2026-00473 Approval of Americans with Disabilities Act (ADA) Public Right-of-Way Prospective Plan for Fiscal Year (FY) 2025/26

Sacramento City Council
March 3, 2026

Document
2026-00473 Approval of Americans with Disabilities Act (ADA) Public Right-of-Way Prospective Plan for Fiscal Year (FY) 2025/26
Meeting
March 3, 2026
Body
Sacramento City Council
Pages
3
Original file
396 KB
Text extracted from the city's file for reading and search. Open the original on sacramento.granicus.com. That file is the official record.

City of Sacramento
City Council - 2PM Report
915 I Street Sacramento, CA 95814
www.cityofsacramento.org
File ID: 2026-00473 3/3/2026
Approval of Americans with Disabilities Act (ADA) Public Right-of-Way Prospective Plan for Fiscal Year (FY) 2025/26
File ID: 2026-00473
Location: Citywide
Recommendation: Pass a Motion approving the Americans with Disabilities Act (ADA) Public Right- of-Way Prospective Plan for Fiscal Year (FY) 2025/26.

Contact: Cecilyn Foote, Associate Civil Engineer, (916) 808-6843, [email protected]; Jesse Gothan, Supervising Engineer, (916) 808-6897, [email protected]; Ofelia Avalos, Engineering Manager, (916) 808-5054, [email protected]; Department of Public Works Presenter: None
Attachments:
1-Description/Analysis
2-FY 2025/26 Americans with Disabilities Act (ADA) Public Right-of-Way Prospective Plan Description/Analysis
Issue Detail: The Barden Settlement Agreement requires the City to remove or ameliorate obstacles in the pedestrian right-of-way and to submit to the Barden Class Counsel an annual Prospective Plan of accessibility improvements.

The Barden, et al., v. City of Sacramento class action lawsuit was settled effective January 1, 2004.

A primary provision of the settlement agreement requires the City to expend an amount equal to twenty percent (20%) of its annual “Transportation Funds” (defined as eligible Measure A and Gas Tax funds) on removing or ameliorating obstacles in the public rights-of-way. The obligation under the Barden Settlement Agreement lasts 30 years from the above effective date.

Under the terms of the settlement agreement, the City agreed to submit to Barden’s Class Counsel a Prospective Plan each year specifying how the City is proposing to spend the Annual Obligation during the year. In compliance with the settlement agreement, staff prepared the FY 2025/26 ADA Prospective Plan for the City Council approval.

Page 1 of 3 ends

File ID: 2026-00473 3/3/2026
The City’s estimated FY 2025/26 Annual Obligation is approximately $6,989,000. The FY 2025/26 Prospective Plan expenditures are estimated to be $10,334,000.

Staff expects that every year there will be either an overage or a shortage in expenditures carried forward from the prior year. In past years, the City typically exceeded the Annual Obligation and carried an overage forward. The current ADA overage is over $3 million.

Policy Considerations: Implementation of the ADA accessibility programs and improvements is consistent with the City’s General Plan goal of providing an equitable, sustainable multimodal system that offers a range of viable and healthy travel choices for users of all ages, backgrounds, and abilities by improving walking connectivity and removing barriers.

Economic Impacts: None.

Environmental Considerations:

California Environmental Quality Act (CEQA): Approval of the FY 2025/26 Prospective Plan is not subject to the provisions of the California Environmental Quality Act (CEQA). Under CEQA General Rule 15061-B-3, CEQA applies only to projects which have the potential for causing a significant effect on the environment. This action will have no effect on the environment and, thus, is not subject to CEQA.

Prior to final approval, each individual project included in this prospective plan will be subject to environmental review in compliance with CEQA.

Sustainability: Implementation of the ADA accessibility programs, services and improvements is consistent with the sustainability goal of improving air quality by designing and constructing pedestrian ways that encourage walking and accommodate all users including persons with disabilities.

Commission/Committee Action: Staff presented and reviewed the FY 2025/26 Prospective Plan with the Disabilities Advisory Commission (DAC) on December 3, 2025. The DAC reviewed and accepted the prospective plan and appreciated the efforts of staff to incorporate accessibility improvements into projects.

Rationale for Recommendation: Approval of the Prospective Plan by the City Council is required under the terms of the Barden Settlement Agreement.

Financial Considerations: The estimated value of the FY 2025/26 Prospective Plan for Accessibility Improvements in the Public Rights-of-Way is $10,334,000.

The FY 2025/26 ADA Prospective Plan is being funded through the following capital improvement

Page 2 of 3 ends

File ID: 2026-00473 3/3/2026
projects and programs:

Program Estimated Expense
Accessibility Program FY20 (T15200600) $2,000,000
Transportation Corridor Improvements FY20 (R15200000) $1,736,000 Active Transportation Program (T15180400) $ 111,000
Fong Ranch Road Pedestrian Crossing (S15120500) $ 113,000 Pedestrian Crossing Enhancements 2025 (S15120500) $ 796,000 Auburn Boulevard Bridge Replacement (T15145300) $ 439,000 Franklin Boulevard Complete Streets Phases 1 & 2 (T15165500) $4,000,000 Jackrabbit Trail Crossing (T15225500*) $ 700,000
Vision Zero School Safety (T15235600**) $ 439,000
$10,334,000
*Funds have already been expended as construction is underway or completed. **Construction funds will be added to the project budget after authorization by Caltrans.

Local Business Enterprise (LBE): Not applicable.

Page 3 of 3 ends

FY 2025/26 Prospective Plan
For Accessibility Improvements in the Public Rights-of-Way

Program Area Description of Accessibility Work Estimate

Curb Ramps, Detectable Warning
Tiles, and Sidewalk

Curb ramps, detectable warning tiles,
barrier removals, and other accessibility
work associated with Street Overlays,
Sidewalk Repairs and Drain Inlet
Upgrades. Estimated 35 curb ramps.

$2,291,000

Citizen Requests

Citizen requests related to curb ramps,
truncated domes, crosswalks, audible
signals, and other barrier eliminations
along class members’ daily path of travel.

Estimated 8 curb ramps.

$300,000

Audible Signals Phase 2

Installation of audible signals.

$1,256,000

Specific Capital Improvement
Projects with Accessibility
Features

(List Attached)

Accessibility features (Curb Ramps,
Crosswalks, Pedestrian Signals,
Pedestrian Islands, Sidewalks, Bulb Outs,
etc.) constructed as part of other projects
for overall efficiency of project work.

$6,487,000

TOTAL ESTIMATED COSTS

$10,334,000

Specific Capital Improvement Projects with Accessibility Features Included in FY 2025/26 Prospective Plan

CIP No.

Project Name

Project Description

Estimated
Cost

S15120510

Fong Ranch Road Pedestrian
Crossing

Construct curb ramps and pedestrian
refuge islands, place truncated domes,
and install high visibility crosswalk.

$113,000

S15120511

Pedestrian Crossing
Enhancements - 2025

Construct curb ramps, place truncated
domes, and install rectangular rapid
flashing beacons.

$796,000

T15145300

Auburn Boulevard Bridge
Replacement

Construct sidewalk, curb and gutter,
curb ramps, driveways, and median cut-
through, place truncated domes, and
install audible pedestrian signals.

$439,000

T15165500

Franklin Boulevard Complete
Street – Phases 1 & 2

Construct sidewalk, curb and gutter,
curb ramps, and driveways, place
truncated domes, and install rectangular
rapid flashing beacons, audible
pedestrian signals, and marked
crosswalks.

$4,000,000

T15225500

Jackrabbit Trail Crossing

Construct sidewalk, curb and gutter,
curb ramps, and median cut-through,
place truncated domes, and install
pedestrian signal and marked
crosswalk.

$700,000

T15235600

Vision Zero School Safety

Construct sidewalk, curb and gutter, and
curb ramps, place truncated domes, and
install rectangular rapid flashing
beacons, audible pedestrian signals,
and marked crosswalks.

$439,000

TOTAL ESTIMATED CIP COSTS $6,487,000