Subject: Closter Park Green Streets - Contract Amendment #4 (CA#4) Dear Ms. Niggemeyer:
We have been happy to support the City on the Closter Park Green Streets project through the conceptual design phase and the delivery of the 60% plans. We received the City's 60% PS&E comments on 5/1 and had started addressing the comments and updating the plans to a 90% level of detail. On 6/6 and 6/10, we received additional comments from the City that will result in significant changes to the initially approved project scope and the approved concept design. As discussed, these changes are primarily the addition of street lighting design and the redesign of Beech Street and Dewey Street. Wallace Group has provided the following contract amendment request for this work.
PROJECT UNDERSTANDING
Lighting: The City of Salinas has requested streetlights at the proposed roundabout at the Towt Street/Acosta Street intersection. This amendment adds lighting (photometric) analysis and preparation of lighting plans to the contract scope of work.
Redesign of Beech Street and Dewey Street: The approved concept design included parallel parking and bioretention planters on each side of the street on all three project streets.
Comments from the City's Traffic Department request changing the design to perpendicular or angled parking along the park frontage, eliminating the planters on this side of the street, adjusting the through lanes, parallel parking, and planters on the residential side. This will require nearly a full redesign of 2/3 of the project. We are happy to support the City with these changes, as they will result in additional valuable parking spaces around the park which will support the on-site park improvements which are sure to draw more users to enjoy the area.
ADDITIVE SCOPE OF SERVICES
We have prepared this contract amendment request to augment the approved project budget and services within the following tasks. The project understanding is integral to the context and assumptions of the additive scope.
Task 1: Project Coordination and Management
Task 1.1 Project Management
The original project scope assumed an approximate 11-month production schedule for coordination and project management services for the design phase through Final PS&E. Due to the expanded preliminary design and initial outreach phases, we propose to extend the project schedule an additional 10 months to achieve final PS&E by the end of this year (see updated schedule as Exhibit A).
Deliverables:
• Progress reports and invoicing (PDF)
• Updated Schedule (PDF)
Closter Park Green Streets - CA#4
City of Salinas
Task 3: Preliminary Design
Task 3.1 Concept Refinement
Wallace Group will develop up to two preliminary 2D only concept plan alternatives for the proposed redesign of Beech Street and Dewey Street. The first alternative will show 45-degree angled parking on Beech Street and Dewey Street, and the second alternative will show 90- degree parking. We anticipate receiving one round of consolidated comments on this concept plan that will be addressed in one updated concept plan for City approval prior to moving forward with the 90% design.
Task 3.3 Lighting Analysis
A lighting analysis for both horizontal and vertical illuminance will be prepared. Roundabout lighting guidelines per NCHRP Research Report 1043, AASHTO Roadway Lighting Design Guide 7th Edition and/or IES RP-8-22 Recommended Practice: Lighting Roadway and Parking Facilities, will be used, as appropriate. The lighting analysis will provide the basis for the lighting design and plans. Analysis for light trespass is not included in this scope.
We will prepare a lighting memorandum that describes existing conditions, design criteria, analysis results and proposed improvements. We anticipate a virtual meeting with the City to discuss the photometric analysis results. We will prepare voltage drop calculations for the City’s acceptance. We anticipate receiving one round of consolidated comments on the lighting memorandum before finalizing the memorandum and moving forward with the 90% design.
Deliverables:
• 2 - Draft Concept Plans (PDF)
• 1 - Final Concept Plan (PDF)
• Draft and Final Lighting Memorandum (PDF)
Task 6: 90% PS&E
Task 6.1 90% Plans
After the concept plan has been approved by the City, we will develop the 3D roadway design for the revised layout and update the project plans. Since the design has changed substantially on 2 of the 3 streets, we anticipate significant updates to the plan callouts, typical cross sections, striping, landscape and irrigation design. In addition, with the direction to include pavement reconstruction for the full width of Beech Street and Dewey Street, the layout sheets will be changed to plan and profile sheets.
Wallace Group will develop lighting plans for the roundabout to be included in the project plan set. It is assumed the roundabout lighting circuit will be able to be added to an existing lighting control cabinet. The lighting plans will include the following:
• Removals and modifications to the existing street lighting circuit(s). • Proposed lighting plan and circuit layout.
• Conduit and conductor schedules.
Task 6.2 90% Technical Specifications
Technical special provisions will be developed for the street lighting work. The special provisions will follow Caltrans standard specifications format to conform with the rest of the project specifications.
Closter Park Green Streets - CA#4
City of Salinas
Task 6.3 90% Estimate
Quantity take-offs and unit cost estimates will be developed for the street lighting improvements. Bid data from recent projects will be referenced to prepare a realistic estimate for City budgeting purposes.
Deliverables:
• 90% Lighting PS&E
Task 7: Final PS&E
We have included additional budget to update the street lighting related portions of the 90% PS&E submittal.
Task 8: Bidding Support
We have included additional budget to respond to street lighting related requests for information and to prepare bid addenda, up to the budgeted amount, if needed.
Task 9: Construction Support
We have included additional budget to review submittals, respond to street lighting related requests for information and to prepare record drawings, up to the budgeted amount, if needed.
PROJECT BUDGET
accordance with the overall contract and in general conformance to the budget summary attached herein (Exhibit B-2). Please note that task budgets are shown for estimating purposes only and are not to be interpreted as budget limits per task. These services will be invoiced monthly on an accrued cost basis, and our total fees, including reimbursables, will not exceed our estimated fee of $65,860 without receiving written authorization from the City, and tasks are proposed to be updated to Wallace Group's current 2024 rate schedule, provided as Exhibit C.
For clarity of terms and expectations our team will perform these services per the terms denoted in the original agreement dated December 30, 2022. We thank you for the opportunity to continue to serve the City on this important project. If you would like to discuss this proposal in greater detail, please feel free to contact me or the Project Manager, Sarah Huffman.
Sincerely,
WALLACE GROUP, a California Corporation
Jorge Aguilar, PE C48704
Principal
612 Clarion Court
San Luis Obispo, California 93401
T 805 544-4011
www.wallacegroup.us
THIS PROPOSAL IS VALID FOR 60 DAYS FROM THE DATE OF THIS DOCUMENT.
ID Task
Mode
Task Name Duration Start Finish
1 Task 1 Project Coordination and Management 729 days Tue 1/10/23 Fri 10/24/25 2 Notice to Proceed 0 days Tue 1/10/23 Tue 1/10/23
3 Task 1.1 Project Management 729 days Tue 1/10/23 Fri 10/24/25 4 Task 1.2 Meetings 123 days Thu 1/26/23 Tue 7/18/23
5 Kick-Off Meeting 0 days Thu 1/26/23 Thu 1/26/23
6 Concept Review Meeting (6/21) 0 days Tue 7/18/23 Tue 7/18/23 7 Task 1.3 QA/QC 230 days Tue 10/24/23Mon 9/9/24
8 QA/QC of 60% Submittal 5 days Tue 10/24/23Mon 10/30/23 9 QA/QC of 90% Submittal 5 days Tue 9/3/24 Mon 9/9/24
10 Task 2 Site Assessment 475 days Tue 1/24/23 Mon 11/18/24 11 Task 2.1 Topographic Survey and Record Right of Way 30 days Tue 1/24/23 Mon 3/6/23 12 Task 2.2 Geotechnical Assessment 165 days Tue 3/7/23 Mon 10/23/23 13 Geotechnical Investigation/Stormwater Infiltration Testing 10 days Tue 3/7/23 Mon 3/20/23 14 Geotechnical Recommendations 19 days Tue 3/21/23 Fri 4/14/23 15 Final Geotechnical Report 10 days Tue 10/10/23Mon 10/23/23 16 Task 2.3 Utility Coordination 445 days Tue 3/7/23 Mon 11/18/24 17 "A" Letters 25 days Tue 3/7/23 Mon 4/10/23
18 Potholing 74 days Tue 2/20/24 Fri 5/31/24
19 Contract Approved 0 days Tue 2/20/24 Tue 2/20/24
20 LTEC Prep 10 days Tue 2/20/24 Mon 3/4/24
21 LTEC Field Work 4 days Tue 3/5/24 Fri 3/8/24
22 Field Survey 1 day Fri 3/8/24 Fri 3/8/24
23 Pothole Results 2 days Mon 3/11/24Tue 3/12/24
24 Review results 14 days Wed 4/3/24 Mon 4/22/24
25 LTEC confirmations 2 days Tue 4/23/24 Wed 4/24/24
26 update design 14 days Tue 5/14/24 Fri 5/31/24
27 Notice to Owner Letters (“B” Letters) 24 days Fri 5/31/24 Thu 7/4/24 28 Submit draft B Letters to City 0 days Fri 5/31/24 Fri 5/31/24 29 City Review 7 days Mon 6/3/24 Tue 6/11/24
30 Submit B letters to utility companies 2 days Wed 6/12/24Thu 6/13/24 31 Utility coordination meeting(s) 5 days Fri 6/28/24 Thu 7/4/24 32 Utility Agreement (“C” Letters) 10 days Tue 11/5/24 Mon 11/18/24 33 Task 3 Preliminary Design 370 days Tue 3/7/23 Mon 8/5/24 34 Task 3.1 Concept Refinement 370 days Tue 3/7/23 Mon 8/5/24 35 Coordination on design vehicles, sight distance, Acosta/Towt intx 30 days Tue 3/7/23 Mon 4/17/23 36 Prepare initial draft layout and planting palatte 24 days Tue 4/18/23 Fri 5/19/23 37 City review 27 days Fri 6/16/23 Mon 7/24/23
38 Create updated concept alternatives 5 days Tue 7/9/24 Mon 7/15/24 39 City Review 10 days Tue 7/16/24 Mon 7/29/24
40 Finalize Preferred Alternative Concept 5 days Tue 7/30/24 Mon 8/5/24 41 Task 3.2 Preliminary Stormwater Design Report 66 days Fri 4/21/23 Fri 7/21/23 42 Prepare draft report 40 days Fri 4/21/23 Thu 6/15/23 43 Finalize draft report 3 days Wed 7/19/23Fri 7/21/23
44 Task 4 Public Stakeholder Outreach 437 days Fri 3/3/23 Mon 11/4/24 45 Develop Community Outreach Strategy Memorandum 19 days Fri 3/3/23 Wed 3/29/23 46 Prepare outreach materials 15 days Mon 5/1/23 Fri 5/19/23 47 Outreach Meeting No. 1 0 days Sat 5/20/23 Sat 5/20/23 48 Prepare outreach materials 30 days Tue 9/24/24 Mon 11/4/24 49 Outreach Meeting No. 2 0 days Mon 11/4/24Mon 11/4/24 50 Task 5 Draft Plans, Specifications & Estimate (60% PS&E) 230 days Tue 7/25/23 Mon 6/10/24 51 Task 5.1 60% Plans 65 days Tue 7/25/23 Mon 10/23/23
52 Task 5.2 60% Technical Specifications 10 days Tue 10/3/23 Mon 10/16/23 53 Task 5.3 60% Engineer’s Opinion of Probable Construction Cost (Estimate)15 days Tue 10/3/23 Mon 10/23/23 54 Submit 60% QA/QC Review Package 0 days Mon 10/23/23Mon 10/23/23 55 Updates to 60% PS&E based on QA/QC Review 5 days Tue 10/31/23Mon 11/6/23 56 Submittal of 60% PS&E 0 days Mon 11/6/23Mon 11/6/23
57 City Review of 60% PS&E 155 days Tue 11/7/23 Mon 6/10/24 58 Task 6 90% PS&E 65 days Tue 8/6/24 Mon 11/4/24
59 Task 6.1 90% Plans 20 days Tue 8/6/24 Mon 9/2/24
60 Task 6.2 90% Technical Specifications 10 days Tue 8/20/24 Mon 9/2/24 61 Task 6.3 90% Estimate 10 days Tue 8/20/24 Mon 9/2/24 62 Task 6.4 Draft Final 90% Stormwater Design Report, O&M Manual 20 days Tue 8/20/24 Mon 9/16/24 63 Submit 90% QA/QC Review Package 0 days Mon 9/2/24 Mon 9/2/24 64 Updates to 90% PS&E based on QA/QC Review 10 days Tue 9/10/24 Mon 9/23/24 65 Submittal of 90% PS&E, SDR, O&M 0 days Mon 9/23/24Mon 9/23/24 66 City Review of 90% PS&E, SDR, O&M 30 days Tue 9/24/24 Mon 11/4/24 67 Task 7 Final PS&E 50 days Tue 11/5/24 Mon 1/13/25
68 Task 7.1 Final Plans 10 days Tue 11/5/24 Mon 11/18/24 69 Task 7.2 Final Technical Specifications 5 days Tue 11/12/24Mon 11/18/24 70 Task 7.3 Final Estimate 5 days Tue 11/12/24Mon 11/18/24 71 Task 7.4 Final Stormwater Design Report, O&M Manual 5 days Tue 11/12/24Mon 11/18/24 72 Submittal of Final PS&E Package 0 days Mon 11/18/24Mon 11/18/24 73 City Review and Advertise 40 days Tue 11/19/24Mon 1/13/25 74 Task 8 Bidding Support 30 days Tue 1/14/25 Mon 2/24/25 75 Task 9 Construction Support 180 days Tue 2/25/25 Mon 11/3/25 1/10
1/10
1/26
7/18
2/20
5/31
5/20
11/4
10/23
11/6
9/2
9/23
11/18
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Manual Progress
Wallace Group Team Schedule for the
City of Salinas
CLOSTER PARK GREEN STREETS PROJECT
2024-06-24 CPGS Schedule.mpp Page 1
Project: 2024-06-24 CPGS Schedu
Date: Tue 7/2/24
Exhibit A
Wallace Group Team Resource Estimate for the
CITY OF SALINAS CLOSTER PARK GREEN STREETS PROJECT - CA #4 BUDGET SUMMARY
PRINCIPAL
SENIOR ENGINEER III
SENIOR ENGINEER I
ASSOCIATE ENGINEER II
DIRECTOR OF LANDSCAPE
ARCHITECTURE
SENIOR LANDSCAPE ARCHITECT II
LANDSCAPE ARCHITECT II
PROJECT ASSISTANT III
CRAFT WATER
BUTANO
Misc. Direct Costs
TOTAL LABOR HOURS TOTAL
TASK DESCRIPTION HRS HRS HRS HRS HRS HRS HRS HRS HRS HRS Cost HRS LABOR COST RATE $270 $210 $200 $145 $185 $165 $145 $135 $ $
1 Project Coordination and Management
1.1 Project Management 2 18 4 6 30 $5,690 $5,690
3 Preliminary Design
3.1 Concept Refinement 12 48 1 4 6 71 $11,075 $11,075
3.3 Lighting Analysis 1 52 6 59 $12,390 $12,390
6 90% PS&E
6.1 90% Plans 24 24 60 1 6 32 147 $24,355 $24,355
6.2 90% Technical Specifications 6 2 8 $1,660 $1,660
6.3 90% Estimate 4 2 2 4 8 20 $3,430 $3,430
7 Final PS&E
7.1 Final Plans 12 2 4 18 $3,500 $3,500
7.2 Final Technical Specifications 2 1 3 $620 $620
7.3 Final Estimate 2 1 3 $620 $620
8 Bidding Support 4 4 $840 $840
9 Construction Support 8 8 $1,680 $1,680
SUB-TOTALS 3 114 68 112 8 14 46 6 371 #REF! $65,860
WALLACE GROUP LABOR COSTS $ 810 $23,940 $13,600 $16,240 $1,480 $2,310 $6,670 $810 $65,860
WALLACE GROUP DIRECT COSTS
DIRECT COSTS OVERHEAD @ 15%
TOTAL $65,860
Task Budgets may fluctuate within Overall Budget
PHASE/TASK
0886-0030 CPGS CA 4 Fee.xlsx Summary Page 1 7/2/24
Exhibit B-2
Exhibit A
Standard Billing Rates
Engineering, Design & Support Services:
Assistant Designer/Technician .................... .................... $120 Designer/Technician I – IV ....................... ...................... $125/$135/$145/$155 Senior Designer/Technician I – III ............... ...................... $165/$172/$179 GIS Technical Specialist .......................... ...................... $160 Senior GIS Technical Specialist .................. ..................... $170 Associate Engineer I – III ....................... ........................ $135/$145/$155 Engineer I – IV .................................. ......................... $170/$175/$180/$185 Senior Engineer I - III .......................... ......................... $200/$205/$210 Director ......................................... ......................... $220 Principal Engineer/Consulting Engineer ........... .................. $245 Principal ........................................ .......................... $270
Surveying Services:
Party Chief ...................................... ......................... $182 Party Chief (*Prevailing Wage) ................... ..................... $250 Instrument Person ................................ ...................... $125 Instrument Person (*Prevailing Wage) ............. .................. $150 Associate Survey Technician ..................... ..................... $120 Survey Technician I – IV ......................... ....................... $135/$140/$150/$155 Land Surveyor I – III ............................ ......................... $160/$170/$180 Senior Land Surveyor I - III ..................... ........................ $185/$190/$195 Director ......................................... ......................... $220 Principal Surveyor ............................... ....................... $245 Principal ........................................ .......................... $270
Planning Services:
Associate Planner I - II ......................... ........................ $110/$120 Planner I – IV ................................... .......................... $140/$150/$160/$170 Senior Planner I - III ........................... ......................... $175/$180/$185 Director ......................................... ......................... $200 Principal Planner ................................ ........................ $210 Principal ........................................ .......................... $270
Landscape Architecture Services:
Associate Landscape Designer I – II .............. ..................... $105/$115 Designer I – IV .................................. ......................... $120/$125/$130/$135 Landscape Architect I - IV ....................... ...................... $140/$145/$150/$155 Senior Landscape Architect I - III ............... ...................... $160/$165/$170 Director ......................................... ......................... $185 Principal Landscape Architect .................... .................... $210 Principal ........................................ .......................... $270
Exhibit D
Exhibit C
2024 Standard Billing Rates 1
Construction Management / Field Inspection Services:
Construction Inspector I - II .................... ........................ $140/$155 Senior Construction Inspector .................... ..................... $160 Construction Inspector (*Prevailing Wage) ........ .................. $180 Construction Office Tech I-III ................... ....................... $115/$125/$135 Assistant Resident Engineer I - II................ ...................... $165/$170 Resident Engineer I - III ........................ ........................ $175/$180/$185 Senior Resident Engineer ......................... ..................... $195 Director ......................................... ......................... $220 Principal Construction Manager ................... .................... $245 Principal ........................................ .......................... $270
Public Works Administration Services:
Project Analyst I - IV ........................... ........................ $120/$130/$140/$150 Senior Project Analyst I - III ................... ........................ $155/$160/$165 Senior Environmental Compliance Specialist I - III ................. $170/$175/$185
Support Services:
Office Assistant ................................. ........................ $110 Project Assistant I – III ........................ .......................... $120/$125/$135
*Prevailing Wage:
State established prevailing wage rates will apply to some services based on state law, prevailing wage rates are subject to change over time and geographic location.
Right to Revisions:
Wallace Group reserves the right to revise our standard billing rates on an annual basis, personnel classifications may be added as necessary.
Additional Professional Services:
Fees for expert witness preparation, testimony, court appearances, or depositions will be billed at the rate of $400 an hour. If required to meet schedule requests, overtime on a project will be billed at 1.5 times the employee’s typical hourly rate.
Direct Expenses:
Direct expenses will be invoiced to the client and a handling charge of 15% may be added.
Sample direct expenses include, but are not limited to the following:
•
travel expenses • sub -consultant service s • agency fees • delivery/copy services • mileage (per IRS rates) • other direct expenses
Invoicing and Interest Charges :
Invoices are submitted monthly on an accrued cost basis. A finance charge of 1.5% per month may be assessed on all balances that are thirty days past due.
WALLACE GROUP 2
2024 Standard Billing Rates