Cost Estimate for Site Closure Activities
August 25, 2021
Mr. Brian Frus
Senior Civil Engineer,
City of Salinas
200 Lincoln Avenue
Salinas, CA 93901
Subject: Cost Estimate for Case Closure Activities
Lamar Building and Melody Lane LUFT Sites, Salinas, CA
Dear Mr. Frus:
We are writing to provide you with a proposal and cost estimate to complete the activities needed to achieve regulatory case closure for the two leaking underground storage tank sites in downtown Salinas. As you know th e Regional Water Quality Control Board (RWQCB) in their letter dated June 7, 2021, indicated that they have no further requirements for investigation and cleanup and will close the cases once the mon itoring wells have been properly destroy ed and all investigation- derived wastes have been removed and properly disposed of.
Our proposed workscope consists of the following tasks:
1. Task 1 – Permitting and Project Coordination: This will involve obtaining Monter ey County well destruction permits for the thirteen monitoring wells along with City of Salinas encroachment permits for the wells located in City right of way. The well locations will be marked for Underground Service Alert utility locating. We will coordinate the destruction work with contactors, agencies and affected private parties.
2. Task 2 – Well Destruction: The thir teen monitoring wells will be destroyed by a combination of overdrill and pressure grouting methods as dictated by Monterey County.
Three locations will require traffic control.
3. Task 3 – Waste Removal: All investigation -derived waste including drill cuttings, purge water and gasoline product will be profiled and transported to properly licensed facilities for disposal or recycling.
4. Task 4 – Reporting: The results of the activities will be reported to the RWQCB
Our estimated budget to complete these activities is approximately $78,000. Exhibit A, attached, provides detail on the anticipated costs.
EXHIBIT A
ESTIMATED BUDGET
WELL DESTRUCTION
Salinas - Lamar Melody
Salinas, CA
TASK 1
1.1 Monterey County Health Dept - Well Destruction Permits 7,306$
1.2 City of Salinas Development Engineering (PW) Encroachment Permits 8,000$
1.3 Ground Zero Personnel
Registered Geologist 180.00$ per hour 4 hours 720$ Senior Geologist 150.00$ per hour 15 hours 2,250$ Senior Geologist 150.00$ per hour 8 hours 1,200$
Project Coordinator 100.00$ per hour 15 hours 1,500$ Subtotal 5,670$
1.4 Materials and Equipment
Measuring Wheel 10.00$ per day 1 day 10$
Misc USA Marking Supplies 20.00$ per each 1 each 20$ Mileage 0.56$ per mile 220 miles 123$
Subtotal 153$
TASK 1 TOTAL 21,129$
TASK 2 WELL DESTRUCTION
2.1 Contractors
Drilling Subcontractor - Cascade Drilling (5 Days) 25,677$ Subtotal 25,677$
2.2 Ground Zero Personnel
Registered Geologist 180.00$ per hour 8 hours 1,440$ Senior Geologist 150.00$ per hour 55 hours 8,250$ Subtotal 9,690$
2.3 Traffic Control Plan & Traffic Control (3 Areas)
Area 1 - MW13 & MW24 3,246.00$ per area 1 area 3,246$ Area 2 - MW12 688.00$ per area 1 area 688$
Area 3 - MW20 688.00$ per area 1 area 688$
Subtotal 4,622$
2.4 Materials and Equipment
Water Level Probe 33.00$ per day 5 days 165$
Per Diem (mileage, hotel, meals) 192.00$ per day 5 days 960$ Porta-potty 730.00$ per rental 1 rental 730$
Miscellaneous 33.00$ per day 5 days 165$
Subtotal 2,020$
TASK 2 TOTAL 42,009$
PROJECT PLANNING, COORDINATION, PERMITTING, SITE CLOSURE ACTIVITIES AND
REGULATORY LIAISON
EXHIBIT A
ESTIMATED BUDGET
WELL DESTRUCTION
Salinas - Lamar Melody
Salinas, CA
TASK 3 WASTE DISPOSAL
3.1 Ground Zero Personnel
Senior Technician 100.00$ per hour 10 hours 1,000$ Mileage 0.56$ per mile 220 miles 123$
Subtotal 1,123$
3.2 Laboratory Analysis
LUFT 5 50.00$ per sample 2 samples 100$
8260 (incl TPHg) 105.00$ per sample 2 samples 210$ Diesel 47.00$ per sample 2 samples 94$
Subtotal 404$
3.3 Free Product, Soil & Water Disposal
Instrat, Inc. - Water and Soil 2,200.00$ total 1 event 2,200$ Instrat, Inc. - Free Product 2,200.00$ total 1 event 2,200$ Subtotal 4,400$
TASK 3 TOTAL 5,927$
TASK 4 WELL DESTRUCTION REPORT PREPARATION (Geotracker Upload)
4.1 Ground Zero Personnel
Registered Geologist 180.00$ per hour 2 hours 360$ Senior Geologist 150.00$ per hour 8 hours 1,200$
Draftsperson 95.00$ per hour 2 hours 190$
Project Coordinator 100.00$ per hour 2 hours 200$ TASK 4 TOTAL 1,950$
10% CONTINGENCY $7,102
TOTAL ESTIMATED COST 78,117$