Pedestrian Crossing Enhancements, Project No. 9188, Federal Project HSIPL‐5045(035) Item # Item Description Quantity Measure Unit Price Item Total Unit Price Item Total Unit Price Item Total Unit Price Item Total Unit Price Item Total Unit Price Item Total 1 Mobilization, Demobilization and Final Clean Up (All
Locations) 1L S $ 60,000.00 $ 60,000.00 $ 102,000.00 $ 102,000.00 $ 49,000.00 $ 49,000.00 $ 69,196.00 $ 69,196.00 $ 115,000 .00 $ 115,000.00 $ 38,900.00 $ 38,900.00 2 Temporary Traffic Control and Construction Area; Complete-In- Place (All Locations) 1L S $ 80,000.00 $ 80,000.00 $ 101,200.00 $ 101,200.00 $ 100,000.00 $ 100,000.00 $ 90,000.00 $ 90,000.00 $ 75,000. 00 $ 75,000.00 $ 88,500.00 $ 88,500.00 3 Furnish and Install Storm Water Pollution Control Plan; Complete-In-Place (All Locations) 1L S $ 5,000.00 $ 5,000.00 $ 10,020.00 $ 10,020.00 $ 4,500.00 $ 4,500.00 $ 5,000.00 $ 5,000.00 $ 25,000.00 $ 25,000.00 $ 3,424.00 $ 3,424.00 4 Remove and Install Pavement Markings; Complete 1 LS $11,000 $11,000 $ 19,640.00 $ 19,640.00 $ 24,000.00 $ 24,000.00 $ 24,000.00 $ 24,000.00 $ 11,900.00 $ 1 1,900.00 $ 135,000.00 $ 135,000.00 5 Furnish and Install, Traffic Signal, All Signs, Poles, posts, and Electrical Systems; Complete-In- Place 1L S $240,000 $240,000 $ 180,900.00 $ 180,900.00 $ 232,500.00 $ 232,500.00 $ 214,000.00 $ 214,000.00 $ 305,000.00 $ 305,000. 00 $ 244,130.00 $ 244,130.00 6 Furnishing and Installing Fiber Optic Cable System; Complete- In-Place 1L S $140,000 $140,000 $ 108,986.00 $ 108,986.00 $ 107,000.00 $ 107,000.00 $ 107,000.00 $ 107,000.00 $ 75,000.00 $ 75,00 0.00 $ 130,200.00 $ 130,200.00 7 Remove Existing Concrete Sidewalk, Curb, Gutter and AC Median 1645 SF $10 $16,450 $ 10.00 $ 16,450.00 $ 8.00 $ 13,160.00 $ 25.00 $ 41,125.00 $ 10.0 0 $ 16,450.00 $ 8.22 $ 13,521.90 8 Remove and Replace Asphalt Concrete and Aggregate Base (1' Depth) 58 SF $45 $2,610 $ 35.00 $ 2,030.00 $ 50.00 $ 2,900.00 $ 115.00 $ 6,670.00 $ 65.0 0 $ 3,770.00 $ 40.36 $ 2,340.88 9 Minor Concrete (Curb) (Salinas Std Plan No. 1, Type A) 323 LF $50 $16,150 $ 59.00 $ 19,057.00 $ 55.00 $ 17,765.00 $ 48.00 $ 15,504.00 $ 50.00 $ 16,150.00 $ 53.09 $ 17,148.07 10 Minor Concrete (Curb and Gutter) (Salinas Std Plan No. 1, Type C) 29 LF $60 $1,740 $ 64.00 $ 1,856.00 $ 50.00 $ 1,450.00 $ 250.00 $ 7,250.00 $ 125.00 $ 3,625.00 $ 64.14 $ 1,860.06 11 Minor Concrete (Median Hardscape) 3864 SF $15 $57,960 $ 12.00 $ 46,368.00 $ 20.00 $ 77,280.00 $ 18.00 $ 69,552.00 $ 25.00 $ 96,600.00 $ 20.23 $ 78,168.72 12 Curb Ramp (Caltrans Std Case Modify Passageway) 182 SF $40 $7,280 $ 17.00 $ 3,094.00 $ 30.00 $ 5,460.00 $ 60.00 $ 10,920.00 $ 25.0 0 $ 4,550.00 $ 48.39 $ 8,806.98 13 Curb Ramp (Caltrans Std Case B Modified) 247 SF $40 $9,880 $ 15.00 $ 3,705.00 $ 60.00 $ 14,820.00 $ 48.00 $ 11,856.00 $ 40.00 $ 9,880.00 $ 44.53 $ 10,998.91 14 Retaining Wall (Caltrans Std Type 6A) 14 LF $580 $8,120 $ 170.00 $ 2,380.00 $ 800.00 $ 11,200.00 $ 2,020.00 $ 28,280.00 $ 70.00 $ 980.00 $ 579.88 $ 8,118.32 15 Remove and Install Pavement Markings (Complete) 1 LS $8,000 $8,000 $ 12,930.00 $ 12,930.00 $ 16,000.00 $ 16,000.00 $ 16,000.00 $ 16,000.00 $ 6,440.00 $ 6,440.00 $ 8,606.00 $ 8,606.00 16 Furnish and Install, RRFBs, All Signs, Poles, Posts, and Electrical Systems; Complete-in-Place 1L S $120,000 $120,000 $ 98,255.00 $ 98,255.00 $ 108,000.00 $ 108,000.00 $ 100,000.00 $ 100,000.00 $ 111,111.00 $ 111,11 1.00 $ 120,545.00 $ 120,545.00 17 Remove Sidewalk, Curb and Gutter 123 SF $25 $3,075 $ 21.00 $ 2,583.00 $ 30.00 $ 3,690.00 $ 56.00 $ 6,888.00 $ 12. 00 $ 1,476.00 $ 20.01 $ 2,461.23 18 Remove and Replace Asphalt Concrete and Aggregate Base 16 SF $90 $1,440 $ 51.00 $ 816.00 $ 65.00 $ 1,040.00 $ 313.00 $ 5,008.00 $ 135.0 0 $ 2,160.00 $ 123.09 $ 1,969.44 19 Hot Mix Asphalt (Type A) 3643 SF $10 $36,430 $ 8.00 $ 29,144.00 $ 10.00 $ 36,430.00 $ 14.00 $ 51,002.00 $ 20.0 0 $ 72,860.00 $ 10.36 $ 37,741.48 20 Minor Concrete (Curb) (Salinas Std Plan No. 1, Type A) 1262 LF $40 $50,480 $ 57.00 $ 71,934.00 $ 55.00 $ 69,410.00 $ 50.00 $ 63,100.00 $ 30.00 $ 37,860.00 $ 43.74 $ 55,199.88 21 Curb Ramp (Caltrans Std Modify Passageway) 121 SF $45 $5,445 $ 28.00 $ 3,388.00 $ 30.00 $ 3,630.00 $ 90.00 $ 10,890.00 $ 40.0 0 $ 4,840.00 $ 56.78 $ 6,870.38 22 Curb Ramp (Caltrans Std Case C Modified) 103 SF $50 $5,150 $ 44.00 $ 4,532.00 $ 60.00 $ 6,180.00 $ 96.00 $ 9,888.00 $ 40. 00 $ 4,120.00 $ 41.81 $ 4,306.43 23 Remove and Install Pavement Markings (Complete) 1 LS $9,000 $9,000 $ 22,780.00 $ 22,780.00 $ 22,000.00 $ 22,000.00 $ 22,000.00 $ 22,000.00 $ 7,000.00 $ 7,000.00 $ 29,800.00 $ 29,800.00 24 Furnish and Install, RRFBs, All Signs, Poles, Posts, and Electrical Systems; Complete-In-Place 1L S $44,000 $44,000 $ 45,600.00 $ 45,600.00 $ 49,500.00 $ 49,500.00 $ 43,000.00 $ 43,000.00 $ 45,000.00 $ 4 5,000.00 $ 37,580.00 $ 37,580.00 25 Remove and Install Pavement Markings (Complete) 1 LS $2,200 $2,200 $ 7,930.00 $ 7,930.00 $ 9,000.00 $ 9,000.00 $ 9,000.00 $ 9,000.00 $ 9,800.00 $ 9,800.00 $ 2,426.00 $ 2,426.00 26 Furnish and Install, RRFB, All Signs, Poles, Posts, and Electrical Systems; Complete-In-Place 1L S $50,000 $50,000 $ 42,400.00 $ 42,400.00 $ 35,250.00 $ 35,250.00 $ 29,800.00 $ 29,800.00 $ 33,000.00 $ 3 3,000.00 $ 62,148.00 $ 62,148.00 27 Remove and Install Pavement Markings (Complete) 1 LS $10,000 $10,000 $ 12,580.00 $ 12,580.00 $ 13,000.00 $ 13,000.00 $ 13,000.00 $ 13,000.00 $ 6,300.00 $ 6,300.00 $ 11,127.00 $ 11,127.00 28 Furnish and Install, RRFB, All Signs, Poles, Posts, and Electrical Systems; Complete-In-Place 1L S $44,000.00 $44,000 $ 39,700.00 $ 39,700.00 $ 32,750.00 $ 32,750.00 $ 29,400.00 $ 29,400.00 $ 33,000.00 $ 33,000.00 $ 54,128.00 $ 54,128.00 29 Remove and Install Pavement Markings (Complete) 1 LS $9,000 $9,000 $ 9,740.00 $ 9,740.00 $ 12,000.00 $ 12,000.00 $ 12,000.00 $ 12,000.00 $ 3,500.00 $ 3,500.00 $ 19,700.00 $ 19,700.00 30 Furnish and Install, RRFB, All Signs, Poles, Posts, and Electrical Systems; Complete-In-Place 1L S $42,000 $42,000 $ 36,100.00 $ 36,100.00 $ 34,275.00 $ 34,275.00 $ 29,400.00 $ 29,400.00 $ 33,000.00 $ 3 3,000.00 $ 50,190.00 $ 50,190.00 Bid Opening: 9/9/21 2:00pm
Base Bid
Location 6 – Wood Street
Precision Grade Inc. Granite Rock Company Granite Construction 1,058,098.00 1,113,190.00 1,150,729.00 1,285,916.68Bid Total (Items 1-30) (For Comparison Only) 1,096,410.00 1,170,372.00 Alfaro Communications
Construction Inc.
Norcal Contractor
PROJECT MANAGER: Andrew Easterling, P.E.
Engineer's Estimate
Location 1 – North Sanborn Road
Location 2 – Pacheco Street
Location 3 – West Laurel Drive
Location 4 – East Laurel Drive
Location 5 - Iverson Street
1 of 1 I:\PWTra\Construction Projects\9188 Pedestrian Crossing Enhancements\Bid\Bid 2\Preliminary 9188 BidTab