CITY OF SALINAS REQUEST FOR PROPOSAL – CEASAR CHAVEZ PARK DG PATH
January 2022 Page 43 of 70
ATTACHMENT D – PRICING PROPOSAL FORM
CESAR CHAVEZ PARK DG PATH
The work shall involve the furnishing of all labor, material, equipment, and incidentals to perform the construction of a decomposed granite path in Cesar Chavez Park in accordance with the Plan, Specifications and Special Provisions.
PROPOSAL ITEMS:
BASE BID
ITEM
NO. ITEM DESCRIPTION APPROX
QTY UNIT UNIT PRICE TOTAL
1 Mobilization 1 LS $27,883.00 $27,883.00
2 Construction Area Signs 1 LS $3,075.00 $3,075.00
3 Clearing and Grubbing 1 LS $19,640.00 $19,640.00
4 Construction Site Management 1 LS $17,410.00 $17,410.00 5 Construction Surveys and Staking 1 LS $12,835.00 $12,835.00 6 Remove existing DG Path 34,830 SF $2.40 $83,592.00
7 Construct 10’ DG Path 36,080 SF $9.00 $324,720.00
8 Minor Concrete (Sidewalk) 300 SF $27.00 $8,100.00
9 Construct 6’ DG Path 7,690 SF $11.00 $84,950.00
10 Remove and Replace 7’ x 14’ DG Bench Pad 5 EA $1,845.00 $9,225.00 11 Construct 6’ x 10’ Exercise Pad (location to be
field located) 6 EA $1,845.00 $11,070.00
BASE BID TOTAL $602,500.00
Additive Alternate #1
ITEM
NO. ITEM DESCRIPTION APPROX
QTY UNIT UNIT PRICE TOTAL
1 Continuous concrete header on 10’ Path 7216 LF X X
ADDITIVE ALTERNATIVE BID TOTAL X
The low bid will be on the base bid total only.