Exhibit E:

Comments Received and Responses
Comments Received at the September 6, 2023 Planning Commission Agency Responses:

Public comment was received via email from Emma Patel, Planning Manager, Monterey-Salinas Transit District (MST) on August 31, 2023. Comments and response to comments are provided below and are also provided in the revised Initial Study and Mitigated Negative Declarations as attachments to this report.

Alisal Marketplace
Minor changes to this IS/MND were made in September 2023 in response to a comment letter received via email from the Monterey-Salinas Transit District (MST) on August 31, 2023 during the 20-day public review period. The MST comments include the following:

Greenhouse Gas Emissions (GHG)
The VMT reduction column under Table 4-8 Scoping Plan Reduction Measures Consistency Analysis mentions that the project site has 6 bus stops within 1000 feet of the project site. Please provide the full list of stops and a vicinity map with all 6 bus stops:

1. Alisal / Work (Stop ID: 3401)

2. E. Alisal / Work (Stop ID: 3467)

3. E. Alisal / California (Stop ID: 6094)

4. E. Alisal / Front (Stop ID: 6085)

5. E. Alisal / Soledad (Stop ID: 6082)

6. E. Alisal / Soledad (Stop ID: 6097)
MST also recommends that future developers incorporate pedestrian and bicycle infrastructure along the project site that are in accordance with AMBAG’s 2045 Metropolitan Transportation Plan/Sustainable Communities Strategies (MTP/SCS) plan. The implementation of complete streets in areas with mixed-use can mitigate the project’s potential increase in GHG emissions.

Transportation
Although no development is proposed at this time, the future development of the project site could result in an increase in traffic and demand for transportation alternatives. Access to adequate transit services can help mitigate both the environmental and transportation related impacts of new developments. Therefore, it is crucial for future developers to incorporate transit into their plans, including bus stop infrastructure improvements and enrolling in MST’s Group Discount Program.

Please make the following corrections:

Page 129 ends
Page 138 ends

MST’s comments have been addressed through minor changes to this IS/MND. The minor changes are indicated by red underlined text within the document and include in-text changes to SECTION 1 INTRODUCTION (current section), SECTION 4 EVALUATION OF ENVIRONMENTAL IMPACTS and addition of Appendix G (Public Review Comment Letter). The in-text changes are summarized as follows:

Page 9 ends
Page 85 ends
Page 87 ends
Page 88 ends
Page 131 ends
Page 132 ends
Page 141 ends

Recirculation of this IS/MND is not required pursuant to CEQA Guidelines Section 15073.5 because the requested changes by MST do not constitute a “substantial revision” whereby a “substantial revision” means: 1) a new, avoidable significant effect is identified, and mitigation measures or project revisions must be added in order to reduce the effect of insignificance, or 2) the lead agency determines that the proposed mitigation measures or project revisions will not reduce potential effects to less than significance and new measures or revisions must be required. The requested changes by MST do not introduce new avoidable significant effects or mitigation measures. Therefore, recirculation pursuant to CEQA guidelines is not required.

Edge of Downtown/Front and John Streets
Minor changes to this IS/MND were made in September 2023 in response to a comment letter received via email from the Monterey-Salinas Transit District (MST) on August 31, 2023 during the 20-day public review period. The MST comments include the following:

Greenhouse Gas Emissions (GHG)
The VMT reduction column under Table 4-8 Scoping Plan Reduction Measures Consistency Analysis mentions that the project site has three (3) bus stops within 1000 feet of the project site. Please provide the full list of stops and a vicinity map with all three (3) bus stops:

1. Front / Summer (Stop ID: 3794)

2. Abbott / John Street (Stop ID: 2341)

3. Abbott / Maple (Stop ID: 3789)
MST also recommends that future developers incorporate pedestrian and bicycle infrastructure along the project site that are in accordance with AMBAG’s 2045 Metropolitan Transportation Plan/Sustainable Communities Strategies (MTP/SCS) plan. The implementation of complete streets in areas with mixed-use can mitigate the project’s potential increase in GHG emissions.

Transportation
Although no development is proposed at this time, the future development of the project site could result in an increase in traffic and demand for transportation alternatives. Access to adequate transit services can help mitigate both the environmental and transportation related impacts of new developments. Therefore, it is crucial for future developers to incorporate transit into their plans, including bus stop infrastructure improvements and enrolling in MST’s Group Discount Program.

MST’s comments have been addressed through minor changes to this IS/MND. The minor changes are indicated by red underlined text within the document and include in-text changes to SECTION 1 INTRODUCTION (current section), SECTION 4 EVALUATION OF ENVIRONMENTAL IMPACTS and addition of Appendix G (Public Review Comment Letter). The in-text changes are summarized as follows:

Page 9 ends
Page 82 ends
Page 84 ends
Page 85 ends
Page 127 ends

Recirculation of this IS/MND is not required pursuant to CEQA Guidelines Section 15073.5 because the requested changes by MST do not constitute a “substantial revision” whereby a “substantial revision” means: 1) a new, avoidable significant effect is identified, and mitigation measures or project revisions must be added in order to reduce the effect of insignificance, or 2) the lead agency determines that the proposed mitigation measures or project revisions will not reduce potential effects to less than significance and new measures or revisions must be required. The requested changes by MST do not introduce new avoidable significant effects or mitigation measures. Therefore, recirculation pursuant to CEQA guidelines is not required.

Foods Co Shopping Center
Minor changes to this IS/MND were made in September 2023 in response to a comment letter received via email from the Monterey-Salinas Transit District (MST) on August 31, 2023 during the 20-day public review period. The MST comments include the following:

Greenhouse Gas Emissions (GHG)
The VMT reduction column under Table 4-8 Scoping Plan Reduction Measures Consistency Analysis mentions that the project site has five (5) bus stops within 1000 feet of the project site. Please provide the full list of stops and a vicinity map with all five (5) bus stops:

1. E Alisal / Towt (Stop ID: 3416)

2.E Alisal/ Towt (Stop ID: 3452)

3.E Alisal/ Sanborn (Stop ID: 3413)

4.E Alisal/ Felice (Stop ID: 3458)

5.E Alisal / Felice (Stop ID: 3410)
MST also recommends that future developers incorporate pedestrian and bicycle infrastructure along the project site that are in accordance with AMBAG’s 2045 Metropolitan Transportation Plan/Sustainable Communities Strategies (MTP/SCS) plan. The implementation of complete streets in areas with mixed-use can mitigate the project’s potential increase in GHG emissions.

Transportation
Although no development is proposed at this time, the future development of the project site could result in an increase in traffic and demand for transportation alternatives. Access to adequate transit services can help mitigate both the environmental and transportation related impacts of new developments. Therefore, it is crucial for future developers to incorporate transit into their plans, including bus stop infrastructure improvements and enrolling in MST’s Group Discount Program.

MST’s comments have been addressed through minor changes to this IS/MND. The minor changes are indicated by red underlined text within the document and include in-text changes to SECTION 1 INTRODUCTION (current section), SECTION 4 EVALUATION OF ENVIRONMENTAL IMPACTS and addition of Appendix G (Public Review Comment Letter). The in-text changes are summarized as follows:

Page 9 ends
Page 85 ends
Page 88 ends
Page 89 ends
Page 131 ends

Recirculation of this IS/MND is not required pursuant to CEQA Guidelines Section 15073.5 because the requested changes by MST do not constitute a “substantial revision” whereby a “substantial revision” means: 1) a new, avoidable significant effect is identified, and mitigation measures or project revisions must be added in order to reduce the effect of insignificance, or 2) the lead agency determines that the proposed mitigation measures or project revisions will not reduce potential effects to less than significance and new measures or revisions must be required. The requested changes by MST do not introduce new avoidable significant effects or mitigation measures. Therefore, recirculation pursuant to CEQA guidelines is not required.

Laurel West Shopping Center
Minor changes to this IS/MND were made in September 2023 in response to a comment letter received via email from the Monterey-Salinas Transit District (MST) on August 31, 2023 during the 20-day public review period. The MST comments include the following:

Greenhouse Gas Emissions (GHG)
The VMT reduction column under Table 4-8 Scoping Plan Reduction Measures Consistency Analysis mentions that the project site has five (5) bus stops within 1000 feet of the project site. Please provide the full list of stops and a vicinity map with all five (5) bus stops:

1. Davis / Post (Stop ID: 3250)

2. Larkin / Davis (Stop ID: 3281)

3. Larkin / Davis (Stop ID: 3288)

4. Larkin / Larkin Circle (Stop ID: 3291)

5. Larkin / Larkin Circle (Stop ID: 3278)
MST also recommends that future developers incorporate pedestrian and bicycle infrastructure along the project site that are in accordance with AMBAG’s 2045 Metropolitan Transportation Plan/Sustainable Communities Strategies (MTP/SCS) plan. The implementation of complete streets in areas with mixed-use can mitigate the project’s potential increase in GHG emissions.

Transportation
Although no development is proposed at this time, the future development of the project site could result in an increase in traffic and demand for transportation alternatives. Access to adequate transit services can help mitigate both the environmental and transportation related impacts of new developments. Therefore, it is crucial for future developers to incorporate transit into their plans, including bus stop infrastructure improvements and enrolling in MST’s Group Discount Program.

MST’s comments have been addressed through minor changes to this IS/MND. The minor changes are indicated by red underlined text within the document and include in-text changes to SECTION 1 INTRODUCTION (current section), SECTION 4 EVALUATION OF ENVIRONMENTAL IMPACTS and addition of Appendix G (Public Review Comment Letter). The in-text changes are summarized as follows:

Page 9 ends
Page 84 ends
Page 86 ends
Page 87 ends
Page 130 ends

Recirculation of this IS/MND is not required pursuant to CEQA Guidelines Section 15073.5 because the requested changes by MST do not constitute a “substantial revision” whereby a “substantial revision” means: 1) a new, avoidable significant effect is identified, and mitigation measures or project revisions must be added in order to reduce the effect of insignificance, or 2) the lead agency determines that the proposed mitigation measures or project revisions will not reduce potential effects to less than significance and new measures or revisions must be required. The requested changes by MST do not introduce new avoidable significant effects or mitigation measures. Therefore, recirculation pursuant to CEQA guidelines is not required.

Sears (Northridge Mall)
Minor changes to this IS/MND were made in September 2023 in response to a comment letter received via email from the Monterey-Salinas Transit District (MST) on August 31, 2023 during the 20-day public review period. The MST comments include the following:

Transportation
Although no development is proposed at this time, the future development of the project site could result in an increase in traffic and demand for transportation alternatives. Access to adequate transit services can help mitigate both the environmental and transportation related impacts of new developments. Therefore, it is crucial for future developers to incorporate transit into their plans by allowing MST to service the Northridge Mall stop and have access to both driveways (vehicle entrance and exit) on Madrid Street.

Greenhouse Gas Emissions (GHG)
The VMT reduction column under Table 4-8 Scoping Plan Reduction Measures Consistency Analysis mentions that the project site has 6 bus stops within 1000 feet of the project site. Please provide the full list of stops and a vicinity map with all 6 bus stops:

1. Northridge Mall (Stop ID: 0011)

2. N Main / Big 5 Sport Store (Stop ID: 6043)

3. N Main / Madrid (Stop ID: 6033)

4. Harden / East Entrance to Shopping Center (Stop ID: 3152)

5. Harden / Entrance to Target Lot (Stop ID: 3149)

6. N Main / Firestone Svc Stn (Stop ID: 6040)
MST also recommends that future developers incorporate pedestrian and bicycle infrastructure along N. Main Street and Madrid Street that are in accordance with AMBAG’s 2045 Metropolitan Transportation Plan/Sustainable Communities Strategies (MTP/SCS) plan. The implementation of complete streets in areas with mixed-use can mitigate the project’s potential increase in GHG emissions.

MST’s comments have been addressed through minor changes to this IS/MND. The minor changes are indicated by red underlined text within the document and include in-text changes to SECTION 1 INTRODUCTION (current section), SECTION 4 EVALUATION OF ENVIRONMENTAL IMPACTS and addition of Appendix G (Public Review Comment Letter). The in-text changes are summarized as follows:

Page 9 ends
Page 81 ends
Page 83 ends
Page 84 ends
Page 125 ends

Recirculation of this IS/MND is not required pursuant to CEQA Guidelines Section 15073.5 because the requested changes by MST do not constitute a “substantial revision” whereby a “substantial revision” means: 1) a new, avoidable significant effect is identified, and mitigation measures or project revisions must be added in order to reduce the effect of insignificance, or 2) the lead agency determines that the proposed mitigation measures or project revisions will not reduce potential effects to less than significance and new measures or revisions must be required. The requested changes by MST do not introduce new avoidable significant effects or mitigation measures. Therefore, recirculation pursuant to CEQA guidelines is not required.