Cities Index.
Staff Report - Annual Levy of Assessments for Landscape and Maintenance Districts

Salinas City Council
July 1, 2025

Document
Staff Report - Annual Levy of Assessments for Landscape and Maintenance Districts
Meeting
July 1, 2025
Body
Salinas City Council
Original file
93 KB
Text extracted from the city's file for reading and search. Open the original on legistar2.granicus.com. That file is the official record.

DATE: JULY 1, 2025
DEPARTMENT: PUBLIC WORKS DEPARTMENT
FROM: DAVID JACOBS, PUBLIC WORKS DEPARTMENT
THRU: ADRIANA ROBLES, CITY ENGINEER
BY: CRISTINA GONZALEZ, PW ADMINSTRATIVE SUPERVISOR
TITLE: ANNUAL LEVY OF ASSESSMENTS FOR LANDSCAPE AND MAINTENANCE DISTRICTS RECOMMENDED MOTION:

A motion to approve resolutions related to the annual levy and maintenance funding for the City’s Landscape Maintenance Assessment Districts (LMAD):

Approve the Engineer’s Reports for the City’s six LMAD’s for Fiscal Year 2025–26; Confirm the assessment diagrams and levy amounts as detailed in the Engineer’s Reports; Authorize the levy and collection of annual assessments in compliance with California Streets and Highways Code Sections 22620–22641; and Approve General Fund transfers to cover the cost of parks and open space maintenance associated with the special benefits received by parcels outside the LMAD boundaries.

EXECUTIVE SUMMARY:

This item requests City Council approval to levy annual assessments for the City’s six Landscape and Lighting Assessment Districts for Fiscal Year 2025-2026. The assessments fund ongoing maintenance of landscaping, parks, and open space within the districts. Approval of the Engineer’s Reports, including the assessment diagrams and levy amounts, is required to comply with state law. Council action also includes approving General Fund transfers to cover maintenance costs for areas outside district boundaries that receive special benefits.

BACKGROUND:

The City of Salinas has six Landscape Maintenance Assessment Districts (LMADs), formed pursuant to the California Streets and Highways Code Section 22500 et seq., known as the Landscaping and Lighting Act of 1972, and locally adopted under Article II, Chapter 21C of the Salinas Municipal Code. These districts fund the maintenance and operation of infrastructure such as landscaping, public lighting, and neighborhood improvements through assessments levied on properties within each LMAD. Assessments are based on the special benefits received by each parcel.

In accordance with state law, an Engineer’s Report must be prepared annually for each LMAD in which assessments are proposed. Each report includes:

An overview of the LMAD;
Plans and specifications for the improvements;
An estimate of the annual costs;
A description of the method of apportioning the assessments; and A diagram identifying the LMAD boundaries and associated improvements.

Draft Engineer’s Reports can be found in each LMAD’s webpage:
https://www.cityofsalinas.org/Your-Government/Departments/Public-Works/PW-Maintenance-Services/Landscape-Maintenance-Assessment-Districts Table 1 below summarizes the work funded by each LMAD within its respective boundaries:

Table 1. Summary of Work funded by each LMAD within its boundaries.

LMAD
Landscape & Water
Walkways, Crosswalks & Signs*
Stormwater Detention Basins
Sewer Pump Station & Subdivision Fence
Street Pavement Maintenance*
Street Lighting (Including PG&E Costs)
Airport
X
**North/East
X
X
Harden Ranch
X
X
X
***Mira Monte
X
X
X
X
****Monte Bella
X
X
X
X
X
Vista Nueva
X
X
X
* Not all street segments included, only segments identified in District’s most recent Engineer’s Report **Includes Natividad Creek bridge maintenance at Lexington Drive *** Includes driveway paver maintenance at courtyards
****Includes a portion of neighborhood park landscaping maintenance. PG&E costs are excluded from streetlights costs.

This item was publicly noticed in accordance with the Ralph M. Brown Act, and the Engineer’s Reports were made available for review at least 72 hours prior to the public hearing. Legal notice announcing the public hearing was published in The Monterey Herald following the City Council’s May 13, 2025, approval of the resolution to initiate the annual assessment process.

To expand outreach, the City created a dedicated webpage for each LMAD. Residents were notified of these webpages, which include a summary of funded improvements, updated quarterly budgets, current landscaping contracts, and the most recently approved Engineer’s Reports.

PROPOSED ASSESSMENTS
The assessment rates for the Airport Business Center, Harden Ranch, and Vista Nueva LMADs have remained unchanged since their formation in 1987, 1991, and 2011, respectively. These districts were established without an annual inflator, meaning the assessment amounts cannot increase automatically over time.

As a result, any proposed increase to these assessment rates must comply with the requirements of Proposition 218, a state constitutional amendment that restricts how local governments can impose or increase certain fees and charges. Specifically, Proposition 218 mandates that a notice and ballot be mailed to each affected property owner, followed by a public hearing. A majority vote in favor is required before any rate increase can be implemented.

Airport Business Center Landscape Assessment District No. 87-1 Assessments in the Airport Business Center Landscape Assessment District No. 87-1 shall remain unchanged. The anticipated rate is $217.49 per acre, with assessments calculated based on parcel acreage.

Harden Ranch Maintenance Assessment District No. 2
Assessments for the Harden Ranch Maintenance Assessment District No. 2 will remain unchanged for Fiscal Year 2025–26. The proposed rates are $66.72 annually per single-family residential parcel and $353.66 per acre for non-single-family residential parcels.

Vista Nueva Maintenance Assessment District No. 97-2
The Vista Nueva Maintenance Assessment District No. 97-2 reached its maximum allowable assessment in 2011. Accordingly, assessments will continue at the current rate of $600 annually per parcel for Fiscal Year 2025–26.

Mira Monte Maintenance District Landscape & Lighting District No 2 and Assessment District 2000-1
The Mira Monte District assessment is proposed to increase by 0.87% to $615.39 per parcel annually for Fiscal Year 2025–26. This adjustment reflects rising maintenance costs and supports future replacement of district improvements.

Monte Bella Maintenance District
Assessments for the Monte Bella Maintenance District are recommended to remain at $645.50 per Equivalent Benefit Unit (EBU) for Fiscal Year 2025–26, representing approximately 45% of the maximum allowable rate of $1,433.10. These assessments fund maintenance of street landscaping, lighting, parks and open space, detention basins, and street maintenance within designated Benefit Zones.

North/East Area Maintenance District Landscape and Lighting District No. 1 and Landscaping Assessment District 88-3
The North/East Area Maintenance District assessment formula is based on Benefit Units (BU) and includes an inflation factor. For Fiscal Year 2025–26, the maximum allowable assessment rate is set at $247.63 per BU, representing a 1.97% increase from the prior year’s rate. Parcels within the district will have assessments adjusted according to their proximity to Parks and Open Space Landscaping Benefit Zones and the actual proportion of special benefit received.

The following table summarizes anticipated assessment rates.

Table 2. Breakdown of LMAD Assessments
District
Unit
FY 24-25
FY 25-26
% Change from Previous Year
Actual
Max Assessment Allowed
Recommended
Airport Business Center
Per parcel
$217.49
$217.49
$217.49
0%
Harden Ranch
Per SFU
$66.72
$66.72
$66.72
0%
Per Acre
$353.66
$353.66
$353.66
0%
Mira Monte
Per parcel
$610.08
$1,067.42
$615.39
.87%
Monte Bella
Per EBU
$645.51
$1,433.10
$645.50
0%
North/East
Low-Density Parcels
$213.02
$247.62
$217.00

1.97%
Medium Density Parcels
$131.81
$148.57
$134.19

1.97%
High Density Parcels
$91.21
$99.04
$92.78

1.97%
Vista Nueva
Per Parcel
$600.00
$600.00
$600.00
0%
Local agency assessment rolls must be submitted to the County Assessor’s Office by August of each tax year to ensure that parcel levies are properly billed and collected.

CEQA CONSIDERATION:

Not a Project.  The City of Salinas has determined that the proposed action is not a project as defined by the California Environmental Quality Act (CEQA) (CEQA Guidelines Section 15378).

CALIFORNIA GOVERNMENT CODE §84308 APPLIES:

No.

STRATEGIC PLAN INITIATIVE:

This item relates to the Council’s Strategic Plan Goal of Infrastructure and Environmental Sustainability by improving City facilities, including lighting and landscaping.

DEPARTMENTAL COORDINATION:

Public Works Department’s Engineering Division oversees the preparation of budget documents and publication of the Engineer’s Reports. Maintenance Division oversees the LMAD’s day-to-day maintenance activities. The Finance Department works closely with Public Works in obtaining and then transmitting the up-to-date levy information to the County for processing.

FISCAL AND SUSTAINABILITY IMPACT:

A further funding breakdown of the LMAD’s FY 25-26 total levy (including the $10 per parcel collection fee), FY 25-26 operating budget, operating reserve fund and capital reserve fund are identified in Table 3 below.

Table 3. Summary of LMAD's FY 24/25 Levies, Budgets and Reserve Balances LMAD
Total Levy
2025-2026 Operating Budget
Estimated Reserve Fund Balance
(as of June 2025)
Recommended Reserve Fund Balance
Estimated Capital Budget
Airport Bus Park Maintenance District (2104)
$14,468
$17,422
$11,461
$8,936
0 N E Salinas Landscape District (2105)
$766,696
$803,500
$1,678,002
$401,750
$18,000
Harden Ranch Landscape District (2106)
$155,164
$135,150
$200,047
$67,575
0 Vista Nueva Maintenance District (2107)
$29,890
$38,150
$193,117
$19,075
$235,000
Mira Monte Maintenance District (2108)
$124,924
$159,350
$305,817
$79,675
0 Monte Bella Maintenance District (2109)
$586,466
$478,000
$4,791,605
$239,000
$3,604,801
The Fiscal Year 2025-26 operating and capital improvement budgets were approved by City Council with the City’s Fiscal Year 2025-26 Operating Budget and Capital Improvement Program and Annual Appropriations Limit on June 17, 2025.

Airport Business Center Landscape Assessment District No. 87-1 The Airport District Operating Fund (2104.50.5562) is projected to receive approximately $700 in miscellaneous revenue and interest earnings for FY 2025-26.

Harden Ranch Maintenance Assessment District No. 2
The Harden Ranch District currently holds an Operating Reserve Fund of approximately $151,945. However, there is no established Capital Improvement Reserve Fund. A detailed capital replacement analysis will be conducted to identify specific projects and timelines for the replacement of district improvements. Once this Capital Improvement Program is finalized, staff will return to City Council to request a transfer from the Operating Reserve Fund to the new Capital Improvement Reserve Fund.

Mira Monte Maintenance District Landscape & Lighting District No 2 and Assessment District 2000-1 The Mira Monte District maintains an Operating Reserve Fund but lacks a Capital Improvement Reserve Fund. According to the district’s formation documents, $7,100 is to be set aside annually for capital replacements. A capital replacement analysis will be conducted to identify specific projects and the timing of replacements, including curb & gutter, sidewalk repairs, concrete paver driveway clusters, striping, landscaping, and street lighting. Once the analysis is complete, staff will return to City Council with a request to transfer funds from the Operating Reserve Fund to the Capital Improvement Reserve Fund for these projects.

Monte Bella Maintenance District
The Monte Bella District’s Capital Improvement Reserve Fund (5800.50.9120) has expended $28,833.22 for roadway improvements within major roadways as outlined in the Engineer’s Report, leaving a balance of approximately $3,604,801 as of June 2025. In June 2025, City Council approved an increase of $611,000 to fund future roadway improvements and the replacement of landscaping infrastructure.

Monte Bella assessments are based on the specific special benefits received from park improvements. Properties within the district are only assessed for the special benefits they directly receive, with the general benefit portion funded by the City’s General Fund. The General Fund will contribute $130,617 to the Monte Bella FY 2025-26 operating budget (2109.50.5567) to cover the cost of benefits for parcels outside the district.

North/East Area Maintenance District Landscape and Lighting District No. 1 and Landscaping Assessment District 88-3
The North/East District’s Capital Improvement Reserve Fund (5800.50.9053) expended $21,809.41 on landscaping improvements during FY 2024-25. An increase of $10,000 was approved by the City Council on June 17, 2025, to fund future landscaping improvements.

Property owners in the North/East District benefit from a combination of general versus specific special benefits with respect to Parks and Open Space Landscaping. The assessment calculation is based on each parcel’s proximity to identified special benefit zones. Parcels within the District may only be assessed for their share of the specific special benefits derived from park improvements. The general benefit portion, which covers areas outside the District’s boundary, must be funded by a source other than the North/East District. Therefore, the City’s General Fund will contribute $83,814 to the North/East District’s FY 2025-26 Operating Budget (2105.50.5563) to cover the general benefits for parcels outside the District.

Vista Nueva Maintenance Assessment District No. 97-2
The Vista Nueva District currently has a balance of $225,000 in its Capital Improvement Reserve Fund (5800.50.9056) for future pump station and street pavement upgrade. An increase of $10,000 was approved by the City Council on June 17, 2025, to fund the following maintenance and repairs:

Resurfacing of residential traffic striping, signs, curb & gutter, and sidewalks Maintenance and repair of streetlight equipment and power Under the 1972 Act, operating reserves cannot exceed six months of anticipated expenses. Therefore, Staff will be preparing detailed needs-based analysis and identifying the specific projects and timing for replacement of improvements within each LMAD. Afterwards, Staff will return to Council to request appropriate transfers from the Operating Reserve Fund to a Capital Improvement Project.

The transfers noted in Table 4 are requested from the General Fund to cover the parks and open space maintenance costs associated with the special benefits received by parcels outside the LMAD’s boundaries, as outlined in the Engineer’s Reports.

Table 4. General Funds Transfer Requests
LMAD
LMAD Operating Budget
General Fund Contribution
N E Area Landscape District (2105)
2105.50.5563
$85,113
Monte Bella Maintenance District (2109)
2109.50.5567
$130,617
ATTACHMENTS:

Resolutions
Engineer Reports
Page | 3
Page | 1
Per FY 25-26 City of Salinas Proposed Operating Budget
Per FY 25-26 City of Salinas Proposed Operating Budget
CIPs 9053 (North/East), 9056 (Vista Nueva), and 9120 (Monte Bella)

CITY OF SALINASCOUNCIL STAFF REPORTCITY OF SALINASCOUNCIL STAFF REPORT

CITY OF SALINAS

COUNCIL STAFF REPORT

CITY OF SALINAS

COUNCIL STAFF REPORT

← All documents from this meeting