RESOLUTION NO. (N.C.S.)
A RESOLUTION AUTHORIZING APPROVAL OF CONTRACT CHANGE ORDER NO. 8 FOR THE FOR THE CITY HALL EMERGENCY ROOF REPAIR, PROJECT NO. 8170
WHEREAS, On April 4, 2023, City Council pursuant to Resolution No.22627 awarded an emergency construction contract to F C & Sons Roofing, Inc. for the City Hall Emergency Roof Repair, Project No. 8170 in the amount of $646,271.00; and WHEREAS, On October 10, 2023, City Council approved Resolution No.22810 authorizing approval of Contract Change Order No. 4 in the amount of $748,122.00 for removal and replacement of the metal deck and authorized 20% of the new contract total or $370,332.80 for construction contingencies for the City Hall Emergency Roof Repair Project No. 8170; and WHEREAS, Contract Change Order No. 13 for the use of galvanized painted metal instead of bonderized metal and Change Order No. 14 in the amount of $8,725.00 and $19,864.00, respectively, brings the cumulative contingencies over the $370,332.80 approved per Resolution No. 22810; and WHEREAS, the City of Salinas has determined that the proposed action is categorically exempt from environmental review under the California Environmental Quality Act (CEQA Guidelines Section 15301).
NOW, THEREFORE, BE IT RESOLVED that the City Council authorizes the Interim City Manager to execute Change Order No. 13 and Change Order No. 14 to F C & Sons Roofing, Inc. for the City Hall Emergency Roof Repair Project No. 8170 in the amount of $8,725.00 and $19,864.00, respectively, and authorize the City Manager to execute all necessary documents related to Contract Change Order No. 13 and Change Order No. 14; and NOW, THEREFORE, BE IT FURTHER RESOLVED that the City Council approves an additional one and a half percent (1.5%) of the new contract amount for construction contingencies ($33.655.37) for the City Hall Emergency Roof Repair Project, CIP No. 8170; and PASSED AND APPROVED this 5th day of March 2024, by the following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
APPROVED:
________________________
Kimbley Craig, Mayor
ATTEST:
_________________________
Patricia M. Barajas, City Clerk