2025 PAVEMENT IMPROVEMENTS PROJECT, CIP 9981 Drawing No.
Bid awarded on _______ by City Council to ___________ Project Engineer:
for the sum of __________ Project Manager:
Dated CONTRACTOR #1 CONTRACTOR #2 CONTRACTOR #3 CONTRACTOR #4 City Clerk ENGINEER'S
ESTIMATE
ITEM APPROX. UNIT UNIT UNIT UNIT UNIT UNIT
NO. QUANTITY PRICE TOTAL PRICE TOTAL PRICE TOTAL PRICE TOTAL PRICE TOTAL PRICE TOTAL BASE BID NO. 1 - East and West Laurel
1 MOBILIZATION 1 LS 150,000.00$ 150,000.00$ 110,000.00$ 110,000.00$ 400,000.00$ 400,000.00$ 400,000.00$ 400,000.00$ 200,000.00$ 200,000.00$ 600,000.00$ 600,000.00$ 2 TEMPORARY TRAFFIC CONTROL 1 LS 90,000.00$ 90,000.00$ 400,000.00$ 400,000.00$ 460,500.00$ 460,500.00$ 680,172.00$ 680,172.00$ 771,623.60$ 771,623.60$ 462,000.00$ 462,000.00$ 3 REMOVE EXISTING AC PAVEMENT 228893 SF 1.50$ 343,339.50$ 1.80$ 412,007.40$ 2.00$ 457,786.00$ 0.68$ 155,647.24$ 1.10$ 251,782.30$ 0.35$ 80,112.55$ 4 MILL 2” EXISTING AC PAVEMENT 313856 SF 0.75$ 235,392.00$ 0.50$ 156,928.00$ 0.50$ 156,928.00$ 0.45$ 141,235.20$ 0.60$ 188,313.60$ 0.35$ 109,849.60$ 5 CONSTRUCT 2" RHMA-G OVERLAY (1/2" AGGREGATE) 7988 TONS 235.00$ 1,877,180.00$ 174.43$ 1,393,346.84$ 155.00$ 1,238,140.00$ 158.00$ 1,262,104.00$ 190.00$ 1,517,720.00$ 275.00$ 2,196,700.00$ 6 CONSTRUCT 2" TYPE A HMA (3/4" AGGREGATE) 3369 TONS 215.00$ 724,335.00$ 140.00$ 471,660.00$ 115.00$ 387,435.00$ 153.00$ 515,457.00$ 147.00$ 495,243.00$ 195.00$ 656,955.00$ 7 CLASS 2 AGGREGATE BASE 2513 CY 100.00$ 251,300.00$ 149.32$ 375,241.16$ 150.00$ 376,950.00$ 188.00$ 472,444.00$ 56.00$ 140,728.00$ 95.00$ 238,735.00$ 8 PATCH AND REPAIR 6" 26110 SF 9.00$ 234,990.00$ 9.13$ 238,384.30$ 8.00$ 208,880.00$ 5.00$ 130,550.00$ 8.00$ 208,880.00$ 9.00$ 234,990.00$ 9 CRACK SEAL 1 LS 30,000.00$ 30,000.00$ 71,250.00$ 71,250.00$ 64,000.00$ 64,000.00$ 64,000.00$ 64,000.00$ 55,000.00$ 55,000.00$ 64,000.00$ 64,000.00$ 10 ADJUST MANHOLE FRAME AND LID TO FINISH SURFACE 60 EA 3,000.00$ 180,000.00$ 1,500.00$ 90,000.00$ 1,500.00$ 90,000.00$ 1,523.00$ 91,380.00$ 1,300.00$ 78,000.00$ 1,875.00$ 112,500.00$ 11 REPLACE DETECTOR LOOPS 1 LS 30,000.00$ 30,000.00$ 45,000.00$ 45,000.00$ 45,000.00$ 45,000.00$ 45,000.00$ 45,000.00$ 45,000.00$ 45,000.00$ 74,850.00$ 74,850.00$ 12 FURNISH AND INSTALL THERMOPLASTIC STRIPING AND MARKINGS; CHANNELIZERS; RAISED PAVEMENT MARKERS (PER PLAN; INCLUDES REMOVAL) 1 LS 400,000.00$ 400,000.00$ 168,000.00$ 168,000.00$ 150,000.00$ 150,000.00$ 174,867.00$ 174,867.00$ 164,000.00$ 164,000.00$ 163,325.00$ 163,325.00$ TOTAL BASE BID NO. 1 (ITEMS 1-12)
(FOR COMPARISON ONLY)
ALTERNATIVES NO. 2 - Acosta St, Cortez St, Green St, Bardin Way/Cir, Sky Pl & Wiren St 14 MOBILIZATION 1 LS 49,131.00$ 49,131.00$ 28,000.00$ 28,000.00$ 5,000.00$ 5,000.00$ 14,000.00$ 14,000.00$ 41,000.00$ 41,000.00$ 200,000.00$ 200,000.00$ 15 TEMPORARY TRAFFIC CONTROL 1 LS 42,232.58$ 42,232.58$ 57,837.00$ 57,837.00$ 45,000.00$ 45,000.00$ 70,000.00$ 70,000.00$ 104,000.00$ 104,000.00$ 100,000.00$ 100,000.00$ 16 REMOVE EXISTING AC PAVEMENT 96794 SF 1.50$ 145,191.00$ 1.10$ 106,473.40$ 1.50$ 145,191.00$ 0.50$ 48,397.00$ 1.15$ 111,313.10$ 0.35$ 33,877.90$ 17 MILL 2" EXISTING AC PAVEMENT 106132 SF 0.75$ 79,599.00$ 0.46$ 48,820.72$ 0.35$ 37,146.20$ 0.50$ 53,066.00$ 0.70$ 74,292.40$ 0.35$ 37,146.20$ 18 CONSTRUCT 2" RHMA-G OVERLAY (1/2" AGGREGATE) 453 TONS 235.00$ 106,455.00$ 170.51$ 77,241.03$ 198.00$ 89,694.00$ 209.00$ 94,677.00$ 197.00$ 89,241.00$ 275.00$ 124,575.00$ 19 CONSTRUCT 2" TYPE A HMA (1/2" AGGREGATE) 2534 TONS 215.00$ 544,810.00$ 140.69$ 356,508.46$ 130.00$ 329,420.00$ 118.00$ 299,012.00$ 131.00$ 331,954.00$ 195.00$ 494,130.00$ 20 CLASS 2 AGGREGATE BASE 200 CY 98.00$ 19,600.00$ 167.83$ 33,566.00$ 150.00$ 30,000.00$ 294.00$ 58,800.00$ 140.00$ 28,000.00$ 110.00$ 22,000.00$ 21 6" PATCH AND REPAIR 376 SF 9.27$ 3,485.52$ 22.00$ 8,272.00$ 10.00$ 3,760.00$ 5.00$ 1,880.00$ 33.00$ 12,408.00$ 25.00$ 9,400.00$ 22 CRACK SEAL 1 LS 15,000.00$ 15,000.00$ 28,250.00$ 28,250.00$ 21,000.00$ 21,000.00$ 21,000.00$ 21,000.00$ 20,000.00$ 20,000.00$ 21,000.00$ 21,000.00$ 23 ADJUST MANHOLE FRAME AND LID TO FINISH SURFACE 10 EA 3,000.00$ 30,000.00$ 1,500.00$ 15,000.00$ 1,500.00$ 15,000.00$ 1,500.00$ 15,000.00$ 1,500.00$ 15,000.00$ 1,875.00$ 18,750.00$ 24 FURNISH AND INSTALL THERMOPLASTIC STRIPING AND MARKINGS; CHANNELIZERS; RAISED PAVEMENT MARKERS (PER PLAN; INCLUDES REMOVAL) 1 LS 23,655.00$ 23,655.00$ 30,600.00$ 30,600.00$ 27,000.00$ 27,000.00$ 13,500.00$ 13,500.00$ 12,600.00$ 12,600.00$ 12,625.00$ 12,625.00$ TOTAL ALTERNATIVES NO.2 (ITEMS 14 -24)
(FOR COMPARISON ONLY)
ALTERNATIVES NO. 4 - Natividad/Laurel, E Bernal, E Alisal/Skyway 26 MOBILIZATION 1 LS 16,377.00$ 16,377.00$ 1,500.00$ 1,500.00$ 1,000.00$ 1,000.00$ 4,000.00$ 4,000.00$ 1,400.00$ 1,400.00$ 3,700.00$ 3,700.00$ 27 TEMPORARY TRAFFIC CONTROL 1 LS 21,116.29$ 21,116.29$ 7,200.00$ 7,200.00$ 10,000.00$ 10,000.00$ 27,000.00$ 27,000.00$ 10,000.00$ 10,000.00$ 5,500.00$ 5,500.00$ 28 FURNISH AND INSTALL THERMOPLASTIC STRIPING AND MARKINGS; CHANNELIZERS; RAISED PAVEMENT MARKERS (PER PLAN; INCLUDES REMOVAL) 1 LS 11,827.50$ 11,827.50$ 49,036.00$ 49,036.00$ 44,000.00$ 44,000.00$ 18,700.00$ 18,700.00$ 17,500.00$ 17,500.00$ 17,485.00$ 17,485.00$ TOTAL ALTERNATIVES NO.4 (ITEMS 26 - 28)
(FOR COMPARISON ONLY)
Local Purchasing Discount (5%) N/A N/A $241,941.51 $243,594.42 $249,249.95 N/A 1 2
3 4
5 6
7 GRAND TOTAL BASE BID W/ LOCAL PURCHASING DISCOUNT (ITEMS 1-12,14-24,26-28)5,655,016.38$ 4,780,122.31$ 4,596,888.69$ 4,628,294.02$ 4,735,749.05$ 6,094,206.25$ NON-COLLUSION AFFIDAVIT * * * * *
* * * *
INSURANCE CERTIFICATION * * * * *
BIDDER'S STATEMENT OF SUBCONTRACTORS - PART I *
*
PROPOSAL * * * * *
BIDDER'S STATEMENT OF FINANCIAL RESPONSIBILITY, TECHNICAL ABILITY, AND EXPERIENCE * * * * * BIDDER'S BOND * * * * *
ITEMS TO BE SUBMITTED WITH PROPOSAL ON BID OPENING DATE SIGNED ADDENDUM NO. 1-5 * * * *
1,059,159.10$ 790,568.61$ 748,211.20$ 689,332.00$ 839,808.50$ 1,073,504.10$ GRAND TOTAL BASE BID (ITEMS 1-12,14-24,26-28) 5,655,016.38$ 4,780,122.31$ 4,838,830.20$ 4,871,888.44$ 4,984,999.00$ 6,094,206.25$ 49,320.79$ 57,736.00$ 55,000.00$ 49,700.00$ 28,900.00$ 26,685.00$ Gilroy CA 95020 Watsonville CA 95076 San Jose CA 95138 Monterey CA 93940 Martinez CA 94553
DESCRIPTION UNIT
4,546,536.50$ 3,931,817.70$ 4,035,619.00$ 4,132,856.44$ 4,116,290.50$ 4,994,017.15$ CONTRACTOR #5
Mckim Corp Granite Construction Co. GraniteRock Co. Coastal Paving & Excavating Inc. JV LUCAS Paving Inc. 8505 Church St 580 West Beach St 5225 Hellyer Avenue Suite 220 24560 Silver Cloud Ct. Suite 101 865 Howe Rd