DATE: MAY 7, 2024
DEPARTMENT: PUBLIC WORKS, TRAFFIC AND TRANSPORTATION DIVISION FROM: DAVID JACOBS, P.E., L.S., PUBLIC WORKS DIRECTOR THRU: ADRIANA ROBLES, P.E., CITY ENGINEER
BY: JONATHAN HERNANDEZ, JUNIOR ENGINEER
TITLE: 2024-2025 RESTRIPING PRIORITIZATION LIST
RECOMMENDED MOTION:
A motion to approve the 2024-2025 Restriping Prioritization List.
EXECUTIVE SUMMARY:
City staff has surveyed major and minor arterial roads where pavement markings and lines are faded and require restriping. The number of roads that require restriping exceed the City’s budgeted resources. Therefore, there is a need to prioritize restriping. Staff recommends approval of the 2024-2025 Restriping Prioritization List.
BACKGROUND:
Most thermoplastic pavement markings have an upper limit life expectancy of (six) 6 to (nine) 9 years depending on weather and traffic conditions. Typically, pavement markings are replaced whenever roadways are resurfaced, which should occur at a similar frequency. However, the City has not been able to perform pavement maintenance within this timeframe and some streets now have faded pavement markings. Staff have surveyed striping conditions on all major and minor arterial roads as well as reviewed requests for restriping received from the public. The number of roads in need of restriping exceeds the City’s budgeted resources. Therefore, there is a need to prioritize restriping.
The City’s street maintenance crews can perform minor restriping work, but the City does not have the equipment nor workforce for large restriping projects and must contract the work out. On October 22, 2019, the City awarded an On-Call Services for Traffic Control Devices Contract to Chrisp Company via Resolution No. 21722. Based on this contract the estimated cost to restripe a road can vary between approximately $6 to $28 per linear feet (LF) depending on the number of lanes and legends on any given roadway.
As of February 29, 2024, service requests for 16 road segments have been received. In addition, City staff has surveyed and identified 30 road segments in need of restriping. Based on the on-call services contract pricing, staff estimates the total cost to restripe all the deficient facilities is approximately $2.4 million. Restriping budget for FY 24-25 is estimated at $300,000, of which $250,000 are allocated towards improvements. In addition, staff anticipates a carryover of approximately $82,000 in the account from FY 23-24. Staff estimates the City can restripe at least (five) 5 segments within the requested budget depending on the length and complexity of the individual restriping segments. Additionally, staff recommends retaining $30,000 in the account, to allow staff to respond to smaller service requests, such as crosswalks, through the end of the fiscal year.
The City has no established prioritization policy for restriping. Staff recommends the 2024-2025 Restriping Prioritization List based on staff’s opinion of need and budgetary constraints. As an example, with a small two-lane, two-way road, centerlines are not always required based on the Manual on Uniform Traffic Control Devices (MUTCD), and the City’s standard for pavement markings. Previously, the City had installed centerlines on Maple Street, Rider Avenue, Schilling Place, Villa Street, and Ambrose Road, possibly as a traffic calming measure. However, these roads do not require centerline markings based on their use. Consequently, with limited funding, staff recommends these roads to be prioritized last. In addition, restriping requests for Old Stage Road have been received, staff also recommends this road be prioritized last since it will be part of the 2024 Pavement Management Project.
Along with the restriping list, included are photographs of the roadways’ current pavement markings conditions (Attachment 1). Table 1 below is the proposed 2024-2025 Restriping Prioritization List. Table 2 provides some relevant traffic data used for consideration. Once the first projects are completed and final costs are known, staff will work on the next highest scoring projects, based on available funding, until the budget is depleted. If the next highest priority project cannot be completed with the remaining funds, but other lower priority projects can be completed with the remaining funds, staff will move forward with the lower priority project to maximize the use of available funds.
Table 1: 2024-2025 Restriping Prioritization List
Recommended Priority Ranking
Segment
Limits
Length (LF)
Estimated Cost
Notes
1 North Sanborn Road
East Laurel Drive to Fairview Avenue
4,343
$138,000
2 Boronda Road
North Main Street to City Limits
645
$17,500
Service Request
3 East Blanco Road
Blanco Circle to Abbott Street
981
$18,800
4 East Market Street
Monterey Street to Greenfield Alley
608
$22,100
5 Harkins Road
Hansen Street to City Limits
5,260
$96,400
Service Request
6 North Main Street at San Juan Grade Road
Intersection
417
$25,800
Service Request
7 Natividad Road
East Boronda Rd to Rogge Road
5,267
$27,700
Service Request
8 Skyway Boulevard
Airport Boulevard to East Alisal Street
2,317
$60,200
9 South Sanborn Road
Fairview Avenue to Work Street
3,310
$59,400
10 San Juan Grade Road
North Main Street to Boronda Road
1,603
$60,200
11 Sherwood Drive
East Market Street to Calle Cebu
705
$32,100
12 East Laurel Drive
Williams Road to North Sanborn Road
3,345
$39,400
13 Central Avenue
South Davis Road to Salinas Street
6,213
$42,300
Service Request
14 Pajaro Street
West Market Street to San Ramon Circle
7,759
$174,100
15 Sherwood Drive/Natividad Road
Sherwood Place to East Laurel Drive
705
$105,700
16 Garner Avenue
Williams Road to North Sanborn Road
3,318
$40,000
17 East Bernal Drive
Rosarita Drive to Sherwood Drive
895
$15,000
18 Las Casitas Drive
Constitution Boulevard to Rider Avenue
2,743
$36,000
19 Salinas Street
East Market Street to Clay Street
2,667
$61,300
20 Post Drive
Calle del Adobe to North Davis Road
1,104
$41,800
21 North Main Street
East Boronda Road to Russell Road
4,690
$156,000
Service Request
22 West Alvin Drive
North Main Street to Cherokee Drive
1,997
$28,100
23 Williams Road
Bardin Road to Del Monte Avenue
972
$61,000
24 Williams Road
East Boronda Road to Old Stage Road
5,964
$30,500
Service Request
25 Monterey Street
East Market Street to John Street
2,565
$63,100
26 Homestead Avenue
Central Avenue to Iverson Street
2,402
$30,700
27 Del Monte Avenue
Williams Road to North Sanborn Road
4,718
$55,600
28 Rogge Road
Natividad Road to San Juan Grade Road
6,824
$62,900
29 East Boronda Road
Natividad Road to Rider Avenue
9,782
$185,200
30 Kern Street
East Alisal Street to Longbow Drive
2,916
$34,500
31 Iris Drive
North Main Street to Lupin Drive
1,855
$18,500
32 East Market Street
Sherwood Drive to Griffin Street
1,507
$48,000
33 Work Street
Work Circle to South Sanborn Road
6,343
$138,000
34 Griffin Street
John Street to East Market Street
3,175
$22,500
35 Madrid Street
Segovia Circle to North Main Street
1,640
$42,800
36 East Laurel Drive
North Main Street to Natividad Road
4,150
$147,700
Service Request
37 West Acacia Street
South Davis Road to South Main Street
7,608
$74,000
38 Mortensen Avenue
Skyway Boulevard to Mercer Way
1,028
$18,100
Service Request
39 Mercer Way
Mortensen Avenue to Airport Boulevard
692
$1,700
Service Request
40 Maple Street
North Main Street to Pajaro Street
775
$7,700
Service Request
41 Rider Avenue
Del Monte Avenue to Mimbrera Way
1,550
$9,300
Service Request
42 Schilling Place
Harkins Road to Eden Street
1,259
$10,500
Service Request
43 Villa Street
Central Avenue to South Davis Road
2,390
$12,700
44 Adams Street
East Laurel Drive to Navajo Drive
1,610
$15,100
Service Request
45 Towt Street
East Alisal Street to East Market Street
1,608
$12,800
Service Request
46 Old Stage Road
Williams Road to City Limits
7,632
$40,400
Service Request
Part of 2024
Pavement Project
Subtotal (1-5)
$292,800
Estimated Remaining Balances
$39,200
Subtotal (6-46)
$2,148,400
Total
$2,441,200
Table 2: Relevant Traffic Data
Segment
Limits
ADT
Fatal + Injury Collisions (2022-2023)
Collision Rate (Fatal + Injury per million vehicle miles) Pavement Condition Index (2020)
North Sanborn Road
East Laurel Drive to Fairview Avenue
21,390
16 1.25
38-50
Boronda Road
North Main Street to Hwy 101 On/Off Ramps
25,241
2 0.89
47 East Blanco Road
Blanco Circle to Abbott Street
20,283
0 0.00
58 East Market Street
Monterey Street to Greenfield Alley
19,903
1 0.60
80 Harkins Road
Hansen Street to City Limits
9,559
2 0.36
40-59
North Main Street at San Juan Grade Road
Intersection
8,914
3 5.84
57 Natividad Road
East Boronda Road to Rogge Road
8,873
6 0.93
50 Skyway Boulevard
Airport Boulevard to East Alisal Street
4,870*
1 0.64
34 South Sanborn Road
Work Street to East Alisal Street
34,884
8 0.50
58-60
Sherwood Drive
East Market Street to Calle Cebu
25,082
3 1.23
61 San Juan Grade Road
North Main Street to Boronda Road
8,914
4 2.02
57 East Laurel Drive
Williams Road to North Sanborn Road
8,268
8 2.09
26-48
Central Avenue
South Davis Road to Salinas Street
3,108
2 0.75
40-54
Pajaro Street
West Market Street to San Ramon Circle
5,590
4 0.67
49-56
Sherwood Drive/Natividad Road
Sherwood Place to East Laurel Drive
25,138
6 0.71
76 Garner Avenue
Williams Road to North Sanborn Road
16,931
7 0.90
22-29
East Bernal Drive
Rosarita Drive to Sherwood Drive
13,935
2 1.16
81 Las Casitas Drive
Constitution Boulevard to Rider Avenue
5,926
12 5.34
31-50
Salinas Street
East Market Street to Clay Street
7,352
8 2.95
24-56
Post Drive
Calle del Adobe to North Davis Road
4,750*
1 1.38
48 North Main Street
East Boronda Road to Russell Road
11,764
17 2.23
74 West Alvin Drive
North Main Street to Cherokee Drive
9,060
7 2.80
46 Williams Road
Bardin Road to Del Monte Avenue
11,273
10 6.60
50 Williams Road
East Boronda Road to Old Stage Road
3,117
6 2.33
29 Monterey Street
East Market Street to John Street
4,454
8 5.06
52-62
Homestead Avenue
Central Avenue to Iverson Street
4,324
1 0.70
39 Del Monte Avenue
Williams Road to North Sanborn Road
4,398
11 3.83
36-55
Rogge Road
Natividad Road to San Juan Grade Road
5,851
0 0.00
33-78
East Boronda Road
Natividad Road to Rider Avenue
17,903
11 0.45
37-44
Kern Street
East Alisal Street to Longbow Drive
9,100*
3 0.82
37-62
Iris Drive
North Main Street to Lupin Drive
4,297
3 2.72
29 East Market Street
Sherwood Drive to Griffin Street
16,716
3 0.86
68 Work Street
John Street to South Sanborn Road
5,653
6 1.21
25-74
Griffin Street
John Street to East Market Street
2,790*
7 5.86
32-70
Madrid Street
Segovia Circle to North Main Street
7,981
8 4.42
36 East Laurel Drive
North Main Street to Natividad Road
26,266
19 1.26
57 West Acacia Street
South Davis Road to South Main Street
3,692
3 0.77
39-52
Mortensen Avenue
Skyway Boulevard to Mercer Way
N/A
0 N/A
22 Mercer Way
Mortensen Avenue to Airport Boulevard
N/A
0 N/A
33 Maple Street
North Main Street to Pajaro Street
3,156
3 8.87
40 Rider Avenue
Garner Avenue to Mimbrera Way
3,871
0 0.00
25 Schilling Place
Harkins Road to Eden Street
2,970*
1 1.93
58 Villa Street
Central Avenue to South Davis Road
3,999
0 0.00
42-65
Adams Street
East Laurel Drive to Navajo Drive
5,261
0 0.00
39 Towt Street
East Alisal Street to East Market Street
4,120
1 2.18
80 Old Stage Road
Williams Road to 900 Block
N/A
4 N/A
33 *ADT approximated from peak hour count, and K=0.10
Traffic and Transportation Commission
The 2024-2025 Restriping Prioritization List was presented to the Traffic and Transportation Commission at its April 11, 2024 meeting. The Commission voted (4-1) in favor to recommend City Council approve the 2024-2025 Restriping Prioritization List.
CEQA CONSIDERATION:
Not a Project. The City of Salinas has determined that the proposed action is not a project as defined by the California Environmental Quality Act (CEQA) (CEQA Guidelines Section 15378).
STRATEGIC PLAN INITIATIVE:
The 2024-2025 Restriping Prioritization List supports the Council’s goals of “Infrastructure and Environmental Sustainability” and “Public Safety”.
DEPARTMENTAL COORDINATION:
The City’s Public Works Department is responsible for the maintenance of roadway striping.
FISCAL AND SUSTAINABILITY IMPACT:
There is no immediate financial impact associated with accepting the 2024-2025 Restriping Prioritization List. Funding for this project will be recommended for appropriation during the budget development process.
ATTACHMENTS:
Resolution
Attachment 1: Current Conditions Photos
Page | 5