Item 06 2025-00427 Contract Change Order - Southside Park Pool Renovation (L19706500)

Sacramento City Council
February 11, 2025

Document
Item 06 2025-00427 Contract Change Order - Southside Park Pool Renovation (L19706500)
Meeting
February 11, 2025
Body
Sacramento City Council
Pages
3
Original file
232 KB
Text extracted from the city's file for reading and search. Open the original on sacramento.granicus.com. That file is the official record.

City of Sacramento
City Council - 2PM Report
915 I Street Sacramento, CA 95814
www.cityofsacramento.org
File ID: 2025-00427 2/11/2025 Consent Item 6.

Contract Change Order: Southside Park Pool Renovation (L19706500) File ID: 2025-00427
Location: 2115 6th Street, District 4, Represented by Councilmember Pluckebaum Recommendation: Pass a Motion 1) authorizing the City Manager or the City Manager’s designee to execute Change Order No. 2 to City Agreement No. 2024-0823 with Dave Gross Enterprises Inc., dba Adams Pool Specialties in an amount not to exceed $85,273 for a new total not-to-exceed amount of $691,022; 2) ratifying the City Manager’s previously approved Change Order No. 1 to City Agreement 2024-0823; and 3) resetting the City Manager's authority to issue change orders for Contract No. 2024-0823.

Contact: Kevin Love, Program Manager, (916) 808-5592, [email protected]; James Christensen, Facilities Manager, (916) 808-5863, [email protected]; Department of Public Works
Presenter: None
Attachments:
1-Description/Analysis
2-Change Order No. 2- Dave Gross Enterprises Inc. dba Adams Pool Specialties Additional Description/Analysis
Issue Detail: In May 2024, the City Council awarded a contract to renovate the Southside Park Pool.

Additional issues with the pool were discovered during construction. Change Order No. 2 in the amount of $85,273 with Dave Gross Enterprises Inc. db a Adams Pool Specialties addresses these unforeseen issues identified during the preparation for the resurfacing of the pool. The perimeter drainage infrastructure, consisting of ductile iron pipe, has numerous leaks and has reached the end of its useful life expectancy. Additionally, the copper return lines, which are responsible for recirculating water back to the pool, have shown signs of advanced corrosion and degradation. The pool is anticipated to be open to the public for swim season 2025.

The copper lines are susceptible to leaks and failure due to prolonged exposure to chlorinated water

Page 1 of 3 ends

File ID: 2025-00427 2/11/2025 Consent Item 6.
and varying pH levels, which accelerate the corrosion process. Over time, pinhole leaks and joint failures have developed, leading to water loss and inefficient system operation. It was also discovered that the current system for disposing of backwashing chemical water needs to comply with modern environmental and operational standards.

The following corrective actions are proposed to address the identified issues: The perimeter drain line has extensive leaks due to the deterioration of ductile iron pipe, which has outlived its expected service life. Replacement involves removing and replacing the deteriorated ductile iron pipe with polyvinyl chloride (PVC) pipe, a high-strength thermoplastic material known for its durability and resistance to corrosion.

Simultaneously, copper return lines will be replaced with PVC lines to minimize potential leaks and improve system longevity.

The third recommended corrective action is rerouting backwash chemical water to the sanitary sewer system. The current method of disposing of backwash chemical water is outdated and poses environmental concerns. Redirecting this water to the sanitary sewer system will ensure compliance with regulatory requirements and enhance operational safety.

Policy Considerations: The recommendations in this report are in accordance with City Code Chapter 3.56= City Code requires contract revisions that add more than (10) percent of the original contract price shall require City Council to approve and ratify the change order previously issued by the City Manager, as per Title 3 Revenue and Finance Chapter 3.04.20.

Economic Impacts: The recommended Change Order is expected to create 0.63 jobs (0.40 direct job and 0.23 jobs through indirect and induced activities) and create $83,270 in total economic output ($53,378 of direct output and another $29,892 of output in indirect and induced activities).

Environmental Considerations:

California Environmental Quality Act (CEQA): The Community Development Department, Environmental Services Manager has reviewed the project and determined that the activity is exempt from the requirements of California Environmental Quality Act (CEQA) pursuant to CEQA Guidelines Section 15301. The project consists of the operation, repair, maintenance, and minor alteration of existing public structures, facilities, mechanical equipment, or topographical features involving negligible expansion of use beyond that existing at the time of the lead agency’s determination.

Sustainability: None
Commission/Committee Action: Not applicable

Page 2 of 3 ends

File ID: 2025-00427 2/11/2025 Consent Item 6.

Rationale for Recommendation: Approval of Change Order No. 2 in the amount of $85,273 with Dave Gross Enterprises Inc. dba Adams Pool Specialties, is necessary to complete the project.

Financial Considerations: Sufficient funding is available in the Southside Park Pool Repairs Project (L19706500) (Fund 2401, Measure U and Fund 3204, Park Development) to execute Change Order No. 2 in the amount of $85,273 and cover the remaining project costs.

Local Business Enterprise (LBE): Dave Gross Enterprises Inc. dba Adams Pool Specialties is an LBE.

Background: On May 28, 2024, the City Council passed a motion authorizing the City Manager to execute a contract with Dave Gross Enterprises Inc. dba Adams Pool Specialties in the amount of $594,921. The planned improvements involve removing the existing fiberglass finish, tiles, and other surfaces. The renovation will include installing new tiles, pool markings, depth markers, rope anchors, main drain covers, wall inlets and other fitting covers. All surfaces will be prepared for a new white plaster finish to ensure safety and functionality.

Change Order No.1 with Dave Gross Enterprises Inc. dba Adams Pool Specialties in the amount not to exceed $10,828 was executed on August 29, 2024, and provided for addressing excessive rust removal on the main drain line, elimination of the original pool ladders and replaced with wall steps and new handrails, and significant modifications to the Activity Pool Main Drain system. These changes, along with the credit for not replacing the existing gutter grates with new ones, will result in a vastly improved pool. Instead, the existing gutter grates will be cleaned, polished, and put back into place.

Page 3 of 3 ends

City of Sacramento

CHANGE ORDER

Contract #: 2024-0823 DATE: 06/04/2024 Budget #: L19706512 Purchase Order #: 0000075263 Change Order #: 2

TO: Dave Gross Enterprise Inc. dba Adams Pool Specialties Contract For: Southside Park Pool Renovation

Upon mutual acceptance of this document the City of Sacramento, hereinafter referred to as "City"' and your firm, hereinafter referred to a "Contractor", in accordance with the terms and conditions of the original contract documents, you are hereby directed to make the following change or changes for the consideration set forth below:

Description: This change request will compensate the contractor for unforeseen conditions to complete the project.

Additional Work: SEE ATTACHED EXHIBIT A

The original contract sum was $ 549,921.00
Net change by previous Change Orders $ 10,828.08 The contract sum prior to this Change Order was $ 605,749.08 The contract sum will be increased by this Change Order $ 85,273.00 New contract sum including all Change Orders $ 691,022.08

Contractor agrees that the amount of increase or decrease in the contract sum specified in this Change Order shall constitute full compensation for the work required by this Change Order, including but not limited to all compensation for the additional costs, if any, which may accrue to the Contractor by reason of any change in work schedules, other contract or cost of the project in any way made necessary by this Change Order. The time for performance of the contract will be extended by 0 working days to complete the project by reason of the performance of the work required by this Change Order. Except as herein above expressly provided, Contractor further agrees that the performance of the work specified in this Change Order or the rescheduling of the other project work made necessary by this Change Order, shall not constitute a delay which will extend the time limit for completion of the work as said term is used in the contract between the City and Contractor for the project.

Approval Recommended By: Approved By:

______________________________ ______________________________ Project Manager Date Matt Eierman Date Director, Public Works

Approved By: Approved By:

______________________________ ______________________________ Contractor Date City Clerk

Approved By:

______________________________
City Attorney

DESCRIPTION AMOUNT
C2024-0823 - Change Order #2
40,120.00$
45,153.00$
85,273.00$
Totals by Reason Changed/Unforeseen Conditions 40,120.00$ Changed to Bid Documents -$
Client Initiated Changes 45,153.00$
$594,921.00

1.82%

14.33%

16.15%
YES
2 Item(s) Total for Contract # C2023-1472
Original Contract
Percent of Original Contract, Previous:

Percent of Original Contract, this CO:

Total Change to Contract:

Council Approval Required:

PCO 009 Client Initiated Change - Gutter Grate Credit
This PCO compensates the contractor for rerouting backwash chemical water directly to the sanitary sewer system with new underground piping. The current method of disposing of backwash chemical water is outdated and poses environmental concerns.This payment, which is fair and just, shall constitute full compensation for this work, including materials, labor, equipment, and markups.

EXHIBIT A
Southside Park Pool Renovation
All changes to the scope are noted below and described further in the corresponding Proposed Change Order ("PCO").

PCO 007 Unforeseen Conditions - Leaking Deteriorated Drain and Return Lines
This PCO compensates the contractor for addressing the removal and replacement of deteriorated drain and return lines along the north, west and south perimeters of the pool. The east lines were addressed in Change Order #1. This payment shall constitute full compensation for this work, including materials, labor, equipment, and markups.