BID TABULATION
Cesar Chavez Park Soccer Field; Project No. 9005
Drawing No. 8250
Item # Item Description Unit of Measure Quantity Unit Price Item Total Unit Price Item Total Unit Price Item Total Unit Price Item Total 1 Construction Coordination/Mobilization LS 1 $71,454.00 $71,454.00 $6,700.00 $6,700.00 $124,500.00 $124,500.00 $185,000.00 $185,000.00 2 SWPPP Development LS 1 $5,000.00 $5,000.00 $24,500.00 $24,500.00 $1,200.00 $1,200.00 $24,000.00 $24,000.00 3 SWPPP Implementation LS 1 $10,000.00 $10,000.00 $14,500.00 $14,500.00 $52,300.00 $52,300.00 $37,756.97 $37,756.97 4 Clear and Grub entire Area SF 140000 $0.25 $35,000.00 $0.11 $15,400.00 $0.95 $133,000.00 $0.89 $124,600.00 5 Demolish/Salvage Irrigation LS 1 $3,000.00 $3,000.00 $17,600.00 $17,600.00 $34,400.00 $34,400.00 $15,927.47 $15,927.47 6 Miscellaneous Demolition LS 1 $3,000.00 $3,000.00 $2,500.00 $2,500.00 $7,100.00 $7,100.00 $15,433.20 $15,433.20 7 Off Haul/Excavation – Turf Field CY 1500 $40.00 $60,000.00 $36.56 $54,840.00 $61.00 $91,500.00 $23.15 $34,725.00 8 Off Haul/Excavation – Trench CY 150 $40.00 $6,000.00 $47.19 $7,078.50 $170.00 $25,500.00 $37.79 $5,668.50 9 Survey Staking SF 67000 $0.60 $40,200.00 $0.13 $8,710.00 $0.22 $14,740.00 $1.22 $81,740.00 10 Rough Grading CY 1350 $40.00 $54,000.00 $26.90 $36,315.00 $56.00 $75,600.00 $6.54 $8,829.00 11 Soil Stabilization (Lime Treated) SF 62000 $2.25 $139,500.00 $1.73 $107,260.00 $2.00 $124,000.00 $1.12 $69,440.00 12 Fine Grading SF 67000 $0.50 $33,500.00 $0.55 $36,850.00 $0.76 $50,920.00 $0.66 $44,220.00 13 Turf Field Base Rock – Class 2 (3” depth) TN 865 $55.00 $47,575.00 $84.83 $73,377.95 $80.00 $69,200.00 $50.64 $43,803.60 14 Trench Rock TN 250 $60.00 $15,000.00 $158.69 $39,672.50 $108.00 $27,000.00 $69.67 $17,417.50 15 Impermeable Liner SF 62000 $0.25 $15,500.00 $0.48 $29,760.00 $0.50 $31,000.00 $1.52 $94,240.00 16 Synthetic Turf and Infill SF 62000 $8.00 $496,000.00 $5.72 $354,640.00 $4.55 $282,100.00 $13.70 $849,400.00 17 Performance Pad SF 62000 $1.50 $93,000.00 $2.09 $129,580.00 $1.85 $114,700.00 $4.88 $302,560.00 18 Perimeter Curb with Nailer LF 1030 $25.00 $25,750.00 $38.73 $39,891.90 $69.50 $71,585.00 $42.78 $44,063.40 19 Turf – Hydroseed SF 73425 $0.35 $25,698.75 $1.21 $88,844.25 $1.00 $73,425.00 $0.84 $61,677.00 20 Bioretention Planting with Pea Gravel SF 5500 $6.00 $33,000.00 $5.79 $31,845.00 $4.80 $26,400.00 $5.97 $32,835.00 21 Split Rail Fence (At Bioretention Area) LF 140 $50.00 $7,000.00 $253.50 $35,490.00 $200.00 $28,000.00 $53.83 $7,536.20 22 Adjust Existing Utility Boxes in Field LS 1 $2,560.00 $2,560.00 $1,500.00 $1,500.00 $1,500.00 $1,500.00 $441.60 $441.60 23 Irrigation SF 73425 $1.00 $73,425.00 $1.21 $88,844.25 $1.00 $73,425.00 $2.32 $170,346.00 24 8” Plastic Perforated Pipe LF 810 $65.00 $52,650.00 $15.59 $12,627.90 $32.00 $25,920.00 $65.66 $53,184.60 25 Plastic Pipe (8” HDPE) LF 141 $95.00 $13,395.00 $75.03 $10,579.23 $133.00 $18,753.00 $72.96 $10,287.36 26 Cleanout EA 7 $150.00 $1,050.00 $500.00 $3,500.00 $735.00 $5,145.00 $2,460.00 $17,220.00 27 Storm Drain Pipe (12” RCP) LF 42 $250.00 $10,500.00 $76.47 $3,211.74 $230.00 $9,660.00 $95.26 $4,000.92 28 Bubbler Box EA 3 $4,200.00 $12,600.00 $2,600.00 $7,800.00 $2,650.00 $7,950.00 $2,336.86 $7,010.58 29 Overflow Inlet EA 1 $4,800.00 $4,800.00 $3,800.00 $3,800.00 $6,650.00 $6,650.00 $8,215.30 $8,215.30 30 Type “A” SDMH EA 1 $10,800.00 $10,800.00 $13,100.00 $13,100.00 $22,650.00 $22,650.00 $4,351.20 $4,351.20 31 Off Haul/Excavation – Bioretention Area CY 653 $100.00 $65,300.00 $69.20 $45,187.60 $60.00 $39,180.00 $6.66 $4,348.98 32 Bioretention Soil Mix (24” depth) CY 190 $80.00 $15,200.00 $168.72 $32,056.80 $243.00 $46,170.00 $81.62 $15,507.80 33 Class 2 Permeable Material (22” depth) CY 174 $70.00 $12,180.00 $196.45 $34,182.30 $217.00 $37,758.00 $28.48 $4,955.52 34 Cobblestone Energy Dissipater CY 6 $150.00 $900.00 $990.00 $5,940.00 $1,530.00 $9,180.00 $1,256.79 $7,540.74 35 Relocate Lighting/Electrical Facilities including Conduit with Conductors (2 Conduits) and pull boxes LS 1 $6,000.00 $6,000.00 $39,000.00 $39,000.00 $42,750.00 $42,750.00 $35,526.34 $35,526.34 $1,500,537.75 $1,456,684.92 $1,804,861.00 $2,443,809.78 Granite Rock Company
5225 Hellyer Avenue, Suite 220
San Jose, CA 95138
408‐574‐1400
Norcal Contractor
260 Espinosa Road
Salinas, CA 93907
831‐238‐1513
Bid awarded on ________, 2023 by Salinas City Council by Resolution No.____________ (NCS) to ________ for the sum of $___________ for Items ___________. All other bids were rejected and bid bonds returned.
Dated this ___ day of _____, 2023.
_____________________________________________
City Clerk
Bid Opening: 4/07/2023 @ 2:00 PM, Electronic
Project Engineer: Elise Ramirez, P.E. Landscape Pros ML Inc Cupertino, CA 95014
408‐920‐7718
Project Coordinator: Josie Lantaca 20432/5B Silverado Avenue PROPOSAL ITEMS:
Engineer's Estimate
Total Bid (Items 1‐35)(For Comparison Only)
1 of 2 J:\p\9005 Cesar Chavez Park Soccer Field\Bid Documents\90 05 Bid Tab BID TABULATION
Cesar Chavez Park Soccer Field; Project No. 9005
Drawing No. 8250
Granite Rock Company
5225 Hellyer Avenue, Suite 220
San Jose, CA 95138
408‐574‐1400
Norcal Contractor
260 Espinosa Road
Salinas, CA 93907
831‐238‐1513
Bid Opening: 4/07/2023 @ 2:00 PM, Electronic
Project Engineer: Elise Ramirez, P.E. Landscape Pros ML Inc Cupertino, CA 95014
408‐920‐7718
Project Coordinator: Josie Lantaca 20432/5B Silverado Avenue Engineer's Estimate
8. BIDDER'S STATEMENT OF SUBCONTRACTORS PART II
ITEMS TO BE SUBMITTED WITH PROPOSAL ON BID OPENING DATE:
4. INSURANCE CERTIFICATION YES YES Incomplete
5. NON‐COLLUSION DECLARATION OF CONTRACTOR YES YES Incomplete
6. BIDDER'S STATEMENT OF SUBCONTRACTORS PART 1 YES YES YES
YES
YES
YES
YES
YES
YES
YES
1. FULLY COMPLETED & SIGNED PROPOSAL FORM Incomplete
3. BIDDER'S STATEMENT OF FINANCIAL RESPONSIBILITY, TECHNICAL ABILITY, AND EXPERIENCE ITEMS TO BE SUBMITTED BY LOWEST BIDDER AND SECOND LOWEST BIDDER WITHIN 5 WORKING DAYS AFTER BID OPENING DATE:
Incomplete
2. BIDDER'S BOND NO
Incomplete
7. ADDENDUM NO. 1 YES
9. NON‐COLLUSION DECLARATION OF SUB‐CONTRACTOR
11. BIDDER'S LIST FOR THE CITY OF SALINAS PUBLIC WORKS DEPARTMENT
10. BIDDER'S STATEMENT OF GOOD FAITH EFFORT FOR LOCAL HIRE 2 of 2 J:\p\9005 Cesar Chavez Park Soccer Field\Bid Documents\90 05 Bid Tab