RESOLUTION NO. (N.C.S.)
A RESOLUTION APPROVING CONTRACT CHANGE ORDER NO. 1 IN THE AMOUNT OF $430,678.35 TO GRANITE CONSTRUCTION COMPANY FOR THE 2022-2023 PAVEMENT MAINTENANCE PROJECT, CIP 9981, 9120, 9080 WHEREAS, on May 16, 2023, the Salinas City Council awarded the 2022-2023 Pavement Maintenance Project, CIP 9981, 9120, 9080 to Granite Construction Company (Resolution No. 22661) in the amount of $8,138,006.96; and WHEREAS, construction commenced on July 31, 2023; and
WHEREAS, the 2022-2023 Pavement Maintenance Project, in general, calls for pavement reconstruction, curb ramps, curbs, gutters, pavement patch repairs, crack treatment, chip seal, slurry seal, installation of new signs and striping; and WHEREAS, Public Works Department Policy 75-1 states that City Council approval and authorization is required for Contract Change Orders of more than $100,000.00; and WHEREAS, staff requests the City Council’s approval of Contract Change Order No. 1, which directs the Contractor to install approximately 277,857 square yards (SY) of Tire Rubber Modified Surface Sealer at locations that will be chip sealed for a total estimated cost of $430,678.35; and WHEREAS, the City of Salinas has determined that the project is categorically exempt from the California Environmental Quality Act (CEQA) Guidelines (Section 1530l(c), Class 1) because the project proposes to maintain existing roadways, crosswalks, signage, and pavement striping, and the project does not qualify for any of the exemptions to the categorical exemptions found at CEQA Guidelines Sections 15300.2; and NOW, THEREFORE, BE IT RESOLVED that the Salinas City Council approves Contract Change Order No. 1 in the amount of $430,678.35 to Granite Construction Company for the 2022-2023 Pavement Maintenance Project, CIP No. 9981, 9120, 9080 and authorizes the City Manager to execute all necessary documents related to Change Order No. 1.

PASSED AND APPROVED this 24th day of October 2023, by the following vote:

AYES:

NOES:

ABSENT:

ABSTAIN:

APPROVED:
________________________
Kimbley Craig, Mayor
ATTEST:
_________________________
Patricia M. Barajas, City Clerk