by Council District (by area, lane miles, centerline miles and % area) – see example figure below
• Pavement distribution by Functional Class (by area, lane miles, centerline miles and % area) • PCI less than 40 (by area, lane-miles, centerline miles and % area) • PCI by Functional Class (weighted by pavement area)
• Length differences – this report will identify any segment where the length difference between the City supplied segment length and the actual measured segment length differs by more than ± 50 feet. • List of streets that were not tested - this will include the street name, begin and end limits, section ID, and reason for not testing, e.g., closed, under construction, private street, etc.
City of Sacramento
Pavement Condition Data Collection and Analysis (RFP No P24151621005) Revised January 2, 2024
Page | 3
Deliverables
• Updated StreetSaver® database with calculated PCIs
• PCI, database statistics and other reports
Task 4: Quality Control Program
Quality control (QC)/quality assurance checks are critical when a large amount of data needs to be collected and processed. As part of NCE’s goal to provide a superior quality product for our clients, we incorporate a QC component into all of our projects. For this project, we have proposed the inclusion of a QC Manager, Dr. James Signore. He will be responsible for:
• Calibrating all data collection activities
• Reviewing field activities, including spot checks on the field crews • Reviewing field procedures and making changes, as needed • Comparing the field data collected with on-site conditions • Reviewing all data entry functions, including random spot checks • Reviewing reports generated and analyses performed to ensure a quality product NCE will prepare a QC Plan that will include the following components:
• Description of condition survey procedures (distress types, severities). All procedures, changes or modifications should be well documented in the QCP so that future updates will be consistent.
• Accuracy required for data collection or acceptability criteria. • Description of how data will be checked for accuracy, e.g., control sections setup and distress comparisons between walking and automated surveys. A sample spreadsheet of distress detail comparisons between walking and automated survey on control sections is listed below.
A draft QC plan will be submitted to the City for approval, and no field work will commence until a final plan has been accepted.
Deliverables
• Quality control plan
City of Sacramento
Pavement Condition Data Collection and Analysis (RFP No P24151621005) Revised January 2, 2024
Page | 4
Task 5: Maintenance and Rehabilitation (M&R) Strategies and Decision Tree Pavement treatments and unit costs in City’s StreetSaver® database were last updated in February 2022. Therefore, NCE will first review maintenance and rehabilitation (M&R) strategies with City staff . This will include the recommendation and selection of appropriate treatments and the determination of treatment unit costs. This will also be an appropriate time to review the use of new/sustainable treatments or materials, such as PCC bonded overlays, rubberized asphalt, rubberized cape seals, microsurfacing, rejuvenators, cold -in-place
recycling (CIR), full depth reclamation (FDR),
warm mix asphalt, etc.
Development of the M&R decision tree is a critical step in any pavement management update as it has a direct and significant impact on the final work plan that is developed, as well as the budgeting consequences. NCE’s experience in pavement engineering and design, as well as local conditions, allows our staff to be able to provide the City with solutions that are innovative, sustainable, practical, and workable.
Since paving construction costs have increased dramatically since 2004 (as much as three times in some cases), NCE will review any recent bid tabs, together with those from neighboring agencies, as appropriate, to update unit costs in the decision tree. We have recently completed similar PMS updates for the Cities of Citrus Heights, Elk Grove and Rocklin and will be able to use these bid tabs of construction costs for comparison if needed.
In addition, all historical M&R records from 2022 to 2024 will be entered into the StreetSaver® database. Populating the database with recent M&R historical data is extremely useful for determining future treatments and predicting performance of the various pavement sections. M&R activities include overlay, reconstruction, and any surface seals or localized repairs. All M&R historical records must include the road names, Street ID and Section IDs, limits of work, date and type of treatments, and cost of treatments (optional).
Deliverables
• Updated StreetSaver® database with historical M&R records. • M&R history report.
• M&R strategies and costs in decision tree.
Task 6: Budget Analysis and Annual Reports
NCE will next perform a Budget Needs analysis using an analysis period to be determined by the City (can be as long as 30 years). The Needs Analysis identifies street sections that need treatment and applies the M&R decision trees to each section. The costs are then summed for the entire period. This forms the basis for performing Budget Scenario evaluations, which optimize the road sections for repair under constrained budgets.
In simple terms, the Budget Needs analysis answers the questions:
“If I have unlimited funding for street maintenance and repair, which streets should I fix? When should I fix them? What treatments should I apply? How much will it cost?” Simple put, this module answers the question: “If I only have limited funds for street maintenance and repair, which streets have the highest priority for repairs, when should I perform the repairs, and how much will it cost?
City of Sacramento
Pavement Condition Data Collection and Analysis (RFP No P24151621005) Revised January 2, 2024
Page | 5
The Budget Scenarios evaluation uses a weighted effectiveness rating to prioritize sections for repair under constrained, realistic, budgetary assumptions. The effectiveness rating is defined as the area under a pavement performance curve.
The effectiveness rating is weighted to place a higher priority on certain roads, such as arterials and collectors.
Multiple funding scenarios may be performed to answer “what -if” questions (the real “meat” of any PMS). NCE will perform up to four budget scenario runs based on the discussion with City staff. Typical scenarios include:
• Impacts of existing funding levels including SB1 funding or Measure A • Funding required to maintain existing PCI
• Funding to improve the PCI to a state of good repair
• Impacts to model changes in funding, e.g. , if increases in funding, e.g., sales tax or bond measures StreetSaver® has powerful prioritization tools that analyses the benefits and costs for each road segment and treatment so that a prioritized list of candidate projects are generated for inclusion in a multi-year work plan. It also has the ability to accommodate projects that are “fixed” e.g. utility projects or projects with committed funding.
A sample graph from similar budgetary analyses is shown directly on the right.
After the analysis is completed, NCE will prepare a draft pavement condition report for the City to review. In this current project, NCE has developed a report that is intended for the City Council and the public – it summarizes vast quantities of data and results in an easy to understand and digestible format (see Section 9). As previously mentioned, data from other cities and counties from the Statewide survey database may be provided for comparison.
NCE will deliver the draft report to the City for review in electronic format. Upon receipt of the comments on the draft report, NCE will complete the final report for submittal.
Deliverables
• Draft report (electric) and final report (electric and 2 hard copies).
Task 7: Training, Technical Support and Presentation
Under this task, NCE will prepare and present a one -day training class with City staff. The class will cover the following items:
• Creating or editing street sections
• Entering pavement distress data
• Performing PCI Calculations
• Entering maintenance and rehabilitation history
• Revising the M&R decision tree
o Determining appropriate unit costs
• Determining budget needs
o Creating budget scenarios Identifying treatment strategies o Project selection tools
o Target-driven analysis
• Generating reports and GIS maps
City of Sacramento
Pavement Condition Data Collection and Analysis (RFP No P24151621005) Revised January 2, 2024
Page | 6
All materials will be provided by NCE. It is assumed that the training will be conducted on- site and will include up to 4 participants. It is assumed that computers and internet access will be provided by the City. Options for virtual training are also available if desired.
NCE has prepared and trained over 100 agencies in California on StreetSaver®. This includes developing all the training materials, ensuring interaction in the training as well as conducting the training. At the end of the training, City staff will be able to perform additional funding scenarios as desired and generate new or revised multi-year work plans.
NCE will also provide technical support for the City staff. Typically, most technical support is related to providing one-on- one assistance, performing budget scenarios, updating M&R records, providing customized reports, providing pavement treatment recommendations, GIS maps, etc. Based on City’s revised GIS shapefile or updated network, NCE will modify the pavement inventory to match existing GIS shapefile. Any missing sections or GIS linkages or miscoded inventory characteristics (i.e. functional classification, section length, surface type, etc.) will be updated to reflect City’s maintained network.
In addition, NCE will make presentations to the City Council, if desired. This may be a short (15 to 20 minutes) informational item or could be a longer (1 -2 hours) educational/advocacy workshop, depending on the City’s needs. NCE has recently completed similar presentations to the Cities of Davis, Fairfield, Folsom and to the Board of Supervisors in Madera, Fresno, Santa Cruz, Siskiyou and Humboldt Counties.
NCE’s value to the City is the information that we can provide from other agencies, and the results of tight budgetary constraints. We can also share the perspective of our work from the California Statewide Needs Assessment study, which included an assessment of all 540 cities and counties. This task includes two videoconference with City staff prior to the presentation to discuss items such as the goal of the presentation, the level of knowledge and backgrounds of the audience, the number of stakeholders involved and other potential issues.
Deliverables
• Training manuals and PowerPoint presentations for software training. • PowerPoint presentation for Council meeting.
“We have been happy with the work performed by Nichols Engineering (NCE)…Margot’s presentation to our City "Council was instrumental in getting their ‘buy in’ to use the PMS for our Pavement Rehabilitation programs.” Elizabeth Chopp, PE, Senior Engineer
City of Chula Vista
City of Sacramento
Pavement Condition Data Collection and Analysis (RFP No P24151621005) Revised January 2, 2024
Page | 7
Project Schedule
2/5 2/12 2/19 2/26 3/4 3 /11 3/18 3/25 4/1 4/8 4/15 4/22 4/29 5/5 5/12 5/19 5/26 6/2 6/9 6/16 6/23 6/30 7/7 7/14 7/21 7/28 Task 1: Kickoff Meeting and Project Coordination NTP X X X X X X Task 2: Pavement Condition Surveys
Task 3: Data Entry and PCI Calculation
Task 4: Quality Control Program
Task 5: M&R Strategies and Decision Tree X
Task 6: Budget Analysis and Annual Reports
Draft Report
City to Review
Final Report
Task 7: Training, Technical Support and Presentation
Assumptions
Assume NTP on week 2/5 and project kickoff meeting on week 2/12. "X" indicates meetings
Task 2 assumes no weather delays are anticipated; approx. 701 centerline miles streets will be inspected annually.
Assume first report will be delivered in Spring 2024 and second report in Spring 2026.
Assume detail project schedule on year 2 will be developed after discussion with the City.
Task Description Feb-24 Mar-24 Jul-24Apr-24 May-24 Jun-24 City of Sacramento
Pavement Condition Data Collection and Analysis (RFP No P24151621005) Revised January 2, 2024
Page | 8
Cost Estimate
($/hr) Hrs Cost ($) Hrs Cost ($) Hrs Cost ($) Hr s Cost ($) Hrs Cost ($) Hrs Cost ($) Hrs Cost ($) HOURS COST Margot Yapp Principal In Charge 125.53 2 251$ 12 1,506$ 24 3,013$ 38 4,770$ Mei-Hui Lee Project Manager 75.46 12 906$ 12 906$ 4 302$ 4 302$ 4 302$ 40 3,018$ 64 4,829$ 140 10,564$ James Signore QC Manager 91.65 8 733$ 4 367$ 8 733$ 4 367$ 16 1,466$ 40 3,666$ Sharlan Dunn Project Engineer 54.69 12 656$ 24 1,313$ 16 875$ 24 1,313$ 12 656$ 80 4,375$ 96 5,250$ 264 14,438$ Marvin Mann Senior Technician 27.31 40 1,092$ 16 437$ 56 1,529$ Jake Rajnowski Technician 26.52 144 3,819$ 144 3,819$ Rebecca Croston Technical Editor 38.46 8 308$ 8 308$ Melissa Clark Graphic Designer 55.16 32 1,765$ 32 1,765$ Terri Buckingham Clerical 29.71 4 119$ 2 59$ 12 357$ 18 535$ Estimated Total Direct Labor Hours/Costs 30 1,932$ 228 7,863$ 24 1,544$ 36 2,348$ 20 1,325$ 190 11,468$ 212 14,915$ 740 41,395$ FRINGE + OVERHEAD COST ( 201.75% ) 3,898$ 15,864$ 3,115$ 4,737$ 2,673$ 23,137$ 30,091$ TOTAL INDIRECT COSTS 5,830$ 23,727$ 4,659$ 7,085$ 3,998$ 34,605$ 45,006$ Marker geospatial (see attached for detailed breakdown) 450$
TOTAL ESTIMATED DIRECT COSTS
TOTAL LABOR, OVERHEAD AND DIRECT COSTS
FIXED FEE 10%
TOTAL COSTS BY TASK
Assumptions
Task 1 assumes one kickoff meeting and monthly progress meeting with City staff.
Task 2 includes approx. 701 miles of street network with automated surveys per year and includes condition survey training for City staff at no additional cost.
Tasks 5 and 6 include virtual meetings for pavement strategies and report discussion.
Small differences exist in totals due to rounding issues.
City of Sacramento
Pavement Condition Data Collection and Analysis (RFP No P24151621005) Cost Proposal - Detailed Cost Breakdown by Task (Year 1) 62,150$
Cost ($)
LABOR COSTS
DIRECT COSTS
Revised December 19, 2023
56,120$ 6,030$
Cost ($) Cost ($)
124,908$
215,000$
100$
6,523$ 95,780$ 11,868$ 7,904$ 4,508$ 38,420$ 5,930$ 87,072$ 10,789$ 7,185$
45,456$
4,546$
50,002$
19,545$ 593$ 8,707$ 1,079$ 719$ 410$ 3,493$ 4,098$ 34,927$
6,130$ 100$ 100$ 322$ 70,547$ Subconsultant Cost ($) Cost ($) Cost ($) Cost ($) Cost ($) 450$
100$ 322$
83,513$
PROJECT STAFF ROLE IN PROJECT
Hourly
Rate
1. Kickoff Meeting and
Project Coordination
2. Pavement Condition
Surveys
3. Data Entry and PCI
Calculation
4. Quality Control
Program
5. M&R Strategies and
Decision Tree
6. Budget Analysis and
Annual Reports TOTAL
7. Training, Technical
Support and
Presentation
195,455$
Travel
Reproduction & Supplies
6,940$ 6,940$
100$ 285$ 100$ 100$ 1,457$ 63,345$
City of Sacramento
Pavement Condition Data Collection and Analysis (RFP No P24151621005) Revised January 2, 2024
Page | 9
($/hr) Hrs Cost ($) Hrs Cost ($) Hrs Cost ($) Hrs Cost ($) Hrs Cost ($) Hrs Cost ($) HOURS COST Ken Huisman Project Manager 60.00 16 960$ 4 240$ 20 1,200$ Ausrine Kelbauskiene Data/Program Analys 39.50 28 1,106$ 34 1,343$ 62 2,449$ John Zimmer Field Survey Technici 42.00 230 9,660$ 2 84$ 232 9,744$ Raquel Huisman Administrative 20.00 5 100$ 1 20$ 6 120$ Estimated Total Direct Labor Hours/Costs -$ 279 11,826$ 41 1,687$ -$ -$ -$ 320 13,513$ FRINGE + OVERHEAD COST ( 225.00% ) -$ 26, 609$ 3,796$ -$ -$ -$ TOTAL INDIRECT COSTS -$ 38,435$ 5,483$ -$ -$ -$
TOTAL ESTIMATED DIRECT COSTS
TOTAL LABOR, OVERHEAD AND DIRECT COSTS
FIXED FEE 10%
TOTAL COSTS BY TASK
Assumptions
Task 2 assumes 701 miles of streets for automated survey and one-time mobilization. A minimum of 2 passes on all arterials with 4+ lanes, and 1 pass on residentials/locals and collectors.
City to provide a StreetSaver database and complete GIS street centerline or polygon map identifying streets for pavement inspection.
City of Sacramento
Pavement Condition Data Collection and Analysis (RFP No P24151621005) Cost Proposal - Marker Geospatial LLC Detailed Cost Breakdown by Task (Year 1) Revised December 19, 2023
LABOR COSTS
PROJECT STAFF ROLE IN PROJECT
Hourly
Rate
1. Kickoff Meeting and
Project Coordination
2. Pavement Condition
Surveys
3. Data Entry and PCI
Calculation
4. Quality Control
Program
5. M&R Strategies and
Decision Tree
6. Budget Analysis and
Annual Reports TOTAL
Cost ($) Cost ($) Cost ($)
30,404$
43,917$
DIRECT COSTS
Subconsultant Cost ($) Cost ($) Cost ($) Cost ($)
12,290$
Reproduction & Supplies 293$ 293$ Travel Costs & Onsite Expenditures - Automated Survey Vehicle 12,290$ 12,583$
51,018$ 5,483$ 56,500$ 12,583$ -$
5,650$
56,120$ 6,030$ 62,150$ 5,102$ 548$
City of Sacramento
Pavement Condition Data Collection and Analysis (RFP No P24151621005) Revised January 2, 2024
Page | 10
($/hr) Hrs Cost ($) Hrs Cost ($) Hrs Cost ($) Hrs Cost ($) Hrs Cost ($) Hrs Cost ($) Hrs Cost ($) HOURS COST Margot Yapp Principal In Charge 129.30 2 259$ 12 1,552$ 24 3,103$ 38 4,913$ Mei-Hui Lee Project Manager 77.72 12 933$ 12 933$ 4 311$ 4 311$ 2 155$ 40 3,109$ 60 4,663$ 134 10,415$ James Signore QC Manager 94.40 8 755$ 4 378$ 8 755$ 16 1,510$ 36 3,398$ Sharlan Dunn Project Engineer 56.33 12 676$ 24 1,352$ 16 901$ 24 1,352$ 8 451$ 80 4,506$ 96 5,408$ 260 14,646$ Marvin Mann Senior Technician 28.13 40 1,125$ 16 450$ 56 1,575$ Jake Rajnowski Technician 27.32 144 3,933$ 144 3,933$ Rebecca Croston Technical Editor 39.61 6 238$ 6 238$ Melissa Clark Graphic Designer 56.81 32 1,818$ 32 1,818$ Terri Buckingham Clerical 30.60 4 122$ 2 61$ 8 245$ 14 428$ Estimated Total Direct Labor Hours/Costs 30 1,990$ 228 8,098$ 24 1,590$ 36 2,418$ 10 606$ 188 11,734$ 204 14,929$ 720 41,365$ FRINGE + OVERHEAD COST ( 201.75% ) 4,015$ 16,338$ 3,208$ 4,878$ 1,223$ 23,673$ 30,119$ TOTAL INDIRECT COSTS 6,005$ 24,436$ 4,798$ 7,296$ 1,829$ 35,407$ 45,048$ Marker geospatial (see attached for detailed breakdown)
TOTAL ESTIMATED DIRECT COSTS
TOTAL LABOR, OVERHEAD AND DIRECT COSTS
FIXED FEE 10%
TOTAL COSTS BY TASK
Assumptions
Task 1 assumes one kickoff meeting and monthly progress meeting with City staff.
Task 2 includes approx. 701 miles of street network with automated surveys per year and includes condition survey training for City staff at no additional cost.
Tasks 5 and 6 include virtual meetings for pavement strategies and report discussion.
Task 5 assumes no changes on the decision tree. M&R records will be updated before conducting budget analysis.
Assume that a 3% inflation increase is applicable to both the labor hourly rate and direct costs in year 2.
Small differences exist in totals due to rounding issues.
Revised December 19, 2023
100$ 65,237$ 6,312$ 100$ 100$
6. Budget Analysis and
Annual Reports
Cost ($)
562$
562$ 72,817$ 406$ 7,149$
1,653$
Travel
19,764$
6,716$ 98,640$ 12,221$ 8,136$ 2,122$ 50,000$ 217,400$ 611$ 8,967$ 1,111$ 740$ 193$ 4,545$ 3,597$ 39,566$
6,105$ 89,673$ 11,110$ 7,396$ 1,929$ 45,454$ 197,638$ 35,969$ 7,149$
285$ 100$ 100$ 100$ 406$ Reproduction & Supplies 100$ Cost ($) Cost ($) Cost ($)
57,804$ 6,212$ 64,016$ Subconsultant Cost ($) Cost ($) Cost ($)
83,455$
124,820$
DIRECT COSTS
Cost ($)
City of Sacramento
Pavement Condition Data Collection and Analysis (RFP No P24151621005) Cost Proposal - Detailed Cost Breakdown by Task (Year 2)
LABOR COSTS
PROJECT STAFF ROLE IN PROJECT
Hourly
Rate
1. Kickoff Meeting and
Project Coordination
2. Pavement Condition
Surveys
3. Data Entry and PCI
Calculation
4. Quality Control
Program
5. M&R Strategies and
Decision Tree
7. Training, Technical
Support and
Presentation
TOTAL
City of Sacramento
Pavement Condition Data Collection and Analysis (RFP No P24151621005) Revised January 2, 2024
Page | 11
($/hr) Hrs Cost ($) Hrs Cost ($) Hrs Cost ($) Hrs Cost ($) Hrs Cost ($) Hrs Cost ($) HOURS COST Ken Huisman Project Manager 61.80 16 989$ 4 247$ 20 1,236$ Ausrine Kelbauskiene Data/Program Analys 40.69 28 1,139$ 34 1,383$ 62 2,522$ John Zimmer Field Survey Technici 43.26 230 9,950$ 2 87$ 232 10,036$ Raquel Huisman Administrative 20.60 5 103$ 1 21$ 6 124$ Estimated Total Direct Labor Hours/Costs -$ 279 12,181$ 41 1,738$ -$ -$ -$ 320 13,918$ FRINGE + OVERHEAD COST ( 225.00% ) -$ 27, 407$ 3,911$ -$ -$ -$ TOTAL INDIRECT COSTS -$ 39,588$ 5,649$ -$ -$ -$
TOTAL ESTIMATED DIRECT COSTS
TOTAL LABOR, OVERHEAD AND DIRECT COSTS
FIXED FEE 10%
TOTAL COSTS BY TASK
Assumptions
Task 2 assumes 701 miles of streets for automated survey and one-time mobilization. A minimum of 2 passes on all arterials with 4+ lanes, and 1 pass on residentials/locals and collectors.
City to provide a StreetSaver database and complete GIS street centerline or polygon map identifying streets for pavement inspection.
Assume that a 3% inflation increase is applicable to both the labor hourly rate and direct costs in year 2. 5,820$
57,805$ 6,213$ 64,016$ 5,255$ 565$
12,962$
52,550$ 5,649$ 58,196$ 12,962$ -$
12,659$
Reproduction & Supplies 303$ 303$ Cost ($) Cost ($) Cost ($)
Travel Costs & Onsite Expenditures - Automated Survey Vehicle 12,659$ 31,316$
45,234$
DIRECT COSTS
Subconsultant Cost ($) Cost ($) Cost ($) Cost ($)
3. Data Entry and PCI
Calculation
4. Quality Control
Program
5. M&R Strategies and
Decision Tree
6. Budget Analysis and
Annual Reports TOTAL
City of Sacramento
Pavement Condition Data Collection and Analysis (RFP No P24151621005) Cost Proposal - Marker Geospatial LLC Detailed Cost Breakdown by Task (Year 2) Revised December 19, 2023
LABOR COSTS
PROJECT STAFF ROLE IN PROJECT
Hourly
Rate
1. Kickoff Meeting and
Project Coordination
2. Pavement Condition
Surveys