RESOLUTION NO. (N.C.S.)
A RESOLUTION AUTHORIZING AN ADDITIONAL $881,868.50 IN CONSTRUCTION CONTINGENCIES FOR THE 2022-2023 PAVEMENT MAINTENANCE PROJECT, CIP 9981, 9120, 9080 WHEREAS, on May 16, 2023 the Salinas City Council awarded the 2022-2023 Pavement Maintenance Project, CIP 9981, 9120, 9080 to Granite Construction Company (Resolution No. 22661) in the amount of $8,138,006.96; and WHEREAS, construction commenced on July 31, 2023; and
WHEREAS, the 2022-2023 Pavement Maintenance Project, in general, calls for pavement reconstruction, curb ramps, curbs, gutters, pavement patch repairs, crack treatment, chip seal, slurry seal, installation of new signs and striping; and WHEREAS, Contract Change Order No. 1 and Contract Change Order No. 2 were approved by the Salinas City Council on October 24, 2023 for a total amount of $680,678.35; and WHEREAS, the Public Works Department recommends that the City Council authorize 10% of the new contract amount for construction contingencies ($881,868.50) to allow the project to move to completion more effectively and efficiently; and WHEREAS, the City of Salinas has determined that the project is categorically exempt from the California Environmental Quality Act (CEQA) Guidelines (Section 1530l(c), Class 1) because the project proposes to maintain existing roadways, crosswalks, signage, and pavement striping, and the project does not qualify for any of the exemptions to the categorical exemptions found at CEQA Guidelines Sections 15300.2; and NOW, THEREFORE, BE IT RESOLVED that the Salinas City Council authorizes an additional $881,868.50 for construction contingencies for the 2022-2023 Pavement Maintenance Project, CIP No. 9981, 9120, 9080.
PASSED AND APPROVED this 24th day of October 2023, by the following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
APPROVED:
________________________
Kimbley Craig, Mayor
ATTEST:
_________________________
Patricia M. Barajas, City Clerk
2 1