AWP ACIP DATA SHEET 28 Sep 2020
Airport Name Salinas Municipal Airport Fiscal Year 2024 Shown On
ALP
Project
Type*
Project Description
Federal
Share
Local
Share
Total
Y D Construction - Taxilane Pavement Rehabilitation
Hangars R and K (Same grant as Twy B)
Construction - Taxilane Pavement Rehabilitation
Hangars L (Same grant as Twy B)
Construction - Taxilane Pavement Rehabilitation
Hangars O (Same grant as Twy B)
Construction - Taxilane Pavement Rehabilitation
Hangars Q (Same grant as Twy B)
Construction - Taxilane Pavement Rehabilitation
Hangars S (Same grant as Twy B)
Construction - Taxilane Pavement Rehabilitation
Hangars T (Same grant as Twy B)
Construction - Taxiway B Pavement Rehabilitation
(Same grant as Taxilane)
885,000
683,100
683,100
683,100
683,100
683,100
243,000
88,500
75,900
75,900
75,900
75,900
75,900
27,000
973,500
759,000
759,000
759,000
759,000
759,000
270,000
* D - Development; P - Planning; E – Environmental
PROVIDE THE FOLLOWING DETAILED INFORMATION FOR PROJECTS ANTICIPATED WITHIN 1-2 YEARS Detail Project Description (Square/Lineal Footage or Length/Width, Location identifier, e.g., RW ##, TW ##, Bldg #, Apron #) Construct approximately 458,000 SF of pavement rehabilitation of taxilane pavement. Work will include crack seal, seal coat, minor removal and replacement of specific pavement areas, and re-marking the improvements. (2017 APMS PCI ranges between 34 and 78). Work will include partial 3" mill and overlay, partial full depth reconstruction, partial crack seal and seal coat, and re-marking the improvements.
Construct approximately 385,000 SF of pavement rehabilitation of the Taxiway B. Work will include crack seal, seal coat, and re-marking the improvements.
Project Schedule (Anticipated date for bids or negotiated prices, consultant selection for planning or environmental projects, length of construction or design, planning or environmental process) Project to bid Q1 2024
Construction start August 2024
Anticipated grant closeout prior to March 2025
NEPA Environmental Status (With grant application include copy of ROD, FONSI or CATEX letter of approval) CATEX to be submitted 2022, revalidated in 2023
Land Title Status & Date of Exhibit "A" Status Date
Exhibit A Property Map was approved on 11/23/2010
Open AIP Funded Projects (include grant number and grant description) Expected Close-out Date AIP 3-06-0206-028: Rehabilitate 8/26 - December 2021
AIP 3-06-0206-029: ALCMS - December 2021
AIP 3-06-0206-030: AMPU - March 2023
Certification: To the best of my knowledge and belief, all information shown in the ACIP Data Sheet is true and correct and had been duly authorized by the Sponsor.
Brett Godown, Airport Manager, (831) 758-7214