DATE: OCTOBER 24, 2023
DEPARTMENT: PUBLIC WORKS DEPARTMENT
FROM: DAVID JACOBS P.E., L.S., PUBLIC WORKS DIRECTOR
BY: GERARDO RODRIGUEZ, ASSISTANT ENGINEER
TITLE: ALISAL SAFE ROUTES TO SCHOOL PROJECT
RECOMMENDED MOTION:

A motion to approve a resolution:

Awarding a contract to FBD Vanguard Construction, Inc. for the Alisal Safe Routes to School Project; and Authorizing an increase of $155,000 to CIP 9360 appropriation and use Measure G fund balance for construction.

RECOMMENDATION:

It is recommended that the City Council approve 1) awarding a contract to FBD Vanguard Construction Inc. for the Alisal Safe Routes to School Project; and 2) authorizing an increase of $155,000 to CIP 9360 appropriation and use Measure G fund balance for construction.

EXECUTIVE SUMMARY:

The City was successful in an Active Transportation Grant Program application and was selected to be awarded grant funds in the amount of $998,000.

On March 21, 2023, City Council approved Resolution 22608 to approve plans and specifications, the categorical exemption, and authorize the Public Works Director to execute all agreements and any required paperwork with Caltrans for the Active Transportation Grant Program.

The City opened bids on September 26, 2023 and FBD Vanguard Construction, Inc. was the apparent low bidder with a bid of $855,820.

The total estimated construction costs including contingencies, construction engineering and administrative overhead is $ 1,061,820.00 which is $138,820 more than what is in the current CIP.

BACKGROUND:

On December 14, 2021, City Council approved Resolution 22267 (Attachment 1) to appropriate $750,000 of anticipated funding from the American Rescue Plan Act towards improving the marked midblock crosswalk on Williams Road, and to direct staff to proceed with implementation to fully effectuate the intent of the Resolution. On March 18, 2022, the City published a request for proposals to provide design services for the Williams Road Pedestrian Hybrid Beacon Project. Three firms submitted proposals and staff ranked Kimley Horn and Associates as the most qualified applicant. The City entered into an agreement with Kimley-Horn and Associates effective May 23, 2022 to prepare construction documents for the pedestrian hybrid beacon (PHB) at Williams Road.

On June 15, 2022, the City in partnership with the Transportation Agency for Monterey County (TAMC) submitted an application to the Active Transportation Grant Program to request funding for improvements identified in the Salinas Safe Routes to Schools Plan (Attachment 2), including the PHB system on Williams Rd, plus funds to replace street trees and install radar feedback signage. In addition to funding for infrastructure improvements, the application included non-infrastructure funding for classroom bicycle/pedestrian education workshops, bike rodeos, and walk/bike to school encouragement days. The City was successful in its grant application and was selected to be awarded grant funds in the amount of $998,000.

On March 21, 2023, City Council approved Resolution 22608 (Attachment 3) to approve plans and specifications, the categorical exemption, and authorize the Public Works Director to execute all agreements and any required paperwork with Caltrans for the Active Transportation Grant Program. Following the approval of the plans and specifications staff submitted the allocation request to Caltrans for grant funds. Allocation of funds was approved by Caltrans on May 17, 2023 and staff has 6 months to award project for construction.

The project was advertised on August 28, 2023, and the City opened bids on September 26, 2023. Two contractors submitted bid proposals for the project, and the results are as follows:

Contractor
Total Bid
FBD Vanguard Construction, Inc.
$855,820
Precision Grade, Inc.
$861,348
FBD Vanguard Construction, Inc. was the low bidder, and a full bid tab is included in the attachments (Attachment 4). All bid contract documents and bonds have been received. The City has verified FBD Vanguard Construction Inc. and their subcontractors, Chrisp Company, Lone Star Landscape, Farwest Safety, Inc., St. Francis Electrical, and Mike O’Dell Surveys have active Department of Industrial Relations (DIR) registration. FBD Vanguard Construction Inc. has an active contractor’s license.

Staff recommends that the City Council approve a Resolution awarding the contract to FBD Vanguard Construction, Inc. for the Alisal Safe Routes to School Project; CIP 9360, in the amount of $855,820 and also Authorizing an increase of $155,000 to CIP 9360 appropriation and use Measure G fund balance for construction.

CEQA CONSIDERATION:

The City of Salinas has determined that the project is categorical exempt from the California Environmental Quality Act (CEQA) Guidelines (Section 15301, Class 1(c)) because the actions consist of operation and minor alteration of an existing City street. A notice of exemption has been prepared and will be submitted to the County Clerk’s office.

STRATEGIC PLAN INITIATIVE:

This item supports the City Council’s goal of “Infrastructure and Environmental Sustainability” and “Public Safety”.

DEPARTMENTAL COORDINATION:

The Public Works Department and Finance Department manage the project accounting. The Public Works Department manages construction contract, inspection, and final acceptance of construction projects.

FISCAL AND SUSTAINABILITY IMPACT:

The estimated funding for this project comes from the source below:

CIP No.

Name
Funding Source
Appropriations
Available Balance
9360
Alisal Safe Routes to School Project
Active Transportation Program Grant
$913,000
$913,000
Total
$913,000
$913,000
Construction Cost
Base Bid $855,820
Contingencies (10%) $86,000
Construction Engineering (8%) $70,000
Admin Overhead $50,000
Total Estimated Construction Costs $ 1,061,820
The account balance at the time of this report is the $913,000. $119,204 is budgeted for staff time and $793,796 for construction costs. Based on the bid results and the existing balance there is a budget shortfall of $138,820. Staff recommends an increase of $155,000 to CIP 9360 appropriation and use of Measure G fund balance to cover the budget shortfall.

ATTACHMENTS:

Resolution
Attachment 1: Resolution 22267
Attachment 2: Salinas Safe Routes to Schools Plan
Attachment 3: Resolution 22608
Attachment 4: Bid Tab
Page | 2
Page | 1

CITY OF SALINASCOUNCIL STAFF REPORTCITY OF SALINASCOUNCIL STAFF REPORT

CITY OF SALINAS

COUNCIL STAFF REPORT

CITY OF SALINAS

COUNCIL STAFF REPORT

← All documents from this meeting