City of Salinas

Sewer System Management Plan

Revision 2 – May 2025

WDID: 3SSO10314

Prepared By:

Sewer System Management Plan – Revision 02

City of Salinas
May 2025
Page i

City of Salinas

SEWER SYSTEM MANAGEMENT PLAN
Revision 2
WDID: 3SSO10314
May 2025

The Sewer System Management Plan, Revision 2 was created with the assistance of the following City of Salinas and Wallace Group Staff:

City of Salinas Staff
Gary Gabriel, Wastewater Manager
Adriana Robles, PE, CFM, City Engineer
Ray Lerma, Wastewater Supervisor
Wallace Group Staff
Bill Callahan, Senior Environmental Compliance Specialist

Sewer System Management Plan – Revision 02
Certification Statement

City of Salinas
May 2025
Page ii

CERTIFICATION STATEMENT
I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations.

______________________________________
Gary Gabriel
Wastewater Manager / LRO
Sewer System Management Plan – Revision 02

City of Salinas
May 2025
Page iii
SSMP – REVISION RECORD
City of Salinas Sewer System SSMP has undergone the following revisions:

Revision
No. Revision Date Description of
Revisions
Revision
Completed By
Revision
Approved By
0 July 2009
The City developed an
initial Sewer System
Management Plan
(SSMP) to address the
requirements of the
2006 Sanitary Sewer
System (SSS) Orders
issued by the State
Water Resources
Control Board
(SWRCB).
1st SSMP City
Staff
City
Wastewater
Division
Manager and
City Council
1 December 2019
The SSMP was
updated based on the
findings of the 2019
SSMP Audit.

City Staff and
Wallace Group
City
Wastewater
Division
Manager and
City Council
2 May 2025
The SSMP was
updated based on the
findings of the 2024
SSMP Audit and based
on regulatory
requirements in the
2022 WDRs.

City Staff and
Wallace Group
City
Wastewater
Division
Manager and
City Council

Sewer System Management Plan – Revision 02
Table of Contents

City of Salinas
May 2025
Page iv

TABLE OF CONTENTS
Acronyms and Abbreviations
SSMP Update and Adoption Record
Introduction
▪ Section 0.1 – Requirement Background
▪ Section 0.2 – Introduction & Executive Summary
Element 1 – Goals, Regulatory Context, Asset Overview and Schedule ▪ Section 1.1 – Regulatory Requirement
▪ Section 1.2 – Sanitary Sewer System Goals
▪ Section 1.3 – Regulatory Context and Schedule for Audits and Updates ▪ Section 1.4 – System Asset Overview and Service Area
Element 2 – Organization
▪ Section 2.1 – Regulatory Requirements
▪ Section 2.2 – Responsible and Authorized Representatives ▪ Section 2.3 – SSMP Program Implementation
▪ Section 2.4 – Chain of Communication for Responding to Sewer Spills Element 3 – Legal Authority
▪ Section 3.1 – Regulatory Requirements
▪ Section 3.2 – SSMP Sanitary Sewer System Legal Authority Element 4 – Operation and Maintenance Program
▪ Section 4.1 – Regulatory Requirements
▪ Section 4.2 – Collection System and Storm Water Maps
▪ Section 4.3 – Preventative Maintenance Program
▪ Section 4.4 – Training

Sewer System Management Plan – Revision 02
Table of Contents

City of Salinas
May 2025
Page iv

TABLE OF CONTENTS
▪ Section 4.5 – Equipment and Replacement Parts Inventory Element 5 – Design and Performance Provisions
▪ Section 5.1 – Regulatory Requirements
▪ Section 5.2 – Design and Construction Standards and Specifications ▪ Section 5.3 – Inspection and Testing Procedures and Standards Element 6 – Spill Emergency Response Plan
▪ Section 6.1 – Regulatory Requirements
▪ Section 6.2 – Initial Spill Notification Procedures
▪ Section 6.3 – Spill Response Program
▪ Section 6.4 – Spill Notification and Reporting Procedures ▪ Section 6.5 – SERP Training
▪ Section 6.6 – Spill Impact Mitigation Program
▪ Section 6.7 – Spill Coordination with Stormwater Management Agencies and Public Water Systems
▪ Section 6.8 – Post Spill Investigations
Element 7 – Pipe Blockage Control Program
▪ Section 7.1 – Regulatory Requirements
▪ Section 7.2 – Pipe Blockage Control Program Public Education and Outreach ▪ Section 7.3 – FOG Disposal Facilities
▪ Section 7.4 – Discharge Prohibition Legal Authority and Spill Prevention Measures ▪ Section 7.5 – Requirements to Install Grease Removal Devices ▪ Section 7.6 – FOG Control Program Inspection, Enforcement, and Staffing ▪ Section 7.7 – Problem Areas Identification and Sewer Cleaning ▪ Section 7.8 – Other Source Control Measures
Sewer System Management Plan – Revision 02
Table of Contents

City of Salinas
May 2025
Page iv

TABLE OF CONTENTS
Element 8 – System Evaluation, Capacity Assurance and Capital Improvement Plan ▪ Section 8.1 – Regulatory Requirements
▪ Section 8.2 – System Evaluation and Condition Assessment ▪ Section 8.3 – Capacity Evaluation Design Criteria
▪ Section 8.4 – Prioritization of Corrective Actions
▪ Section 8.5 – Capital Improvement Plan
▪ Section 8.6 - Additional WDR Requirements
Element 9 – Monitoring, Measurement, and Program Modifications ▪ Section 9.1 – Regulatory Requirements
▪ Section 9.2 – Data Management
▪ Section 9.3 – Establishing and Prioritizing SSMP Activities ▪ Section 9.4 – Preventative Maintenance Program Assessment ▪ Section 9.5 – SSMP Updates
▪ Section 9.6 – Sewer Spill Trends
Element 10 – Sewer System Management Plan Program Audits ▪ Section 10.1 – Regulatory Requirements
▪ Section 10.2 – SSMP Program Audits
Element 11 – Communication Program
▪ Section 11.1 – Regulatory Requirements
▪ Section 11.2 – Communication Program
▪ Section 11.3 – Satellite & Tributary Systems

Sewer System Management Plan – Revision 02
Table of Contents

City of Salinas
May 2025
Page iv

TABLE OF CONTENTS
Appendices
▪ Appendix 0A – PLACEHOLDER: Meeting Minutes Adopting SSMP, Revision 2 ▪ Appendix 2A – City Organization Charts
▪ Appendix 2B – City Organization Chart Contact Information ▪ Appendix 4A – Hot Spot List
▪ Appendix 4B – Lift Station and Force Main Data
▪ Appendix 8A – Lift Station CIP Ranking Matrix
▪ Appendix 8B – CIP Ranking Matrix
▪ Appendix 8C1 – Existing CIP
▪ Appendix 8C2 – Existing Lift Station CIP
▪ Appendix 8C3 – Future CIP
▪ Appendix 8D – City Capital Projects
▪ Appendix 10A – SSMP Audit and Data Request Template
Sewer System Management Plan – Revision 02
Acronyms and Abbreviations

City of Salinas
May 2025
Page v

ACRONYMS AND ABBREVIATIONS
BMP Best Management Practices
CAP Capacity Assessment Plan
Cal OES California Office of Emergency Services
Cal/OSHA California Division of Occupational Health and Safety CCR California Code of Regulations
CCTV Closed Circuit Television
CDFW California Department of Fish and Wildlife
CFR Code of Federal Regulations
CIP Capital Improvement Plan
CITY City of Salinas
CIWQS California Integrated Water Quality System
CMMS Computerized Maintenance Management System
CWEA California Water Environment Association
EHS Environmental Health Services
ELAP Environmental Laboratory Accreditation Program
EOP Emergency Operating Procedure
ENROLLEE City of Salinas
EPA Environmental Protection Agency
FOG Fats, Oil, and Grease
FSE Food Services Establishment
HMA High Maintenance Area
I/I Inflow & Infiltration
IIPP Injury and Illness Prevention Program
IWF Industrial Waste Facility
LRO Legally Responsible Official
mgd Million Gallons per Day
MRP Monitoring and Reporting Program (Used in this SSMP to reference MRP Order No. 2022-0103-DWQ.)
SERP Spill Emergency Response Plan
OES Office of Emergency Services
O&M Operation and Maintenance
OSHA Occupational Safety and Health Administration
Sewer System Management Plan – Revision 02
Acronyms and Abbreviations

City of Salinas
May 2025
Page v

ACRONYMS AND ABBREVIATIONS
PLSD Private Lateral Sewage Discharge
PM Preventative Maintenance
PPE Personal Protective Equipment
R&R Rehabilitation and Replacement
RWQCB Central Coast Regional Water Quality Control Board SCADA Supervisory Control and Data Acquisition
SECACIP Sewer Evaluation, Capacity Assurance and Capital Improvement Plan SMP Sewer Master Plan
SOP Standard Operating Procedure
SSMP Sewer System Management Plan
SPILL Sanitary Sewer Spill
SSS Sanitary Sewer System
SWRCB State Water Resources Control Board
WDR Waste Discharge Requirements (Used in this SSMP to reference WDR Order No. 2022-0103-DWQ, the Statewide General WDR for SSSs.) Sewer System Management Plan – Revision 02
Introduction

City of Salinas
May 2025

Page 0 ends

INTRODUCTION
This Sewer System Management Plan (SSMP) six (6) year update was performed in compliance with the requirements of the State Water Resources Control Board (SWRCB) Statewide General Waste Discharge Requirements (WDR), Order No. 2022-0103-DWQ, which are available at the City Wastewater Division Office and on the State Water Resources Control Board website: https://www.waterboards.ca.gov/water_issues/programs/sso/ .

0.1 Requirement Background
The WDRs require all public wastewater collection system agencies in California that own and operate sanitary sewer systems greater than one mile in length, which collect or convey untreated or partially treated wastewater to a publicly owned treatment facility, to develop, implement, and maintain a SSMP and report sanitary sewer spills(Spills) using the State’s electronic reporting system, California Integrated Water Quality System (CIWQS).

The City of Salinas (City) SSMP includes the following eleven (11) Elements:

1. Goal

2. Organization

3. Legal Authority

4. Operation and Maintenance Program

5. Design and Performance Provisions

6. Spill Emergency Response Plan

7. Pipe Blockage Control Program

8. System Evaluation, Capacity Assurance and Capital Improvement Plan

9. Monitoring, Measurement, and Program Modifications

10. Sewer System Management Plan Program Audits

11. Communication Program
Each SSMP Element is prefaced with the associated WDR section and narrated with the City’s policies and procedures, which address the respective SWRCB requirement.

Sewer System Management Plan – Revision 02
Introduction

City of Salinas
May 2025

Page 0 ends

EXECUTIVE SUMMARY
The State Water Resources Control Board’s (SWRCB’s) Statewide General Waste Discharge Requirements (WDR) for Sanitary Sewer Systems, Order No. 2022-0103-DWQ require the City of Salinas (City) to have and maintain a Sewer System Management Plan (SSMP), which provides a plan and schedule to properly manage, operate, and maintain all parts of the sanitary sewer system in order to help reduce and prevent sanitary sewer spills (Spills), as well as mitigate any Spills that do occur.

The SSMP includes the following eleven (11) Elements:

Goal
City goals, which are included in the SSMP, are:
▪ Properly manage, operate, and maintain the wastewater collection system; ▪ Maintain design construction standards and specifications for the installation of new wastewater systems;
▪ Verify the wastewater collection system has adequate capacity to convey industrial wastewater during peak flows;
▪ Minimize the frequency of system overflows;
▪ Respond to system overflows quickly and mitigate the impact of the overflow; ▪ Provide training on a regular basis for staff in collection maintenance and operations;
▪ Develop a closed-circuit televising (CCTV) program for the industrial sewer collection system;
▪ Identify and prioritize structural deficiencies and implement short-term and long-term maintenance and rehabilitation actions to address each deficiency;
▪ Meet all applicable regulatory notification and reporting requirements; and ▪ Provide excellent customer service.

Organization
The Organization Element of the SSMP identifies City and Contract Staff, who are responsible for implementing the SSMP, responding to sewer spills, and meeting sewer spill reporting requirements, and identifies the lines of authority of SSMP responsibilities and chains of communication for sewer spill response and reporting. The Legally Responsible Officials (LRO) are also designated in this SSMP Element in order to meet the SWRCB requirements for completing and certifying sewer spill reports in the SWRCB’s online regulatory information database and tracking system, California Integrated Water Quality System (CIWQS).

Sewer System Management Plan – Revision 02
Introduction

City of Salinas
May 2025

Page 0 ends

Legal Authority
This SSMP Element outlines the City Municipal Code Chapters and Ordinances that provide the City with the legal authority to:
a. Prevent illicit discharges into its sanitary sewer system from inflow and infiltration (I&I); unauthorized stormwater; chemical dumping; unauthorized debris; roots; fats, oils, and grease; and trash, including rags and other debris that may cause blockages;
b. Collaborate with storm sewer agencies to coordinate emergency spill responses, ensure access to storm sewer systems during spill events, and prevent unintentional cross connections of sanitary sewer infrastructure to storm sewer infrastructure;
c. Require that sewer system components and connections be properly designed and constructed;
d. Ensure access for maintenance, inspection, and/or repairs for portions of the service lateral owned and/or operated by the Enrollee;
e. Enforce any violation of its sewer ordinances, service agreements, or other legally binding procedures; and
f. Obtain easement accessibility agreements for locations requiring sewer system operations and maintenance, as applicable.

Operation and Maintenance Program
City operation and maintenance of its collection system ensures that the system is kept in good working condition, and this SSMP Element outlines the work that is conducted to accomplish the optimal operation and maintenance of the City collection and conveyance system. This SSMP Element details a:
a. Up-to-date maps of the sanitary sewer system, and procedures for maintaining and providing State and Regional Water Board staff access to the maps. The maps must show gravity line segments and manholes, pumping facilities, pressure pipes and valves, and applicable stormwater conveyance facilities within the sewer system service area boundaries.;
b. A scheduling system and a data collection system for preventive operation and maintenance activities conducted by staff and contractors. a. The scheduling system includes:
i. Inspection and maintenance activities;
ii. Higher-frequency inspections and maintenance of known problem areas, including areas with tree root problems;
iii. Regular visual and closed-circuit television (CCTV) inspections of manholes and sewer pipes.

The data collection system documents data from system inspection and Sewer System Management Plan – Revision 02
Introduction

City of Salinas
May 2025

Page 0 ends

maintenance activities, including system areas/components prone to root- intrusion potentially resulting in system backup and/or failure. c. In-house and external training provided on a regular basis for sanitary sewer system operations and maintenance staff and contractors. The training covers:
i. The requirements of this General Order;
ii. The Enrollee’s Spill Emergency Response Plan procedures and practice drills;
iii. Skilled estimation of spill volume for field operators; and iv. Electronic CIWQS reporting procedures for staff submitting data. d. An inventory of sewer system equipment, including the identification of critical replacement and spare parts.

Design and Performance Provisions
The Design and Performance Provisions Element describes the standards and specifications for new construction, repair of the existing sanitary sewer system, and the inspection and testing of these items.

Spill Emergency Response Plan
The Spill Emergency Response Plan (SERP) contains the following information in order to protect public health and the environment in the event of a sewer spill:
a. Notify primary responders, appropriate local officials, and appropriate regulatory agencies of a spill in a timely manner;
b. Notify other potentially affected entities (for example, health agencies, water suppliers, etc.) of spills that potentially affect public health or reach waters of the State;
c. Comply with the notification, monitoring and reporting requirements of this General Order, State law and regulations, and applicable Regional Water Board Orders;
d. Ensure that appropriate staff and contractors implement the Spill Emergency Response Plan and are appropriately trained;
e. Address emergency system operations, traffic control and other necessary response activities;
f. Contain a spill and prevent/minimize discharge to waters of the State or any drainage conveyance system;
g. Minimize and remediate public health impacts and adverse impacts on beneficial uses of waters of the State;
h. Remove sewage from the drainage conveyance system;
Sewer System Management Plan – Revision 02
Introduction

City of Salinas
May 2025

Page 0 ends

i. Clean the spill area and drainage conveyance system in a manner that does not inadvertently impact beneficial uses in the receiving waters; j. Implement technologies, practices, equipment, and interagency coordination to expedite spill containment and recovery;
k. Implement pre-planned coordination and collaboration with storm drain agencies and other utility agencies/departments prior, during, and after a spill event; l. Conduct post-spill assessments of spill response activities; m. Document and report spill events as required in this General Order; and n. Annually, review and assess effectiveness of the Spill Emergency Response Plan, and update the Plan as needed.

Pipe Blockage Control Program
The goal of the Pipe Blockage Control Program is to reduce and/or eliminate the amount of pipe blocking materials such as fats, oils and grease wipes, roots, etc., that may be discharged to the sanitary sewer system. This is implemented through public outreach, operations and maintenance activities, investigations and FOG Program inspections.

System Evaluation, Capacity Assurance, and Capital Improvement Plan The City completed a Sanitary Sewer Master Plan Update (SSMPU) in 2023 to assess the existing, near term and long-term capacity needs and the condition of the system to safely collect and convey wastewater. The SSMPU identified capital improvement projects which included staff O&M based projects, hydraulicly deficient projects, lift station evaluation projects and ongoing CCTV data. The City prioritized these projects based on the following criteria:
o Overflow to Waters of the State
o Ability to meet Design Criteria
o O&M Hot Spots
o Community Impacts
o Surcharge
These analyses identify areas that are capacity deficient and/or structurally deficient under existing and future conditions. Recommended capital improvement projects are prioritized as a result of this analysis. An additional Vulnerability Assessment will be required to meet some of the additional (2022) requirements included in the WDRs.

Monitoring, Measurement, and Program Modifications
The City monitors the implementation of the SSMP Elements in order to measure the effectiveness of the City SSMP program in reducing sewer spills. This SSMP Element outlines the manner in which each SSMP Element is monitored and evaluated and the schedule with which the City completes this monitoring and evaluation.

Sewer System Management Plan – Revision 02
Introduction

City of Salinas
May 2025

Page 0 ends

Sewer System Management Plan Program Audits
The SSMP Program Audits Element outlines the audit process and identifies City Staff responsible for conducting or participating in SSMP Program Audits and generating the required SSMP Program Audit Report. SSMP Program Audits must occur at a minimum of every three (3) years and are required to evaluate the City SSMP Program, identify program deficiencies, and provide an improvement schedule based on the audit findings.

Communication Program
This SSMP Element describes the manner in which the City communicates the development, implementation, and performance of its SSMP with the public in order to provide them with the opportunity to provide input as the SSMP program is developed and implemented.

Sewer System Management Plan – Revision 02
Element 1 – Goal

City of Salinas
May 2025

Page 1 ends

ELEMENT 1 - GOALS, REGULATORY CONTEXT, ASSET OVERVIEW AND

SCHEDULE
The City of Salinas (City) has the following goals for the management and maintenance of the sanitary sewer collection system. These goals provide focus for City Staff to continue high- quality work to operate and maintain City facilities and to implement improvements for management of the collection system to prevent sanitary sewer spills (Spills). The role of the SSMP in supporting these goals is discussed below.

These goals will be evaluated annually in Element 9: Monitoring, Measurement and Program Modification to assess the City’s success in implementing and meeting the objectives of these goals.

1.1 Regulatory Requirement
WDR Order No. 2022-0103-DWQ Attachment D1 states:

The goal of the Sewer System Management Plan (Plan) is to provide a plan and schedule to: (1) properly manage, operate, and maintain all parts of the Enrollee’s sanitary sewer system(s), (2) reduce and prevent spills, and (3) contain and mitigate spills that do occur.

1.2 Sanitary Sewer System Goals
The City seeks to provide high quality and reliable wastewater collection and conveyance for its residents and businesses.

City SSMP Goals:
▪ Properly manage, operate, and maintain the wastewater collection system; ▪ Maintain design construction standards and specifications for the installation of new wastewater systems;
▪ Verify the wastewater collection system has adequate capacity to convey industrial wastewater during peak flows;
▪ Minimize the frequency of system overflows;
▪ Respond to system overflows quickly and mitigate the impact of the overflow; ▪ Provide training on a regular basis for staff in collection maintenance and operations;
▪ Develop a closed-circuit televising (CCTV) program for the industrial sewer collection system;
▪ Identify and prioritize structural deficiencies and implement short-term and long-term maintenance and rehabilitation actions to address each deficiency;
▪ Meet all applicable regulatory notification and reporting requirements; and ▪ Provide excellent customer service.

Sewer System Management Plan – Revision 02
Element 1 – Goal

City of Salinas
May 2025

Page 1 ends

1.3 Regulatory Context and Schedule for Audits and Updates As required by Statewide Sanitary Sewer Systems General Order 2022-0103-DWQ, the SSMP contains several elements which are referenced in the table of contents that will help the City accomplish the goals mentioned in this element. The City is dedicated to implementing each Element of the SSMP and tracking any revisions that may be necessary as program implementation progresses. The current 2025 SSMP update was completed prior to the due date of May 2, 2025.

The City will begin their next SSMP Audit after May 2, 2027, Audit Period End Date with an identified Audit period of May 2, 2024, through May 2, 2027, for completion by November 2, 2027. The Audit will evaluate how the SSMP meets regulatory requirements, implementation of the SSMP, success of preventative maintenance program, and sewer spill trends. A plan and schedule will be developed for the correction of any deficiencies identified in the audit and any necessary updates or general plan changes that may be required.

The City will annually review and evaluate the SSMP, Preventative Maintenance Program, and Spill Trends to identify areas of their sewer operations that may need to be modified to comply with existing regulatory requirements and reduce the number of sewer spills occurring in a calendar year.

The SSMP 6-Year Update will begin on or before January 2031 for completion, adoption and recertification by May 2, 2031.

In addition to the SSMP Update and SSMP Audit discussed above, the City has identified additional near-term compliance dates as required by General Order WQ-2022-0103-DWQ:
• Annual Report of Category 4 Non-Lateral Spills: February 1st of each calendar year • Annual Report: April 1st of each calendar year
• Electronic Sanitary Sewer System Service Area Boundary Map: December 31, 2025

1.4 System Asset Overview and Service Area
The City sewer collection and conveyance system is located in Monterey County and consists of 292 miles of gravity pipelines, which vary in diameter from 6 -inch to 54 -inches, ten (10) City - owned lift stations, one (1) City-maintained lift station, and two (2) miles of force mains with two (2) air/vacuum relief valves. Approximately 70% of the City’s collection system was constructed before 1980, with 41% of the system constructed between 1960 -1979. The remaining 30% of the system was constructed from 1980 to present. Most of the existing collection system piping material is Vitrified Clay Pipe (VCP). Although Polyvinyl Chloride (PVC) pipe would have likely been installed with newer construction from 1980 to present.

There are 3,462 Manholes and 1,403 cleanouts throughout the system. The sewer system is restricted to providing sanitary sewer flows only with no diversion of stormwater into the sewer system.

Sewer System Management Plan – Revision 02
Element 1 – Goal

City of Salinas
May 2025

Page 1 ends

The following table shows the various pipeline sizes:

Pipe Diameter (Inches) Length (Miles) Percent of Sewer
System
Unknown 27.5 9.6%
6” 61.3 21.4%
8” 124.0 43.2%
10” 19.9 6.9%
12” 14.2 5.0%
15” 10.1 3.5%
18” 9.2 3.2%
21” 4.4 1.5%
24” 3.8 1.3%
27” 2.6 0.9%
30” 2.6 0.9%
33” 1.2 0.4%
36” 0.5 0.2%
42” 1.8 0.6%
48” 1.2 0.4%
54” 2.4 0.9%
TOTAL 286.7 100%

The City serves a population of approximately 159,506 people¹. Sewer system customers are broken down as follows:

Type of Connection % of Total Connections
Residential 37.7%
Commercial 55.8%
Industrial 6.5%
Total 100%

A general overview showing the service area boundaries is provided below.

¹ United States Census Bureau, Population Estimate 2023 Sewer System Management Plan – Revision 02
Element 1 – Goal

City of Salinas
May 2025

Page 1 ends

Data management for the operations and maintenance of the sewer systems is provided utilizing the City Computerized Maintenance Program utilizing ArcGIS field mapping applications. The web -based application includes map updates, data storage and produces tasks for sewer inspections and maintenance.

Sewer laterals are owned, operated and maintained by individual property owners from the wye connection at the sewer main, back to each building. The City does not own or maintain any sewer laterals within the service area other than laterals on City owned property.

Sewer System Management Plan – Revision 02
Element 2 – Organization

City of Salinas
May 2025

Page 2 ends

ELEMENT 2 - ORGANIZATION
The Organization Element of the SSMP identifies City of Salinas (City) staff that are responsible for the management and implementation of this SSMP. This Element identifies staff’s responsibilities responding to sewer spill events, and meeting sewer spill reporting requirements. The Legally Responsible Officials (LRO) are designated below to meet SWRCB requirements for completing and certifying sewer spill reports in the California Integrated Water Quality System (CIWQS).

This SSMP Element outlines the City organization, SSMP responsibilities of personnel, authorized representatives, and chains of communication for sewer spill response and reporting.

2.1 Regulatory Requirements
WDR Order No. 2022-0103-DWQ Attachment D 2 states:

The collection system agency’s SSMP must identify:
a) The name of the Legally Responsible Official defined in this Order; b) The position titles, telephone numbers, and email addresses for management, administrative, and maintenance positions responsible for implementing specific Sewer System Management Plan elements;
c) Organizational lines of authority; and
d) Chain of communication for reporting spills from receipt of complaint or other information, including the person responsible for reporting spills to the State and Regional Water Boards and other agencies, as applicable. (For example, county health officer, county environmental health agency, and State Office of Emergency Services.) WDR Order No. 2022-0103-DWQ Section 5.1 states:

The Enrollee shall designate a Legally Responsible Official that has authority to ensure the enrolled sanitary sewer system(s) complies with this Order and is authorized to serve as a duly authorized representative. The Legally Responsible Official must have responsibility over management of the Enrollee’s entire sanitary sewer system and must be authorized to make managerial decisions that govern the operation of the sanitary sewer system, including having the explicit or implicit duty of making major capital improvement recommendations to ensure long-term environmental compliance. The Legally Responsible Official must have or have direct authority over individuals that:
• Possess a recognized degree or certificate related to operations and maintenance of sanitary sewer systems, and/or

• Have professional training and experience related to the management of sanitary sewer systems, demonstrated through extensive knowledge, training and experience.

Sewer System Management Plan – Revision 02
Element 2 – Organization

City of Salinas
May 2025

Page 2 ends

2.2 Responsible and Authorized Representatives
The name of the authorized representatives described in WDR Section 5.1 above is listed in Table 2-1:

Table 2-1: City of Salinas Authorized Representatives
Name Title CIWQS SSO Database
Gary Gabriel Wastewater Manager Legally Responsible Official Ray Lerma Wastewater Crew Supervisor Legally Responsible Official

2.3 SSMP Program Implementation
An organization table showing the lines of authority for the City is described below in Table 2-2 and updated City Organization Charts which show lines of authority can be found in Appendix 2A & 2B.

Sewer System Management Plan – Revision 02
Element 2 – Organization

City of Salinas
May 2025

Page 2 ends

Table 2-2: City of Salinas Staff and Contract Staff with SSMP Responsibilities and Contact Information
Name and Title SSMP Responsibilities Contact Information City Council
Dennis Donohue
Mayor

Jose Luis Barajas
Councilmember

Tony Barrera
Councilmember

Margaret D’Arrigo
Councilmember

Gloria De La Rosa
Councilmember

Andrew Sandoval
Councilmember

Aurelio Salazar
Councilmember

The City Council annually adopts a
budget in which funding would be
allocated for SSMP related tasks.

The City Council is also responsible
for considering and approving
updates to the City’s SSMP.

[email protected]
(831) 758-7201

[email protected]
(831) 758-7201

[email protected]
(831) 758-7201

[email protected]
(831) 758-7201

[email protected]
(831) 758-7201

[email protected]
(831) 758-7201

[email protected]
(831) 758-7201
Rene Mendez

City Manager
The City Manager directs City Staff
who manage all eleven (11) SSMP
Elements.

Office: (831) 758-7465
[email protected]
Christopher A.

Callihan

City Attorney
The City Attorney assists in the
management of Element 3, Legal
Authority.

Office: (831) 758-7418
[email protected]

Gary Gabriel The Wastewater Manager is
responsible for the overall
Office: (831) 758-7103
Sewer System Management Plan – Revision 02
Element 2 – Organization

City of Salinas
May 2025

Page 2 ends

Name and Title SSMP Responsibilities Contact Information Wastewater Manager

management of the SSMP and
specifically directs the implementation
of:
• Element 1 – Goal;
• Element 2 – Organization;
• Element 3 – Legal Authority;
• Element 4 - Operation and
Maintenance Program;
• Element 5 – Design and
Performance Provisions;
• Element 6 – Spill Emergency
Response Plan;
• Element 7 – Pipe Blockage
Control Program;
• Element 8 – System
Evaluation, Capacity
Assurance and Capital
Improvement Plan;
• Element 9 – Monitoring,
Measurement, and Program
Modifications;
• Element 10 – SSMP Audits;
and
• Element 11 – Communication
Program

The Wastewater Manager is assisted
by Sewer System Operators to
manage and implement these
Elements.

[email protected]

David Jacobs, Public
Works Director
The Public Works director is
responsible for Element 5 Design and
Performance Provisions and Element
8 System Evaluation, Capacity
Assurance and Capital Improvement
Plan to determine adequate design
and performance measures are in
place and that adequate hydraulic
capacities are in place for City
collection and conveyance systems.

Office: (831) 758-7390

[email protected]

Sewer System Management Plan – Revision 02
Element 2 – Organization

City of Salinas
May 2025

Page 2 ends

2.4 Chain of Communication for Responding to Sewer Spills Sewer Spill reports typically begin with a call from an observer to the City Office or 911 dispatchers.

City of Salinas
Business Hours: (831) 758-7233 7am - 3:30pm Monday through Friday, except Legal Holidays
After Hours: 911
During the process of responding to a sewer spill, the following actions are taken as outlined in Figure 3-1 and described below to verify the report and ensure the safety of the public:

1. During business hours, Wastewater Operators receive the call from an observer, the Police Department and/or the Fire Department and obtains the location of concern and a description of the problem. The name and phone number of the caller is requested and documented if not anonymous for follow-up information.

2. After hours, the Police Department and/or the Fire Department and the On-Call Staff proceeds to the location to verify the report.

3. If a sewer spill is verified, the On-Call Staff notifies the Wastewater Division Manager and directed to the described location. The Spill Emergency Response Plan (SERP) is initiated.

4. Operations staff will notify the CPO and Wastewater Manager both during and after business hours.

5. California Office of Emergency Services (CalOES) must be contacted within two (2) hours of a Category 1 or Category 2 Spill, when the Spill is over 1,000 gallons and reaches a drainage channel or surface water. The Central Coast Regional Water Quality Control Board (RWQCB) may also be notified as a courtesy or if warranted due t complications contacting OES.

Sewer System Management Plan – Revision 02
Element 2 – Organization

City of Salinas
May 2025

Page 2 ends

Figure 2-1: Sewer Spill Response Chain of Command
SSMP Element 6 – Spill Emergency Response Plan contains a chain of communication for reporting Spills for use in the field by the Operations Staff in Figure 6—1 which is the same as Figure 2-1 above.

Sewer Spill notification is outlined in the City’s – Spill Emergency Response Plan. The contact information and notification requirements associated with notifying Cal OES and other applicable agencies, such as Monterey County Environmental Health Division, are included in that SSMP Element.

Upon completion of containment and clean-up, the Wastewater Manager initiates the Draft Sewer Spill Report in CIWQS.

After-hours
Contacts
Observer
Notifies City Office
(831) 758-7233
After Hours
Observer directed
to Call 911

Emergency Phone #
911

Wastewater Staff
Responds

On Call Staff is
contacted

Wastewater Staff
Mitigates Spill
Wastewater Manager
(831) 970-7629

Compile CIWQS
Data:

On Call Staff and
Wastewater Manager
Spill Notification & Reporting to
Appropriate Agencies

If additional
resources are
necessary

If no
additional
resources
are
necessary
Sewer System Management Plan – Revision 02
Element 3 – Legal Authority

City of Salinas
May 2025

Page 3 ends

ELEMENT 3 - LEGAL AUTHORITY
The City of Salinas (City) maintains the legal authority for the sanitary sewer system in the City Municipal Code sections listed below. These Codes are on file at the City Office and can also be located on the City Website:
https://library.municode.com/ca/salinas/codes/code_of_ordinances

3.1 Regulatory Requirements
WDR Order No. 2022-0103-DWQ Attachment D 3 states:

The wastewater collection system agency must include copies or an electronic link to the Enrollee’s current sewer system use ordinances, service agreements and/or other legally binding procedures to demonstrate the Enrollee possesses the necessary legal authority to:
(a). Prevent illicit discharges into its sanitary sewer system from inflow and infiltration (I&I); unauthorized stormwater; chemical dumping; unauthorized debris; roots; fats, oils, and grease; and trash, including rags and other debris that may cause blockages;

(b). Collaborate with storm sewer agencies to coordinate emergency spill responses, ensure access to storm sewer systems during spill events, and prevent unintentional cross connections of sanitary sewer infrastructure to storm sewer infrastructure;

(c). Require that sewer system components and connections be properly designed and constructed;

(d). Ensure access for maintenance, inspection, and/or repairs for portions of the service lateral owned and/or operated by the Enrollee;

(e). Enforce any violation of its sewer ordinances, service agreements, or other legally binding procedures; and

(f). Obtain easement accessibility agreements for locations requiring sewer system operations and maintenance, as applicable.

3.2 SSMP Sanitary Sewer System Legal Authority [WDR D 3 (a) – (f)] Table 3-1 below provides the mechanisms by which the City maintains the legal authorities required by the WDRs for public and private sewer systems. Theses Codes and Ordinances can be found in the following links:

• Monterey One Water (formally MRWPCA)
http://montereyonewater.org/about_ordinances.html
• City of Salinas Codes
https://library.municode.com/ca/salinas/codes/code_of_ordinances

Sewer System Management Plan – Revision 02
Element 3 – Legal Authority

City of Salinas
May 2025

Page 3 ends

Table 3-1: City Legal Authority References
WDR Requirement City Code
D 3 (a) Prevent illicit
discharges into its sanitary
sewer system (examples
may include Inflow &
Infiltration (I/I), storm water,
chemical dumping,
unauthorized debris and cut
roots, etc.).

City Municipal Code Chapter 36-12.2 Compliance with
discharge requirements of Monterey One Water
City Municipal Code Chapter 36-20.1. Disposal of hazardous and unacceptable waste
City Municipal Code Chapter 36-20.4. Prohibition on storm drainage, ground water and unpolluted water
City Municipal Code Chapter 36-21-1 Prohibitions on Industrial Discharges
D 3 (b) Collaborate with
storm sewer agencies to
coordinate emergency spill
responses, ensure access to
storm sewer systems during
spill events, and prevent
unintentional cross
connections of sanitary
sewer infrastructure to storm
sewer infrastructure
The City owns and operates the sewer and storm drain
systems and coordinates internally for spills that may threaten the City’s storm drain system. The City monitors new
infrastructure projects through plan checks and construction inspection to ensure cross connections do not occur between sewer and storm drain systems. The following Code sections restrict illegal/cross connections:
• Sec. 29 -9 General discharge prohibition —Illegal
discharges
• Sec 29-13 Illicit Connections
D 3 (c) Require that sewers
and connections be properly
designed and constructed;
City of Salinas Standard Specifications, Design Standards and Standard Plans 2008 Edition & Municipal Code Chapter 2, Article IX, Section 2-52: Compliance Required
City Resolution No. 11648 for Installation of Sewer Laterals https://www.cityofsalinas.org/Your-Government/Find-a-
Department/Public-Works/PW-Maintenance-
Services/Environmental-Maintenance-Services/Sanitary-
Sewer-Maintenance

D 3 (d) Ensure access for
maintenance, inspection, or
repairs for portions of the
lateral owned or maintained
by the Public Agency;
The City does not own any portion of private sewer laterals in the service area however the following code give them access to sewer laterals:

Chapter 36, Section 36-34 Inspection of Premises and Access to Records

Sewer System Management Plan – Revision 02
Element 3 – Legal Authority

City of Salinas
May 2025

Page 3 ends

WDR Requirement City Code
D 3 (e) Enforce any violation
of its sewer ordinances.

City Municipal Code Chapter 36 -12.2 Compliance with
discharge requirements of MRWPCA.

MRWPCA (Monterey One Water) Ordinance No. 2008-01
which establishes the regulation of wastewater.

D 3 (f) Obtain easement
accessibility agreements for
locations requiring sewer
system operations and
maintenance, as applicable
The City has the legal authority to develop easements as necessary for underground utilities.

City Municipal Code Chapter 31 Subdivision Ordinance:

Section 31-903.12 - Easements

Sewer System Management Plan – Revision 02
Element 4 – Operation and Maintenance Program

City of Salinas
May 2025

Page 4 ends

ELEMENT 4 - OPERATION AND MAINTENANCE PROGRAM
The City of Salinas (City) provides sanitary sewer collection and conveyance services the City’s sewer system. The City service area consists of approximately 286.7 miles of gravity pipelines, which vary in diameter from 6-inch to 54-inches, ten (10) City-owned lift stations, one (1) City- maintained lift station, and two (2) miles of force mains with two (2) air/vacuum relief valves.

Approximately 70% of the City’s collection system was constructed before 1980, with 41% of the system constructed between 1960-1979. The remaining 30% of the system was constructed from 1980 to present. Most of the existing collection system piping material is Vitrified Clay Pipe (VCP). The majority of day-to-day operations and maintenance activities are conducted by City Staff. This SSMP Element 4 outlines the work that is conducted to accomplish the optimal operation and maintenance of the City’s collection system. Table 4.1 illustrates the current age of sewer lines in the system.

Table 4-1: Age of Sewer Lines
Sewer Line Age Percent of Sewer System
1980 to Present 30%
1960 to 1979 41%
1900 to 1959 29%

A general overview of the City Sewer System is provided in Figure 4 -1: Collection System Overview Map. Indexed pages to this map are located at City Wastewater Division Office, City Yard and in Service Trucks.

Sewer System Management Plan – Revision 02
Element 4 – Operation and Maintenance Program

City of Salinas
May 2025

Page 4 ends

Figure 4-1: Collection System Overview Map

City owns and maintains ten (10) wastewater lift stations and maintains one (1) private wastewater lift station. Lift Stations are locations are identified in the Sewer Atlas Map maintained at the City Wastewater Division Office and illustrated on Figure 4-1.. A System overview for the entire City sewer system is included on the City website:
https://www.cityofsalinas.org/Your-Government/Departments/Public-Works/PW- Maintenance-Services/Environmental-Maintenance-Services/Sanitary-Sewer- Maintenance.

4.1 Regulatory Requirements
Attachment D 4. states:

The SSMP must include those sections listed below that are appropriate and applicable to the Enrollee’s system:
(a) Up-to-date map(s) of the sanitary sewer system, and procedures for maintaining and providing State and Regional Water Board staff access to the map(s). The map(s) must show gravity line segments and manholes, pumping facilities, pressure pipes

Sewer System Management Plan – Revision 02
Element 4 – Operation and Maintenance Program

City of Salinas
May 2025

Page 4 ends

and valves, and applicable stormwater conveyance facilities within the sewer system service area boundaries.;
(b) A scheduling system and a data collection system for preventive operation and maintenance activities conducted by staff and contractors. a. The scheduling system must include:
i. Inspection and maintenance activities;
ii. Higher-frequency inspections and maintenance of known problem areas, including areas with tree root problems;
iii. Regular visual and closed-circuit television (CCTV) inspections of manholes and sewer pipes.

The data collection system must document data from system inspection and maintenance activities, including system areas/components prone to root-intrusion potentially resulting in system backup and/or failure.
(c) In-house and external training provided on a regular basis for sanitary sewer system operations and maintenance staff and contractors. The training must cover:
i. The requirements of this General Order;
ii. The Enrollee’s Spill Emergency Response Plan procedures and practice drills;
iii. Skilled estimation of spill volume for field operators; and iv. Electronic CIWQS reporting procedures for staff submitting data. (d) An inventory of sewer system equipment, including the identification of critical replacement and spare parts.

4.2 Collection System and Storm Water Maps

4.2.1 Sewer Collection and Conveyance
The City maintains maps, which are based on record drawings, and are prepared into Zone Atlas Maps. Zone Atlas maps identify sewer line; location, size, material and year of installation.

Zone Atlas Maps are distributed to field crew and engineering staff to map out and track field activities.

Corrections for Zone Atlas Maps are noted and submitted to Engineering Staff. Engineering Staff maintains a “Master” Zone Atlas Map and will show corrections here. Updated hard-copy maps are re-distributed to maintenance staff and will display a date identifying the latest version of the Atlas Map. The City also maintains a GIS map layer of the sewer system.

The City’s sewer system mapping and maintenance tracking is a collaborative effort by the City’s Engineering and Transportation Division, Information Systems, GIS, and Environmental and Maintenance Services Division of Public Works. A GIS database/tracking system has been established to track maintenance of the sanitary sewer system. Existing municipal maintenance and sewer spill information is incorporated into the database/tracking system. The database includes completed maintenance work and a record of problem areas to facilitate maintenance planning and oversight.

A general overview of the sewer collection and conveyance system is shown in Figure 4-1.

Sewer System Management Plan – Revision 02
Element 4 – Operation and Maintenance Program

City of Salinas
May 2025

Page 4 ends

The City Public Works Department maintains copies of all wastewater collection and conveyance plans upon completion of construction and acceptance by the City. A general overview map of the entire City sewer collection and conveyance system is included on the City website: https://www.cityofsalinas.org/our-city-services/public-works.

4.2.2 Storm Water Conveyance Map
The City owns and operates storm water conveyance facilities within the service area. Storm water maps are maintained at the City Wastewater Division Office as hard copy maps and as a GIS layer. This map can be printed as hard copy maps to be utilized by City maintenance staff in the event of a Sanitary Sewer Spill (Spill) to identify storm water inlets and outlets and isolate/capture wastewater that may enter the storm drain system. An overview map of the City MS4 System is available of the City website: https://www.cityofsalinas.org/our-city- services/public-works.

4.3 Preventative Maintenance Program
The City manages, schedules, and tracks preventative maintenance activities in their GIS based Computerized Maintenance and Management System (CMMS). The system covers the following:
o Sewer Line Cleaning
o High Priority Area Cleaning and Inspections
o Manhole Inspections and Maintenance
o Lift Station Inspection and Maintenance
o Customer Complaints
o Work Orders
o CCTV Inspections
o FOG Program Inspections
o Air Relief and Vacuum Relief Valve Inspections

Routine maintenance that requires follow up is flagged in the CMMS with a “Follow up Maintenance Needed” code in the system.

4.3.1. CCTV Inspection
The City conducts CCTV inspections utilizing two (2) methods:
1) City Staff conducts CCTV investigations on an ongoing basis as an investigative tool to identify problems identified in the field such as flow restriction, customer complaints, or as a result of line cleaning follow up investigations.
2) Contracted CCTV investigations are being conducted as part of a system-wide CCTV investigation which is anticipated to be completed in the next ten (10) years. Contracted CCTV work is conducted annually in different areas or basins within the City system as part of an ongoing condition assessment.

Contractor CCTV information will be one of the primary methods to identify sewer line rehabilitation and replacement projects in the future. Data will be evaluated on an ongoing basis to help develop City Capital Projects.

As CCTV investigations are complete they will be analyzed to; identify, rank and prioritize areas of the sewer system that require rehabilitation and replacement. A summary of these CCTV Sewer System Management Plan – Revision 02
Element 4 – Operation and Maintenance Program

City of Salinas
May 2025

Page 4 ends

investigations will be on file at the Wastewater Division office when completed. A decision tree informing CCTV reinspection after initial inspection is provided below in Figure 4-2:

Figure 4-2 CCTV Grades above based on NASSCO defect ranking codes

4.3.2 Line Cleaning
The City implements a seven (7) year schedule to clean the entire system. Staff is dedicated to cleaning the system 2 days per week and documents line cleaning conditions on a Routine Sewer Line Cleaning and Manhole Inspection form.

The City evaluates the frequency at which the entire system is cleaned based on the results of sewer line cleaning logs, sewer spill history and the results of CCTV data. Changes in sewer line cleaning and prioritization of sewer repairs based on sewer line cleaning observations follow the following protocol in Figure 4-3 belowl:

Sewer System Management Plan – Revision 02
Element 4 – Operation and Maintenance Program

City of Salinas
May 2025

Page 4 ends

Figure 4-3: Sewer Line Cleaning Flow Chart

4.3.3 Manhole Inspection
City manholes are inspected in conjunction with routine sewer line cleaning activities and as part of the High Priority List inspections. The City utilizes the Manhole Inspection Form for routine documentation of manhole conditions. When significant issues are observed during these routine manhole inspections, a more detailed inspection and assessment is conducted by maintenance staff. Relevant information from these sheets is maintained in the City CMMS for consideration in future rehabilitation and/or CIP.

Sewer System Management Plan – Revision 02
Element 4 – Operation and Maintenance Program

City of Salinas
May 2025

Page 4 ends

4.3.4 High Priority Areas
The Departments goal is to service high priority problem areas 3 days of each week. The City’s Wastewater Supervisor maintains “high priority” lists of problem areas needing additional maintenance and cleaning. This list, developed over several years, identifies problem locations for blockages that may potentially lead to overflows. This list was developed and is based on the required frequency of maintenance to avoid blockages. Currently, monthly and quarterly high priority maintenance lists are maintained. These lists are based on sewer spill data and staff field observations. These lists have been effective to minimize sanitary sewer spills. The locations on both lists are grouped by area – East Salinas, West Salinas, North Salinas and South Salinas. The current lists provided are for example purposes only as they are dynamic and revised as needed. The lists show specific locations to be serviced, and the length of pipe.

These documents are maintained at the Wastewater Division office. The current High Priority Lists are provided in Appendix 4A.

4.3.5 Lift Station Operation and Maintenance
As previously mentioned in the introduction to this SSMP Element, the City operates ten (10) City-owned lift stations, and one (1) City maintained lift station within the City service area.

Stations are provided with duplex and triplex pumping systems depending on the size of the station for redundancy and reliability. This redundant system allows for continued operation of a lift station in the event of pump failure. Several of the City’s lift stations have backup generator power. In addition, the City maintains 5 portable (towable) diesel powered generators to provide emergency power to those stations not equipped with permanent on-site electrical generators.

This gives effective coverage of all sanitary lift stations and reduces the potential for overflows during power outages. To ensure redundancy in the system, City lift stations are equipped with receptacles for mobile generator hookups in the unlikely event of a permanent generator failure.

Stations are monitored remotely through a SCADA system which contacts “on-call” staff in the event of an emergency. Operational parameters and alarms for each station can be adjusted manually as necessary. Technical Information for these lift stations is included in the City’s Lift Station Spill Emergency Response Plans on file at the City’s Wastewater Division office.

The four (4) highest flow sewer lift stations (Carpenter Hall, Lake Street, Santa Rita, and TP2) are inspected daily. All other sewer lift stations are inspected weekly. The City has a pump maintenance mechanic logbook to identify maintenance activity at the sewer lift stations and also keeps records on a laptop for use in the field. Routine maintenance includes but is not limited to:
o inspection of electrical panels,
o pump and level controls,
o air compressors,
o wet well and dry well conditions, and
o pump motor operation.

Site visits for maintenance activities are logged in the Lift Station Log kept on file at the City’s Wastewater Division office. In the absence of the pump mechanic other maintenance personnel are cross trained to address any lift station problems.

Air relief valves, vacuum relief valves and bridge and aerial crossings of gravity and force main lines are visually inspected on a quarterly basis. The findings of these inspections and any necessary preventive maintenance are logged in the CMMS system.

Sewer System Management Plan – Revision 02
Element 4 – Operation and Maintenance Program

City of Salinas
May 2025

Page 4 ends

Table 4-2 lists City-owned and private lift stations that discharge to the City collection and conveyance system.

Table 4-2 Lift Stations
City Owned or Operated Lift Stations
Airport (Moffett) De La Torre Lake Street Mill Lake
Carpenter Hall Harkins Road Las Casitas Santa Rita
Spicer TP2
Private Lift Stations Discharging to City
Salinas Adult School 11 Harris Place 1121 Alamo Way Sherwood Hall 150 Sherwood Drive Natividad Hospital 58 Natividad Road Northridge Mall Oregon & Sanborn Street 115 San Juan Grade Road

Figure 4-2 identifies the locations of City and Private lift stations.

Sewer System Management Plan – Revision 02
Element 4 – Operation and Maintenance Program

City of Salinas
May 2025

Page 4 ends

Figure 4-2 Lift Station Locations

A summary of all City owned or maintained lift station and force main attributes is located in Appendix 4B.

4.3.6 Customer Requests/Complaints
The City utilizes Q-Alert reporting system a work order (Daily Sanitary Sewer Work Order) to document customer requests and complaints and to address routine work requests within the system. Staff investigates and completes associated sewer related tasks as appropriate and generates a work order based on the nature of the investigation. Completed Q-Alerts are electronically stored in a Q-Alert database. If staff investigations result in significant discoveries in the field (E.g. sewer line restriction or spill) relevant data is reported to the Wastewater Division Manager for follow-up.

Sewer System Management Plan – Revision 02
Element 4 – Operation and Maintenance Program

City of Salinas
May 2025

Page 4 ends

4.4 Training
Training programs include formal classroom, tailgate training and on-the-job training. Training is facilitated by both City staff and outside training workshops. On-the-job cross training is pursued to ensure staff has a proficient working knowledge of the sanitary sewer system and that critical tasks can be performed without interruption. Task proficiency is a requirement for all job positions and promotions. Operations and Maintenance (O&M) related training is conducted on an ongoing and as needed basis. O&M staff are initially trained in the proper operation and maintenance of all major new mobile equipment and facilities by the respective contractor or manufacturer. Written operation and maintenance manuals are used as resource material for equipment start-up training and new staff training. In addition to these resource materials, the City has developed the following Operations and Maintenance Standard Operating Procedures applicable to the wastewater collection and conveyance system:
o SOP -01 Annual Collection System Cleaning
o SOP-02 Sewer Line Cleaning & Safety Guides for Vac-Con Truck o SOP-03 Lift Stations
o SOP-08 Vac-Con 692 Hydro Truck
o SOP-11 Confined Space Written Program
o SOP-13 Generator Operation
o WATCH Traffic Control Manual
The City also conducts regular training in the following areas:
o The requirements of General Order WQ 2022-0103-DWQ;
o Spill Emergency Response Plan procedures and practice drills; o Estimation of spill volume and spill response/mitigation; and o Electronic CIWQS reporting procedures for staff submitting data.

Training records are maintained by the Wastewater Division Manager at the Public Works Office.

4.5 Equipment and Replacement Parts Inventory
Equipment and replacement parts inventories are provided as discussed below.

4.5.1 Critical Parts and Equipment
The City maintains an inventory of critical parts and equipment which are utilized for both routine and emergency operations. A critical parts and equipment list is maintained in the office of the Wastewater Division Manager. In the event of an emergency, local retailers and contractors are available to supply additional equipment and parts on short notice.

Sewer System Management Plan – Revision 02
Element 5 – Design and Performance Provisions

City of Salinas
May 2025

Page 5 ends

ELEMENT 5 - DESIGN AND PERFORMANCE PROVISIONS
The standards and specifications for new construction and repair of the existing sanitary sewer system described in this SSMP Element are utilized to ensure a high quality, well designed, and functioning sanitary sewer system.

5.1 Regulatory Requirements
WDR Order No. 2022-0103-DWQ Section D 5 states that the SSMP must identify:
(a) Updated design criteria, and construction standards and specifications, for the construction, installation, repair, and rehabilitation of existing and proposed system infrastructure components, including but not limited to pipelines, pump stations, and other system appurtenances. If existing design criteria and construction standards are deficient to address the necessary component - specific hydraulic capacity as specified in section 8 (System Evaluation, Capacity Assurance and Capital Improvements), the procedures must include component- specific evaluation of the design criteria.;
(b) Procedures, and standards for the inspection and testing of newly constructed, newly installed, repaired, and rehabilitated system pipelines, pumps, and other equipment and appurtenances

5.2 Design and Construction Standards and Specifications In 2008, the City adopted Standard Specifications, Design Standards and Standard Plans for sewer mains to provide minimum standards for the design, methods of construction, kinds and uses of materials, and the preparation of plans for construction, sewerage, road repair and facilities within the City service area.

Where any portion of such improvement is to be offered to the City for operation and/or maintenance, 2008 Design Standards include:

o Part I Standard Specifications, Section 71 Sewers
This section cover provides requirements for:
▪ acceptable materials,
▪ acceptable conditions for installation,
▪ repairs,
▪ fittings & joints,
▪ installation requirements,
▪ field inspection,
▪ field testing requirements,
▪ acceptable sizing for pipelines and manholes
▪ Lift Stations (Pumping Plant Equipment) are referenced in Section 74 and identified as utilizing State Standard Specifications. Staff reports that Lift Stations are designed by Licensed Professional Engineers to meet existing conditions in the field.

o Part II: Sanitary Sewer Design
Sewer System Management Plan – Revision 02
Element 5 – Design and Performance Provisions

City of Salinas
May 2025

Page 5 ends

▪ A. Design: provides direction on acceptable peak flow rates and slopes ▪ B. Depth of Sewers: provides direction on acceptable sewer depths for mains and laterals
▪ C. Connections to Sewers: provides direction on acceptable wye connections to sewer mains.
o Part III: Standard Plans
▪ Standard Plan 16: Trench Backfill and Surface Restoration ▪ Standard Plan 25: Type A & Type B Manholes
▪ Standard Plan 26: Type C Manhole (Shallow Type)
▪ Standard Plan 27: Manhole Frame and Cover
▪ Standard Plan 28: Manhole Frame and Cover Adjustment
▪ Standard Plan 29: Sewer Saddle Connection
▪ Standard Plan 30: Flushing Inlet Frame and Cover Flushing Inlet ▪ Standard Plan 31: Flushing Inlet
▪ Standard Plan 32: Sewer Lateral (VCP)
All work must be completed based on the above standards. Any alterations to this must be approved by the City Engineer.

The City 2008 Standard Specifications, Design Standards, and Standard Plans are located on the City Website: https://www.cityofsalinas.org/Your-Government/Departments/Public- Works/Development-Engineering
A hard copy of City Standard Specifications, Design Standards, and Standard Plans is also on file at City offices.

5.3 Inspection and Testing Procedures and Standards
Procedures and standards for the acceptance testing and inspection of new and repaired sewer mains are specified in:
o Part I Standard Specifications, Section 71 Sewers
This section cover provides requirements for:
▪ acceptable materials,
▪ acceptable conditions for installation,
▪ repairs,
▪ fittings & joints,
▪ installation requirements,
▪ field inspection,
▪ field testing requirements,
▪ acceptable sizing for pipelines and manholes
Sewer System Management Plan – Revision 02
Element 6 – Overflow Emergency Response Plan

City of Salinas
May 2025

Page 6 ends

ELEMENT 6 - SPILL EMERGENCY RESPONSE PLAN
Sanitary Sewer Spills (Spills can occur due to unforeseen accidents, unusual equipment failures, or other events not controllable by the City. A Spill Emergency Response Plan is maintained by the City Wastewater Division for City maintenance personnel to use as guidance in responding to Spills. The Spill Emergency Response Plan defines procedures to:
▪ protect public health and the environment
▪ comply with local, state, and federal regulatory agency requirements ▪ protect City personnel, the wastewater collection system, and private and public properties

The Spill Emergency Response Plan (SERP) is summarized in this SSMP Element. The City has developed a comprehensive Spill Emergency Response Plan to address emergency response and follow activities for Spills experienced in the City’s collection and conveyance system located in on the City’s website: https://www.cityofsalinas.org/Your- Government/Find-a-Department/Public-Works/PW-Maintenance-Services/Environmental- Maintenance-Services/Sanitary-Sewer-Maintenance. The City also maintains a separate Emergency Response Plans for the individual lift stations. These response plans are kept on file at the City Wastewater Division Office.. These documents are the primary references for staff to use during all Spills.

6.1 Regulatory Requirements
WDR Order No. 2022-0103-DWQ Attachment D 6 states:

The Plan must include an up-to-date Spill Emergency Response Plan to ensure prompt detection and response to spills to reduce spill volumes and collect information for prevention of future spills. The Spill Emergency Response Plan must include procedures to:
a) Notify primary responders, appropriate local officials, and appropriate regulatory agencies of a spill in a timely manner;
b) Notify other potentially affected entities (for example, health agencies, water suppliers, etc.) of spills that potentially affect public health or reach waters of the State;
c) Comply with the notification, monitoring and reporting requirements of this General Order, State law and regulations, and applicable Regional Water Board Orders;
d) Ensure that appropriate staff and contractors implement the Spill Emergency Response Plan and are appropriately trained;
e) Address emergency system operations, traffic control and other necessary response activities;
f) Contain a spill and prevent/minimize discharge to waters of the State or any drainage conveyance system;
g) Minimize and remediate public health impacts and adverse impacts on beneficial uses of waters of the State;
h) Remove sewage from the drainage conveyance system;
Sewer System Management Plan – Revision 02
Element 6 – Overflow Emergency Response Plan

City of Salinas
May 2025

Page 6 ends

i) Clean the spill area and drainage conveyance system in a manner that does not inadvertently impact beneficial uses in the receiving waters;

j) Implement technologies, practices, equipment, and interagency coordination to expedite spill containment and recovery;

k) Implement pre-planned coordination and collaboration with storm drain agencies and other utility agencies/departments prior, during, and after a spill event;

l) Conduct post-spill assessments of spill response activities;

m) Document and report spill events as required in this General Order; and

n) Annually, review and assess effectiveness of the Spill Emergency Response Plan, and update the Plan as needed.

6.2 Initial Spill Notification Procedures
If a member from the public witnesses a Spill, they contact City on call staff by way of the City office at (831) 758-7233 during normal business hours. Calls to the City after hours or on weekends and holidays are directed to the 911 and County Dispatch which contacts staff responsible for “on-call” duty.

6.2.1 The City Staff as the First Responder
If City staff are contacted during normal business hours Monday through Friday, excluding legal holidays, administrative staff at the City office, calls the Wastewater Crew Supervisor or the next available Wastewater Staff to investigate the situation utilizing the contact information found in the SERP. If City staff need assistance responding to the Spill, the first responder calls additional senior wastewater staff utilizing the contact information found in Table 6-1.

Table 6-1: Maintenance Staff Contact Information
Title Contact Number
Wastewater Division
Manager Gary Gabriel (831) 970-7629

Maintenance Staff / On Call
Responder
On Call Phone (831) 970-7634
Ray Lerma (Wastewater Crew
Supervisor)
(831) 970-8287
Matthew Bates (Wastewater Crew
Supervisor)
(831) 737-3010
Albert Aries (831) 208-4862
Robert Reyna (831) 970-7621

Sewer System Management Plan – Revision 02
Element 6 – Overflow Emergency Response Plan

City of Salinas
May 2025

Page 6 ends

If City staff are contacted after normal business hours, on a holiday, or during the weekend, on-call maintenance staff are contacted by dialing the City office or 911. The call will be routed to County Dispatch who contacts the City on-call phone, and staff respond accordingly.

After normal operating hours, one member of the Wastewater staff is on-call as a primary on- call wastewater emergency responder.

Figure 6-1 illustrates the chain of command, which must be observed and followed when a Spill occurs.

Figure 6-1: Spill Response Chain of Command

6.3 Spill Response Program
The City SERP documents provide a comprehensive Emergency Response Program consisting of the following:
o Spill Detection and Notification
o Spill Response Procedures
o Spill Recovery and Cleanup
o Water Quality Monitoring/Sampling
o Private Property Spill Response Procedures
o Notification, Reporting and Record Keeping Requirements o Post Spill Debriefing
o Failure Analysis Investigation
After-hours
Contacts
Observer
Notifies City Office
(831) 758-7233
After Hours
Observer directed
to Call 911

Emergency Phone #
911

Wastewater Staff
Responds

On Call Staff is
contacted

Wastewater Staff
Mitigates Spill
Wastewater Manager
(831) 970-7629

Compile CIWQS
Data:

On Call Staff and
Wastewater Manager
Spill Notification & Reporting to
Appropriate Agencies

If additional
resources are
necessary

If no
additional
resources
are
necessary
Sewer System Management Plan – Revision 02
Element 6 – Overflow Emergency Response Plan

City of Salinas
May 2025

Page 6 ends

o Spill Response Training (training records maintained at City office) o Spill Response Workbook
o Lift Station Emergency Response Procedures

6.4 Spill Notification and Reporting Procedures
This section of the SERP ensures proper notification and reporting of Spills, which occur in the City’s sanitary sewer system, to protect public and environmental health.

An overview of the notification and reporting process is listed in Table 6-1. This overview is not inclusive of all the notification and reporting requirements and procedures. The following section of this SSMP Element correspond to each Spill category for notifications and reporting that must be referenced and followed.

Sewer System Management Plan – Revision 02
Element 6 – Overflow Emergency Response Plan

City of Salinas
May 2025

Page 6 ends

Spill Category 1:

Spills to Surface Waters and/or SW Conveyance System
Spill
Requirement Schedule Method
Notification

Within two (2) hours of the Enrollee’s knowledge of a
Category 1 spill of 1,000 gallons or greater, discharging or threatening to discharge to surface waters:

Notify the California Office of Emergency
Services and obtain a notification control
number.

California
Office of
Emergency
Services at:
(800) 852-
7550

Reporting
• Submit Draft Spill Report within three (3) business
days of the Enrollee’s knowledge of the spill;
• Submit Certified Spill Report within 15 calendar
days of the spill end date;
• Submit Technical Report within 45 calendar days after the spill end date for a Category 1 spill in which 50,000 gallons or greater discharged to surface waters; and
• Submit Amended Spill Report within 90 calendar days after the spill end date.

CIWQS
Spill Category 2:

Spills of 1,000 Gallons of Greater That Do Not Discharge to Surface Waters Spill
Requirement Schedule Method
Notification

Within two (2) hours of the Enrollee’s knowledge of a
Category 2 spill of 1,000 gallons or greater, discharging or threatening to discharge to waters of the State:

Notify California Office of Emergency Services and obtain a notification control number.

California Office
of Emergency
Services at:
(800) 852-7550

Reporting
• Submit Draft Spill Report within three (3) business
days of the Enrollee’s knowledge of the spill;
• Submit Certified Spill Report within 15 calendar
days of the spill end date; and
• Submit Amended Spill Report within 90 calendar
days after the spill end date.

CIWQS
Sewer System Management Plan – Revision 02
Element 6 – Overflow Emergency Response Plan

City of Salinas
May 2025

Page 6 ends

Spill Category 3:

Spills of Equal or Greater than 50 Gallons and Less than 1,000 Gallons That Does Not Discharge to Surface Waters

Spill
Requirement Schedule Method

Notification

Not Applicable

Not Applicable
Reporting
• Submit monthly Certified Spill Report to the online
CIWQS Sanitary Sewer System Database within 30
calendars days after the end of the month in which
the spills occur; and
• Submit Amended Spill Reports within 90 calendar
days after the Certified Spill Report due date.

CIWQS
Spill Category 4:

Spills Less Than 50 Gallons That Do Not Discharge to Surface Waters Spill
Requirement Schedule Method

Notification

Not Applicable

Not Applicable
Reporting
• If, during any calendar month, Category 4 spills occur, certify monthly, the estimated total spill volume exiting the sanitary sewer system, and the total number of all
Category 4 spills into the online CIWQS Sanitary
Sewer System Database, within 30 days after the end
of the calendar month in which the spills occurred.

• Upload and certify a report, in an acceptable digital format, of all Category 4 spills to the online CIWQS
Sanitary Sewer System Database, by February 1st
after the end of the calendar year in which the spills
occur.

CIWQS

Sewer System Management Plan – Revision 02
Element 6 – Overflow Emergency Response Plan

City of Salinas
May 2025

Page 6 ends

Enrollee Owned and/or Operated Lateral Spills That Do Not Discharge to Surface Waters Spill
Requirement Schedule Method

Notification
Within two (2) hours of the Enrollee’s knowledge of a spill of 1,000 gallons or greater, from an enrollee- owned and/or operated lateral, discharging or threatening to discharge to waters of the State:

Notify California Office of Emergency Services and
obtain a notification control number.

Not applicable to a spill of less than 1,000 gallons.

California
Office of
Emergency
Services at:
(800) 852-
7550

Reporting
• Upload and certify a report, in an acceptable digital format, of all lateral spills (that do not discharge to a surface water) to the online CIWQS Sanitary Sewer
System Database, by February 1st after the end of the
calendar year in which the spills occur.
• Report a lateral spill of any volume that discharges to a surface water as a Category 1 spill.

CIWQS
Table 6-1: Spill Notification and Reporting Overview

6.4.1 Spill Notification Procedure
Spill notification procedures vary based on whether the Spill is classified as a Category 1, Category 2, Category 3, Category 4 or Enrollee Owned Lateral and are included in the SERP:

Spill Notification section.

Notification of Spills of 1,000 Gallons or Greater to the California Office of Emergency Services
Per Water Code section 13271, for a spill that discharges in or on any waters of the State, or discharges or is deposited where it is, or probably will be, discharged in or on any waters of the State, the City shall notify the California Office of Emergency Services and obtain a California Office of Emergency Services Control Number as soon as possible but no later than two (2) hours after:
• The City has knowledge of the spill; and
• Notification can be provided without substantially impeding cleanup or other emergency measures.

The notification requirements in this section apply to individual spills of 1,000 gallons or greater, from an Enrollee-owned and/or operated laterals, to a water of the State.

Sewer System Management Plan – Revision 02
Element 6 – Overflow Emergency Response Plan

City of Salinas
May 2025

Page 6 ends

Spill Notification Information
The Enrollee shall provide the following spill information to the California Office of Emergency Services before receiving a Control Number, as applicable:
• Name and phone number of the person notifying the California Office of Emergency Services;
• Estimated spill volume (gallons);
• Estimated spill rate from the system (gallons per minute); • Estimated discharge rate (gallons per minute) directly into waters of the State or indirectly into a drainage conveyance system; • Spill incident description:
o Brief narrative of the spill event, and
o Spill incident location (address, city, and zip code) and closest cross streets and/or landmarks;
• Name and phone number of contact person on-scene;
• Date and time the Enrollee was informed of the spill event; • Name of sanitary sewer system causing the spill;
• Spill cause or suspected cause (if known);
• Amount of spill contained;
• Name of receiving water body receiving or potentially receiving discharge; and
• Description of water body impact and/ or potential impact to beneficial uses.

Notification of Spill Report Updates
Following the initial notification to the California Office of Emergency Services and until such time that the Enrollee certifies the spill report in the online CIWQS Sanitary Sewer System Database, the Enrollee shall provide updates to the California Office of Emergency Services regarding substantial changes to:
• Estimated spill volume (increase or decrease in gallons initially estimated);
• Estimated discharge volume discharged directly into waters of the State or indirectly into a drainage conveyance system (increase or decrease in gallons initially estimated); and
• Additional impact(s) to the receiving water(s) and beneficial uses.

Sewer System Management Plan – Revision 02
Element 6 – Overflow Emergency Response Plan

City of Salinas
May 2025

Page 6 ends

6.4.1.1 Category 1 Spills (Spills to Surface Waters)
Within two (2) hours of the City’s knowledge of a Category 1 spill of 1,000 gallons or greater, discharging or threatening to discharge to surface waters:
o Notify the California Office of Emergency Services and obtain a notification control number.

Table 6-2: Regulatory Agency Notification Information for a Spill to Surface Water

Regulatory Agency Contacts
California Office of
Emergency
Services (Cal OES)
Within two (2) hours of the City’s knowledge of a Category 1 spill of 1,000 gallons or greater, discharging or threatening to discharge to surface waters notify the California Office of Emergency Services and obtain a notification control number at (800) 852-7550.

Regional Water
Quality Control
Board (RWQCB)
Optional – If spill is over 1,000 gallons, reaches waterway, or occurred in area with likely public contact, call (805) 549-3147.

Monterey County
Environmental
Health
Optional- If spill reaches waterway, call (800) 253-2687. Give the spill information.

California
Department of Fish
and Wildlife
Optional -If spill reaches waterway, call State office (831) 649- 2870.

6.4.1.2 Category 2 Spills
(Spills of 1,000 Gallons or Greater That Do Not Discharge to Surface Waters) Within two (2) hours of the City’s knowledge of a Category 2 spill of 1,000 gallons or greater, discharging or threatening to discharge to waters of the State:
o Notify California Office of Emergency Services and obtain a notification control number.

6.4.1.3 Category 3 Spills
(Spills of Equal or Greater than 50 Gallons and Less than 1,000 Gallons That Does Not Discharge to Surface Waters)
o Not Applicable

6.4.1.4 Category 4 Spills
(Spills Less Than 50 Gallons That Do Not Discharge to Surface Waters) o Not Applicable

6.4.1.5 Enrollee Owned and or Operated Lateral Spills that do not Discharge to Surface Waters
Within two (2) hours of the City’s knowledge of a spill of 1,000 gallons or greater, from an enrollee- owned and/or operated lateral, discharging or threatening to discharge to waters of the State:

Sewer System Management Plan – Revision 02
Element 6 – Overflow Emergency Response Plan

City of Salinas
May 2025

Page 6 ends

o Notify California Office of Emergency Services and obtain a notification control number.
o Not applicable to a spill of less than 1,000 gallons.

6.4.2 Spill Reporting Procedure
Spill reporting procedures vary based on whether the Spill is classified as Category 1, Category 2, Category 3, Category 4 or City Owned Lateral. A full description of Spill reporting requirements is found in the City SERP.

Category 1 Spills
• Submit Draft Spill Report within three (3) business days of the City’s knowledge of the spill;
• Submit Certified Spill Report within 15 calendar days of the spill end date; • Submit Technical Report within 45 calendar days after the spill end date for a Category 1 spill in which 50,000 gallons or greater discharged to surface waters; and • Submit Amended Spill Report within 90 calendar days after the spill end date.

Spill Technical Report
Category 2 Spills
• Submit Draft Spill Report within three (3) business days of the City’s knowledge of the spill;
• Submit Certified Spill Report within 15 calendar days of the spill end date; and • Submit Amended Spill Report within 90 calendar days after the spill end date.

Category 3 Spills
• Submit monthly Certified Spill Report to the online CIWQS Sanitary Sewer System Database within 30 calendars days after the end of the month in which the spills occur; and
• Submit Amended Spill Reports within 90 calendar days after the Certified Spill Report due date.

Category 4 Spills
• If, during any calendar month, Category 4 spills occur, certify monthly, the estimated total spill volume exiting the sanitary sewer system, and the total number of all Category 4 spills into the online CIWQS Sanitary Sewer System Database, within 30 days after the end of the calendar month in which the spills occurred.

Sewer System Management Plan – Revision 02
Element 6 – Overflow Emergency Response Plan

City of Salinas
May 2025

Page 6 ends

• Upload and certify a report, in an acceptable digital format, of all Category 4 spills to the online CIWQS Sanitary Sewer System Database, by February 1st after the end of the calendar year in which the spills occur.

Enrollee Owned and/or Operated Lateral Spills That Do Not Discharge to Surface Waters
• Upload and certify a report, in an acceptable digital format, of all lateral spills (that do not discharge to a surface water) to the online CIWQS Sanitary Sewer System Database, by February 1st after the end of the calendar year in which the spills occur. • Report a lateral spill of any volume that discharges to a surface water as a Category 1 spill.

6.5 SERP Training
The City implements a formal training program which includes annual training of City staff on this SSMP Element and SERP. The City also requires contractor personnel to train on and follow SERP through their contracts. The City maintains a log of SERP Training as training is completed.

6.6 Spill Impact Mitigation Program
The Spill Mitigation Program is comprised of the mitigation practices contained in the SERP, which is on file at the City Department of Public Works Wastewater Division Office.

The SERP includes Water Quality Monitoring, Beneficial Uses Identification and Spill Impact Mitigation section providing information to post water body warning and closure signs in the event that a spill reaches a surface water, and City Department of Public Works conducts water quality sampling for the spill impact assessment.

6.7 Spill Coordination with Stormwater Management Agencies and Public Water Systems
City Stormwater Compliance Division of Public Works manages the MS4 Stormwater Program which includes the entire City service area. Maps of the stormwater collection and conveyance system are available to City staff which allows them to isolate any areas impacted by a sewer spill, recover wastewater and return it to the sewer system. Municipal water system contacts are identified for notification of spills that may occur within 1000 ft of a surface water intake in the City SERP.

6.8 Post Spill Investigations
The City conducts Post Spill Investigations for Category 1, 2, and 3 spills as warranted.

Sewer System Management Plan – Revision 02
Element 7 – Fats, Oils and Grease Control Program

City of Salinas
May 2025

Page 1 of 3 ends

ELEMENT 7 – PIPE BLOCKAGE CONTROL PROGRAM
The City of Salinas has identified a significant number of commercial facilities that contribute fats, oils and grease (FOG) into the City’s sewer system. FOG has been a contributing factor in sanitary sewer spills and requires the City to conduct additional maintenance. Roots and disposable wipes have also been identified as pipe blocking sources.

7.1 Regulatory Requirements
WDR Order No. 2022-0103-DWQ Attachment D 7 states:

The Sewer System Management Plan must include procedures for the evaluation of the Enrollee’s service area to determine whether a sewer pipe blockage control program is needed to control fats, oils, grease, rags and debris. If the Enrollee determines that a program is not needed, the Enrollee shall provide justification in its Plan for why a program is not needed. The procedures must include, at minimum:
(a). An implementation plan and schedule for a public education outreach program that promotes proper disposal of pipe blocking substances; (b). A plan and schedule for the disposal of FOG generated within the sanitary sewer system service area. This may include a list of acceptable disposal facilities and/or additional facilities needed to adequately dispose of FOG generated within a sanitary sewer system service area;
(c). The legal authority to prohibit discharges to the system and identify measures to prevent spills and blockages;
(d). Requirements to install grease removal devices (such as traps or interceptors) and the development of design standards for such devices, maintenance requirements, BMP requirements, record keeping and reporting requirements; (e). Authority to inspect grease producing facilities, enforcement authorities, and whether the City has sufficient staff to inspect and enforce the FOG ordinance; (f). An identification of sewer system sections subject to FOG blockages and establishment of a cleaning maintenance schedule for each section; and Implementation of source control measures for all sources of fats, oils, and grease reaching the sanitary sewer system for each section identified above

7.2 Pipe Blockage Control Program Public Education and Outreach The City of Salinas currently has approximately 286.7.25 miles of sanitary sewer pipelines.

The service area includes a variety of residential, commercial and industrial facilities. The focus of an effective Pipe Blockage Control Program include s residential customers, commercial and industrial facilities and commercial and industrial food service/preparation facilities.

The City participates in the Southern Monterey Bay Dischargers Group (Group) partnering with Monterey One Water and other local agencies on a Pipe Blockage Control Program and continued participation in an effective public outreach program. The City of Salinas continues to utilize the Group to assist in developing a regional public education program for users of the system for the purpose of reducing FOG problems in the collection system.

Sewer System Management Plan – Revision 02
Element 7 – Fats, Oils and Grease Control Program

City of Salinas
May 2025

Page 2 of 3 ends

The education campaign typically includes newspaper ads (three in English, one in Spanish), radio ads on two local stations and theaters ads in a major Salinas movie outlet. The Southern Monterey Bay Discharges Group directed resources to a multi -agency web site which was completely updated in 2018 for fats, oils and grease information at https://www.clogbusters.org/ . The regional program is modified yearly as conditions warrant.

The City of Salinas continues to participate by funding approximately 52% of the costs for the regional grease source control education program. The City’s participation is critical to the regional effort as the program is prohibitively expensive for the other participants to finance the program independently.

In addition to the City’s Pipe Blockage Control Program outreach through ClogBusters, the City has independently developed outreach materials for other pipe blocking materials such as “disposable” wipes and any other consumer items that do not belong in the sewer through a flyer labeled “Toilets Are Not Trashcans”.

The City provides the following outreach and education materials that consist of the following:
o Residential and commercial outreach on proper Disposal of Wipes - “Toilets are not Trashcans” flyer,
o Residential Fats Oils and Grease Disposal outreach,
o Residential Door Hangers – FOG Program,
o Residential FOG Program - Lateral Graphic,
o Commercial FOG Program - Best Management Practices
o Commercial FOG Program - List of Licensed FOG Haulers Copies of educational outreach documents for food service establishments are posted and available on the City’s website https://www.cityofsalinas.org/Your-Government/Find-a- Department/Public-Works/PW-Maintenance-Services/Environmental-Maintenance- Services/Sanitary-Sewer-Maintenance. The City refers the appropriate businesses to the available information, to assist them with FOG compliance. .

7.3 FOG Disposal Facilities
The City does not own nor operate a FOG disposal facility; however, licensed FOG hauling contractors are identified as part of the City’s FOG Pipe Blockage Control Program, and the City provides a list of these licensed haulers to each food service establishment (FSE). Monterey One Water (M1W), located in Marina CA accepts hauled FOG for disposal.

A list of grease trap and interceptor vendors, pumping and waste hauling contractors in Monterey County that haul FOG to facilities such as M1W for disposal is available in the City’s Sanitary Sewer website link identified above and is also provided below:

Sewer System Management Plan – Revision 02
Element 7 – Fats, Oils and Grease Control Program

City of Salinas
May 2025

Page 3 of 3 ends

7.4 Discharge Prohibition Legal Authority and Spill Prevention Measures The City’s Source Control Program is run in cooperation with the Monterey One Water Source Control Program and relies heavily on Monterey One Water ordinances and requirements. The City’s current Municipal Code expressly incorporates all Monterey One Water regulations, including those related to requirements for grease and fats, source control and pretreatment requirements.

Monterey One Water’s authority for the Regional Grease Program is derived from Ordinance 2008-1. The City of Salinas City Code Chapter 36 expressly requires that all users within the City comply with all Monterey One Water regulations.
• Sec. 36-12.2. Compliance with discharge requirements of Monterey One Water. All dischargers into the sanitary sewer shall comply with all the discharge requirements of Monterey One Water. (Ord. No. 2102 (NCS).)
• Section 36-1 acknowledges that the City’s sanitary sewer collection system is tributary to the Monterey One Water treatment facility. It states that Monterey One Water implements a pretreatment program for its member jurisdictions (including the City of Salinas).
• Section 36-11 requires that all private sewage disposal systems conform with the City plumbing code currently in effect.
• Section 36-12 requires that a City permit be issued for all connection to or use of the public sanitary sewer system.
• Sections 36-12.1 and 36-12.2 state that final approval for a sanitary sewer permit is contingent upon compliance with the requirements of Monterey One Water and that all Grease Haulers in Monterey County
*Sites that accept FOG for disposal, recycling or rendering All Valley Environmental, Inc. (559) 498-8378
Ameriguard Maintenance Services (800) 347-7876 x 14
Bay Pumping (831) 422-6436
Greenline Liquid Waste Company (831) 422-2298
P.S.T.S (Peninsula Septic Tank Service) (831) 574-2958
Pioneer Liquid Transport (408) 287-5800
*Mahoney Environmental (800) 892-9392
*Monterey One Water (831) 424-1108
Sewer System Management Plan – Revision 02
Element 7 – Fats, Oils and Grease Control Program

City of Salinas
May 2025

Page 4 of 3 ends

dischargers into the sanitary sewer must comply with all discharge requirements of Monterey One Water.
• Section 36-16 requires that design and construction of building sewers conform to the requirements of the city plumbing code and the City Design Standards and Standard Specifications currently in effect at the time of installation. (Elsewhere in the City Code, the California Plumbing Code is adopted by reference.)

7.5 Requirements to Install Grease Removal Devices
The City’s Municipal Code expressly incorporates all Monterey One Water regulations, including those related to requirements for grease and fats, source control and pretreatment requirements. The City has adopted and incorporates the requirements of the California Uniform Plumbing Code. The City of Salinas City Code Chapter 36, Section 36-31 states:

Requires that grease traps (grease, oil, wax and sand interceptors) be provided when, in the opinion of the director, they are necessary for the proper handling of liquid wastes, sand or other harmful ingredients. All interceptors must be of a type and capacity approved by the director and located so as to be readily and easily accessible for cleaning and inspection. Failure by the owner to clean and maintain the interceptors is sufficient cause for punitive action as provided in the chapter, or for disconnection from the industrial sewer.

7.6 FOG Control Program Inspection, Enforcement, and Staffing The City of Salinas utilizes in-house inspection staff for food service facility inspection in conjunction with the City Storm Water Program. The Monterey County Department of Environmental Health is the designated authority as the City’s Health Officer, to inspect for any Health and Safety issues. Monterey One Water source control inspectors also have inspection authority for grease control equipment and wastewater related issues if necessary.

Both the City and Monterey One Water have inspection and enforcement authority regarding discharges to the sanitary sewer collection system. Authority to inspect is embedded in:
• Monterey One Water Ordinance No. 2008-01 - An Ordinance Establishing Regulations For The Interception, Treatment And Disposal Of Sewage And Wastewater; Providing For And Requiring Charges And Fees Therefore; And Fixing Penalties For The Violation Of Said Regulations
• Article 4 – discharge reports, wastewater discharge permits, notification, reporting requirements and administration.

• Section (§) 4.07 Inspection and Sampling – The Agency shall inspect the facilities of any user to ascertain whether the purpose of this Ordinance are being met and all requirements are being complied with. Persons or occupants of premises where wastewater is created or discharged shall allow the Agency's representative ready access at all reasonable times to all parts of the premises for the purposes of inspection or sampling or in the performance of any of their duties. The Agency shall have the right Sewer System Management Plan – Revision 02
Element 7 – Fats, Oils and Grease Control Program

City of Salinas
May 2025

Page 5 of 3 ends

to set up on the user's property such devices as are necessary to conduct sampling or metering operations. Where a user has security measures in force which would require proper identification and clearance before entry into their premises, the user shall make necessary arrangements with their security guards, that upon presentation of suitable identification, personnel from the Agency will be permitted to enter without delay for the purpose of performing their specific responsibilities.

7.7 Problem Area Identification and Sewer Cleaning
Locally, grease from both residential areas and food preparation facilities have been found to be contributing factors to grease related blockages in the sanitary sewer system. System blockages are generally attributable to issues of grease, roots or an accumulation of system solids and debris.

The City has a proactive maintenance program to meet the WDR requirement to identify sections of the sewer system subject to grease blockages and establish a cleaning maintenance schedule for these locations.

The Wastewater Division of the Maintenance Services Department performs daily maintenance activities to the system. The City has developed a proactive maintenance program with the goal of performing routine maintenance two days each week and priority locations three days each week. Priority, when required due to staffing shortage or availability of maintenance equipment, is given to servicing high priority locations over routine maintenance.

The “Sewer Maintenance High Priority List” referenced in Element 4 is the maintenance schedule that the City of Salinas Wastewater Division uses for ongoing maintenance of areas that have a history of blockages, buildup or overflows. The list is a dynamic document that changes as problems in some pipeline sections and other sections are identified for additional maintenance. The list consists of both monthly and quarterly maintenance locations to prevent the potential for sanitary sewer spills. The criteria for being on the list varies depending on the history of grease buildup, root intrusion, hydraulic deficiencies or other causes. Each location/pipe segment has been placed on a schedule of monthly or quarterly cleaning based on spill history or other system problems.

Other maintenance activities include routine maintenance to sewer lines, manhole inspections and system repairs when needed. The city also operates a pipeline inspection video truck to assist with identifying system problems.

7.8 Other Source Control Measures
The City’s source control efforts to reduce or eliminate pipe blocking materials and related problems in the pipeline sections identified in the ‘High Priority’ maintenance list are addressed through the actions previously described in this Element. Additionally, the City provides outreach and education to residential customers through the ClogBusters campaign and through the City website previously referenced in this Element. The education campaign typically includes newspaper ads, radio ads, and theaters ads in a major Salinas movie outlet.

The Southern Monterey Bay Discharges Group has directed resources to a multi-agency web site for pipe blocking material information at (https://www.clogbusters.org/). The regional program is modified yearly as conditions warrant. Additionally, the City has programs to Sewer System Management Plan – Revision 02
Element 7 – Fats, Oils and Grease Control Program

City of Salinas
May 2025

Page 6 of 3 ends

eliminate roots and an outreach program to encourage members of the public to keep other pipe clogging materials out of the sewer system.

Sewer System Management Plan – Revision 01
Element 8 – System Evaluation and Capacity Assurance Plan

City of Salinas
May 2025

Page 1 of 8 ends

ELEMENT 8 SYSTEM EVALUATION, CAPACITY ASSURANCE AND

CAPITAL IMPROVEMENT PLAN

8.1 Regulatory Requirements
Attachment D 8 states:

The Plan must include procedures and activities for:
• Routine evaluation and assessment of system conditions; • Capacity assessment and design criteria;
• Prioritization of corrective actions; and
• A capital improvement plan.

(a). System Evaluation & Condition Assessment: The Plan must include procedures to:
o Evaluate the sanitary sewer system assets utilizing the best practices and technologies available;
o Identify and justify the amount (percentage) of its system for its condition to be assessed each year;
o Prioritize the condition assessment of system areas that:
▪ Hold a high level of environmental consequences if vulnerable to collapse, failure, blockage, capacity issues, or other system deficiencies; ▪ Are located in or within the vicinity of surface waters, steep terrain, high groundwater elevations, and environmentally sensitive areas; o Are within the vicinity of a receiving water with a bacterial-related impairment on the most current Clean Water Act section 303(d) List;
o Assess the system conditions using visual observations, video surveillance and/or other comparable system inspection methods;
o Utilize observations/evidence of system conditions that may contribute to exiting of sewage from the system which can reasonably be expected to discharge into a water of the State;
o Maintain documents and recordkeeping of system evaluation and condition assessment inspections and activities; and
o Identify system assets vulnerable to direct and indirect impacts of climate change, including but not limited to: sea level rise; flooding and/or erosion due to increased storm volumes, frequency, and/or intensity; wildfires; and increased power disruptions.

Sewer System Management Plan – Revision 01
Element 8 – System Evaluation and Capacity Assurance Plan

City of Salinas
May 2025

Page 2 of 8 ends

(b). Capacity Assessment & Design Criteria: The Plan must include procedures to identify system components that are experiencing or contributing to spills caused by hydraulic deficiency and/or limited capacity, including procedures to identify the appropriate hydraulic capacity of key system elements for:
o Dry-weather peak flow conditions that cause or contributes to spill events; o The appropriate design storm(s) or wet weather events that causes or contributes to spill events;
o The capacity of key system components; and
o Identify the major sources that contribute to the peak flows associated with sewer spills.
o The capacity assessment must consider:
▪ Data from existing system condition assessments, system inspections, system audits, spill history, and other available information; ▪ Capacity of flood-prone systems subject to increased infiltration and inflow, under normal local and regional storm conditions;
▪ Capacity of systems subject to increased infiltration and inflow due to larger and/or higher-intensity storm events as a result of climate change; ▪ Increases of erosive forces in canyons and streams near underground and above- ground system components due to larger and/or higher-intensity storm events;
▪ Capacity of major system elements to accommodate dry weather peak flow conditions, and updated design storm and wet weather events; and ▪ Necessary redundancy in pumping and storage capacities. (c). Prioritization of Corrective Action: The findings of the condition assessments and capacity assessments must be used to prioritize corrective actions. Prioritization must consider the severity of the consequences of potential spills. (d). Capital Improvement Plan: The capital improvement plan must include the following items:
o Project schedules including completion dates for all portions of the capital improvement program;
o Internal and external project funding sources for each project; and o Joint coordination between operation and maintenance staff, and engineering staff/consultants during planning, design, and construction of capital improvement projects; and Interagency coordination with other impacted utility agencies.

8.2 System Evaluation & Condition Assessment
In 2023 the City completed the Sanitary Sewer Master Plan Update (SSMPU) was completed that included evaluation of the entire City sanitary sewer system. The condition assessment consisted of the following:

Sewer System Management Plan – Revision 01
Element 8 – System Evaluation and Capacity Assurance Plan

City of Salinas
May 2025

Page 3 of 8 ends

o Survey of manhole rim and invert elevations on each sewer manhole included in sewer model,
o Evaluations of the City’s eleven lift stations to establish signs of corrosion and recommendations based on structural investigation of the wet wells. Evaluation of the condition of piping and internal components, documentation of the size of the wet well/pumping station, approximate depth and size of inverts, perform a pump draw down test and determine approximate flow from each pump, full load amperage and Meg-ohm readings on each motor, verification of automation of controls, evaluation of the electrical system deficiencies/code violations, documentation of pumps and motors make/model number, inspection of pumps for signs of wear and tear including inspecting pump seals and fittings, electrical components for code violations, evaluation of pump seals, fittings, and overall condition, and pump tests to determine approximate flow, and measure amperage/power draws to check for signs of pump motor concerns. Evaluation of the system’s ability to meet existing and future demands based on the pumping capacity and lift station upgrade recommendations.
o Updates to the City’s GIS system to include new developments and upgrades to the City sewer system.
o City staff observations and recommendations for sewer system repairs. o The condition assessment includes CCTV data for approximately 5,300 linear feet (0.3%) of the City sewer system. The City is in the process of conducting CCTV inspections to have the entire system televised and assessed over the course of the next ten (10) years. Manhole inspections will be included as part of the CCTV investigations.

Capital improvement projects were identified as part of the condition assessment. These projects are identified in Section 8.5 of this Element.

The SSMPU is on the City website: https://www.cityofsalinas.org/Your- Government/Find-a-Department/Public-Works/PW-Maintenance- Services/Environmental-Maintenance-Services/Sanitary-Sewer-Maintenance

8.3 Capacity Evaluation & Design Criteria
The City’s collection system consists of 292 miles of gravity pipes, which vary in diameter from 6-inch to 54- inches, and eleven (11) lift stations, providing service throughout the City and a portion of Bolsa Knolls near Rogge Road. The main trunk sewer system was analyzed using the Innovyze InfoSWMM Version 14.7 hydraulic modeling program to evaluate performance of the wastewater collection system under both existing and future flow conditions.

Design criteria, as shown in Table 8-1 below, were applied in the analysis of the trunk sewer collection model. Gravity pipe performance was analyzed based on maximum percent full depth over diameter (d/D) ratio, defines as the depth of flow in a pipe divided by the diameter of the pipe.

Sewer System Management Plan – Revision 01
Element 8 – System Evaluation and Capacity Assurance Plan

City of Salinas
May 2025

Page 4 of 8 ends

Table 8-1: Hydraulic Criteria for Existing Systems
Standard Criteria
Velocity
Minimum: 2.0 ft/s for peak flows; 1.75 ft/s at
average
rate of flow
Maximum: 8.0 ft/sec
Minimum
Slope
6-inch: 1.0%
8-inch: 0.40%
10-inch: 0.26%
12-inch & above: 0.20%
Friction
Factor
Manning’s n (gravity)=0.013 for Vitrified Clay Pipe
(VCP)

0.011 for Polyvinyl Chloride (PVC)
Hazen-Williams C (pressure)=100 to 120 depending
on pipe size, material, and age
Minimum
Pipe Size 8-inch
Maximum
Allowable
Flow Depth
10-inch or less: d/D=0.67
12-inch to 24-inch: d/D=0.80
27-inch or greater: d/D=0.90
Surcharging Allowed as long as the Hydraulic Grade Line (HGL) remains at least 5-Feet Below the rim elevation
Forcemain
Hydraulics
Minimum: 2.0 ft/s
Maximum: 5.0 ft/s

Where improvements were recommended to the collection system, worst case d/D values were provided for reference. These d/D values represent a snapshot of the system under either;
o existing conditions, or
o proposed conditions with all improvements in place.

Through the digital sewer model, maximum d/D was analyzed for the system as a whole, ensuring that recommended updates did not trigger additional downstream or upstream improvements.

Inline flow monitoring was completed to capture dry and wet weather hydraulic conditions and evaluate hydraulic conditions through projected City build out.

Sewer System Management Plan – Revision 01
Element 8 – System Evaluation and Capacity Assurance Plan

City of Salinas
May 2025

Page 5 of 8 ends

Capital improvement projects were identified as part of this hydraulic evaluation for existing and future conditions. Projects are included in Section 8.5 of this Element.

8.4 Prioritization of Corrective Actions
The SSMPU identified capital improvement projects which included staff O&M based projects, hydraulic deficient projects, lift station improvement projects and CCTV data.

The City prioritized these projects based on the following criteria:
o Overflow to Waters of the State
o Ability to meet Design Criteria
o O&M Hot Spots
o Community Impacts
o Surcharge
Each of these categories was provided a weighted importance factor and each project received an overall ranking score. The importance factor was multiplied by the overall score of the project and then these two (2) factors were added together for a final score/ranking. The City reviews these projects to assess if rankings require adjustment regularly.

Lift Station CIP Ranking
Lift Station CIPs have been categorized in two separate ways: one based on improvements needed at each lift station as a whole and the other based on improvement project type for all lift stations.

Appendix 8A, Table 7-3 ranks each individual lift station based on eight categories:
o overflow to a water body,
o inspection frequency,
o existing pumping capacity deficiencies,
o peak hour emergency response time,
o if bypassing capabilities are needed,
o if an onsite generator with automatic transfer switch is needed, o if control system upgrades are needed, and
o potential impact to the community.

Although not included in the scoring, Table 7-3 also shows if the lift station would be impacted by future development.

Sewer System Management Plan – Revision 01
Element 8 – System Evaluation and Capacity Assurance Plan

City of Salinas
May 2025

Page 6 of 8 ends

Hydraulic and Maintenance Repair CIP Ranking
Appendix 8B, Table 7-2 ranks each sewer pipeline project based on the type of project (Hydraulic Deficiency or O&M Project) and five (5) ranking criteria:
o Overflow to Water Body of the State (0-10 Points)
o Meets Design Standards (0 – 10 Points)
o Maintenance Hot Spot (0-10 Points)
o Community Impact/Population (0-10 Points)
o Surcharge Near City Manhole Monitor (0-5 Points)
o Impacted by Future Development (also considered but no points were assigned)

8.5 Capital Improvement Plan
The City developed a ranked Capital Improvement List which is included in Appendix 8C.

There are two (2) tables that identify Pipeline/Manhole CIP (Table 7-4 & 7-6) and one (1) table that identifies Lift Station CIP (Table 7-5).

Funding for Projects and Future Investigations
The City recently completed a revenue rate study and is planning to move forward with Proposition 218 rate increase for all sewer users. This revenue plan would provide for the following:
o $2 million per year for sewer system repairs
o $1.1 million per year for ongoing CCTV investigations o $154K per year for manhole inspections
The City is also in the process of completing projects funded by the American Rescue Plan Act (ARPA) which has a deadline for spending December 31, 2026.

Operations and Maintenance staff work with Engineering staff to develop and rank Capital Projects.

The status of these projects is shown in Appendix 8D with current and anticipated sources of funding. Full project descriptions are provided in the 2023 SSMPU.

In addition to the funding sources identified in Appendix 8D, grant programs from the EDA Public Works and Economic Development Program, the State Water Resources Control Board, and others are the preferred sources for additional funding for sewer upgrades. If grant funding proves to be unavailable other potential funding options may also include:
• User rates
• Connection fees

Sewer System Management Plan – Revision 01
Element 8 – System Evaluation and Capacity Assurance Plan

City of Salinas
May 2025

Page 7 of 8 ends

• Municipal bonds
• Special assessment districts
• Public/private partnerships
• California Infrastructure and Economic Development Bank: infrastructure state revolving fund program; industrial development bonds
• California State loans and grants: State Revolving Fund (SRF); direct state appropriations
• Federal grants and loans: EDA Public Works and Economic Development Program; direct federal appropriations

The City continues to evaluate additional sources of funding for Capital Projects and will amend project information pertaining to schedules and sources of funding included in Appendix 8D.

8.6 Additional WDR Requirements
The City plans to conduct a Vulnerability Assessment to address the following WDR requirements:
o Prioritize the condition assessment of system areas that:
▪ Hold a high level of environmental consequences if vulnerable to collapse, failure, blockage, capacity issues, or other system deficiencies; ▪ Are located in or within the vicinity of surface waters, steep terrain, high groundwater elevations, and environmentally sensitive areas; o Are within the vicinity of a receiving water with a bacterial-related impairment on the most current Clean Water Act section 303(d) List;
o Assess the system conditions using visual observations, video surveillance and/or other comparable system inspection methods;
o Utilize observations/evidence of system conditions that may contribute to exiting of sewage from the system which can reasonably be expected to discharge into a water of the State;
o Identify system assets vulnerable to direct and indirect impacts of climate change, including but not limited to: sea level rise; flooding and/or erosion due to increased storm volumes, frequency, and/or intensity; wildfires; and increased power disruptions. o Outline how capacity assessment considers:
▪ Data from existing system condition assessments, system inspections, system audits, spill history, and other available information; ▪ Capacity of flood-prone systems subject to increased infiltration and inflow, under normal local and regional storm conditions;
▪ Capacity of systems subject to increased infiltration and inflow due to larger and/or higher-intensity storm events as a result of climate change; ▪ Increases of erosive forces in canyons and streams near underground and above- ground system components due to larger and/or higher-intensity storm events;

Sewer System Management Plan – Revision 01
Element 8 – System Evaluation and Capacity Assurance Plan

City of Salinas
May 2025

Page 8 of 8 ends

o Capital Improvement Plan that includes:
▪ Project schedules including completion dates for all portions of the capital improvement program;
▪ Internal and external project funding sources for each project; and ▪ Joint coordination between operation and maintenance staff, and engineering staff/consultants during planning, design, and construction of capital improvement projects; and Interagency coordination with other impacted utility agencies.

The Vulnerability Assessment is planned for completion by 2027. Capital Projects associated with this Vulnerability Assessment will be incorporated into the Capital Projects list included in Appendix 8.

Sewer System Management Plan – Revision 02
Element 9 – Monitoring, Measurement, and Program Modifications

City of Salinas
May 2025

Page 9 ends

ELEMENT 9 - MONITORING, MEASUREMENT & PROGRAM MODIFICATIONS The City monitors the implementation of the SSMP elements in order to measure the effectiveness of the City’s SSMP in reducing sewer spills. The manner in which each SSMP element is monitored and evaluated and the schedule with which the City completes this monitoring and evaluation is described in this SSMP Element.

9.1 Regulatory Requirements
WDR Order No. 2022-0103-DWQ Section D 9 states:

The Plan must include an Adaptive Management section that addresses Plan- implementation effectiveness and the steps for necessary Plan improvement, including:
(a). Maintaining relevant information, including audit findings, to establish and prioritize appropriate Plan activities;
(b). Monitoring the implementation and measuring the effectiveness of each Plan Element;
(c). Assess the success of the preventative maintenance activities; (d). Updating Plan procedures and activities, as appropriate, based on results of monitoring and performance evaluations; and
(e). Identifying and illustrating spill trends, including spill frequency, locations and estimated volumes.

9.2 Data Management
The City manages, schedules, and tracks preventative maintenance activities through GIS based Computerized Maintenance and Management System. The system covers the following:
o Sewer Line Cleaning
o High Priority Area Cleaning and Inspections
o Manhole Inspections and Maintenance
o Lift Station Inspection and Maintenance
o Customer Complaints
o Work Orders
o CCTV Inspections
o FOG Inspections
Triennial SSMP Audit Reports are maintained at the City’s Wastewater Division office.

Corrective actions from audit reports are generally addressed in updates of the City’s SSMP.

More immediate actions are completed in accordance with the recommended corrective action schedule in each triennial audit.

9.3 Establishing and Prioritizing SSMP Activities
Table 9-1 outlines the relevant information maintained by the City to establish and prioritize appropriate sewer collection system activities and the City staff who are responsible for monitoring implementation and measuring the effectiveness of each element, when appropriate.

Sewer System Management Plan – Revision 02
Element 9 – Monitoring, Measurement, and Program Modifications

City of Salinas
May 2025

Page 9 ends

Table 9-1: SSMP Implementation Management
SSMP Element SSMP Relevant Information Responsible Party

1. Goal This SSMP Element contains the City’s goals for the operation, maintenance, and management of
the sanitary sewer collection system, which
provide focus to reduce Spills and mitigate Spills
that do occur.

Wastewater Division
Manager

2. Organization A table containing names, job titles, roles, responsibilities, and contact information is
contained in this SSMP Element, which identifies
the most knowledgeable person for each aspect
of the SSMP Program. An organizational chart
identifies the lines of authority.

Wastewater Division
Manager

3. Legal Authority Web links in this SSMP Element contain the sections of City Policies and Ordinances
governing the sewer collection and conveyance
system.

Wastewater Division
Manager and City Legal
Counsel

4. Operation and
Maintenance
Program
Information in this SSMP Element document the
sanitary sewer system operation and maintenance
activities.

Wastewater Division
Manager

5. Design and
Performance
Provisions
City website links in this SSMP Element include
City Design Standards and Specifications that
include Testing requirements.

Wastewater Division
Manager and Engineering
Staff

6. Spill Emergency
Response Plan
The City updated a Spill Emergency Response
Plan in 2023 which include staff contact
information, mandatory Spill reporting information,
and response and mitigation programs.

Wastewater Division
Manager

7. Pipe Blockage
Control Program
Monitor any changes in the program that may
require updates to this Element..

Wastewater Division
Manager

8. System Evaluation,
Capacity
Assurance, and
Capital
Improvements Plan
The City will review and update this SSMP
Element as applicable to update project
schedules, status of projects and sources of
funding for associated projects.

Wastewater Division
Manager and Engineering
Staff

9. Monitoring,
Measurement, and
Program
Modifications
This SSMP Element will be updated annually with
the data in Tables 9-2 and 9-3 in a calendar year.

Wastewater Division
Manager

10. SSMP Program
Audits
SSMP Audit Reports are required triennially.

Corrective actions are implemented and tracked.

Wastewater Division
Manager

11. Communication
Program
Examples of public outreach materials and
pertinent City website links provided, as well as
meeting agendas, pertinent City Council reports
and minutes are found on the City’s website and
City offices.

Wastewater Division
Manager

Sewer System Management Plan – Revision 02
Element 9 – Monitoring, Measurement, and Program Modifications

City of Salinas
May 2025

Page 9 ends

9.4 Preventative Maintenance Program Assessment
The City’s Preventative Maintenance Program includes CCTV inspection, line cleaning, visual manhole inspection, lift station maintenance, high priority area identification and maintenance.

The City will review these operation and maintenance practices annually and compare them with annual Spill records. A summary of the performance metrics identified in Table 9-2 will be developed annually.

Table 9-2: Sanitary System Performance Metrics for Monitoring and Measurement Performance Measure Source
System Statistics Total miles of gravity sewer Atlas Maps Total miles of pressure sewer Atlas Maps
Total number of manholes Atlas Maps
Total number of sewer lift stations Atlas Maps
Operations and
Maintenance
Linear feet of sewer line cleaned CMMS/GIS & Work
Order Requests or Staff
Field Notes
Linear feet of high priority lines cleaned CMMS/GIS & Work Order Requests or Staff
Field Notes
Number of blockages/backups not
resulting in sewer spill
CMMS/GIS & Work
Order Requests or Staff
Field Notes
Linear feet of CCTV CMMS/GIS & Work
Order Requests or Staff
Field Notes
Number of manholes inspected CMMS/GIS & Work
Order Requests or Staff
Field Notes
Lift station inspections CMMS/GIS & Work
Order Requests or Staff
Field Notes
FOG inspections. Number of inspections
and reinspection’s
CMMS/GIS & Work
Order Requests or Staff
Field Notes
Root control linear feet CMMS/GIS & Work
Order Requests or Staff
Field Notes
Measures Based on Number and percentage of dry weather vs. CIWQS Sewer System Management Plan – Revision 02
Element 9 – Monitoring, Measurement, and Program Modifications

City of Salinas
May 2025

Page 9 ends

Performance Measure Source
Sewer Spill Numbers wet weather spills
Number of spills by cause (operational,
capacity, system, other)
CIWQS
Number of spills per 100 miles per Year CIWQS
Total volume of spills CIWQS
Average spill volume CIWQS
Total volume recovered and percentage of
overall total Spill Volume
CIWQS
Net volume of spills (total minus
recovered) and percentage of overall total
spill volume
CIWQS
Total volume reaching storm drainage
channel and not recovered or reaching
surface waters and percentage of overall
total spill volume.

CIWQS
Spill Response Time Average response time during business hours
CIWQS
Average response time outside of
business hours.

CIWQS
Condition
Assessment,
Rehabilitation, and I/I
Control
Amount of CCTV inspection performed
(linear feet)
CCTV Reports
Number of manholes inspected CMMS/GIS & Work
Order Requests or Staff
Field Notes
Number of inflow sources detected and
corrected.

CMMS/GIS & Work
Order Requests or Staff
Field Notes
Capital Projects Summary of short- and long-term projects, sources of funding and status of each
project.

Capital Projects
Schedule
Outreach Pipe Blockage Control Program summary
of outreach efforts.

ClogBusters outreach
and City Outreach
Goals Summary of how goals are being met and
areas of improvement where goals have
not been achieved.

Element 1 Goals and
Supporting data to
demonstrate
performance.

Sewer System Management Plan – Revision 02
Element 9 – Monitoring, Measurement, and Program Modifications

City of Salinas
May 2025

Page 9 ends

Performance Measure Source
Training Summary of training to meet Element 4
training requirements and other City
training programs.

Training Records

9.5 SSMP Updates
The City will use the SSMP for management, training, planning and regular maintenance of the collection system. As the management plan is utilized, any deficiencies or discrepancies will be corrected. Program elements will be updated based on performance evaluations, organizational, operational, and maintenance changes, new regulatory requirements, repairs, replacements, and upgrades made to the collection system.

At a minimum, the City will review and revise the SSMP annually as warranted. The Wastewater Division Manager is responsible for revising and maintaining the SSMP.

A revision record will be maintained to track changes.

9.6 Sewer Spill Trends
The trends in City sewer spill history should be tracked for a three-year period utilizing the criteria in Table 9-3. The cause categories identified in Table 9-3 are the causes available for use in the Sewer Spill Report provided in California Integrated Water Quality System (CIWQS).

City Staff are responsible for determining which cause category is appropriate for each Spill when the Spill is reported in CIWQS.

Table 9-3 City of Salinas per Indicator per Year
Criteria Indicator
Spills No. of Spills
Multiple Spills at Same
Location # of Locations with Multiple Spills
Spill Volume (gal)
Volume
Volume Recovered
Volume Reached Surface Water
Spill Causes
Debris - Construction
Debris – General
Debris – Rags
Flow Exceeded Capacity
FOG
Sewer System Management Plan – Revision 02
Element 9 – Monitoring, Measurement, and Program Modifications

City of Salinas
May 2025

Page 9 ends

Criteria Indicator
Operator Error
Other
Pipe Structural Problem/Failure
Pump Station Failure
Rainfall Exceeded Design
Root Intrusion
Vandalism
Comparison with
Regional and State
Averages
Average Spill Volume
Average # of Spills

The City will continue to plan and adjust operation and maintenance practices so that the number of Spills experienced on an annual basis remains low.

Sewer System Management Plan – Revision 02
Element 10 – Sewer System Management Plan Program Audits

City of Salinas
May 2025

Page 10 ends

ELEMENT 10 - SEWER SYSTEM MANAGEMENT PLAN PROGRAM AUDITS SSMP audits are required to identify and correct deficiencies in the most current revision of the City’s SSMP and provide a schedule to correct identified deficiencies. This SSMP Element outlines the audit process and identifies staff responsible for conducting or participating in SSMP audits and generating the required SSMP Audit Report.

10.1 Regulatory Requirements
WDR Order No. 2022-0103-DWQ Section D 10 requires:

The Plan shall include internal audit procedures, appropriate to the size and performance of the system. Additionally, the General Order requires;
The internal audit shall be appropriately scaled to the size of the system(s) and the number of spills. The Enrollee’s sewer system operators must be involved in completing the audit. At minimum, the audit must:
o Evaluate the implementation and effectiveness of the Enrollee’s Sewer System Management Plan in preventing spills;
o Evaluate the Enrollee’s compliance with this General Order; o Identify Sewer System Management Plan deficiencies in addressing ongoing spills and discharges to waters of the State; and
o Identify necessary modifications to the Sewer System Management Plan to correct deficiencies.

The Enrollee shall submit a complete audit report that includes:
o Audit findings and recommended corrective actions;
o A statement that sewer system operators’ input on the audit findings has been considered; and
o A proposed schedule for the Enrollee to address the identified deficiencies.

10.2 SSMP Program Audits
The Wastewater Manager (LRO) or their designee is responsible for assuring the SSMP audit is conducted and complete based on the schedule outlined on the SWRCB lookup website which requires audits to be conducted at a three-year interval from the prior audit. Audits should be conducted with the cooperation of the City staff responsible for sewer system operations and maintenance, administrative staff, and engineering staff. When conducting the SSMP audit, City staff must evaluate the effectiveness of each SSMP Element. A comprehensive, effective review of the City’s SSMP must be documented in a SSMP Audit Report.

10.2.1 Summary of Procedure:

1. Gather appropriate documents using the SSMP Audit Data & Records Request, which is provided in Appendix 10A.

2. Interview City staff responsible for the administration, operations, maintenance and engineering associated with system performance information.

Sewer System Management Plan – Revision 02
Element 10 – Sewer System Management Plan Program Audits

City of Salinas
May 2025

Page 10 ends

3. Develop Audit Report and reference all documents reviewed and used as evidence of compliance with the WDR. Create a plan and schedule for updates to the SSMP based on changes in operational strategies or deficiencies found in the SSMP.

4. Evaluate the effectiveness of the City’s SSMP and compliance with each WDR requirement using the ranking methodology outlined in Table 10-1.

Table 10-1: SSMP Audit Ranking Criteria
Ranking Ranking Basis
In Compliance All requirements specified in the element are met.

Substantial Compliance The majority of requirements in the element are met.

Partial Compliance Half of the requirements in the element are met.

Marginal Compliance Less than half of the requirements in the element are met.

Out of Compliance None of the requirements in the element are met.

The SSMP Audit Report must be signed and certified by the Legally Responsible Official (LRO).

The SSMP Audit Report must be certified using the language provided below:
“I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted. Based on my inquiry of the person or persons who manage the system or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations.”
Subsequent SSMP audits must be conducted continuously on a three-year interval following the schedule outlined below which is based on the dates required by the 2022 WDR:
• SSMP Audit Period: May 2, 2024 - May 2, 2027 (Audit report due 11/2/27) • SSMP Update: Update due 5/2/31.

Additional SSMP Audit and SSMP Update regulatory schedules required after the dates shown above should be identified in the following link:
https://www.waterboards.ca.gov/water_issues/programs/sso/lookup/ To assist in the audit process, the City should consider quarterly or semiannual reviews and revisions to specific SSMP Elements and associated supporting documents. These reviews and revisions will help ensure current operational practices and procedures are reflected in the Sewer System Management Plan – Revision 02
Element 10 – Sewer System Management Plan Program Audits

City of Salinas
May 2025

Page 10 ends

SSMP and documentation of these activities is readily available during an audit by the Regional Water Quality Control Board, and/or State Water Resources Control Board.

SSMP Audit Reports must be kept on file and submitted to the online CIWQS Sanitary Sewer Database within six (6) months after the end of the 3-year audit period.

Sewer System Management Plan – Revision 2
Element 11 – Communication Program

City of Salinas
May 2025

Page 11 ends

ELEMENT 11 - COMMUNICATION PROGRAM
Communicating the objectives of the SSMP and the importance of sanitary sewer system management practices to the public is essential. An informed public can assist and support the City by reducing customer caused blockages, which will potentially decrease ewer spills.

11.1 Regulatory Requirements
WDR Order No. 2022-0103-DWQ Section D 11 states:

The Plan must include procedures for the Enrollee to communicate with:
o The public for:
▪ Spills and discharges resulting in closures of public areas, or that enter a source of drinking water, and
▪ The development, implementation, and update of its Plan, including opportunities for public input to Plan implementation and updates.

o Owners/operators of systems that connect into the Enrollee’s system, including satellite systems, for:
▪ System operation, maintenance, and capital improvement-related activities.

11.2 Communication Program
The purpose of the City sanitary sewer system communication program is to educate stakeholders, which include residential and commercial users of the collection system, about the SSMP. Public awareness of different components of the SSMP is accomplished through different mediums and may reach different audiences. The following are activities that the City practices to increase awareness and education about the importance of having a properly constructed, maintained, and operated sewer collection system.

Table 11-1: City Communication Program Overview
Activity Frequency Stakeholders
City Website: www.cityofsalinas.org Year-round All
City Council Meetings Tuesdays @ 4:00 pm All
Social Media – Facebook,
Instagram and GovDelivery Year-round All
City Office Year-round All

11.2.1 City Website
Information is posted on the City website, www.cityofsalinas.org and includes reports, documents, maps, links, City meeting minutes and agendas, educational material and public service announcements. The City SSMP can be found on the City website. Sewer spill emergency contact information is also provided on the City website.

Sewer System Management Plan – Revision 2
Element 11 – Communication Program

City of Salinas
May 2025

Page 11 ends

Updates and revisions to the SSMP will be posted and maintained on the City website when completed.

11.2.2 City Council Meetings
City Council Meetings are generally held on alternating Tuesdays of each month at the City Hall Rotunda. Utility sewer operation, Sewer Spill Reports, SSMP updates, significant revisions, audits and SSMP status reports are presented at the Council meetings to receive input.

11.2.3 Social Media
The City uses social media (Facebook and Instagram and GovDelivery) to post information about utility projects, public education and outreach, and highlight items on the Council agenda.

11.2.4 City Public Works Office
The City Office located at 200 Lincoln Avenue, has copies of educational material, public service announcements, and staff that provide assistance and education to the public. Office hours are Monday- Friday from 8:00am to 5:00pm.

11.2.5 Public Notices for Spills – Public Areas
The public is notified of spills and discharges that result in closures of public areas (including streets and surface waters) by erecting cones and barricades, and by posting warning signs in accordance with the Spill Emergency Response Plan. The necessary equipment and signage are kept in the City’s emergency response vehicles.

11.2.6 Public Notices for Spills – Public Areas
The City has identified two water purveyors who would be notified in the event of a sewer spill in the vicinity of a source of drinking water. These purveyors are listed below:
o Alisal Water Service (ALCO)
249 Williams Road, Salinas CA 93905
(831) 424-0441
[email protected]
o California Water Service (Salinas Valley Region)
254 Commission Street, Salinas CA 93901
Business Hours (831) 757-3644 or
After Hours (831) 757-3644

11.3 Satellite and Tributary Systems
The wastewater collection system of the unincorporated community of Boronda to the northwest of Salinas is tributary to the Salinas sanitary sewer system. The County of Monterey Public Works Department is responsible for the operation and maintenance of this system.

Communication with the Boronda area is conducted on an as needed basis when conditions are warranted. Typical scenarios that require communication are:
o FOG Control Program (administered by the City of Salinas) o Capital Improvement Projects
o Sewer Spills
o Required Sewer System Maintenance
Sewer System Management Plan – Revision 02
Appendix 0A

City of Salinas
May 2025

Appendix 0A Placeholder – Meeting Minutes Adopting 2025 SSMP, Revision 2 Sewer System Management Plan – Revision 02
Appendix 2A

City of Salinas
May 2025

Appendix 2A Cover Sheet – City Organization Chart
City of Salinas
Maintenance Services Department Organization Chart
426 Work Street, Salinas, Ca. 93901

Administration: (831) 758‐7233

water

Sewer System Management Plan – Revision 02
Appendix 4A

City of Salinas
May 2025

Appendix 4A Cover Sheet – Hot Spot List
Page #1
\\wlg-fs01\projects\0886-0046 SSMP Update\06 - Reports and Calculations\Drafts\Appendix\hot spots monthlynew.doc.03/07/25.8:22 AM.tm

CITY OF SALINAS
Wastewater Division
Sewer Maintenance High Priority List
Revised December 20, 2016

Monthly:

No Street From To Lin Ft Ser
East Salinas Area
1 .
2 Murphy St M.H. @ E. Alisal & Murphy Shoot to M.H. on Murphy & also shoot towards R.R. tracks

3 E. Alisal St M.H. @ 347 E. Alisal St
4 E Alisal St M.H. @ intersection of E.

Alisal & Griffin
Shoot to Prader St
5 E. Alisal St Griffin St Shoot to Rianda St
6 E. Alisal St Turn pocket @ E. Alisal &
Kern
Shoot to Roosevelt & also to
Madeira Ave

7 E. Market St King St Shoot tot N. Madeira Ave.
8 King St. Intersection King & Roosevelt Shoot to M.H. on E Market St 9 E. Alisal St (M.H. @ fast Lane) King St Shoot towards Roosevelt 10 N. Wood St M.H. @ 24 N. Wood St Shoot towards M.H. @ Pearl St & Shoot with flow to La Paz Park

11 Roosevelt St M.H. @ 530 Roosevelt St Shoot towards building complex 12 N. Madeira Ave. From middle intersection N.

Madeira and Roosevelt
Shoot towards M.H. @ 31 N.

Madeira

13 N. Madeira Ave M.H. across 31 N. Madeira Ave
@ sidewalk
Shoot towards building
14 N. Madeira Ave & Roosevelt St M.H. closest to curb Shoot to M.H. on sidewalk at 31 N.

Madeira & also shoot towards
building complex

Page #2
\\wlg-fs01\projects\0886-0046 SSMP Update\06 - Reports and Calculations\Drafts\Appendix\hot spots monthlynew.doc.03/07/25.8:22 AM.tm Monthly:

No Street From To Lin Ft Ser
15 E. Alisal St M.H. @ Intersection of Wood
& E. Alisal
Shoot to F.I. @ 548 E Alisal St, the
radio station

16 San Benito St M.H. @ Wood St & San Benito Shoot to E. Alisal & also shoot to S.

Madeira Ave

17 S. Wood St Second M.H. @ Wood St &
San Benito St
Shoot under trees to Pearl St
18 S. Wood St. Santa Maria Ave Shoot towards F.I. on Santa Maria & also to E. Alisal

19 S. Wood St James St Shoot towards F.I. on James St
20 S. Madeira Ave M.H. @ 75 S. Madeira Ave Shoot towards Santa Maria & shoot down F.I. on James & also shoot
with flow to Apartments

21 John St John St (north bound off ramp) Shoot to Santa Maria & shoot with flow to T.P.2

22 John St M.H. @ grass area @ 535 John Shoot to M.H. @ end of San Benito in ice plant

23 John St M.H. @ Parking lot @ 535
John St
Shoot to Hwy 101 M.H. @ grass
area & also shoot with flow to T.P.2

24 S. Hebbron Ave Prince Pl Shoot all Prince Pl
25 E. Alisal St Hebbron Ave Shoot towards Prince Pl & to E.

Market St

26 Garden Wy M.H. @ 933 Garden Wy Shoot to Filice St
27 John St Magnolia Ave Shoot to Hebbron Ave
28 S. Filice St M.H. @ John St Shoot to F.I. on Filice
29 E. Market St M.H. @ 101 bridge Shoot to Kern
30 N. Madeira Ave Terrace St Shoot to F.I. on terrace
31 E. Market St Carr St Shoot tow F.I. on Carr St & also with flow to Hebbron Ave

32 Carr St Terrace St Shoot to F.I. on Terrace
33 Carr St Fremont St Shoot to F.I. on Fremont
34 Elton Pl M.H. @ Elton & Hebbron Shoot to F.I. on Elton Pl 35 N. Hebbron Ave M.H. @ Hebbron & Fremont Shoot to Elton Pl. Lower Pressure Toilet Blown out
36 E. Market St M.H. @ E. Market & Hebbron Shoot to Fremont & also shoot to Page #3
\\wlg-fs01\projects\0886-0046 SSMP Update\06 - Reports and Calculations\Drafts\Appendix\hot spots monthlynew.doc.03/07/25.8:22 AM.tm Monthly:

No Street From To Lin Ft Ser
37 E. Market St Division St Shoot with flow down Division St 38 Mayfair Dr M.H. @ 335 Mayfair Dr Shoot to F.I. on Mayfair Dr 39 S. Sanborn Rd M.H. on Island at Sanborn Rd Shoot under houses towards Magnolia Dr and Meadow

40 Fairview Dr Beverly Dr Shoot to M.H. on Beverly to Barbara Pl & also shoot with the flow to
M.H. across 101 @ Ice plants

41 S. Sanborn Rd M.H. @ Sanborn 101 on ramp Shoot south to the Ice plants 42 Terven Ave Vertin Ave Shoot to dead end on Vertin
43 Terven Ave 1057 Terven Ave Shoot to Vertin
44 Hilltop Dr M.H. at 1215 Hilltop Dr Shoot all 3 directions one with flow to Circle Pl

45 St George M.H. across 588 St. George Shoot all 3 directions one with flow 46 St. Thomas St. George Shoot to St. Edwards
47 Towt St First St Shoot to M.H. at 1248 First St
48 E. Market St Kenneth St Shoot to E. Laurel Dr
49 E. Market St First St Shoot to F.I. on First St
50 Cedar Pl Top Pl Shoot to F.I. on Top Pl
51 Kentucky St Valencia St Shoot to F.I. on Valencia
52 Washington Dr M.H. @ 101 Washington Dr Shoot to F.I. on Washington Dr 53 Cooper St M.H. @ 1458 Cooper St Shoot to F.I. on E. Laurel 54 E. Laurel Dr M.H. @ 1020 E. Laurel Dr Shoot to down St & also shoot to Sanborn Rd

55 Oregon St M.H. @ 105 Oregon St Shoot towards Laurel Dr 56 Fairhaven St First St Shoot to Williams & follow it to Towt St
Call 772-0407 Esperanza
Perez 1209 Fairhaven
57 Grandhaven First St Shoot to Williams & follow it to Towt St

58 Bellehaven St First St Shoot to Williams Rd & shoot to St.

Joseph cir and also follow it to Towt

59 Alma Ave Second Ave Shoot to Williams & shoot to Towt St

60 Garner Ave Towt St Shoot to Williams & also @
Page #4
\\wlg-fs01\projects\0886-0046 SSMP Update\06 - Reports and Calculations\Drafts\Appendix\hot spots monthlynew.doc.03/07/25.8:22 AM.tm Monthly:

No Street From To Lin Ft Ser
intersection of Garner & Second
shoot to Alma
61 Acosta St Machado Ave /E. Sanborn Shoot to Beech St
62 Montana St Sanborn Rd Shoot to Beech St
63 Kimmel St Sanborn Rd Shoot to Beech St
64 916 Acosta Plaza M.H. @ 916 Acosta Plaza Shoot to Gee St & also shoot with flow to tree

65 66 Wiren St Williams Rd Shoot to F.I. on Wiren St
67 Rider St Holly St Shoot to F.I. on Holly St
68 Elm St F.I. @ dead end of Elm St Shoot to Rider Ave
69 Rider Ave Garner Ave Shoot to Alamo & shoot to Gee St & shoot to Charro Ave

70 Williams Rd E. Laurel Dr Shoot to all the way to Garner Ave 71 New Deal Del Monte Ave Shoot to Cortez St
72 Cortez St M.H. @ intersection Mae &
Cortez
Shoot to Town Houses @ Cortez
73 Mae Ave Del Monte Ave Shoot to Cortez
74 Del Monte Ave Williams Rd Shoot to Sanborn Rd all the streets in between both side

75 Green St M.H. @ Garner Ave Shoot to F.I. on Green St 76 Sunrise St M.H. @ Garner Ave Shoot to F.I. on Sunrise St 77 Mae Ave M.H. @ Garner Ave Shoot to F.I. on Mae Ave
78 C St M.H. @ Mae Ave Shoot to F.I. on C St
79 D St M.H. @ Mae Ave Shoot to F.I. on D St
80 81 Elkington Ave M.H. @ Del Monte Ave Shoot to F.I. on Elkington Ave 82 Pacific Ave M.H. @ Del Monte Ave Shoot to F.I. on Pacific Ave 83 Pacific Ave Sieber St Shoot to Del Monte Ave
84 Sieber St M.H. @ 1028 Sieber St Shoot to Pacific Ave 85 Garner Ave Sieber St Shoot to M.H. @ 1028 Sieber St & shoot to F.I. on Garner to Pacific

86 Garner Ave Pacific Ave Shoot to F.I. on Pacific Ave Page #5
\\wlg-fs01\projects\0886-0046 SSMP Update\06 - Reports and Calculations\Drafts\Appendix\hot spots monthlynew.doc.03/07/25.8:22 AM.tm Monthly:

No Street From To Lin Ft Ser
87 Rider Ave M.H. @ 1234 Rider Ave Shoot under houses to Caoba 88 Paseo Grande M.H. @ Sanborn Rd Shoot to Estrella Wy
89 Towt St M.H. in from of 769 Towt St Shoot under house 90 Cross Ave M.H. @ E. Market St Shoot to Bardin Rd
91 Dennis Ave Tampa St Shoot to Bardin Rd
92 Toro Ave Tampa St Shoot to Bardin Rd
93 Afton Rd Ct Sycamore St Shoot to Margaret St Call First Mrs. Moreno at 155 Sycamore #758-9046
Lower Pressure Toilet
Blown out
94 Tampa St Paloma Ave Shoot to Sycamore
95 Avis Sycamore St Shoot to F.I. on Avis Ct
96 Paloma Ave Quilla Ave Shoot to Tampa St
97 Cross St E. Paloma Shoot to East Market Street
98 E. Alisal St E. Market St Shoot to Margaret St
99 Afton St. Sycamore St. Avis St.
100 Rider Ave M.H.@ Rider Ave & Las
Casitas
Shoot to F.I. on Hawaii Pl
101 Rider Ave @ Las casitas Rider Ave Shoot to F.I. on Las Casitas (not force Main)

102 La Honda/ Alamo Wy Lift Station @ Las Casitas Shoot to all Ranchero & to La Honda and also pull to F.I west on Alamo

103 Vista Nueva lift station All the streets to lift station 104 Bison St Eagle Dr Shoot to Bison Wy
105 Eagle Dr M.H. @ 1048 Eagle Dr Shoot to east on Eagle & with flow to Freedom

106 Rider Ave Buckhorn Dr Shoot to Chamise Dr
107
108
109 John St M.H. @ 1219 John St M.H. at corner of fence, side of nursery

110
111 Paloma St. Paloma &Sycamore St. Afton St.

Page #6
\\wlg-fs01\projects\0886-0046 SSMP Update\06 - Reports and Calculations\Drafts\Appendix\hot spots monthlynew.doc.03/07/25.8:22 AM.tm Monthly:

No Street From To Lin Ft Ser
112 Paloma St. Paloma &Sycamore St. Margaret St.
113 East Alisal St. East Alisal & Tampa Paloma
114 Toro Ave. Toro & Tampa Paloma
115 Garner Ave. Garner & Towt St. F.I On Towt St.
116 Sanborn St. Sanborn & Mohar Beech St.
117 Division St. Division & East Market St. East Sanborn 118 Bridge At Ford Dealer (Elvee) Parking Lot Manhole in the Field 119 Orchard St. Orchard & Seiber Delmonte Ave.
120 Sanborn St. Sanborn & East Market St. Both ways to Cedar 121 Manhole at Sanborn & E. Acosta Manhole at Sanborn & E.

Acosta
Shoot Three Ways Am List
122 Acosta St. Second Ave F.I towards Towt
123 St. Charles Way St. Edwards/ St. Augustine N. Madiera 124 Dewey St. Beech St. F.I On Towt Street
125 Second St. E. Laurel Drive Acosta St.
126 Midway St. E. Market St. E. Laurel Dr.
127 East Laurel Dr. Towt St. Midway St.
128 Sanborn Rd M.H @Laurel and Sanborn Shoot all directions Am List 129 Sanborn Rd Sanborn and E. Alisal St. Shoot to Towt Am List

Page #7
\\wlg-fs01\projects\0886-0046 SSMP Update\06 - Reports and Calculations\Drafts\Appendix\hot spots monthlynew.doc.03/07/25.8:22 AM.tm Monthly:

No Street From To Lin Ft Ser

North Salinas Area:

1 Truman St M.H. @ Eisenhower St Shoot to Fillmore St
2 Eisenhower St M.H. @ Arthur St &
Eisenhower St
Shoot to F.I. on Eisenhower to
Barkley Dr & Also shoot to F.I. on
Eisenhower to Truman & shoot to
F.I. on Arthur

3 Hoover St Souza St Shoot to Arthur St
4 Souza St Lenny St Shoot both ways
5 Lenny St M.H. @ 18802 Lenny St Shoot to F.I. on Lenny St/ Souza – F.I From Souza

6 Louise St M.H. @ 13220 Louise St Shoot to Lenny St & shoot under houses to Arthur St

7 Louise St M.H. @ 13170 Louise St Shoot to Lenny St & also with flow to Van Buren

8 Jackson St M.H. @ Van Buren & Jackson Shoot to F.I. on Jackson to Swaner 9 Van Buren St M.H. @ intersection Van Buren
& Bolivar
Shoot to Jackson st
10 Bolivar St M.H. @ 207 Bolivar St Shoot to Van Buren St 11 Bolivar St M.H. @ Bolivar & Soto Pl Shoot to Santa Rita & also shoot with flow to Lift Station Shoot To
Prado

12 Prado St M.H. @ 108 Prado St Shoot to F.I. on Prado & also to N.

Main St

13 San Juan Grade Rd M.H. @ 33 San Juan Grade Rd Shoot to Boronda Rd 14 Madrid St M.H. @ Madrid St/ Madrid Cir Shoot to dead end 15 Madrid St M.H. @ Cherokee & Madrid Shoot to Segovia Cir 16 Cherokee Dr M.H. @ Cherokee & Seville
Wy
Shoot both ways
17 Seville Wy M.H. @ Seville St & Seville Shoot to Cherokee Dr Page #8
\\wlg-fs01\projects\0886-0046 SSMP Update\06 - Reports and Calculations\Drafts\Appendix\hot spots monthlynew.doc.03/07/25.8:22 AM.tm Monthly:

No Street From To Lin Ft Ser
18 Seville St M.H. @ 1606 Seville St Shoot to Seville Wy / To F.I @ 1655 19 Seville St M.H. @ 1501 Duran St Shoot to 1606 Seville St 20 Douglas Ave M.H. @ N. First St & Douglas Shoot to F.I. on Douglas Ave 21 N. First St M.H. @ Curtis St & N. First St Shoot to Douglas St Lower Pressure Toilet Blown out
22 Adams St M.H. @ Adams St & Tulane St Shoot to Crescent Wy 23 Rochex St M.H. @ Rochex & N. Four @
cross walk
Shoot to Parkside St & shoot with
flow to Laurel Dr

24 W. Laurel Dr. M.H. @ W. Laurel Dr &
Baldwin St
Shoot to F.I. on Baldwin St
25 Polk St M.H. @ Polk St & Monroe Shoo to F.I. towards W. Laurel Dr 26 W. Laurel Dr M.H. in front of black bear
restaurant @ Parking lot
Shoot towards Laurel Inn sign
27 Iris Alley M.H. @ Iris Dr & Iris Alley Shoot both ways let restaurant know before servicing

28 Iris Dr M.H. @ Iris Dr & Lupin Dr Shoot to Iris Alley 29 Lupin Dr M.H. @ Lupin & Gardenia Cir Shoot to Iris Dr 30 Gardenia Cir M.H. @ Gardenia Cir &
Gardenia Dr
Shoot to Lupin & with flow to M.H.
@ Heather Apartment M.H. Ice plant

31 Iris Dr. M.H. @ 350 Iris Dr Shoo to Heather Apartment to M.H. @ Ice plant

32 Iris Dr M.H. @ Heather Apt. driveway Shoot to Skyline Care Center around parking lot towards kitchen area &
also shoot with flow to Heather cir

33 Heather Cir M.H. in front of 939 Heather
cir
Shoot to Iris Dr
34 Columbia Dr Heather Dr Shoot under houses to Parkside 35 Columbia Dr Heather Dr Shoot to Lupin Dr
36 N. Main St M.H. @ N. Main St & Navajo Shoot to Alvin Dr 37 N. Main St M.H. @ 1339 N. Main @
Wendy’s
Shoot to Navajo
38 N. Main St M.H. @ N. Main & Curtis St Shoot to Wendy’s & also shoot to N.

First St

Page #9
\\wlg-fs01\projects\0886-0046 SSMP Update\06 - Reports and Calculations\Drafts\Appendix\hot spots monthlynew.doc.03/07/25.8:22 AM.tm Monthly:

No Street From To Lin Ft Ser
39 N. Main St M.H. @ N. Main & Rochex St Shoot to Curtis St & also shoot to Parkside St

40 N. Main St M.H. @ 1165 N. Main St Shoot to Rochex
41 N. Main St M.H. @ 1111 N. Main St Shoot to M.H. @ 1165 N. Main St

42 N. Main St M.H. @ 1045 N. Main St
Goodwill Store
Shoot to M.H. @ 1111 N. Main St
43 N. Main St M.H. @ Iris & N. Main Shoot to M.H. @ 1045 N. Main St 44 N. Main St M.H. on N. Main @ Clear
Channel billboard Sherwood
Garden Shopping center
Shoot to Iris Dr
45 N. Main St M.H. @ N. Main & Bernal Shoot to Sherwood garden shopping center & shoot with flow to Santa
Clara St

46 N. Main St M.H. @ 500 N. Main St Shoot to Hwy 101 underpass 47 N. Main St M.H. @ N. Main St & Deer St Shoot to F.I. on Deer St & also shoot to Bernal Dr

48 N. Main St M.H. @ North east corner of
Alvin/ N. Main St
Shoot to Wheeler M.H center along
sidewalk to Julia St.

49 50 Julia St M.H. @ 45 Julia St Shoot under house to N. Main St 51 Calaveras Dr M.H. @ 680 Calaveras Dr @
Dead end
Shoot to Klamath & with flow to
Natividad Rd

52 Donner Wy M.H. @ Emerald Dr Shoot to Humboldt
53 Tahoe Dr M.H. @ 1741 Tahoe Dr Shoot to Donner Wy
54 Tahoe Dr M.H. @ 1752 Tahoe Dr Shoot to 1741 Tahoe & with flow to Natividad Rd

55 Pescadero Dr Los Coches Shoot to El Sur Ave
56 Natividad Rd M.H. on island at Natividad &
Millbrae
Shoot to Mexican Restaurant
57 Marin Ave M.H. @ E. Alvin & Marin Ave Shoot to Mariposa St 58 Rainier Dr M.H. @ Rainier & Lassen Shoot to Linwood
59 Rainier Dr M.H. @ Rainier & Tampico Shoot to Lassen 60 Rainier Dr M.H. @ Rainier & Marin Shoot to Tampico & shoot with flow Page #10
\\wlg-fs01\projects\0886-0046 SSMP Update\06 - Reports and Calculations\Drafts\Appendix\hot spots monthlynew.doc.03/07/25.8:22 AM.tm Monthly:

No Street From To Lin Ft Ser
to Natividad Rd
61 Tampico Ave M.H. @ Tampico & Elwood Shoot to Linwood & also shoot to Chaparral Dr

62 Chaparral Dr M.H. @ 411 Chaparral Dr Shoot under house 63 Maryal Dr M.H. @ Chaparral & Maryal Shoot to F.I. on Chaparral to Noice & also shoot to North Salinas High

64 Maryal Dr M.H. @ Maryal & Reata Shoot to Chaparral Dr 65 Reata St M.H. Reata & Dororo Shoot to Maryal Dr
66 Dororo St M.H. @ Tapadero & Dororo Shoot to Reata St Lower Pressure Toilet Blown out
67 E. Laurel Dr M.H. 13 E. Laurel Dr @ Laurel
Square shopping center
Shoot under property line to Curtis
St & also shoot to Tapadero St

68 N. Main St M.H. @ old Lucky,s Parking
lot
Shoot with flow to sport complex
69 @ Muni Parking Lot F.I. next to restrooms Shoot with flow towards entrance to ball park

70 @ Muni Parking Lot M.H. inside entrance @ muni
ball park
Shoot towards snack bar& with flow
towards sports complex maint. shed

71 @ muni M.H. @ entrance to soft ball
fields @ Sport complex
Shoot to Maint. shed
72 Bernal Dr M.H. @ Bernal Dr & Alpine St Shoot to M.H. in park next to swimming pool

73 Bernal Dr M.H. next to Tennis Court Shoot to Park
74 Bernal Dr M.H @ Dirt Road Shoot to F.I. @ 10 Bernal
75 E. Rossi St M.H. @ E. Rossi & California Shoot to 150 Sherwood Dr 76 77 M.H. @ Kmart Parking Lot M.H. @ Kmart Parking Lot Shoot to Sherman Dr 78 Sherman Dr M.H.@ Sherman Dr/Sherman
Cir
Shoot with flow to wall & also to
Alvarado Dr

79 Natividad Rd. Rainer St. Marin St.
80 Nantucket Whittman De Cunha Ct.
81 Newport Dr. M.H @1642 Newport Shoot Both Ways
82 Imperial way M.H @ Sutter Manhole shoot to Napa way Page #11
\\wlg-fs01\projects\0886-0046 SSMP Update\06 - Reports and Calculations\Drafts\Appendix\hot spots monthlynew.doc.03/07/25.8:22 AM.tm Monthly:

No Street From To Lin Ft Ser
South Salinas Area:
1 Villa St M.H. @ villa & Kirkwood Shoot to Wilson
2 Villa St M.H. in front of Bus Station Shoot M.H. @ Villa & Kirkwood 3 Wilson St M.H. @ villa St Shoot to Catalina Ave
4 Riker St M.H. @ Central Ave Shoot to Park St
5 Anne St Alexander St Shoot to F.I. on Anne St
6 W. Market St Capitol St Shoot to Stone St & also shoot to Riker
Low Pressure Call 424-
1928 American Supply
Caroline or Perry
7 Capitol St M.H. @ Archer (2 M.H.) Shoot both M.H. to W. Market St 8 Station Pl M.H. @ W. Market St Shoot to Station building 9 W. Market St Stone St Shoot to Station Pl
10 Stone St Central Ave Shoot to W. Market St
11 Central St Capitol St Shoot to Stone St
12 Capitol St M.H. @ intersection Gabilan &
Capitol
Shoot to Archer
13 Capitol St M.H. @ W. Alisal St Shoot to W. Gabilan St 14 California Alley M.H. @ E. Alisal St Shoot both ways 15 Gonzales Alley M.H. @ E. Alisal St Shoot both ways
16 Greenfield Alley M.H. @ E. Alisal St Shoot both ways & shoot to front St & also with flow to Pajaro St

17 18 Harmony Ln M.H. @ E. Alisal St Shoot to E. San Luis St & also shoot to Monterey St

19 Melody Ln M.H. @ E. Alisal St Shoot both ways (need to open M.H. at Gabilan to keep smell & overflowing
in restaurant)

20 Howard St M.H. @ Lincoln St Shoot to F.I. on Howard to Salinas St 21 W. Alisal St M.H. @ Lincoln & W. Alisal St Shoot to San Luis St & shoot to Howard St & also shoot to Salinas St
Am List
22 Lacey Ln M.H. @ E. Gabilan St Shoot to Lacey Alley

Page #12
\\wlg-fs01\projects\0886-0046 SSMP Update\06 - Reports and Calculations\Drafts\Appendix\hot spots monthlynew.doc.03/07/25.8:22 AM.tm Monthly:

No Street From To Lin Ft Ser
23 E. Gabilan St M.H. @ intersection of
Gabilan/Monterey
Shoot to Lacey Ln
24 Lodge Alley M.H. @ Gabilan St Shoot to Market St
25 W. Alisal St Capitol St Shoot to Lorimer St
26 Central Ave San Gabriel Shoot to National St & also shoot to College Dr

27 San Gabriel Cir M.H. @ dead end on San
Gabriel
Shoot to Central & also shoot with
flow to W. Alisal St

28 W. Alisal St M.H.@ 623 W. Alisal St Shoot to San Gabriel 29 Riker St M.H. @ intersection Clay &
Riker
Shoot to Lang St & shoot to F.I. on
Clay St to Homestead ( low pressure)

30 Geil St M.H. @ 247 Geil St Shoot to Riker
31 Geil St M.H @ Iverson/Geil Shoot to Riker St
32 Iverson St M.H. @ 805 Iverson Shoot to Geil St
33 College Dr M.H. @ intersection Marion &
College
Shoot to Iverson
34 Lincoln Ave M.H. @ intersection Clay &
Lincoln
Shoot to F.I. on Lincoln to Avenue A
35 Lincoln Ave M.H. @ 500 Lincoln Ave Shoot under parking lot to S. Main St 36 Lincoln Ave M.H. @ intersection San Luis
St & Lincoln
Shoot to Clay St
37 South Main St. M.H @ John St. Shoot both Ways Am List 38 John St M.H. @ Monterey & John St Shoot to S. Main St Am List 39 John St M.H. @ intersection Pajaro &
John
Shoot to San Luis St & also shoot
Main St.

Am List
40 Pajaro St M.H. @ 427 Pajaro St Shoot to San Luis St (big line) Am List 41 Pajaro St San Luis St Shoot to John St
42 Abbott St M.H. @ intersection John St &
Abbott St
Shoot to Summer St (done A.M. due to
traffic)
Am List
43 John St M.H. @ intersection Front &
John St
Shoot to Abbott St Am List
44 Abbott St M.H. @ slow lane on Sanborn
@ Chevron Gas station side
Shoot all the way to537 Abbott St
(acme car wash)
Am List
45 Abbott Pl M.H. Bet. Fire Station #3 & gas Shoot to R.R. tracks Page #13
\\wlg-fs01\projects\0886-0046 SSMP Update\06 - Reports and Calculations\Drafts\Appendix\hot spots monthlynew.doc.03/07/25.8:22 AM.tm Monthly:

No Street From To Lin Ft Ser
Station
46 S. Main St M.H. @ intersection San
Joaquin & S. Main St
Shoot to Plaza Cir & also shoot to
Pajaro St

47 Woodside St Briarwood St Shoot to Baywood
48 Sierra Madre St M.H. @ Santa Monica & Sierra
Madre
Shoot under homes to Blanco Rd
49 Palma St M.H. @ W. Alisal St & Palma Shoot to Carmelita St 50 Carmelita St Palma St Shoot to F.I on Carmelita St
51 San Blanco Ct M.H. @ San Blanco Las Cruces
Wy
Shoot 3 directions one with flow under
houses

52 Kipling St M.H. @ Kipling & Shelley Wy Shoot to F.I. on Shelley Wy 53 S. Main St M.H. @ Stephanie/S. Main Shoot south to Hwy 68 Am List 54 Stephanie Dr M.H.@ 76 Stephanie Dr Shoot to S. Main St Am List

55 532 Capital Street From M.H on Clay Street to F.I on Capital 56 W. Alisal Street Homestead Ave. Lorimer Street Am List 57 Monterey St. M.H @ East Alisal Shoot to Pajaro and East Gabilan Am List 58 W. Market St. Uni Kool Buis.

Park
M.H in back of property Villa St.
59 W. Market St. Mission Linen M.H in back of property Shoot towards Villa St. 60 Clark st. M.H in school bus proprty Shoot towards Villa St.

Page #14
\\wlg-fs01\projects\0886-0046 SSMP Update\06 - Reports and Calculations\Drafts\Appendix\hot spots monthlynew.doc.03/07/25.8:22 AM.tm Monthly:

No Street From To Lin Ft Ser

AM Manholes
1 2 S. Main St M.H. @ intersection John & S.

Main
Shoot both ways
3 John St M.H. @ Monterey & John St Shoot to S. Main St 4 John St M.H. @ intersection Pajaro &
John
Shoot to San Luis St & also shoot
Main St.

5 W. Alisal St M.H. @ Lincoln & W. Alisal St Shoot to San Luis St & shoot to Howard St & also shoot to Salinas St

6 Pajaro St San Luis St Shoot to John St
7 W. Alisal St M.H. @ intersection
Homestead & Alisal st
Shoot to Lorimer St
8 Abbott St M.H. @ intersection John St &
Abbott St
Shoot to Summer St (done A.M. due to
traffic)

9 Abbott St M.H. @ slow lane on Sanborn
@ Chevron Gas station side
Shoot all the way to537 Abbott St
(acme car wash)

10 Tervin St M.H. @ intersection Tervin &
Sanborn Pl
Shoot to Vertin St
11 S. Main St M.H. @ Stephanie/S. Main Shoot south to Hwy 68 12 Stephanie Dr M.H.@ 76 Stephanie Dr Shoot to S. Main St 13 E. Market St M.H. @ Sanborn & Market Shoot to both ways & shoot Market St to Cedar st

14 E. Alisal St M.H. @ Sanborn & Alisal Shoot to Towt St 15 Sanborn Rd M.H. @ intersection Laurel &
Sanborn
Shoot both ways
16 Sewer Hot Spot List
Revised 12/10/2024

Quarterly

No Street From To Lin Ft Ser

East Salinas Area: Serviced Every ---Feb. – May – Aug. – Nov. 1 Kern St. E. Alisal and Griffen St. F.I. on Kern St. 500 2 S. Madiera St. James St. M.H. near apts on John St. 300 3 Mayfair St. Sanborn Rd. 800 ft. on Mayfair 900
4 Meadow Dr. Island on Sanborn Rd. Meadow and Magnolia Dr. 600 5 Hwy 101 on ramp at 101 and
SanbornRd.
101 on Ramp at Sanborn Rd. Fairview Dr. heading East under Freeway
800
6 Airport Blvd. M.H. on Airport Blvd. Across
Smuckers
M.H. near Hanson St. and Airport
Blvd.
900
7 Kimmel St. N. Sanborn Rd. F.I. on Kimmel St. 1150
8 Sunrise St. Garner Ave. F.I. on Sunrise St. 1070
9 Towt St. Del Monte Ave. F.I. at end of Towt 900
10 Wiren St. Williams Rd. F.I. end of Wiren St. 1000
11 Pacific St. Del Monte Ave. F.I. on Pacific St. 800
12 Acosta Plaza Apts. M.H. near tree M.H. in upper parking lot 800 13 New Deal St. Del Monte Ave. Cortez St. 800
14 Valencia St. Kentucky Ave. F.I. on Valencia St. 500
15 Garner Ave. Towt St. F.I. near Williams Rd. 1500
16 Pacific St. Seiber St. Del Monte Ave. 900
17 Pacific Del Monte F.I. on Pacific 800
18 Sewer Hot Spot List
Revised 12/10/2024

Quarterly

No Street From To Lin Ft Ser
North Salinas Area: Serviced Every – Feb. – May – Aug. – Nov.

1 Calveras Dr. Klamath Dr. Yreka Dr. 900
2 Dororo Dr. Tapadero Dr. Reata Dr. 1100
3 Kammen Park Laurel Dr. In Park Area Rochex Dr. 620
4 N. Main St. Navajo St. M.H. just beyond Bernal Dr. head South
6600
5 Deer St. N. Main St. F.I. On Deer St. 320
6 M.H. at Bernal Dr. and N.Main
St.

M.H. at Bernal Dr. and N. Main
St.

M. H. at Santa Clara St. 500
7 Columbine St. M.H. at Columbine St. and
Heather Dr.

M.H. at basketball Court near fence off
of Parkside Dr. in rear of Apts.
580
8 E. Laurel Dr. M.H. at N. Main St. and E.

Laurel Dr. head East
800 East of Noice St. On East Laurel
Dr.
800
9 E. Laurel Dr. N. Main St. on Eastside of N.

Main St.

M.H. in Old Lucky’s Parking Lot near
fence at Rodeo Grounds
350
10 Lucky Parking Lot near fence at
Rodeo Grounds
Lucky Parking Lot near fence
at Rodeo Grounds
Identify Locations when servicing
M.H. to M.H. out to Bernal
????????????
11 Muni – Ball Park Stadium 500
12 Carpenter’s Hall Rec Ditch Bunkers at Carpenter’s Hall Ditch – Northside
Bunkers just South of Main Rec Ditch
1665
300
13 33 San Juan Rd. Manhole bet. N.Main and
Boronda
400
14 Boronda Rd. MH-E4-003 MH-E4-002 281.57
West Salinas Area: Serviced Every – Feb. – May – Aug. – Nov.

1 Harmony Alley W. Alisal St. E. San Luis St. 800
2 Capitol St. W. Alisal St. Gabilan St. 800
Sewer Hot Spot List
Revised 12/10/2024

Quarterly

No Street From To Lin Ft Ser
3 Riker Terrace St. W. Alisal St. and Riker Terrace F.I. on Riker Terrace 1000 4 W. Alisal St. Lorimer St. 800’ To Capitol St. 1000
5 Lincolin St. Clay St. M.H. South of Liquor Store 600
6 Monterey St. E. Alisal St. Gabilan St. 700
7 Lacey Lane Gabilan St.. Market St. 600
8 Gabilan St. Monterey St. Lacey Lane 200
9 Lodge Alley Gabilan St. Market St. 700
10 150 Sherwood Dr. Service line from Rossi at
California St. heading North
through empty lot next to PGE
If you can’t get through line from
Rossi and California than go to F.I.
500

South Salinas Area: Serviced Every – Feb. – May – Aug.- Nov.

1 Sierra Madre Dr. Santa Monica Dr. Service with flow to Blanco St. 200 2 San Juaquin St. S. Main St. F.I. on San Juaquin St. 700 3 S. Main St. F.I. near Winham St. M.H. at John St. and Pajaro St. 800 4 S. Main St. SanJuaquin St. F.I. on S. Main St. 500
5 John St. Pajaro St. S. Main St. 800
6 Pajaro St. San Luis John St. 800

Sewer System Management Plan – Revision 02
Appendix 8

City of Salinas
May 2025

Appendix 8 Cover Sheet - CIP
8A – Lift Station Ranking Matrix
8B – CIP Ranking Matrix
8C1 – Existing CIP
8C2 – Existing Lift Station CIP
8C3 – Future CIP
8D – Capital Projects Schedule
TABLE 7-3

CITY OF SALINAS SSMPU

EXISTING LIFT STATION CIP RANKING MATRIX
Importance Factor 5 4 3 3 2 2 2 1
Overflow to Water
Body of the State Inspection Frequency
Existing Pumping
Capacity Deficiencies
Peak Hour Emergency Response
Time Bypass Required?
Onsite Generator with Automatic
Transfer Switch Required?
Critical Control/Electronic
Upgrades Required? Community Impact
Impacted By Future
Development
Yes - 10
No - 0
Emergency Callouts-10
Daily Inspections-5
Weekly Inspections-0
Yes-10
No-0
0-15 minutes-10
15-30 minutes-5
Greater than 30 minutes-0
Yes-5
No-0
Yes-5
Replace Generator-3
No-0
Yes-5
No-0
< 5,000 - 0
5,001 to 10,000 - 5
>10,000 - 10 Yes/No
Lake St Lift Station 10 10 10 10 0 3 5 10
Yes, Target Area V, East
Alisal Street/East Market
Street, Central Area and
East Area Specific Plans,
and East Area FGA
Pumps must be upsized
for future flows.
176 1
Santa Rita Lift Station 10 10 0 10 5 3 5 5
Bolsa Knolls Septic
Conversion & Target Area
K 151 2
Carpenter Hall Lift Station 10 5 0 10 5 3 0 10
Yes, North Boronda FGA
and Targe Areas K & V 126 3
De La Torre Lift Station 10 10 0 0 5 5 5 0
Possible, Southeast FGA
Pumps may need to be
upsized for future flows 120 4
Spicer Lift Station 10 10 0 0 5 5 5 0 No 120 5
Mill Lake Lift Station 10 5 0 10 5 0 5 0 No 120 6
Vista Nueva Lift Station 10 10 0 0 0 0 0 0 No 90 7
Las Casitas Lift Station 10 0 0 10 0 0 5 0 No 90 8
TP2 Lift Station 10 0 0 0 5 3 0 10
Yes, East Alisal
Street/East Market Street
and East FGA.

Pumps must be upsized
for future flows. 76 9
Harkins Lift Station 0 10 0 0 5 5 5 0
Yes, Salinas Ag-
Industrial Center
Pumps must be upsized
for future flows 70 10
Airport Lift Station 10 0 0 0 0 0 0 0 Yes, Southeast FGA 50 11 Project Name
Score =
Importance
Factor X Points Ranking
7-7
TABLE 7-2

CITY OF SALINAS SSMPU

EXISTING HYDRAULIC AND MAINTENANCE REPAIR CIP RANKING MATRIX Importance Factor 5 4 3 2 1
Overflow to Water
Body of the State Design Standard Maintenance Hot Spo t Community Impact Near City Manhole Monitor Impacted By Future Development Yes - 10
No - 0
Meets Design Standard - 0
Doesn't Meet Design Standards - 2
Surcharging - 5
Overflowing - 10
Not Critical - 0
Yearly Check - 5
Weekly or Monthly Checks - 10
< 5,000 - 0
5,001 to 10,000 - 5
>10,000 - 10
Yes-5
No-0 Yes/No
Cesar Chavez Park
(includes North Madeira Avenue Repairs) Hydraulic Deficiency 10 5 5 10 0 Yes, East Alisal Redevelopment 105 1 Upper Carr Lake Repairs O&M 10 0 10 10 0 Yes, North Boronda FGA 100 2 Upstream TP2 Diversion Hydraulic Deficiency 10 5 0 10 0 No 90 3 Northridge Mall Hydraulic Deficiency 10 5 0 10 0 Yes, Target area K 90 4 East Market and Upstream of Lake Street Repairs O&M 1 0 0 5 5 0 No 75 5 Louis & Van Buren Repairs O&M 10 0 5 0 5 No 70 6
West Market at Davis Overcrossing O&M 10 0 5 0 0 Yes, West Boronda FGA 65 7 Cherokee Dr Hydraulic Deficiency 0 5 0 10 5 Yes, Target Area K 45 8 Malarin St and Wilgart Way Repairs O&M 0 5 5 5 0 No 45 9 Romie Lane Repairs & Reconfiguration Analysis O&M 0 0 10 5 0 No 40 10 King Street Repairs O&M 0 0 10 0 5 No 35 11
Del Monte and Mae Repairs O&M 0 0 10 0 5 No 35 12
Riker Street Repair O&M 0 0 10 0 5 No 35 13
West Market Street Repairs O&M 0 0 10 0 5 No 35 14
Johnson Place Repairs O&M 0 5 5 0 0 No 35 15
N Main St Hwy 101 Underpass Bunker Repair O&M 0 0 10 0 0 Yes, Target area V 30 16 Donner Way Repair O&M 0 0 10 0 0 No 30 17
San Miguel Ave Repair O&M 0 0 10 0 0 No 30 18
Noice Drive/Tyler Street Hydraulic Deficiency 0 5 0 5 0 No 30 19 Natividad Rd or Alternative Natividad Consolidation Hydraulic Deficiency 0 5 0 5 0 Yes, Target area V, north boronda FGA 30 20 Acacia, Bautista, Woodside Repairs O&M 0 0 5 0 5 No 20 21 Comanche, Polk, and North First Repairs O&M 0 0 5 0 5 Yes, Target area K 20 22 Sherwood Dr Repairs O&M 0 0 5 0 5 Yes, Target area V 20 23 East Laurel and Williams Repairs O&M 0 0 5 0 0 No 15 24 Hoover Street Repair O&M 0 0 5 0 0 No 15 25
Project Name
Score =
Importance
Factor X Points Ranking Type of Project
7-5
TABLE 7-2

CITY OF SALINAS SSMPU

EXISTING HYDRAULIC AND MAINTENANCE REPAIR CIP RANKING MATRIX Importance Factor 5 4 3 2 1
Overflow to Water
Body of the State Design Standard Maintenance Hot Spo t Community Impact Near City Manhole Monitor Impacted By Future Development Yes - 10
No - 0
Meets Design Standard - 0
Doesn't Meet Design Standards - 2
Surcharging - 5
Overflowing - 10
Not Critical - 0
Yearly Check - 5
Weekly or Monthly Checks - 10
< 5,000 - 0
5,001 to 10,000 - 5
>10,000 - 10
Yes-5
No-0 Yes/NoProject Name
Score =
Importance
Factor X Points RankingType of Project
Katherine Ave & Pajaro St Repairs O&M 0 0 5 0 0 No 15 26 Wood Street Reconfiguration Analysis O&M 0 0 5 0 0 No 15 27 Inflow/Infiltration Evaluation Hydraulic
-- -- -- -- -- -- --
Dependent on
significant wet
weather year
CCTV Inspection Program O&M -- -- -- -- -- -- -- Annual Program Brick Manhole Inspection & Replacement O&M -- -- -- -- -- -- -- Ongoing Inspection Flushing Inlet (Cleanout) Inspection & Replacement O &M -- -- -- -- -- -- -- Ongoing Inspection 7-6
TABLE 7-4.

CITY OF SALINAS EXISTING CAPITAL IMPROVEMENT PROGRAM (CIP) Project # Title Description Tributary
Area
Length
(Ft)
Old
Diameter
(in)
New
Diameter
(in)
Street Location Upstream Manhole
Number
Downstream Manhole
Number
Construction Cost
($)
Soft
Cost
($)*
Total Project Cost
($)**
Lake St 2,100 15 18 Acosta Plz Garner Ave to E Laurel
Dr J7-007 K7-017
Lake St 3,000 21 24 Open Space/Park E Laurel Dr to near Circle Dr K7-017 L6-001
Lake St 3,500 24 27 Open Space/Park Circle Dr to Longbow Way L6-001 K5-007
New sewer main Lake St 70 -- 24 Open Space/Park Near York shire Way K5-007 K5-014

1.1 Mark Thomas 2017 Findings
Minor defects, needs new frame and cover, lining
interior of manhole (Garde:10) (K5-001); Visible
agregate and broken frame, needs new frame & cover,
lining interior of manhole (Grade: 3) (K5-003); Pipe
(Grade:4),WLS of 0.6, encrustations
Lake St 380 24 24 N Madeira Ave
N Madeira north of
Cesar Chavez park
between St Helen Way
and Terrace St
K5-001 K5-003 $438,000 $175,200 $613,200
Mark Thomas 2017 Findings
New MH frame and cover, install marker (Grade:5)
(MH I6-004); expose and raise MH- curently buried
(Grade:10) (I6-006); New MH frame and cover, install
marker (Grade:10) (I6-005); (I6-004 to I6-006) Pipe
WLS =0.35, root ball, (Grade: 3); (I6-006 to I6-005 )
(Grade:2)
Lake St 410 21 21 Laurel Dr. Bike Trail Near
Veteran's Way I6-004 I6-005 $396,500 $158,600 $555,100
Mark Thomas 2017 Findings
New MH frame & cover w/ PCC collar, line in 5 yrs
(Grade:3) (J6-001); New frame & cover w/ PCC collar,
line in 5 yrs (Grade:3) (J6-002);Pipe d/D: 0.75, grease deposits (Grade: 10)
Lake St 300 27 27 Trail around Upper
Carr Lake
Off of E Laurel Dr near
Veteran's Way J6-001 J6-002 $406,000 $162,400 $568,400
$802,500 $321,000 $1,123,500
3 Upstream TP2 Diversion Weir Construction TP2 -- -- -- East Alisal St South Sanbo rn Rd M6-012 -- $45,000 $18,000 $63,000 Upsize sewer main -- 2,300 15 18 North Main St
From East Boronda
Road to San Juan
Grade Road
E4-007 F4-011
Sewer Main Connection/Realignment -- 320 -- 18 North Mai n St From Big 5 Sporting Goods to Harden Pkwy F4-007 F4-031
Northridge Mall 4
Upper Carr Lake Repairs
$1,916,000
Upsize sewer main Cesar Chavez Park
$766,400 $2,682,400
2 $3,347,600 $11,716,600 $8,369,000 1
CCTV evaulation noted pipe encrustations and manholes need new frames, covers, and lining in a portion of the Cesar Chavez Park CIP. These repairs are noted below and should be replaced if Cesar Chavez Park CIP is not constructed in the near term.

Total Repair Project Costs
7-8
TABLE 7-4.

CITY OF SALINAS EXISTING CAPITAL IMPROVEMENT PROGRAM (CIP) Project # Title Description Tributary
Area
Length
(Ft)
Old
Diameter
(in)
New
Diameter
(in)
Street Location Upstream Manhole
Number
Downstream Manhole
Number
Construction Cost
($)
Soft
Cost
($)*
Total Project Cost
($)**
Mark Thomas 2017 Findings
Expose and raise MH to grade, buried (Grade:10) (K5-
008)
Lake St -- -- -- Yorshire Way
Yorkshire Way, between
Longbow Way and
Doncaster Pl
K5-008 -- $5,900 $2,360 $8,260
Mark Thomas 2017 Findings
Expose and raise MH to grade, buried (Grade:10) (K5-
010); Pipe broken, encrustations (Grade:5)
Lake St 150 24 24 Longbow Way Long bow Way and Kern
St K5-009 K5-010 $169,400 $67,760 $237,160
Mark Thomas 2017 Findings
Replace frame & cover w PCC collar, reline, Corroded
frame & chimney (Grade: 10) (K5-012); Replace
Frame & cover w PCC collar, install marker, corrosion,
grease and surcharge (Grade:10) (K5-021); Pipe
cracks, grease deposits, (Grade:3); Replace frame &
cover w PCC collar, install marker, corroded frame and
aggregate (Grade:3) (K5-019); Replace frame & cover,
install ecc. Cone for fence, corroded frame & heavy
grease & surch. (Grade:10) (K5-020); Pipe WLS:

0.25,d/D:0.9, grease deposits (Grade:2)
Lake St 840 24 & 30 24 & 30 East of Sun St Between Sun St and HWY 101 K5-012, K5-019 K5-020, K5-021 $1,125,100 $450,040 $1,57 5,140 Mark Thomas 2017 Findings
New frame & cover, lining interior of manhole
(Grade:10) (L4-002 and L4-004)
Lake St -- -- -- E Market St E Market St, between
Sun St and Peach Dr L4-002 L4-004 $23,800 $9,520 $33,320 $1,324,200 $529,680 $1,853,880
Pipe sags, surcharging manholes Santa Rita 260 8 8 Louis e St Louise St, between Lenny St and Louise Ct D5-001 D4-003 $149,000 $59,600 $208,600 Pipe sags, surcharging manholes Santa Rita 70 8 8 Van Bu ren Ave near East Bolivar St D4-007 D4-055 $63,500 $25,4 00 $88,900 $212,500 $85,000 $297,500
7 West Market at Davis
Overcrossing Bunker doors on Large Trunk line need replacement - - -- -- -- West Market St N Davis Road Overcrossing J2-045 K2-038 $13,350 $5,340 $18,690
8 Cherokee Drive Upsize sewer main -- 1,600 18 24 Cherokee Dr From Seminole Way to Tulane Street G3-008 H3-009 $1,920,000 $768,000 $2,688,000 Pipe issue joints, roots -- 380 8 8 Wilgart Way Wilgart Way, E Romie Ln to FI O4-050 O4-011 $171,000 $68,400 $239,400
Mark Thomas 2017 Findings
Heavy corrosion, reline manhole (Grade:4) -- -- -- -- Near Railroad Between Work St and
Brunken Ave, near
railroad
N5-003 -- $9,300 $3,720 $13,020
Mark Thomas 2017 Findings
Grease deposits and surcharging, recommend PCC
collar to prevent I/I, new bench and rechannelize
(Grade:10)
-- -- -- -- Los Palos Dr
Near intersection of Los
Palos Dr and Fairmont
Dr
O5-019 -- $6,300 $2,520 $8,820
$186,600 $74,640 $261,240
10 Romie Lane Repairs &
Reconfiguration Analysis
Hydrogen Sulfide damage, MH rings and lids need
replacement. Concrete in roadway. Recommended
reconfiguration analysis before repairs.
4,030 18 18 Romie Lane Near Los Palos Drive to
South Main Street O4-007 N3-002 -- $100,000 $100,000
11 King Street Repairs Major pipe sags TP2 1,170 8 10 King St King St, E Market to E Alisal L5-033 L5-039 $585,000 $234,000 $819,000
Trough pipe missing in MH Lake St -- -- -- C Street On C St, Galindo St to Mae Ave -- K8-012 $16,000 $6,400 $22,400
Pipe sags, needs replacement Lake St 820 8 8 Del Monte A ve Del Monte Ave, Mae Ave to Green St K8-011 J8-020 $369,000 $147,600 $516,600 Total Louise and Van Buren St Repair Project Costs
5 9
The Louis and Van Buren maintenance repairs are alo ng the future San Juan Grade CIP. These segments should be replaced if the future San Juan Grade CIP is not constructed in the near term. 12 Del Monte and Mae Repairs
Total Repair Project Costs
East Market and Upstream
of Lake Street Repairs
Total Repair Project Costs
Louise and Van Buren
Street Repair6
Malarin St and Wilgart Way
Repairs
7-9
TABLE 7-4.

CITY OF SALINAS EXISTING CAPITAL IMPROVEMENT PROGRAM (CIP) Project # Title Description Tributary
Area
Length
(Ft)
Old
Diameter
(in)
New
Diameter
(in)
Street Location Upstream Manhole
Number
Downstream Manhole
Number
Construction Cost
($)
Soft
Cost
($)*
Total Project Cost
($)**
Pipe sags, broken pipe, trough and pipe are gone Lak e St 830 6 6 Mae Ave Mae Ave, D St to Del Monte J8-008 K8-013 $332,000 $132,800 $464,800
$717,000 $286,800 $1,003,800
13 Riker Street Repair Pipe has damage and missing sections at manhole -- 20 6 6 Riker Street Lang Street -- M3-035 $8,000 $3,200 $11,200 Pipe has major sags, consider re-alignment of secti on.

Concrete in roadway. -- 450 8 8 Villa Street At Villa St and Kirkwood Ave L2-016 K3-016 $231,750 $92,700 $324,450
Both F.I.'s are blown out -- -- -- -- West Market St Near El Cerrito Market L3-043 L3-010 $32,000 $12,800 $44,800 Pipe sags. Concrete in roadway. -- 840 6 6 Capitol St Capitol St, W Market St to Archer St L3-013 L3-040 $336,000 $134,400 $470,400
Pipe sags. Concrete in roadway. Replace F.I. with new
manhole. -- 710 6 6 Capitol St Capitol St, Archer St to F.I. L3-041 F.I $346,150 $138,460 $484,610
$945,900 $378,360 $1,324,260
15 Johnson Place Repairs Pipe damage, sags, spidering under tracks, ongoing backups, MH O5-005 has settled, always surcharging -- 1,470 12 12 Johnson Pl Johnson Pl Abbott Pl to railroad tracks N5-011 O5-005 $839,200 $335,680 $1,174,880 16 N Main St Hwy 101
Underpass Bunker Repair
Bunker damage to pipe, pipe missing at bunker on
both sides, clogging -- 50 10 10 N Main St N Main St at Hwy 101 J4-012 J4-013 $2 5,000 $10,000 $35,000 17 Donner Way Pipe damages, sags, etc. Carpenter Hall 280 8 8 Donner W ay Truckee Way to Emerald Dr G6-037 G6-060 $126,000 $50,400 $176,400
18 San Miguel Ave Repair Pipe Damage; broken pipe 10-feet from manhole -- 10 8 8 Pajaro St Pajaro St and San Miguel 04-025 O3-038 $4,500 $1,800 $6,300
Upsize sewer main -- 2,100 8 12 Noice Dr From Chaparral Street to East Laurel Drive G4-015 H4-011
Reconstruct manhole -- -- -- -- E Laurel Dr East Laurel Drive near N Main Street H4-012 --
New sewer main -- 60 -- 12 E Laurel Dr East Laurel Drive to North Main Street H4-006 H4-001
Upsize sewer main -- 3,300 12 15 Tyler Street West Laurel Drive down to HWY 101 H3-023 I3-001
Upsize sewer main Carpenter Hall 2,700 12 15 Natividad R d From near Sausal Drive to East Alvin Drive G6-002 H6-003
Weir Construction Carpenter Hall -- -- -- Natividad Rd Ea st Alvin Drive H6-003 -- Carpenter Hall 3,600 15 18 Natividad Rd East Alvin Drive to near East Laurel Drive H6-003 I5-007
Carpenter Hall 305 12 15 Off of Sherwood Dr
From Sherwood Drive
toward East Bernal
Drive
J5-003 J5-005
Carpenter Hall 2,000 15 18 Parallel to E Bernal
Dr and N Main St
From near Sherwood Dr
to Santa Clara Ave J5-005 J4-010
-- 2,400 15 21 Natividad Rd East Alvin Drive to
Pacheco St H6-003 I5-011
-- 5,000 15 24 Natividad Rd to Sherwood Park on
East Bernal Drive I5-011 J4-022
-- 1,100 21 30 Easement Portion along Alpine Dr J4-022 J4- 011 -- 620 21 30 J4-011 K4-002
Total Repair Project Costs
14 $3,400,000 $4,760,000
West Market Street Repairs
Under Highway 101
$9,120,000Alternative Natividad
Consolidation Upsize sewer main
Upsize sewer main
$6,090,000 $2,436,000 $8,526,000
20 $1,360,000Noice Drive/Tyler Street19
$3,648,000 $12,768,000
Natividad Rd
Total Repair Project Costs
7-10
TABLE 7-4.

CITY OF SALINAS EXISTING CAPITAL IMPROVEMENT PROGRAM (CIP) Project # Title Description Tributary
Area
Length
(Ft)
Old
Diameter
(in)
New
Diameter
(in)
Street Location Upstream Manhole
Number
Downstream Manhole
Number
Construction Cost
($)
Soft
Cost
($)*
Total Project Cost
($)**
Pipe Sags, replace F.I. with new manhole -- 130 8 8 Acac ia Circle North W Acacia St F.I. N3-039 $74,500 $29,800 $104,300 Pipe Sags -- 280 8 8 Woodside Dr Woodside Dr, Teakwood
Pl to Riker St O3-016 O3-015 $126,000 $50,400 $176,400
Pipe Sags -- 490 8 8 Bautista Dr Bautista Dr, W Romie
Ln to Orange Dr N3-014 N3-060 $220,500 $88,200 $308,700 Pipe issue joints, roots, offsets, replace F.I. with new manhole -- 230 8 8 Bautista Dr Bautista Dr, F.I to W
Acacia F.I N3-029 $119,500 $47,800 $167,300
$540,500 $216,200 $756,700
Pipe issue, joints, replace F.I. with new manhole -- 690 6 6 Comanche Way Shawnee Way to Cherokee Dr F.I. G3-010 $292,000 $116,800 $408,800
Pipe issue joints, roots, replace F.I. with new manhole -- 490 8 8 Polk St Polk St, Monroe St to W Laurel Dr F.I. I3-045 $236,500 $94,600 $331,100
Pipe sags -- 640 8 8 N 1st St N 1st St, Boeing Ave, W
Curtis St H4-061 H4-054 $288,000 $115,200 $403,200
$816,500 $326,600 $1,143,100
23 Sherwood Dr Repairs Pipe cracks at 220-ft mark downstream from K4-052.

Obstruction (possibly old water line) in K4-076 Lake St 840 12 12 Sherwood Dr Near Sioux Dr to E Rossi St K4-052 K4-076 $486,400 $194,560 $680,960
Pipe sags, broken pipe -- 450 10 10 Easement E Laurel Dr at 105 Oregon St K7-011 K7-014 $225,000 $90,000 $315,000
Pipe sags -- 1,080 8 8 Williams Rd Williams Rd, E Market St to Quilla St L7-009 M7-006 $486,000 $194,400 $680,400 $711,000 $284,400 $995,400
25 Hoover Street Repair F.I. repair blown out Santa Rita -- -- -- Hoover Street 1 885 Hoover Street -- -- $16,000 $6,400 $22,400 Mark Thomas 2017 Findings
Exposed aggregate & heavy corrosion,fiberglass
peeling, weld cover, recommend reline manhole, new
bench, and rechannelize (Grade:10) (O4-001);
Welded/broken cover, recommend new frame & cover
(Grade:10), (O4-002); Pipe d/D 0.85 (Grade: 1)
-- -- -- -- Katherine Ave Katherine Ave and
Alameda Ave O4-001 O4-002 $16,800 $6,720 $23,520
Mark Thomas 2017 Findings
Corrosion, broken cover, rechannel, needs new
manhole (Grade:10)
-- -- -- -- Pajaro St Pajaro St near Katherine
Ave O4-006 NA $14,600 $5,840 $20,440
$31,400 $12,560 $43,960
27 Wood Street
Reconfiguration Analysis
Pipe sags, always plugs, can't CCTV
Entire area needs reconfiguration Lake St 1,820 -- -- Easement Between Wood and Roosevelt Street L5-029 L5-034 -- $50,000 $50,000
-- CCTV Program CCTV inspection of 20% (approximately 58 miles) of the collection system each year All -- -- -- -- -- -- -- -- $9,392,000 $9,392,000 -- Inflow/Infiltration
Evaluation
Conduct full I/I evaluation of the entire collection
system (during significant wet weather year) and
update the sewer model
All -- -- -- -- -- -- -- -- $140,000 $140,000
Coat: $432,000 Coat: $172,800 Coat: $604,800
New Manhole: $1,728,000 New Manhole: $691,200 New Manhole: $2,419,200 Inspection Port: $4,910,500 Inspection Port: $1,964, 200 Inspection Port: $6,874,700 New Manhole: $22,448,000 New Manhole: $8,979,200 New Manhole: $31,427,200 $59-$90 millionEXISTING SEWER PROJECT CIP TOTAL COSTS
Total Repair Project Costs
Total Repair Project Costs
-- --
-- --
--
Brick Manhole Inspection &
Coat/New Manhole
Replacement
Inspect and replace brick manholes
(108 based on field survey and City input) All -- -- -- -- -- --
Flushing Inlet (Cleanout)
Inspection & Port/New
Manhole Replacement
Inspect and replace flushing inlets/cleanouts
(1,403 based on City GIS) All -- --
Acacia, Bautista, Woodside
Repairs21
-- -- --
*Soft costs include a 40% escalation of the construction costs for planning, engineering, CM, legal/admin. **All CIP costs are expressed in May 2022 dollars, using McGraw-Hill ENR Construction Cost Index of 13004, and will need to be escalated to the year or years scheduled for the work.

East Laurel and Williams
Repairs24
Total Repair Project Costs
Total Repair Project Costs
26 Katherine Ave & Pajaro St
Repairs
22 Comanche, Polk, and North
First Repairs
7-11
TABLE 7-5.

CITY OF SALINAS EXISTING LIFT STATIONS CAPITAL IMPROVEMENT PROGRAM (CIP) Project # Title Description Tributary
Area (Acres)
PHDW
Flow
(gpm)
Firm
Capacity Street Location Upstream Manhole
Number
Downstream Manhole
Number
Construction
Cost
($)
Soft
Cost
($)*
Total Project
Cost
($)**
1 Lake Street Lift Station Full lift station replacement/relocation, see cutsheet for summary 4,108 6,375 -13% 146 East Rossi
Street
Intersection of E Lake St
and E Rossi St across
from Monterey County
Housing Alliance
K4-022 K4-019 9,500,000 3,800,000 13,300,000
2 Santa Rita Lift Station Full lift station replacement, see cutsheet for summary 348 670 112% 2021 Sucre Court Behind the parking lot of Salinas Valley Motel D4-019 -- 3,500,000 1,400,000 4,900,000 3 Spicer Lift Station Full lift station replacement, see cutsheet for summary 79 99 107% 59 Spicer St On Spicer street near A & S Metals N5-009 N5-007 2,200,000 880,000 3,080,000
4 Mill Lake Lift Station Full lift station replacement, see cutsheet for summary 43 132 287% 81 Gardenia Dr Off of Heather Circle J4-020 I3-001 2,750,000 1,100,000 3,850,000 5 Carpenter Hall Lift
Station
Lift station rehabilitation, see cutsheet for
summary 508 1,226 31% 516 North Main St Behind the Coast Auto Insurance parking lot J4-011 K4-002 1,050,000 420,000 1,470,000 6 De La Torre Lift
Station
Full lift station replacement, see cutsheet for
summary 10 7 4845% 1200 De La Torre
St
Across De La Torre St
from Inns of California
Salinas
O7-001 N7-009 1,200,000 480,000 1,680,000
7 Vista Nueva Lift
Station
Full lift station replacement, see cutsheet for
summary 6 41 408% 704 Garner Ave Off Garner Ave near
Natividad Creek J7-034 J7-014 2,200,000 880,000 3,080,000 8 Harkins Road Lift
Station
Full lift station replacement, see cutsheet for
summary 146 135 175% 1200 Harkins Rd
Intersection of Dayton St
and Harkins Rd Q6-001 Q6-009 1,300,000 520,000 1,820,000 9 Las Casitas Lift
Station
Lift station rehabilitation, see cutsheet for
summary 38 137 189% 721 Las Casitas Dr
Near intersection of
Ranchero Dr and Las
Casitas Dr
I7-001 -- 650,000 260,000 910,000
10 TP2 Lift Station Full lift station replacement, see cutsheet for summary 136 279 99% 650 Elvee Dr
Across Alisal Creek from
Fleet Service Center N5-006 N5-022 2,500,000 1,000,000 3,500,000 11 Airport Lift Station Lift station rehabilitation, see cutsheet for summary 584 60 960% 730 La Guardia St
South west corner of the
Ramco Enterprise LP
parking lot
O8-004 O8-005 800,000 320,000 1,120,000
38,710,000 EXISTING LIFT STATION CIP TOTAL PROJECT COSTS *Soft costs include a 40% escalation of the construction costs for planning, engineering, CM, legal/admin. **All CIP costs are expressed in May 2022 dollars, using McGraw-Hill ENR Construction Cost Index of 13004, and will need to be escalated to the year or years scheduled for the work. 7-12
TABLE 7-6.

CITY OF SALINAS FUTURE CAPITAL IMPROVEMENT PROGRAM (CIP) Title Description Tributary
Area
Length
(Ft)
Old
Diameter
(in)
New
Diameter
(in)
Street Location Upstream Manhole
Number
Downstream Manhole
Number
Construction
Cost
($)
Soft
Cost
($)*
Total Project
Cost
($)**
San Juan Grade Upsize sewer main Santa Rita 3,800 8 and 10 12 San Juan Grade Road From Russell Rd to Van Buren Ave C5-008 D4-055 $2,370,000 $948,000 $3,318,000
-- 240 18 24 Tulane Street Between Cherokee Dr
and US HWY 101 H3-009 H3-013
-- 1,700 24 30 N Davis Rd HWY 101 to Calle del
Adobe H3-013 H2-002
-- 3,400 30 32 Parallel to N Davis Rd
Calle del Adobe to
intersect with N Davis
Rd near Rossi Rico
Parkway
H2-002 J2-047
West Laurel Drive Upsize sewer main -- 1,550 12 15 W Laurel Dr From N Main St to near Laurel Park H4-001 H3-023 $1,020,000 $408,000 $1,428,000 Victor Street Upsize sewer main -- 1,600 15 18 Victor St From Ashby Way to W Rossi St J3-012 J2-007 $1,250,000 $500,000 $1,750,000
Lake St 2,025 10 15 Freedom Parkway From Estrella Way to N Sanborn Rd J9-005 J9-001
Lake St 2,725 12 18 Freedom Parkway From N Sanborn Rd to Nogal Dr J9-001 I8-013
Lake St 230 18 21 Natividad Creek Park
Crossing Freedom
Parkway to Natividad
Creek Park
H8-002 H8-004
Carpenter Hall 3,800 24 27 Natividad Creek Park
Natividad Creek Park to
Twin Creeks Golf
Course
H8-004 I7-005
-- 5,400 15 18 E Alisal St From Bardin Rd to
Williams Rd M8-010 M7-009
Part in TP2 2,200 18 21 E Alisal St From Williams Rd to S Sanborn Rd M7-009 M6-012
-- 1,300 12 15 Abbott St From Harris Rd Q7-001 Q7-004
-- 850 12 15 Abbott St To Harkins Rd P6-015 P6-006
-- 700 15 18 Harkins Rd From Abbot St toward
Schilling Pl P6-006 after P6-003
(no City ID)
$1,836,000
$768,000
$2,312,000Upsize sewer mainEast Alisal Street
North Davis Road
Freedom Parkway Upsize sewer main
Upsize sewer main $8,430,000 $11,802,000$3,372,000
$1,312,000$3,280,000 $4,592,000
$2,688,000
$6,426,000Upsize sewer mainNatividad Creek Park $4,590,000 $5,780,000
Abbott Street Upsize sewer main $1,920,000
$8,092,000
7-13
TABLE 7-6.

CITY OF SALINAS FUTURE CAPITAL IMPROVEMENT PROGRAM (CIP) Title Description Tributary
Area
Length
(Ft)
Old
Diameter
(in)
New
Diameter
(in)
Street Location Upstream Manhole
Number
Downstream Manhole
Number
Construction
Cost
($)
Soft
Cost
($)*
Total Project
Cost
($)**
Increase Overflow
Elevation TP2 -- -- 65.09 ft
(elevation) S Sanborn Rd S Sanborn at E Alisal St -- M6-012 -- 4,365 18 21 S Sanborn Rd From E Alisal St to
Pellet Ave M6-012 O6-006
-- 500 21 24 S Sanborn Rd From Pellet Ave to
Industrial St O6-006 O6-008
-- 1,500 24 27 S Sanborn Rd From Industrial St to
near Abbott St O6-008 O5-002
$48,468,000
*Soft costs include a 40% escalation of the construction costs for planning, engineering, CM, legal/admin. **All CIP costs are expressed in May 2022 dollars, using McGraw-Hill ENR Construction Cost Index of 13004, and will need to be escalated to the year or years scheduled for the work. $2,392,000
Upsize Sewer Main
South Sanborn Road $5,980,000 $8,372,000
7-14
Sewer System Management Plan – Revision 02
Appendix 8D

City of Salinas
May 2025

City of Salinas Capital Projects
Last Updated 3/7/25: Projects Identified as Planned are contingent on 2025 Prop 218 Funding which had not been approved at the time the SSMP was developed.

Lift Stations
Ranking Title Description Project
Status
Source of
Funding
1 Lake Street Lift
Station
Full lift station
replacement/relocation
Planned for
Completion
2029
Sewer Enterprise
Fund
2 Santa Rita Lift
Station Full lift station replacement
Planned for
Completion
2029
Sewer Enterprise
Fund
3 Spicer Lift Station Full lift station replacement
Planned for
Completion
2030
Sewer Enterprise
Fund
4 Mill Lake Lift
Station Full lift station replacement
Planned for
Completion
2029
Sewer Enterprise
Fund
5 Carpenter Hall Lift
Station Lift station rehabilitation
Planned for
Completion
2030
Sewer Enterprise
Fund
6 De La Torre Lift
Station Full lift station replacement
Planned for
Completion
2032
Sewer Enterprise
Fund
7 Vista Nueva Lift
Station Full lift station replacement
Planned for
Completion
2029
Sewer Enterprise
Fund
8 Harkins Road Lift
Station Full lift station replacement
No Funding
Currently for
project
Sewer Enterprise
Fund
9 Las Casitas Lift
Station Lift station rehabilitation
No Funding
Currently for
project
Sewer Enterprise
Fund
10 TP2 Lift Station Full lift station replacement
No Funding
Currently for
project
Sewer Enterprise
Fund
Sewer System Management Plan – Revision 02
Appendix 8D

City of Salinas
May 2025

11 Airport Lift Station Lift station rehabilitation
Planned for
Completion
2032
Sewer Enterprise
Fund

Pipelines and Manholes
Ranking Title Description Summary Project Status Source of Funding
1 Cesar Chavez
Park
Upsize sewer main & section of
new sewer main.

Planned for
Completion
2029
Sewer Enterprise
Fund
Development
Fees
2 Upper Carr Lake
Repairs Manhole Repairs
Planned for
Completion
2026
Sewer Enterprise
Fund
3 Upstream TP2
Diversion Weir Construction
Planned for
Completion
2028
Sewer Enterprise
Fund
4 Northridge Mall
Upsize sewer main and sewer
main realignment
Planned for
Completion
2027
Sewer Enterprise
Fund
Development
Fees
5 East Market and
Upstream of Lake
Street Repairs
Manhole Repairs, repairs to
broken pipe
No Funding
Currently for
project
Sewer Enterprise
Fund
6 Louise and Van
Buren Street
Repair
Repair pipe sags and surcharging
manhole
Planned for
Completion
2033
Sewer Enterprise
Fund
7 West Market at
Davis
Overcrossing
Bunker doors on Large Trunk
line need replacement
In Progress
Under
Construction
Spot Repair
Project
ARPA Funded
8 Cherokee Drive Upsize sewer main
Planned for
Completion
2028
Sewer Enterprise
Fund
Development
Fees
Sewer System Management Plan – Revision 02
Appendix 8D

City of Salinas
May 2025

9 Malarin St and
Wilgart Way
Repairs
Pipe joint repairs and manhole
repairs
No Funding
Currently for
project
Sewer Enterprise
Fund
10 Romie Lane
Repairs &
Reconfiguration
Analysis
Hydrogen Sulfide damage, MH
rings and lids need replacement.

Concrete in roadway.

Recommended reconfiguration
analysis before repairs.

Planned for
Completion
2032 Sewer Enterprise
Fund
11 King Street
Repairs Major pipe sags
No Funding
Currently for
project
Sewer Enterprise
Fund
12 Del Monte and
Mae Repairs Pipe sags and manhole repairs
In Progress
Under
Construction
Spot Repair
Project
ARPA Funded

13 Riker Street
Repair
Pipe has damage and missing
sections at manhole
In Progress
Under
Construction
Spot Repair
Project
ARPA Funded
14 West Market
Street Repairs
Pipe sags, F. I. s are blown out,
possible realignment
Planned for
Completion
2026
Sewer Enterprise
Fund
15 Johnson Place
Repairs
Pipe damage, sags, spidering
under tracks, ongoing backups,
MH O5-005 has settled, always
surcharging
No Funding
Currently for
project
Sewer Enterprise
Fund
16 N Main St Hwy
101 Underpass
Bunker Repair
Bunker damage to pipe, pipe
missing at bunker on both sides,
clogging
In Progress
Under
Construction
Spot Repair
Project
ARPA Funded
17 Donner Way Pipe damage, sags, etc.

In Progress
Under
Construction
Spot Repair
Project
ARPA Funded
Sewer System Management Plan – Revision 02
Appendix 8D

City of Salinas
May 2025

18 San Miguel Ave
Repair
Pipe Damage; broken pipe 10-
feet from manhole
In Progress
Under
Construction
Spot Repair
Project
ARPA Funded
19 Noice Drive/Tyler
Street
Upsize sewer mains and manhole
repairs
Planned for
Completion
2033
Sewer Enterprise
Fund
Development
Fees
Outside
of
SSMPU
identified
projects
Villa Street/Wilson Pipe Repair
In Progress
Under
Construction
Spot Repair
Project
ARPA Funded
20 Natividad Rd Upsize sewer mains and weir
construction
No Funding
Currently for
project
Sewer Enterprise
Fund
Development
Fees
21 Acacia, Bautista,
Woodside Repairs
Pipe sags and new manhole, joint
repairs
No Funding
Currently for
project
Sewer Enterprise
Fund
22 Comanche, Polk,
and North First
Repairs
Pipe sags manhole replacement,
joint repairs
No Funding
Currently for
project
Sewer Enterprise
Fund
23 Sherwood Dr
Repairs
Pipe cracks at 220-ft mark
downstream from K4-052.

Obstruction (possibly old water
line) in K4-076
No Funding
Currently for
project
Sewer Enterprise
Fund
24 East Laurel and
Williams Repairs
Pipe sags and broken pipe
No Funding
Currently for
project
Sewer Enterprise
Fund
25 Hoover Street
Repair F.I. repair blown out
No Funding
Currently for
project
Sewer Enterprise
Fund
26 Katherine Ave &
Pajaro St Repairs
New manholes
No Funding
Currently for
project
Sewer Enterprise
Fund
Sewer System Management Plan – Revision 02
Appendix 8D

City of Salinas
May 2025

27 Wood Street
Reconfiguration
Analysis
Pipe sags, always plugs, can't
CCTV, Entire area needs
reconfiguration
No Funding
Currently for
project
Sewer Enterprise
Fund

Future Projects (contingent of future development)
Title Description Summary Project Status Source of Funding San Juan Grade Upsize sewer main
Planned for Completion
2029
Sewer Enterprise
Fund Development
Fees
North Davis Road Upsize sewer main Planned for Completion 2030
Sewer Enterprise
Fund Development
Fees
West Laurel Drive Upsize sewer main
No Funding Currently
for project
Sewer Enterprise
Fund Development
Fees
Victor Street Upsize sewer main
No Funding Currently
for project
Sewer Enterprise
Fund Development
Fees
Freedom
Parkway

Upsize sewer main
Planned for Completion
2029
Sewer Enterprise
Fund Development
Fees
Natividad Creek
Park
Upsize sewer main
Planned for Completion
2027
Sewer Enterprise
Fund Development
Fees
East Alisal Street
Upsize sewer main
Planned for Completion
2029
Sewer Enterprise
Fund Development
Fees
Abbott Street Upsize sewer main
Planned for Completion
2026
Sewer Enterprise
Fund Development
Fees
South Sanborn
Road
Increase overflow elevation and
upsize sewer main
Planned for Completion
2034
Sewer Enterprise
Fund Development
Fees

Sewer System Management Plan – Revision 02
Appendix 10A

City of Salinas
May 2025

Appendix 10A Cover Sheet – SSMP Audit Data and Records Request Template

SSMP AUDIT DATA & RECORDS REQUEST
A. SSMP ADMINISTRATIVE YES LOCATED
WHERE? NO N/A COMMENTS
A1 a. Has your agency enrolled in the State-wide GWDR and designated the responsible or authorized representative (LRO)?
b. Provide a copy of the SSMP Certification in CIWQS.
c. Provide a copy of the CIWQS print-out for all LROs and Data Submitters.
d. Provide a copy of your Operational Report(s) from CIWQS. e.

Does the SSMP include a narrative that discusses; summary of plan and associated schedules, sewer system asset overview, updated maps?
A2 a. Has your agency adopted a SSMP?
b. Provide a copy of the SSMP.
c. Provide a copy of the Meeting Minutes for the agency governing body's meeting during which the SSMP was adopted.

A3 a. Does your agency have a copy of the GWDRs available to agency staff? Where is it kept?
A4 a.

How does agency ensure revenues and expenditures related to sanitary sewer system are available to; comply with General Order, fully implement the SSMP, conduct O&M and necessary repairs, ensure proper spill response?
WG SSMP Audit Data Records Request
06/17/2024 Page 1 of 11

SSMP AUDIT DATA & RECORDS REQUEST
B. GOALS YES LOCATED
WHERE? NO N/A COMMENTS
B1 a. Has your agency developed SSMP and Spill reduction goals? b.

Provide documentation that your agency has made progress toward meeting these goals.

C. ORGANIZATION YES LOCATED
WHERE? NO N/A COMMENTS
C1 a. Does your SSMP clearly identify the names and job titles the LROs? C2 a. Does your SSMP have an organizational chart or table showing individual roles and responsibilities for implementation of the SSMP? b. Are names, titles, and telephone numbers provided in this chart or table?
C3 a. Is the chain of communication for reporting Spills included in the SSMP?
b. Are names, titles, and telephone numbers provided in this chain of communication?
WG SSMP Audit Data Records Request
06/17/2024 Page 2 of 11

SSMP AUDIT DATA & RECORDS REQUEST
D. LEGAL AUTHORITY YES LOCATED
WHERE? NO N/A COMMENTS
D1 a.

Provide the sanitary sewer system use ordinances, service agreements, or other legally binding procedures or documents, which demonstrates the agency's legal authority:
b. Prohibit illicit discharges
c.

Collaborate w/ Stormwater Agencies for sewer spill response and prevent cross connections of sanitary sewer and storm sewer infrastructure.
c. Require that sewers and connections be properly designed and constructed
d. Ensure access for maintenance, inspection, or repairs for portions of the lateral owned or maintained by the Public Agency e. Limit the discharge of fats, oils, and grease and other debris that may cause blockages and/or sewer spills
f. Enforce any violation of its sewer ordinances
E. OPERATIONS AND MAINTENANCE (O&M) YES LOCATED
WHERE? NO N/A COMMENTS
E1 a. Provide the following documents:
b. An updated map of the agency's sanitary sewer system and storm drain system.
c. A schedule for maintenance and cleaning of the sanitary sewer system.

WG SSMP Audit Data Records Request
06/17/2024 Page 3 of 11

SSMP AUDIT DATA & RECORDS REQUEST
d. How do O&M and R&R schedules enhance System Resilience? e. Documentation for maintenance and cleaning of the sanitary sewer system.
f. Documentation for scheduled and conducted activities, such as work orders and/or reports and invoices from contractors. g. The O&M contract if the agency's collection system is operated and maintained by a contract operations firm.
h. The agency's Rehabilitation and Replacement Plan
i. » Summary of the agency's CCTV program and schedule.

Include samples of inspections and summary of findings. j. » List of current and planned projects
k. » Time schedule for planned projects
l. » Schedule for developing the funds needed for rehabilitation and replacement projects
m. Standard Operating Procedures for Sewer System Operations and Maintenance activities.
n.

Training records for staff operations and maintenance activities and contractor operations and maintenance activities. Training records for CIWQS reporting, Spill volume estimation, Spill response training.

WG SSMP Audit Data Records Request
06/17/2024 Page 4 of 11

SSMP AUDIT DATA & RECORDS REQUEST
o. » All applicable licenses and certifications required for agency or contract staff. Provide documents stating this requirement. p. Assessment of O&M Staff "Core Competencies" (Skills, Knowledge and Abilities)
q. Equipment and replacement part inventories, including identification of critical replacement parts.
r.
» If critical replacement parts are not kept in stock, identify and provide method in which these parts are acquired when needed (List of emergency contractors and/or suppliers). s. » If critical replacement parts are not kept in stock, provide applicable mutual aid agreements.
q. Equipment and replacement part inventories, including identification of critical replacement parts.
r.
» If critical replacement parts are not kept in stock, identify and provide method in which these parts are acquired when needed (List of emergency contractors and/or suppliers). s. » If critical replacement parts are not kept in stock, provide applicable mutual aid agreements.

F. DESIGN & PERFORMANCE PROVISIONS YES LOCATED
WHERE? NO N/A COMMENTS
F1 a. Provide the following documents:
b. Design and construction standards and specifications for:
c. » the installation of new sanitary sewer systems
WG SSMP Audit Data Records Request
06/17/2024 Page 5 of 11

SSMP AUDIT DATA & RECORDS REQUEST
d. » pump stations and other appurtenances specific to the agency's collection and conveyance system
e. » the rehabilitation and repair of existing sanitary sewer systems
f.

Procedures and standards for inspecting and testing the installation of new sewers, pumps, and other appurtenances specific to the agency's collection and conveyance system and for rehabilitation and repair projects.

WG SSMP Audit Data Records Request
06/17/2024 Page 6 of 11

SSMP AUDIT DATA & RECORDS REQUEST
G. SPILL EMERGENCY RESPONSE PLAN YES LOCATED
WHERE? NO N/A COMMENTS
G1 a. Provide the agency's Spill Emergency Response Plan b.

Notification procedures ensuring that the primary responders, regulatory agencies, and potentially affected entities are informed of all Spills in accordance with the Monitoring and Reporting Program, Order No. 2022-0103.
c. A program to ensure an appropriate response to all spills. d.

Procedures to ensure that appropriate staff and contractor personnel are aware of and follow the Spill Emergency Response Plan and are appropriately trained.
e. Procedures to address emergency operations, such as traffic and crowd control and other necessary response activities.
f. Procedures to address spill volume estimation.
g.

A program to ensure that all reasonable steps are taken to contain and prevent the discharge of untreated and partially treated wastewater to waters of the United States.
h.

A program to ensure that all reasonable steps are taken to minimize or correct any adverse impact on the environment resulting from the Spills, including such accelerated or additional monitoring as may be necessary to determine the nature and impact of the discharge.
i.

Plan to coordinate with storm drain agencies and other impacted utilities in the event of a Spill. Plan to conduct Post Spill Assessments.

WG SSMP Audit Data Records Request
06/17/2024 Page 7 of 11

SSMP AUDIT DATA & RECORDS REQUEST
H. SEWER PIPE BLOCKAGE CONTROL PROGRAM YES LOCATED
WHERE? NO N/A COMMENTS
H1 a. Public Education and Outreach Program for pipe blocking substances. b. Disposal facilities for pipe blocking substances.
c. Ordinance demonstrating the agency's legal authority to prohibit discharges to the sewer system and prevent spills and blockages. d.

Requirements to install grease removal devices, design standards for these devices, maintenance requirements, BMPs, recordkeeping and reporting requirements.
e. Ordinance demonstrating the agency's legal authority to prohibit FOG discharges to the system and inspect FOG producing facilities. f. Evidence of FOG Control Program inspection and enforcement activities.
g. Documentation of hot spots in the collection system, which are caused by FOG.

I. SYSTEM EVALUATION, CAPACITY ASSURANCE, AND CIP YES LOCATED WHERE? NO N/A COMMENTS
I1 a. Provide procedures to evaluate the sanitary sewer system assets. b. Percentage of system assessed annually and rationale for this frequency.

WG SSMP Audit Data Records Request
06/17/2024 Page 8 of 11

SSMP AUDIT DATA & RECORDS REQUEST
c.

Provide information that demonstrates condition assessment prioritizes areas that: 1) Have high level of environmental consequences if vulnerable to failure or are deficient for any reason; 2) Are located in or within the vicinity of surface waters, steep terrain, high groundwater elevations, and environmentally sensitive areas; 3) Are within the vicinity of a receiving water with a bacterial-related impairment on the most current Clean Water Act section 303(d) List
d.

Provide information demonstrating system is assessed using visual observations, video surveillance and/or other comparable system inspection methods.
e.

Provide information demonstrating corrective actions for areas that may contribute to exiting of sewage from the system which can reasonably be expected to discharge into a water of the State. f.

Provide information that demonstrates you have identified system assets vulnerable to direct and indirect impacts of climate change, including but not limited to: sea level rise; flooding and/or erosion due to increased storm volumes, frequency, and/or intensity; wildfires; and increased power disruptions
g.

Provide analysis and procedures to identify system components that are experiencing or contributing to spills caused by hydraulic deficiency and/or limited capacity, including procedures to identify the appropriate hydraulic capacity of key system elements for:
• Dry-weather peak flow conditions that cause or contributes to spill events;
• The appropriate design storm(s) or wet weather events that causes or contributes to spill events;
• The capacity of key system components; and
• Identify the major sources that contribute to the peak flows associated with sewer spills.

WG SSMP Audit Data Records Request
06/17/2024 Page 9 of 11

SSMP AUDIT DATA & RECORDS REQUEST
h.

Information that demonstrates the capacity assessment considers:
• Data from existing system condition assessments, system inspections, system audits, spill history, and other available information;
· Capacity of flood-prone systems subject to increased infiltration and inflow, under normal local and regional storm conditions; · Capacity of systems subject to increased infiltration and inflow due to larger and/or higher-intensity storm events as a result of climate change;
· Increases of erosive forces in canyons and streams near underground and above- ground system components due to larger and/or higher-intensity storm events;
· Capacity of major system elements to accommodate dry weather peak flow conditions, and updated design storm and wet weather events; and
· Necessary redundancy in pumping and storage capacities. i.

Demonstrate how corrective actions are prioritized based on these condition assessments based on the severity of the consequences of potential spills.
j.

Capital Improvement Plans: based on the results of these condition assessments provide the following:
1) project schedules, including completion dates for all rehabilitation and replacement projects or CIP;
2) Internal and External project funding sources for each project; 3) Information demonstrating coordination between operations and maintenance staff, engineering staff, and consultants during the planning, design and construction of CIP.

If other utility agencies are impacted, document coordination efforts.

WG SSMP Audit Data Records Request
06/17/2024 Page 10 of 11

SSMP AUDIT DATA & RECORDS REQUEST
J. MONITORING, MEASUREMENT & PROGRAM MODIFICATIONS YES LOCATED WHERE? NO N/A COMMENTS
J1 a. Adaptive Management strategies
b. · Provide relevant information, including audit findings, to establish and prioritize appropriate Plan activities;
c. · Provide relevant information demonstrating the implementation and measuring the effectiveness of each Plan Element;
d. · Provide relevant information demonstrating the success of the preventive operation and maintenance activities;
e.
· Provide relevant information demonstrating update of plan procedures and activities, as appropriate, based on results of monitoring and performance evaluations;
f. Identification of Spill trends.

K. SSMP PROGRAM AUDITS YES LOCATED
WHERE? NO N/A COMMENTS
K1 a. Provide historical SSMP Program Audit Reports.

L. COMMUNICATION PROGRAM YES LOCATED
WHERE? NO N/A COMMENTS
L1 a. Provide the agency's Communication Program and evidence of its implementation.

WG SSMP Audit Data Records Request
06/17/2024 Page 11 of 11