TABLE OF CONTENTS

SECTION PAGE NO.

TABLE OF CONTENTS .......................................................................................................................................... 2 LOCATION MAP ..................................................................................................................................................... 8 NOTICE TO BIDDERS.......................................................................................................................................... 10 PART A – BID CONTRACT DOCUMENTS .................................................................................................... 15

CONTRACT DOCUMENTS TO BE SUBMITTED WITH BID ON BID OPENING DATE ....................................................................................................................................................... 16 PROPOSAL ............................................................................................................................... 17 BIDDER’S STATEMENT OF FINANCIAL RESPONSIBILITY, TECHNICAL ABILITY AND EXPERIENCE ................................................................................................................. 22 NON-COLLUSION DECLARATION OF CONTRACTOR ................................................... 23 INSURANCE CERTIFICATION ............................................................................................. 24 BIDDER’S STATEMENT OF SUBCONTRACTORS – PART I ........................................... 25 CONTRACT DOCUMENTS TO BE SUBMITTED TO THE CITY WITHIN 5 WORKING DAYS AFTER BID OPENING DATE ...................................................................................... 26 BIDDER’S STATEMENT OF SUBCONTRACTORS – PART I I ........................................... 27 NON-COLLUSION DECLARATION OF SUBCONTRACTOR ........................................... 29 STATEMENT OF GOOD FAITH EFFORT FOR LOCAL HIRE ........................................... 30 BIDDER’S LIST FOR THE CITY OF SALINAS PUBLIC WORKS DEPARTMENT ......... 31 PART B – SUCCESSFUL BIDDER’S CONTRACT DOCUMENTS TO BE SUBMITTED AFTER PROJECT IS AWARDED ..................................................................................................................................... 32 GENERAL INSTRUCTIONS TO LOW BIDDERS ................................................................ 33 BOND OF FAITHFUL PERFORMANCE ............................................................................... 35 PAYMENT BOND (LABOR AND MATERIAL BOND) ...................................................... 37 AGREEMENT .......................................................................................................................... 39 CERTIFICATE INSURANCE REQUIREMENTS .................................................................. 43 LABOR LAW REQUIREMENTS ............................................................................................ 46 PUBLIC WORKS CONTRACT AWARD INFORMATION (D.A.S. 140) ............................ 48 PART C – CITY OF SALINAS FORMS AND MEMORANDUM DOCUMENTS ................................... 49 STATEMENT OF COMPLIANCE .......................................................................................... 50 INSTRUCTIONS FOR PREPARATION OF STATEMENT OF COMPLIANCE ................. 51 CITY OF SALINAS FRINGE BENEFIT STATEMENT ........................................................ 52 CITY OF SALINAS PUBLIC WORKS PAYROLL REPORTING FORM ............................ 53 LOCAL HIRING ADMINISTRATIVE MEMORANDUM 98-2 ........................................... 55 LOCAL HIRING RESIDENCY COMPLIANCE DOCUMENTATION................................. 58 PUBLIC WORKS DEPARTMENT BID PROTEST ................................................................ 59 CITY OF SALINAS NOTICE OF POTENTIAL CLAIM ....................................................... 60 SUBCONTRACTING REQUEST FORM ............................................................................... 61 PART D – SPECIAL PROVISIONS .................................................................................................................... 62 SECTION 1 SPECIFICATIONS AND PLANS ................................................................................... 63 SECTION 2 BIDDING ........................................................................................................................... 64 2-1.01  GENERAL .......................................................................................................................... 64 2-1.02  APPROXIMATE ESTIMATE ........................................................................................... 64 2-1.03  EXAMINATION OF PLANS, SPECIFICATIONS, CONTRACT AND SITE OF WORK ............................................................................................................................................ 64 2-1.04  DIR REGISTRATION ....................................................................................................... 65 2-1.05  SUBCONTRACTING ........................................................................................................ 65 2-1.06  EXAMINATION OF SITE ................................................................................................ 65 2-1.07  BID PROTEST AND BID PROTEST FEE ....................................................................... 66 SECTION 3 CONTRACT AWARD AND EXECUTION .................................................................. 67 SECTION 4 SCOPE OF WORK .......................................................................................................... 68 4-1.01  BID ITEM DESCRIPTION ................................................................................................ 68 4-1.02  COMPLETE-IN-PLACE .................................................................................................... 69 4-1.03  CHANGES IN WORK ....................................................................................................... 70 4-1.04  CHANGED CONDITIONS ............................................................................................... 70 4-1.05  ITEMS NOT LISTED ........................................................................................................ 71 SECTION 5 CONTROL OF WORK .................................................................................................... 7 1 5-1.01  PERMITS AND LICENSES .............................................................................................. 71 5-1.02  NOTICE OF POTENTIAL CLAIM ................................................................................... 72 5-1.03  CLAIMS ............................................................................................................................. 73 5-1.04  DISCREPANCIES ............................................................................................................. 73 5-1.05  COORDINATION AND COOPERATION ....................................................................... 73 5-1.06  WORK TO BE DONE BY OTHERS ................................................................................. 73 5-1.07  UTILITY DETERMINATION........................................................................................... 74 5-1.08  COORDINATION AND COOPERATION WITH UTILITY COMPANIES AND OTHER CONTRACTORS ................................................................................................. 74 5-1.09  CONSTRUCTION EASEMENTS ..................................................................................... 75 5-1.10  SOUND CONTROL REQUIREMENTS ........................................................................... 75 5-1.11  GRAFFITI .......................................................................................................................... 75 5-1.12  WATER POLLUTION CONTROL COMPLIANCE ........................................................ 75 5-1.13  CONTRACTOR RESPONSIBILITIES FOR MAINTAINING TRAFFIC ....................... 76 5-1.14  DEWATERING .................................................................................................................. 78 5-1.15  INSPECTIONS AND CONTROL OF WORK .................................................................. 78 5-1.16  CLOSING OF UNINSPECTED WORK ........................................................................... 78 5-1.17  AREAS FOR CONTRACTOR’S USE .............................................................................. 78 5-1.18  OPEN AND/OR TRENCH EXCAVATIONS DEEPER THAN FOUR FEET BELOW THE SURFACE .................................................................................................................. 7 8 5-1.19  PRESERVATION OF PROPERTY ................................................................................... 79 5-1.20  FINAL INSPECTION AND CLEANUP ........................................................................... 79 SECTION 6 CONTROL OF MATERIALS ........................................................................................ 79 6-1.01  GENERAL .......................................................................................................................... 79 6-1.02  RELATIVE COMPACTION/MATERIAL TESTING ...................................................... 80 6-1.03  SUBSTITUTIONS ............................................................................................................. 80 SECTION 7 HEALTH AND SAFETY ................................................................................................. 80 7-1.01  CONTRACTOR’S RESPONSIBILITY FOR SAFETY .................................................... 80 7-1.02  SAFETY MEASURES ....................................................................................................... 81 7-1.03  CONFINED SPACE SAFETY ........................................................................................... 81 7-1.04  PERSONAL HYGIENE ..................................................................................................... 82 7-1.05  PUBLIC SAFETY AND CONVENIENCE ....................................................................... 82 7-1.06  WARNINGS AND BARRICADES ................................................................................... 82 7-1.07  FIRE PREVENTION .......................................................................................................... 82 7-1.08  SAFETY HELMETS, CLOTHING AND EQUIPMENT .................................................. 83 7-1.09  HAZARDOUS AREAS ...................................................................................................... 83 7-1.10  EMERGENCIES ................................................................................................................ 83 7-1.11  SUBMITTALS ................................................................................................................... 8 3 7-1.12  IMPLEMENTATION ......................................................................................................... 84 7-1.13  PAYMENT ......................................................................................................................... 84 SECTION 8 LEGAL RELATIONS AND RESPONSIBILITY ......................................................... 84 8-1.01  LAWS ................................................................................................................................. 84 8-1.02  GENERAL .......................................................................................................................... 84 8-1.03  PUBLIC CONTRACTS CODE 9204 PUBLIC WORKS PROJECT ................................ 85 8-1.04  LABOR NONDISCRIMINATION .................................................................................... 88 8-1.05  WAGE DETERMINATION .............................................................................................. 88 8-1.06  PUBLIC SAFETY .............................................................................................................. 89 8-1.07  PUBLIC CONVENIENCE ................................................................................................. 89 8-1.08  PROTECTION OF SITE .................................................................................................... 89 8-1.09  DISPOSAL OF MATERIAL ............................................................................................. 90 SECTION 9 PAYMENT ........................................................................................................................ 90 9-1.01  BEGINNING OF WORK, TIME OF COMPLETION, LIQUIDATED DAMAGES AND TEMPORARY SUSPENSION OF WORK ....................................................................... 90 9-1.02  SCHEDULE OF VALUES ................................................................................................. 91 9-1.03  MEASUREMENT AND PAYMENT ................................................................................ 92 9-1.04  PROGRESS PAYMENTS AND RETENTION ................................................................. 92 9-1.05  PROMPT PROGRESS PAYMENT TO SUBCONTRACTORS ....................................... 93 9-1.06  PROMPT PAYMENT OF FUNDS WITHHELD TO SUBCONTRACTORS .................. 93 9-1.07  INCREASE OR DECREASE QUANTITY ....................................................................... 94 9-1.08  COMPENSATION ADJUSTMENTS FOR OIL PRICE INDEX FLUCTUATIONS ...... 94 9-1.09  ARBITRATION ................................................................................................................. 94 SECTION 10 CONSTRUCTION DETAILS ....................................................................................... 94 SECTION 10-1 GENERAL ................................................................................................................................ 94 10-1.01  ORDER OF WORK ........................................................................................................... 94 10-1.02  BASELINE SCHEDULE ................................................................................................... 95 10-1.03  PROGRESS SCHEDULE .................................................................................................. 95 10-1.04  WORKMANSHIP .............................................................................................................. 95 10-1.05  WARRANTIES .................................................................................................................. 95 10-1.06  OBSTRUCTIONS .............................................................................................................. 96 10-1.07  UNDERGROUND OBSTRUCTIONS .............................................................................. 96 10-1.08  SUBMITTALS/DRAWINGS OF RECORD/CRITERIA FOR FURNISHING PLANS AND SPECIFICATIONS TO CONTRACTOR ................................................................. 96 10-1.09  WATERING ....................................................................................................................... 98 10-1.10  CONSTRUCTION SURVEYS AND STAKING .............................................................. 98 10-1.11  SURVEY MONUMENTS .................................................................................................. 98 10-1.12  PROJECT SIGNS ............................................................................................................... 99 10-1.13  CONSTRUCTION AREA SIGNS ..................................................................................... 99 10-1.14  CLEAN UP ......................................................................................................................... 99 10-1.15  CONSTRUCTION AND DEMOLITION WASTE REDUCTION PLAN/RECYCLING 99 SECTION 10-2 REMOVAL AND DISPOSAL/SALVAGE EXISTING FACILITIES ............................. 100 10-2.01  GENERAL ........................................................................................................................ 100 10-2.02  REMOVAL OF ASBESTOS AND HAZARDEOUS SUBSTANCES ........................... 100 SECTION 11 ITEMS OF CONSTRUCTION ................................................................................... 100 SECTION 11-1 GENERAL .............................................................................................................................. 100 SECTION 11-2 EARTHWORK ....................................................................................................................... 101 11-2.01  GENERAL ........................................................................................................................ 101 11-2.02  QUALITY ASSURANCE ................................................................................................ 101 11-2.03  HAULING ........................................................................................................................ 101 11-2.04  GRADE TOLERANCE .................................................................................................... 101 SECTION 11-3 ASPHALT CONCRETE ........................................................................................................ 101 11-3.01  GENERAL ........................................................................................................................ 101 11-3.02  PRIME COAT .................................................................................................................. 102 11-3.03  PAINT BINDER ............................................................................................................... 102 11-3.04  TACK COAT.................................................................................................................... 102 11-3.05  ASPHALTIC EMULSION ............................................................................................... 102 11-3.01  REMOVAL OF ASPHALT CONCRETE PAVEMENT ................................................. 103 SECTION 11-4 CONCRETE FACILITIES .................................................................................................... 103 11-4.01  GENERAL ........................................................................................................................ 103 11-4.02  REMOVAL AND DISPOSAL OF CONCRETE SIDEWALK, CURB AND GUTTER 103 11-4.03  CONSTRUCTION OF CONCRETE SIDEWALK, CURB AND GUTTER .................. 104 SECTION 11-5 REINFORCEMENT .............................................................................................................. 104 11-5.01  GENERAL ........................................................................................................................ 104 SECTION 11-6 AGGREGATE BASE ............................................................................................................ 104 11-6.01  GENERAL ........................................................................................................................ 104 SECTION 11-7 THERMOPLASTIC PAVEMENT STRIPING AND MARKINGS.................................. 104 11-7.01  GENERAL ........................................................................................................................ 104 11-7.02  MATERIALS ................................................................................................................... 105 11-7.01  REMOVAL OF PAVEMENT STRIPING AND PAVEMENT MARKINGS ................ 105 SECTION 11-8 SIGNS ...................................................................................................................................... 105 11-8.01  GENERAL ........................................................................................................................ 105 11-8.02  SIGN POST ...................................................................................................................... 105 11-8.03  ANCHORAGE ................................................................................................................. 105 11-8.04  MOUNTING..................................................................................................................... 106 SECTION 11-9 CURB DRAIN AND RECTANGULAR DRAINAGE CHANNEL ................................. 106 11-9.01  GENERAL ........................................................................................................................ 106 SECTION 11-10 DETECTABLE WARNING SURFACE ........................................................................... 106 11-10.01  GENERAL ........................................................................................................................ 106 SECTION 11-11 COBBLE SPLASH PAD ..................................................................................................... 110 11-11.01  GENERAL ........................................................................................................................ 110 PART E– CONSTRUCTION BEST MANAGEMENT PRACTICES (BMPS), CONSTRUCTION AND

DEMOLITION DIVERSION REQUIREMENTS, AND OTHER MISCELLANEOUS INFORMATION ................................................................................................................................................................................... 111 CONSTRUCTION SITE BEST MANAGEMENT PRACTICES ............................. 113 POLE DETAIL .......................................................................................................................... 120 CONSTRUCTION AND DEMOLITION DIVERSION REQUIREMENTS ...................... 121 ATTACHMENT A: CITY OF SALINAS HOLIDAY SCHEDULE .................................... 126 PART F – QUALITY ASSURANCE PROGRAM .......................................................................................... 128

7 [THIS PAGE LEFT INTENTIONALLY BLANK]

8 LOCATION MAP

9 [THIS PAGE LEFT INTENTIONALLY BLANK]
10 NOTICE TO BIDDERS
Notice is hereby given that the City of Salinas, County of Monterey, State of California (hereinafter referred to as “City”), hereby invites sealed Bid Proposals (“Bids”) for the following work to be completed according to Plans and Specifications on file, to wit:

COVENTRY STREET AND VICTOR STREET TRAFFIC CALMING DEVICES A scanned copy of the Bid’s proposal package (“Bids”) for the a bove-mentioned work shall be submitted electronically via PlanetBids. Bids will only be received until 2:00 PM Pacific Standard Time on July 1, 2025, at which time or thereafter said bids will be electronically opened and read aloud via Zoom. It is the Bidder’s responsibility to ensure that said Bid shall be fully uploaded/transmitted via the PlanetBids website, prior to the aforemen tioned designated date and time. The City’s Clerk’s Office will not be accepting paper bids.

Join Zoom Meeting
https://cityofsalinas.zoom.us/j/85333588527?pwd=Z73DD84uDTbj9tozU2M7u2skkzmlpk.1 Meeting ID: 853 3358 8527
Passcode: 117842
---
One tap mobile
+16699006833,,85333588527#,,,,*117842# US (San Jose)
+16694449171,,85333588527#,,,,*117842# US
---
Dial by your location
• +1 669 900 6833 US (San Jose)
• +1 669 444 9171 US
• +1 253 215 8782 US (Tacoma)
• +1 346 248 7799 US (Houston)
• +1 719 359 4580 US
• +1 253 205 0468 US
• +1 301 715 8592 US (Washington DC)
• +1 305 224 1968 US
• +1 309 205 3325 US
• +1 312 626 6799 US (Chicago)
• +1 360 209 5623 US
• +1 386 347 5053 US
• +1 507 473 4847 US
• +1 564 217 2000 US
NOTICE TO BIDDERS – cont.
11 • +1 646 931 3860 US
• +1 689 278 1000 US
• +1 929 205 6099 US (New York)
Meeting ID: 853 3358 8527
Passcode: 117842
Find your local number: https://cityofsalinas.zoom.us/u/kdSlsIMO67

In addition to electronic Bid submittals, sealed original hard copies as listed in Part A of these Specifications (to be used for verification) must also be sent via courier service, mailed, or delivered within 5 working days after Bid opening date. Failure to comply with these requirements may result in the forfeiture of the Bidder’s rank in the Bid process.

Scope of Work : In general, the work consists of the construction of one (1) traffic circle, one (1) raised crosswalk, furnishing and installation of detectable warning surfaces, curb drains, drainage channels, street signs on new poles/posts, removal of existing pavement markings , removal of existing asphalt concrete pavement, removal of existing c oncrete ramps and sidewalk, new concrete sidewalk, new striping and pavement markings, and all incidental and appurtenant improveme nts and restorations specified on the Plans and herein these Special Provisions.

AUXILIARY AIDS AND SERVICES
Disability-related modification or accommodation, including aux iliary aids or services, may be requested by any person with a disability who requires a modification or accommodation in order to participate in any meetings for this project. Requests should be referred to the City Clerk’s Office at City Hall, 831-758-7381, as soon as possible but no later than 5 p.m. of the last business day prior to the scheduled meeting. Hearing impaired or TTY/TDD text telephone users may contact the City b y dialing 711 for the California Relay Service (“CRS”) or by telephoning any other service providers’ CRS telephone number.

STATE LICENSING REQUIREMENTS
No bid shall be accepted from a Contractor who has not been licensed in accordance with the Provisions of Chapter of Division 3 of the Business and Professions Code.

Contractor shall possess a Type Class A (General Engineering) issued by the California Contractor’s State License Board (CSLB) or other license qualifying the Bidder to Bid as a prime Contractor prior to SUBMITTAL of Bid and the license must be valid prior to awar d and throughout the Contract.

Subcontractors shall possess the license appropriate for their classification of work.

A Bid shall not be accepted nor any contract or subcontract ent ered into without proof of the contractor or subcontractor’s current registr ation to perform public work pur suant to Labor Code Section 1771.1. Per Division 2, Part 7, Chapter 1, Article 1, Section 1771.1 of the California Labor Code, a Contractor or Subcontractor shall not be qualified to bid on, be listed in a bid proposal, subject to the requirements of NOTICE TO BIDDERS – cont.
12 Section 4104 of the Public Contr act Code or engage in performan ce of any contract for public work, as defined in this chapter, unless currently registered and qualified to perform public work pursuant to Section 1725.5. It is not a violation of this section for an unregistered Contractor to submit a Bid that is authorized by Section 7029.1 of the Busin ess and Professions Code or by Se ction 10164 or 20103.5 of the Public Contract Code, provided the Contractor is registered to perform public work pursuant to Section 1725.5 at the time the contract is awarded.

All Contractors (prime and subs) must possess and maintain such registration with the Department of Industrial Relations (“DIR”) in or der to be awarded and to perf orm work on public works projects. The following is the link to DIR’s Contractor Registration searchab le database: Contractors - DIR Services (ca.gov)
In addition, the successful Bidder and all Subcontractors must have a valid City of Salinas business license before the commencement of work (https://www.cityofsalinas.org/Business/Business-Licenses-and-Home- Based-Business-Permits).

PREVAILING WAGES
All wage scales shall be in accordance with applicable determin ations made by the Director of the DIR of the State of California, as provided by Article 2, Chapter 1, D ivision 2, Part 7 of the Labor Code of the State of California, commencing with Section 1771. In accordanc e with Section 1773.2 of the said Labor Code, copies of the aforesaid determinations of the Director of the DIR are available on the website address http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm. It shall be mandatory for the Contractor to whom the Contract is awarded to pay not less than the applicabl e prevailing wage rate to all workers employed for the execution of the Contract and employ apprentic es pursuant to Section 1777.5 of the California Labor Code.

This project is subject to compliance monitoring and enforcement by the DIR.

Additionally, all contractors and subcontractors must furnish certified payroll records directly to the Labor Commissioner (aka Division of Labor Standards Enforcement) on a weekly basis and in the format prescribed by the DIR, which may include electronic submission.

GENERAL CONTRACT TERMS
The City of Salinas reserves the right to reject any or all Proposals and to waive any informality in Proposals received.

By submitting a Bid, it is assumed that the Contractor has eval uated the site and the Bid submitted reflects that the Contractor is satisfied as to the existing conditions, said conditions being reflected in the Bid.

Each Bid shall be in accordance with the Plans and Specificatio ns on file, submitted on the Proposal form furnished and accompanied by a certified or cashier’s check or Bid Bond made payable to the City of Salinas, for an amount equal to or at least ten percent (10%) of that amount of the Bid, such guaranty to be forfeited should the Bidder to whom the Contract is awarded fail to enter into Contract within 15 calendar days after notification of the award of Contract to the Bidder. The Contractor shall diligently prosecute the NOTICE TO BIDDERS – cont.
13 work to completion on or before the expiration of 40 working days (this does not include the allotted for materials submittals, the ordering and receiving of materials) after said notification.

PROJECT PLANS & SPECIFICATIONS AND PLANET BID REGISTRATION Bidders will be responsible for printing or obtaining on their own accord, hard copies of the Bid Proposal Package, Plans, Specifications, Prospective Bidders List and any addenda and notifications for their use in submitting a Bid.

Bidders are responsible to register as a Prospective Bidder for this project on the PlanetBids Vendor Portal website when submitting a Bid and shall maintain their status a s a “Bidder” throughout the Bid process; Bidders that fail to do so shall be disqualified. Prospective Bidders are permitted to access and download all information and documents available for the project on the PlanetBids website. Only registered Prospective Bidders for the particular City of Salinas project will automatically receive updates, notifications, and addenda when issued, however, it is the Bidder’s responsibility to ensure that the forgoing have been received.

Bidders can register as a Prospective Bidder in two ways:
(1) Bidders are encouraged to register for FREE through PlanetBids Vendor Portal for the City of Salinas at PlanetBids Vendor Portal,
(2) Bidders may also register to PlanetBids’ website directly for a FEE at VendorLine - Connecting Vendors and Contractors to Bid Opportunities (planetbids.com) and sign up for City of Salinas bid opportunities. The link “View Current Construction Projects Out for Bid” on the City of Salinas website listed below will take you to the registration page on the PlanetBids Vendor Portal for the City of Salinas website: Construction Projects - City of Salinas.

All Project Plans and Specifications are available for download on PlanetBids through the City of Salinas website, Construction Projects - City of Salinas.

For assistance in downloading the documents, contact PlanetBids online or by calling 818-992-1771.

All questions regarding this project shall be submitted to the City of Salinas through the project page on the PlanetBids website, 9 calendar days prior to bid opening date. Questions received after the date stated here shall not be answered. All registered Prospective Bidders for this project will receive an email notification once a response to a question has been posted on the PlanetBids website.

STANDARD SPECIFICATIONS, DESIGN STANDARDS AND STANDARDS PLANS, 2008 Edition and subsequent revisions, City of Salinas, Public Works Departm ent (herein referred to as the “Standard Specifications” ) may be downloaded on the City of Salinas webs ite at: revised2008citystandards.pdf (cityofsalinas.org)
Any and all Addenda to the Contract Documents shall only be iss ued electronically through the PlanetBids Vendor Portal website and ONLY Bidders who are registered Prospective Bidders online at the PlanetBids Vendor Portal website as having received a set of Plans and Specifications. The City shall not be responsible for issuance of said Addenda to non-registered Plan holders.

NOTICE TO BIDDERS – cont.
14 SUBSTITUTION OF SECURITIES
For any moneys earned by the Contractor and withheld by the City of Salinas to ensure the performance of the Contractor, the Contractor may, at their request and expens e, substitute securities equivalent to the amount withheld in the form and manner and subject to the condi tions provided in Section 22300 of the Public Contracts Code of the State of California.

BID RIGGING
Th U.S. Department of Transportation (DOT) provides a toll-free hotline to report bid rigging activities.

Use the hotline to report bid rigging, bid collusion, and other fraudulent activities. The hotline number is (800) 424-9071. The service is available 24 hours 7 days a week and is confidential and anonymous. The hotline is part of the DOT’s effort to identify and investigate highway construction contract fraud and abuse and is operated under the direction of the DOT Inspector General.

CONSTRUCTION ESTIMATES AND CAD FILES
Pursuant to the General Contract Terms of the Notice to Bidders , a bid bond based on 10% of the bid amount is required. Until bids are opened, the engineer’s estimate, fund allocation and any other portion of the project estimate are not public information. The release of this construction estimates and/or CAD files, prior to award, may compromise the integrity of the competitive bidding process.

The bid tab will be published at project award.

15 PART A –

BID CONTRACT DOCUMENTS

16 CONTRACT DOCUMENTS TO BE SUBMITTED WITH BID ON

BID OPENING DATE

17 PROPOSAL
FOR

COVENTRY STREET AND VICTOR STREET TRAFFIC CALMING DEVICES

SALINAS, CALIFORNIA
FROM:

NAME OF BIDDER:

BUSINESS ADDRESS:
(Street Address)
CITY: STATE: ZIP:

PHONE:

RESIDENCE ADDRESS:

CITY: STATE: ZIP:

PHONE:

City of Salinas
Salinas, California

Gentlemen/Ladies:

Pursuant to the foregoing Notice to Bidders, the undersigned hereby proposes and binds himself/herself on award by the City Council under this Proposal to execute in acc ordance with such award, a Contract with necessary bonds of which this Proposal, the Notice to Bidders, and the Plans and the Specifications, shall be a part, to furnish any and a ll required labor, material, and services for performing and completing the work set forth in the said Specifications and shown on the Plan s accompanying them, within the time hereinafter set forth and at the prices named in this Proposal as follows:
□By checking this box, the Bidder herby affirms it meets the requirements set forth under Chapter 12 Article III A-Local Purchasing Preference. All Local Contractors must have a Declaration of Local Business Enterprise form filed with the City of Salinas Finance Department. Refer to link for requirements https://www.cityofsalinas.org/Business/Bids-and- RFQs/Bidding-Basics and Declaration of Local Business Form.

PROPOSAL – cont.
18 All of the Proposal items below shall include all labor, materials, tools, equipment, and incidental costs for each item complete or complete-in-place, per Plans and Specifications.

COVENTRY STREET AND VICTOR STREET TRAFFIC CALMING DEVICES

PROPOSAL ITEMS

BASE BID
Item
No. Item Description Approx.

Quantity
Unit of
Measure Unit Price Total
1 Mobilization 1 LS
2 Temporary Traffic Control 1 LS
3 Furnish and Install Traffic Circle,
Complete-In-Place 1 LS
4 Furnish and Install Raised Crosswalk,
Complete-In-Place 1 LS

In case of discrepancy between t he item price and the total set forth for a unit basis item, the item price shall prevail, provided, however, if the amount set forth as an item price is ambiguous, unintelligible or uncertain for any cause, is omitted, or is the same amount as t he entry in the "Total" column, then the amount set forth in the "Total" column for the item shall preva il and shall be divided by the estimated quantity for the item, and the price thus obtained shall be the item price.

Contractor shall provide a schedule of values for all lump sum items of work listed in the Proposal and noted in the Special Provisions. The schedule of values shall be submitted to the City Engineer for approval within 15 calendar days after the Contract has been awarded.

NOTE: For Bid package to be VALID: (1) the Bidder must submit a Bid for all Base Bids, and all Additive Alternatives; (2) the Bidder must submit all completely executed and signed City of Salinas forms; and (3) the Contractor and all Subcontractors shall have valid, current and active Contractor’s license(s) for the classification(s) of work performed and be registered with the DIR pursuant to Labor Code section 1725.5, and the license(s) must be valid prior to the award of Contract and throughout the Contract as approved by Council. In addition, the contractor and all subcontractors mus t have a valid City of Salinas Business License prior to commencement of work.

It is expressly understood and agreed that this Bid shall have the following documents completed, all of which are incorporated into and made a part hereof. The following information shall be submitted with the Bid Proposal on the Bid Opening Date:

1. Complete Proposal signed and dated.

2. Signed Addendum (if any).

3. Bidder’s Bond.

PROPOSAL – cont.
19 4. Bidder’s Statement of Financial Responsibility Technical Ability and Experience.

5. Insurance Certification.

6. Non-Collusion Declaration of Contractor.

7. Bidder’s Statement of Subcontractors – Part I (The Contractor a nd all Subcontractors shall have valid, current, and active Contractor’s licenses for the classi fication of work performed, prior to submittal of Bid, during Award, and throughout the Contract).

If the Bidder’s Statement of Subcontractors – Part I is not submitted, it shall be assumed that the Contractor shall do all the work herein specified. All prospective Contrac tors may use the website https://www2.cslb.ca.gov/OnlineServices/CheckLicenseII/checklicense.aspx to check each Subcontractor’s license status and the DIR’s Contractor Registration searchable database Contractors - DIR Services (ca.gov) to verify each Subcontractor’s registration status.

The lowest, second, and third lowest ranked project Bidders sha ll submit the original Bid Documents and the following forms, fully compl eted, to the Public Works Depar tment, City of Salinas, within 5 working days after Bid opening date and/or when the lowest responsible Bidder is known:

8. Bidder’s Statement of Subcontractors – Part II

9. Non-Collusion Declaration of Subcontractor

10. Statement of Good Faith Effort for Local Hires

11. Bidder’s List for the City of Salinas Public Works Department. The Prime Contractor shall submit original(s). All Subcontractor(s) shall submit original (s) or faxed copy (copies) Failure to comply with these requirements may result in the forfeiture of the Bidder’s rank in the Bid process.

The City shall award the contract to the lowest responsive and responsible Bidder, if a contract is awarded. The basis of award shall be the lowest Total Base Bid, as noted on the Pr oposal. This does not preclude the City from adding to or deleting from the contract, any of the bid items after the lowest responsible bidder had been determined. The City further reserves the right to award or reject the Base Bid or any item(s) within, depending on available funding.

Also, the award of the Contract, if it be awarded, shall be to the lowest responsive and responsible Bidder whose Proposal complies with all the requirements prescribed and who has met or has demonstrated, to the satisfaction of the City of Salinas adequate good faith efforts to do so.

The successful Bidder and all Subcontractors must have a valid City of Salinas business license before the commencement of work.

Except as may otherwise be provided herein, all work to be done under this Contract shall conform to the applicable requirements of the Design Standards, Standard Specifications and Standard Plans, 2008 Edition and subsequent revisions, City o f Salinas Public Works Departme nt, and the 2024 State of California, Department of Transportation, Standard Specifications herein re ferred to as the “State Standard Specifications” and the most current approved version of the California Manual on Uniform Traffic Control Devices (CA-MUTCD).

The undersigned understands that the quantities given are approximate only, being given as a basis for the comparison of Bids, and the City of Salinas does not, expressly or by implication, agree that the actual amount of work shall correspond therewith, but reserves the right to increase or decrease the amount of any PROPOSAL – cont.
20 portion of the work or to omit portions of the work as may be d eemed necessary or advisable by the City Engineer without claim for damage or loss of anticipated profit and that payment shall be made only on the basis of the actual quantities of work performed.

Each Bid shall be in accordance with the Plans and Specificatio ns adopted therefore, submitted on the Proposal form furnished and accompanied by a certified or cashi er's check or Bid Bond made payable to the City of Salinas, for an amount equal to at least ten percent (10%) of that amount of the bid, such guaranty to be forfeited should the Bidder to whom the Contract is awarded fail to enter into the Contract within 15 calendar days after notification of the award of Contract to the Bidder. The Contractor shall diligently prosecute the work to completion on or before the expiration of 40 Working Days (this does not include the allotted for material submittals after said notification).

The undersigned agrees, if awarded the Contract, that there sha ll be paid by the undersigned and by all Subcontractors under him/her, to all laborers, workmen and mech anics employed in the execution of such Contract or any Subcontract thereunder, not less than the gener al prevailing rate of per diem wages and rates for overtime and legal holidays in the locality in which the work is to be performed, as ascertained and determined, pursuant to the s tate statute thereto applicabl e, by the City Council, the schedule thereof being set forth in the advertisement for Bids and in the Specifications for said work.

The undersigned further agrees that all work to be done under t his Contract shall be done in accordance with the provisions of that certain form of Agreement attached hereto and hereby made a part of these Specifications.

Enclosed herein is a (Bidder’s bond, certified check, or cashie r check) for not less than 10% of the total amount of the Proposal and the undersigned agrees that, in case of their default in executing the Contract and the necessary bonds after awards and due notice thereof, the said check or bond and the money payable thereon shall become and remain the property of the City of Salinas as liquidated damages.

All questions about the meaning or intent of the Contract documents shall be submitted to the City of Salinas through the project page on the Planet Bids website. Responses shall be issued by Addenda electronically on-line through the Planet Bids Vendor Portal website and ONLY to Bidders who are registered Prospective Bidders for this project. QUESTIONS RECEIVED LESS THAN 9 CALENDAR DAYS PRIOR TO THE DATE OF THE OPENING BIDS SHALL NOT BE ANSWERED. Only questions answered by Addenda shall be binding. Oral and other interpretations or clarifications shall be without legal effect.

For any money earned by the Undersigned and withheld by the City of Salinas, to ensure the performance of the Contract, the Undersigned may, at his/her request and expense, substitute securities equivalent to the amount withheld in the form and manner and subject to the condi tions provided in Section 22300 of the Public Contracts Code of the State of California.

Licensed in accordance with an act providing for the registration of Contractors:

L i c e n s e N o . : D I R R e g i s t r a t i o n N o . :

Expiration Date: DIR Reg. Exp. Date:
(If Bidder is a joint venture, each member must specify license number, expiration date and statement regarding representations made.)
PROPOSAL – cont.
21 (If an individual, so state. If a firm or co-partnership, stat e the firm name and give the names of all individuals; co-partners composing the firm. If a corporation, state legal names of corporation, also names of President, Secretary, Treasurer, and Manager thereof.)

Business Address
Signature of Bidder:
(Signature in blue ink)
Dated: , 20

22 BIDDER’S STATEMENT OF FINANCIAL RESPONSIBILITY,

TECHNICAL ABILITY AND EXPERIENCE
(This form must be completed and submitted with this Bid) The Bidder is required to state what work of a similar characte r to that included in the proposed Contract he/she has successfully performed and give references which will enable the City Council to judge his/her responsibility, experience, skill and business standing.

The undersigned submits herewith a statement of his/her financial responsibility.

The undersigned submits below a statement of the work of a simi lar character to that included in the Proposed Contract which he/she h as successfully performed. (In clude the type of work, name and phone number of all references.)

TYPE NAME PHONE NUMBER

SIGNED:
(Signature) (Date)
Attach Notary Acknowledgment if signature is not the same as the Proposal signature(s)

23 NON-COLLUSION DECLARATION OF CONTRACTOR
(This form must be completed and submitted with this Bid) State of , }SS County of ,
, being first duly sworn, deposes and says that:

I am the (owner, partner, officer, representative, or agent) _________________ of , the party making the foregoing Bid:

The Bid is not made in the interest of or on behalf of any undi sclosed person, partnership, company, association, organization, or co rporation. The Bid is genuine and not collusive or sham. The Bidder has not, directly or indirectly, induced or solicited any other bid der to put in a false or sham Bid. The Bidder has not, directly or indirectly, colluded, conspired, connived, or agreed with any bidder or anyone else to put in a sham Bid or to refrain from bidding. The Bidder has no t in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone t o fix the bid price of the Bidder or any other bidder, or to fix any overhead, profit, or cost element o f the bid price or of that of any other bidder.

All statements contained in the Bid are true. The Bidder has not, directly or indirectly, submitted his or her Bid price or any breakdown thereof or the contents thereof or divulged information or data relative thereto, to any corporation, partnership, company, association, organization, bid depository, or to any member or agent thereof, to effectuate a collusive or sham Bid, and has not paid, and will not pay, any person or entity for such purpose.

Any person executing this declaration on behalf of a Bidder that is a corporation, partnership, joint venture, limited liability company, limited liability partnership, or any other entity, hereby represents that he or she has full power to execute, and does execute, this declaration on behalf of the Bidder.

I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct and that this declaration is executed on _______[date], at __________[city], ________[state].

Signed

Title

Attach Notary Acknowledgment if signature is not the same as the Proposal signature(s)

24 INSURANCE CERTIFICATION
(This certification shall be completed and submitted with the proposed Bid)

By signing below, I hereby certify that
(Insert company name)
is currently insured by an i nsurance company that is an “Authorized” carrier by the Insurance Commissioner of the California State Department of Insurance to transact the business of insurance in the State of California, and shall be written by insurers with a cu rrent A.M. Best Rating of “A-Class VIII” or better, and a financial size of “VII” or greater. Said insurance will expire on _______________.

I further hereby certify that, as the signer of this Bid Propos al, I have read and understand the City’s insurance requirements as described in the Section entitled “In surance Requirements” within these Specifications and that proof of insurance shall be required be fore the Public Works Services Contract is recommended for Award. Such proof shall be provided on an ISO Accord 25(s) form and an endorsement naming the City of Salinas as additionally insured is on the IS O CG 20 10 11 85 form or any other comparable endorsement, which does not further limit coverage, and which may be approved and accepted by the City Attorney.

(Print Name)
Signature of Bidder:
(Signature) (Date)

25 BIDDER’S STATEMENT OF SUBCONTRACTORS – PART I
(This form shall be completed and submitted with this Bid) List each subcontractor that is a first tiered subcontractor an d will perform a portion of the work in an amount in excess of one-half of one percent (0.5%) of the Bidde r’s total contract price or $10,000 (whichever is greater). Substituting a Subcontractor in place of a Subcontractor listed in the original Bid is prohibited and may result in rejection of the Bidder’s proposal.

The Contractor and all Subcontractors shall have valid Contract or’s licenses for the classification of work performed, prior to award of Contract, and throughout the Contract.

The Contractor and all Subcontractors must possess and maintain a current Public Works Contractor registration with the Department of Industrial Relations (DIR), at the time Bid is submitted, and throughout the Contract.

SUBCONTRACTOR TYPE OF WORK DIR NO. LICENSE NO./
STATE

SIGNED _____________________________________
(Signature) (Date)
Attach Notary Acknowledgment if signature is not the same as the Proposal signature(s)

26 CONTRACT DOCUMENTS TO BE SUBMITTED TO THE CITY
WITHIN 5 WORKING DAYS AFTER BID OPENING DATE

27 BIDDER’S STATEMENT OF SUBCONTRACTORS – PART I I
(This information may be submitted with your Proposal. If it is not, and you are the apparent low Bidder, the second or third low Bidder, it shall be subm itted and received by the Public Works Department no later than 5 working days after Bid opening date and/or when the lowest responsible Bidder is known.) List all first tiered Subcontractors performing work on site, i ncluding first tiered Subcontractors under one-half of one percent (0.5%) of the total contract bid or $10,000.

The undersigned submits herewith a list of Subcontractors whom he/she proposes to employ on the work, with the proper firm name and business address of each.

If no list submitted, it shall be assumed that the Contractor shall do all the work as specified.

The Contractor and all Subcontractors shall have valid Contract or’s licenses for the classification of work performed, at time of award of C ontract, and throughout the Con tract. All prospective Contractors may use the website https://www2.cslb.ca.gov/OnlineServices/CheckLicenseII/CheckLicense.aspx t o check each Subcontractor’s license status and expiration dates.

The Contractor and all Subcontractors must possess and maintain a current Public Works Contractor registration with the Department of Industrial Relations (DIR), at the time Bid is submitted, and throughout the Contract. All prospective Contractors may search the DIR’s Public Works C ontractor Registration searchable database https://www.dir.ca.gov/public-works/publicworks.html to verify each Subcontractor’s registration status.

Subcontractor: _______________________________________ License No. / State:

DIR Registration No.: ___________________ DIR Registration Expiration Date: _____________ Address: _______________________________ City: _______________ ______ Zip: ____________ Description of Work: __________________________________________ ________________________ Telephone: ______________ Fax: _______________ Email Address: ___________________________ Bid Item No. & % of each: ______________________________________________________________

*Business License No.

Subcontractor: _______________________________________ License No. / State:

DIR Registration No.: ____________________ DIR Registration Expiration Date: _______________ Address: _______________________________ City: _______________ ______ Zip: ____________ Description of Work: __________________________________________ ________________________ Telephone: ______________ Fax: _______________ Email Address: ___________________________ Bid Item No. & % of each: ______________________________________________________________ *Business License No.

Contractor shall provide all Subcontractor information requested above.

28 *City of Salinas Business License shall be acquired before commencement of work.

Subcontractor:______________________________________ License No. / State:

DIR Registration No.: ___________________ DIR Registration Expiration Date: _____________ Address: _______________________________ City: _______________ ______ Zip: ____________ Description of Work: __________________________________________ ________________________ Telephone: ______________ Fax: _______________ Email Address: ___________________________ Bid Item No. & % of each: ______________________________________________________________ *Business License No.

Subcontractor: _______________________________________ License No. / State: _____________ DIR Registration No.: ___________________ DIR Registration Expiration Date: _____________ Address: _______________________________ City: _______________ ______ Zip: ____________ Description of Work: __________________________________________ ________________________ Telephone: ______________ Fax: _______________ Email Address: ___________________________ Bid Item No. & % of each: ______________________________________________________________ *Business License No.

Subcontractor: _______________________________________ License No. / State: _____________ DIR Registration No.: ___________________ DIR Registration Expiration Date: _____________ Address: _______________________________ City: _______________ ______ Zip: ____________ Description of Work: __________________________________________ ________________________ Telephone: ______________ Fax: _______________ Email Address: ___________________________ Bid Item No. & % of each: ______________________________________________________________ *Business License No.

Subcontractor: _______________________________________ License No. / State: _____________ DIR Registration No.: ___________________ DIR Registration Expiration Date: _____________ Address: _______________________________ City: _______________ ______ Zip: ____________ Description of Work: __________________________________________ ________________________ Telephone: ______________ Fax: _______________ Email Address: ___________________________ Bid Item No. & % of each: ______________________________________________________________ *Business License No.

Contractor shall provide all Subcontractor information requested above.

SIGNED:
(Signature) (Date)
Attach Notary Acknowledgment if signature is not the same as the Proposal signature(s)

29 NON-COLLUSION DECLARATION OF SUBCONTRACTOR
(This information may be submitted with your Proposal. If it is not, and you are the apparent low Bidder, the second or third low Bidder, it shall be subm itted and received by the Public Works Department no later than 5 working days after Bid opening date and/or when the lowest responsible Bidder is known.) State of , }SS County of ,
, being first duly sworn, deposes and says that:

He/she is (owner, partner, officer, representative, or agent) of , hereinafter referred to as the “Subcontractor”;
He/she is fully informed respecting the preparation and contents of the Subcontractor’s Proposal submitted by the Subcontractor to ,
the Contractor for certain work in connection with the
(City or County and State);
The proposal is not made in the interest of or on behalf of any undisclosed person, partnership, company, association, organization, or corporation. The proposal is gen uine and not collusive or sham. The Subcontractor has not, directly or indirectly, induced or solicited any other bidder to put in a false or sham Bid. The Subcontractor has not, directly or indirectly, collud ed, conspired, connived, or agreed with any bidder or anyone else to put in a sham Bid, or to refrain from bidding. The Subcontractor has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the bid price of the Bidder or any other bidder, or to fix any over head, profit, or cost element of the bid price or of that of any other bidder. All statements contained in the proposal are true. The Subcontractor has not, directly or indirectly, submitted his or her proposal price or any breakdown thereof, or the contents thereof or divulged information or data relative thereto, to any corpor ation, partnership, company, association, organization, bid depository, or to any member or agent thereof, to effectuate a collusive or sham Bid, and has not paid, and will not pay, any person or entity for such purpose.

Any person executing this declaration on behalf of a Subcontractor that is a corporation, partnership, joint venture, limited liability company, limited liability partnersh ip, or any other entity, hereby represents that he or she has full power to execute, and does execute, this declaration on behalf of the Subcontractor.

I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct and that this declaration is executed on _______[date], at __________[city], ________[state].

Signed

Title

Attach Notary Acknowledgment

30 STATEMENT OF GOOD FAITH EFFORT FOR LOCAL HIRE
For
The City of Salinas
Public Works Department
(This information may be submitted with your Proposal. If it is not, and you are the apparent low Bidder, the second or third low Bidder, it must be subm itted and received by the Public Works Department no later than 5 working days after Bid opening date and/or when the lowest responsible Bidder is known.) In conformance with Article IV to Chapter 12 of the Salinas Mun icipal Code, each Contractor and Subcontractor shall complete and submit this Statement of Good Faith Effort.

Project Title:

Contractor (or Subcontractor ):

Address:

City: State: Zip:

Contractor (or Subcontractor ) estimates that fifty percent (50%) or more of its workforce, f o r t h i s project, meets the local hire requirements for this contract:

Yes N o If “No”, the apparent successful Bidder (low Bidder) and the second low Bidder shall complete and submit the following form to the office at which bids were received so the information is received by the Department no later than 5 working days after bid opening:

Name and Address of
Local Recruitment
Source
Date of
Recruit.

Contact
Person
Contacted
and Phone
#
Recruitment
For: Trade &
Classification
Number
of
Referrals
Requested
# of Local
Hires as
Result of
Contact
Names and
address of
Local Hire (2)
as a Result of
Contac
t

I certify that the information contained in this form is true and correct, to the best of my knowledge, (Please sign all pages.) (Submitted under penalty of perjury, Salinas City Code, Section 12-31.)

Signature Name (Please Print) Title or Position (Please Print) Date Attach Notary Acknowledgment
Page of
Revision Date 02/20/03 This Form May Be Copied as Needed

32 PART B –
SUCCESSFUL BIDDER’S CONTRACT DOCUMENTS TO BE

SUBMITTED AFTER PROJECT IS AWARDED

33 GENERAL INSTRUCTIONS TO LOW BIDDERS

BIDDER'S SIGNATURES
(A) The Bidder shall sign two documents included in the Bid Documents:

1. Agreement

2. Bidder's Security
(B) The name of the Bidder shall be typewritten or printed below the signature line. The type of legal entity shall be included in the name of the Bidder (examples: i ndividual, sole proprietorship, general partnership, limited partnership, or corporation).

(C) The name and title of all individuals signing for the entity shall be typewritten or printed below the signature line. All signatures shall be notarized with a notary acknowledgment. (D) The Bidder shall provide eviden ce that the individual signing t he document is authorized to bind the legal entity of the Bidder. The notarization does not constitute such proof unless the Bidder is signing as an individual.
(E) If the Bidder is a corporation, proof of authorization shall be established (pursuant to Corporations Code Section 313) if one of the corporate officers listed in column A below and one of the corporate officers listed in column B below both sign the documents.

A B
Chairman of the Board Secretary
o r o r
President AND Assistant Secretary
o r o r
Vice President Chief Financial Officer
o r
Assistant Treasurer
For any other combination of signatures of corporate officers, a copy of the Board minutes, resolution, or articles of incorporation may be submitted to prove that the individuals have the authority to bind the corporation.
(F) If the Bidder is any legal entity other than an individual or c orporation, documentation must be submitted which establishes that the individuals have the legal authority to bind the legal entity of the Bidder.

GENERAL INSTRUCTIONS TO LOW BIDDER – cont.
34 (G) If the legal entity is a Limited Partnership, a Certificate of Limited Partnership (State form LP-1) is sufficient to establish the authority of a single General Partner to bind the Limited Partnership. (H) If the Bidder is a General Partnership, a Certificate of Genera l Partnership or General Partnership Agreement is sufficient to establish the names of all general partners of a General Partnership. (I) All general partners must sign the documents, unless proof is s ubmitted which authorizes an individual partner to bind the other general partners.
(J) If the individual signing the document is signing as a sole pro prietorship, either a Fictitious Business Name Statement or a City of Salinas business License i s sufficient to establish the authority of an individual to bind a sole proprietorship. (K) If the individual or individuals signing the documents are signing on behalf of an entity other than the Bidder, and that other entity is authorized to bind the leg al entity of the Bidder, then documentation must be submitted which establishes that the individuals have the authority to bind the other entity, and that the other entity has the authority to bind the legal entity of the Bidder.

BIDDER'S/CONTRACTOR'S SECURITY
All Bidders’ security (including Bid Bond, Performance Bond, La bor and Materials Bond, and any other required bond) shall be in one of the following forms:
a. Cash
b. Cashier's check made payable to the City
c. A certified check made payable to the City
A bond executed by an admitted surety insurer, made payable to the City in the form of the bonds in the Contract documents. The Power of attorney for the attorney-in-f act of the surety must be current, contain an authorization to bind for at least minimum dollar amount of the bond, and be attached to the bond. The signature of the attorney-in-fact must be notarized.

35 BOND OF FAITHFUL PERFORMANCE
(To be completed and submitted after project award)
KNOW ALL MEN BY THESE PRESENT, that WHEREAS, the City Council o f the City of Salinas, Monterey County, State of California, by Resolution No. (N.C.S. ) passed , 20 , has been awarded to
hereinafter designated as
"Principal," a Contract for constructing

COVENTRY STREET AND VICTOR STREET TRAFFIC CALMING DEVICES WHEREAS, said Principal is required under the terms of said Con tract to furnish a Bond for the faithful performance of said Contract;
Now, therefore, We, the Principal and as
Surety, are held and firmly bounded to the City of Salinas, Mon terey County, California, in the penal sum of
($ ) Dollars, lawful money of the United States, being not less than 100% of the estimated Contract cost of the work, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators a nd successors, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION IS SUCH, that if the above bou nd Principal, his/her or its heirs, executors, administrators, successors or assigns, shall in all things stand to and abide by, and well and truly keep and faithfully perform the covenants, conditions , and agreements in the said Contract and any alterations made as therein provided, on his/her or their part, to be kept and performed at the time and in the manner therein specified, and in all respects according to their true intent and meaning, and shall indemnify and save harmless the City of Salinas, its officers a nd agents, as therein stipulated, then this obligation shall become null and void; otherwise it shall be and remain in full force and virtue.

As a condition precedent to the sa tisfactory completion of the said Contract the above obligation in the amount of not less than 10% of the estimated Contract cost, shall hold good for a period of 1 year after the completion acceptance of the said work, during which time if the above bound Principal, his/her or its heirs, executors, administrators, successors or assigns shall fail to make full complete and satisfactory repair and replacements or totally protect the said City of Salinas from loss or damage made evident during said period of 1 year from the date of acceptance of said work, and resulting from o r caused by defective materials or faulty workmanship in the pro secution of the work done, the abo ve obligation in the amount of not less than 10% of the total bid Proposal cost shall remain in full force and virtue, otherwise the above obligation shall be void. However, nothing in this paragraph to the contr ary notwithstanding, the obligation of the Surety hereunder shall continue so long as any obligation of the Principal remains.

BOND OF FAITHFUL PERFORMANCE - cont.
36 For any moneys earned by the Principal and withheld by the City of Salinas to ensure the performance of the Contract, the Principal may, at his/her request and expense , substitute securities equivalent to the amount withheld in the form and manner and subject to the condi tions provided in Section 22300 of the Public Contracts Code of the State of California.

And the said Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration and addition to the terms of the Contract or to the work to be performed thereunder or the Specifications accompanying the same shall in any wise affect i ts obligations on this bond, and it does hereby waive notice of any such change, extension of time, alte ration or addition to the terms of the Contractor or to the work or to the Specifications.

IN WITNESS WHEREOF the above bond parties have executed this in strument under their seals this day of , 20 , the name and
corporate seal of each corporate party being hereto affixed and these presents duly signed by its undersigned representative; pursuant to authority of its governing body.

Principal Name:

Address:

(Attach Notary Acknowledgment) B y :
(Signature in blue ink)
B y :
(Signature in blue ink)
Surety Name:

Address:

(Attach Notary Acknowledgment) B y :
(Signature in blue ink)
B y :
(Signature in blue ink)

37 PAYMENT BOND
(LABOR AND MATERIAL BOND)
(To be completed and submitted after project award)
KNOW ALL MEN BY THESE PRESENT, that WHEREAS, the City Council o f the City of Salinas, Monterey County, State of California, by Resolution No. (N.C.S. ) passed , 20 , has been awarded to
hereinafter designated as
"Principal," a Contract for constructing

COVENTRY STREET AND VICTOR STREET TRAFFIC CALMING DEVICES WHEREAS, said Principal is required to furnish a bond in connection and with said Contract, providing that if said Principal, or any of his/her or its Subcontractors, shall fail to pay for any materials, provisions, provender or other supplies or teams used in, upon, for or about the performance for the work Contracted to be done, or for any work or labor done thereon of any kind, the Surety of this bond will pay the same to the extend hereinafter set forth;
WHEREAS, said Principal is required under the terms of said Con tract to furnish a Bond for the faithful performance of said Contract;
Now, therefore, We, the Principal and as
Surety, are held and firmly bounded to the City of Salinas, Mon terey County, California, in the penal sum of
($ ) Dollars, lawful money of the United States, being not less than 100% of the estimated Contract cost of the work, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators a nd successors, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION IS SUCH, that if said Principal, his/her or its heirs, executors or administrators, successors or assigns, shall fail to pay for any materials, provisions, provender, or other supplies or teams used in, upon, for or about the performance of the work Contracted to be done, or for any work or labor thereon of any respect to such work or labor, as required by the provisions of Division 2, Part 1, Chapter 5 of the Public Contracts Code of the State of Calif ornia, and provided that the persons, companies or other supplies, teams, appliances or power used in, upon, for or about the performance of the work contracted to be executed or performed, or any person, company or corporation renting or hiring teams or implements or machinery of power for or contributing to said work to be done, or any person who performs work or labor upon same, or any person who supplies bo th work and materials therefore, shall have complied with the provisions of said Government Code, then said Surety will pay the same in or to an amount not exceeding the amount hereinabove set forth, and also will pay in case suit is brought upon this PAYMENT BOND - cont.
38 bond, such reasonable attorney's fee as shall be fixed by the c ourt, awarded and taxed as in the above- mentioned Code provided.

This bond shall inure to the benefit of any and all persons, companies and corporations entitled to file claims under said Government Code, so as to give a right to action to them or their assigns in any suit brought upon this bond.

And the said Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Contract or to the w ork to be performed thereunder or the Specifications accompanying the same shall in anyway affect its obligations of this bond and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the Contract or to the work or to the Specifications.

IN WITNESS WHEREOF the above bond parties have executed this in strument under their seals this day of , 20 , the name and
corporate seal of each corporate party being hereto affixed and these presents duly signed by its undersigned representative; pursuant to authority of its governing body.

Principal Name:

Address:

(Attach Notary Acknowledgment) By:
(Signature in blue ink)
B y :
(Signature in blue ink)
Surety Name:

Address:

(Attach Notary Acknowledgment) By:
(Signature in blue ink)
B y :
(Signature in blue ink)

39 AGREEMENT
(To be completed and submitted for project award)
THIS AGREEMENT, made and entered into this day of , 20 , by and between the CITY OF SALINAS, a municipal corporation of the State of California, hereinafter called "City", and hereinafter called "Contractor",

WITNESSETH
FIRST: Contractor hereby covenants and agrees to furnish and provide a ll labor, materials, tools, appliances, equipment, plant, transportation, and all other thi ngs required or necessary to be furnished, provided or done, and build, erect, construct, and complete the work at the time and in the manner provided, and in strict accordance with the Plans and Specifications therefore, for

COVENTRY STREET AND VICTOR STREET TRAFFIC CALMING DEVICES Adopted by the Council of the City of Salinas on ________________________, 20____, and identified by the signature of Contractor and the signature of the Mayor of the City of Salinas.

SECOND: It is expressly understood and agreed that this Contract consists of the following documents, all of which are incorporated into this Agreement and made a pa rt hereof as fully and completely as if set forth herein verbatim, to wit:
a. Notice to Bidders.
b. Signed and executed Bid and Proposal of Contractor, and if any signed Addendum, as accepted by City.
c. Bidder’s Statement of Financial Responsibility, Technical Ability and Experience. d. Non-Collusion Declaration of Contractor.
e. Insurance Certification.
f. Bidder’s Statement of Subcontractors – Part I.
g. Bidder’s Statement of Subcontractors – Part II.
h. Non-Collusion Declaration of Subcontractor.
i. Statement of Good Faith Effort for Local Hire.
j. Bidder’s List for the City of Salinas Public Works Department. k. Completely executed and signed City of Salinas forms. l. Instructions to Successful Bidder and General Conditions. m. Performance Bond.
n. Payment Bond (Labor and Materials Bond).
o. The aforesaid Plans and Specifications.
p. Design Standards and Standard Specifications and Standard Plans , 2008 Edition, or as amended, or otherwise indicated in the specifications.
q. 2024 State of California Department of Transportation, Standard Specifications (For Construction of Local Streets and Roads), and latest edition. r. California Manual on Uniform Traffic Control Devices (Latest Edition).

AGREEMENT – cont.
40 s. this Agreement.

THIRD: That said Contractor agrees to receive and accept the following prices as full compensation for furnishing all materials and for doing all the work embrace d and contemplated in this Agreement, and as set forth in the Proposal adopted by the City of Salinas, a true copy thereof hereto attached; also, for all loss or damage arising out of the nature of said work, from the action of the elements, or from any unforeseen difficulties or obstructions which may arise or be e ncountered in the prosecution of the work until the acceptance thereof by th e City of Salinas, and for al l risk connected with the work, and for well and faithfully completing the work, and the whole thereof, in t he manner and according to the said Plans and Specifications and the Provisions of this agreement and the requirements of the City Engineer under them, to wit: The prices as set forth in the Proposal of said Contractor for the work to be constructed and completed under this Agreement, which prices shall be considered as though repeated herein.

The Contractor and City hereby agree that the Contractor shall perform the work, and be paid the amount of bid items No.______________________________, specified in th e Proposal of the Contractor, for the as total price of _____________________________________________ ___________________________ ($______________________) Dollars.

The undersigned Contractor further agrees to so plan the work a nd to prosecute it with such diligence that said work, and all of it, shall be completed on or before the expiration of the time specified in the Proposal after the execution of the Contract on behalf of the City of Salinas and the receipt from the City of Salinas of a Notice to Proceed with the work.

FOURTH: The City of Salinas hereby promises and agrees with said Contra ctor to employ, and does hereby employ, said Contractor t o provide the materials and to do the work according to the terms and conditions herein contained and referred to, for the price afor esaid, and hereby Contracts to pay the same at the time, in the manner, and upon the conditions set forth i n the Specifications and the said parties, for themselves, their heirs, executo rs, administrators, successors, and assigns, do hereby agree to the full performance of the covenants herein contained.

FIFTH: No interest in this Agreement shall be transferred by the Contr actor to any other party, and any such transfer shall cause the annulment of this Agreement, so far as the City of Salinas is concerned.

All rights of action, however, for any breach of this Agreement are reserved to City.

SIXTH: The Contractor shall keep harmless and indemnify the City of Sa linas, its officers, agents, and employees from all loss, damage, cost, or expense that aris es or is set up for infringement of patent rights of anyone for use by the City of Salinas, its officers, agents, or employees, or articles supplied by the Contractor under this Agreement of which he/she is not entitled to use or sell. Contractor agrees to, at his/her own cost and expense, defend in court the City, its off icers, agents, and employees in any action which may be commenced or maintained against them or any of the, on account of any claimed infringement of patent rights, arising out of this Agreement.

Contractor shall indemnify and save the City of Salinas, its officers, agents, and employees harmless against all claims for damages to person or property arising out of Contractor's execution of the work, or otherwise by the conduct of the Contractor or its employees, agents, Subc ontractors, or others (including the active and passive negligence of the City, its officers, agents, and employees) in connection with the execution of AGREEMENT – cont.
41 the work covered by this Contract and any and all costs, expenses, attorney's fees, and liability incurred by the City, its officers, agents, or employees in defending again st such claims, whether the same proceed to judgment or not, except only those claims arising from the sole negligence or willful conduct of the City, its officers, agents, or employees. Further, Contractor at its own expense shall, upon written request by the City, defend any such suit or action brought against the City, its officers, agents, or employees.

Contractor shall reimburse the City of Salinas for all costs an d expenses (including but not limited to fees for architects, engineers, attorneys, and other professional and court costs) incurred by the City in enforcing the Provisions of this Section.

SEVENTH: The Contractor agrees to immediately repair and replace all def ective material and workmanship discovered within 1 year after acceptance of final payment by Contractor and to indemni fy said City of Salinas against all loss and damage occasioned by any such defect, discovered within said 1 year, even though the damage or loss may not be ascertained until a fter the expiration thereof. Provided, however, that if such failure of the Contractor to perform shou ld not, by reasonable diligence, be discoverable or discovered within said 1 year, then the obligation of the Contractor to repair and replace said defective material or workmanship shall continue until one year after the actual discovery thereof.

EIGHTH: The Contractor shall procure and maintain for the duration of t his Agreement insurance meeting the requirements specified in Attachment A hereto.

NINTH: Contractor agrees to comply with all applicable federal, state and municipal laws and regulations, including but not limited to California Labor Code Division 2, Part 7, Chapter 1.

Apprenticeship utilization: The Contractor agrees to comply wi th the Department of Apprenticeship Standards of the California Labor Code Section 1777.5 and the following:

Prior to commencing work on the awarded contract, the Contracto r shall submit contract award information (form DAS 140) to all applicable apprenticesh ip program(s) that can supply apprentices to the site of the public work. A copy of this information shall also be provided to the City of Salinas.

The ratio of work performed by apprentices to journeyman employed in a particular craft or trade on the public work shall be no less than one hour of apprentice work for every five hours of journeyman work.

At the end of each month of work on the contract, the Contractor and Subcontractors shall submit a record of utilization of apprentices for the previous months work.

Within 60 days after concluding work on the contract, each Cont ractor and Subcontractor shall submit to the City of Salinas and to the ap prenticeship program a verified statement of the journeyman and apprentice hours per formed on the contract.

TENTH: Contractor agrees to comply with all requirements of the City o f Salinas Local Hiring Preference Ordinance 2330, Salinas City Code Chapter 12, Article IV, which hereby establishes local hiring requirement procedures on Public Works Contracts, with respect to person(s) hired directly by the Contractor and all persons hired by the Contractor’s Subcontractor(s).

AGREEMENT – cont.
42 IN WITNESS WHEREOF, City has caused this instrument to be executed and its corporate name and seal to be hereunto attached by its Mayor, pursuant to resolution theretofore duly adopted by the Council of the City of Salinas, and Contractor has caused this instrument to be executed the day and year first hereinabove written.

CITY OF SALINAS, A Municipal Corporation
ATTEST: BY
Mayor
City Clerk

(Attach Notary Acknowledgment) Contractor (signature in blue ink) NOTE: Please refer to the “General Instructions to Low Bidder” for specific signature requirements.

I hereby approved the form of the foregoing Contract this day o f , 20 .

Attorney for the City of Salinas
Checked by the City Engineer on

City Engineer
ALL SIGNATURES SHALL BE NOTARIZED EXCEPT THOSE OF CITY OFFICIALS’

43 Attachment A

CERTIFICATE INSURANCE REQUIREMENTS
Contractor shall procure and maintain for the duration of the contract, and for three years thereafter, insurance against claims for injuries to persons or damages to property which may arise from or in connection with the performance of the work hereunder by the Contractor, his/her/its officers, agents, representatives, employees, and/or subcontractors.

MINIMUM SCOPE AND LIMIT OF INSURANCE
Coverage shall be at least as broad as:

1. Commercial General Liability (“CGL”): Insurance Services Office (“ISO”) Form CG 00 01 covering CGL on an occurrence basis, including products and completed operations, property damage, bodily injury and personal & advertising injury with limits no less than $2,000,000 per occurrence. If a general aggregate limit applies, either the general aggregate limit shall apply separately to this project/location (ISO Form CG 25 03 or 25 04) or the general aggregate limit shall be twice the required occurrence limit.

2. Automobile Liability: ISO Form CA 0001 covering Code 1 (any auto), with limits no less than $1,000,000 per accident for bodily injury and property damage.

3. Workers’ Compensation: as required by the State of California, with Statutory Limits, and Employers’ Liability insurance with a limit of no less than $1,000,000 per accident for bodily injury or disease.

4. Contractors’ Pollution Legal Liability and/or Asbestos Legal Liability and/or Errors and Omissions (if project involves environmental hazards): with limits no less than $1,000,000 per occurrence or claim, and $2,000,000 policy aggregate, on an annual basis.

If the Contractor maintains broader coverage and/or higher limits than the minimums shown above, the Contractor requires and shall be entitled to the broader coverage and/or higher limits maintained by the Contractor. Any available insurance proceeds in excess of the specified minimum limits of insurance and coverage shall be available to the City.

Self-Insured Retentions
Self-insured retentions must be declared to and approved by the City. At the option of the City, either: the Contractor shall cause the insurer shall to reduce or eliminate such self-insured retentions as respects the City, its officers, officials, employees, and volunteers; or the Contractor shall provide a financial guarantee satisfactory to the City guaranteeing payment of losses and related investigations, claim administration, and defense expenses. The policy language shall provide, or be endorsed to provide, that the self-insured retention may be satisfied by either the named insured or City.

44 Other Insurance Provisions
The insurance policies are to contain, or be endorsed to contain, the following provisions:

1. The City, its officers, officials, employees, and volunteers are to be covered as additional insureds on the CGL policy with respect to liability arising out of work or operations performed by or on behalf of the Contractor including materials, parts, or equipment furnished in connection with such work or operations and automobiles owned, leased, hired, or borrowed by or on behalf of the Contractor. General liability coverage can be provided in the form of an endorsement to the Contractor’s insurance (at least as broad as ISO Form CG 20 10, CG 11 85 or both CG 20 10, CG 20 26, CG 20 33, or CG 20 38; and CG 20 37 forms if later revisions used).

2. For any claims related to this project, the Contractor’s insurance coverage shall be primary insurance coverage at least as broad as ISO CG 20 01 04 13 as respects the City, its officers, officials, employees, and volunteers. Any insurance or self-insurance maintained by the City, its officers, officials, employees, or volunteers shall be excess of the Contractor’s insurance and shall not contribute with it.

3. Each insurance policy required by this clause shall provide that coverage shall not be canceled, except with notice to the City.

4. A copy of the claims reporting requirements must be submitted by Contractor to the City.

5. If the services involve lead-based paint or asbestos identification/remediation, the Contractor’s Pollution Liability policy shall not contain lead-based paint or asbestos exclusions. If the services involve mold identification/remediation, the Contractor’s Pollution Liability policy shall not contain a mold exclusion, and the definition of Pollution shall include microbial matter, including mold.

Acceptability of Insurers
Insurance is to be placed with insurers authorized to conduct business in the state with a current A.M.

Best rating of no less than A: VII, unless otherwise acceptable to the City.

Waiver of Subrogation
Contractor hereby agrees to waive rights of subrogation which any insurer of Contractor may acquire from Contractor by virtue of the payment of any loss. Contractor agrees to obtain any endorsement that may be necessary to affect this waiver of subrogation. The Workers’ Compensation policy shall be endorsed with a waiver of subrogation in favor of the City for all work performed by the Contractor, its employees, agents and subcontractors.

Verification of Coverage
Contractor shall furnish the City with original Certificates of Insurance including an additional insured endorsement and all required amendatory endorsements (or copies of the applicable policy language effecting coverage required by this clause) and a copy of the Declarations and Endorsement Page of the CGL policy listing all policy endorsements to City before work begins. However, failure to obtain the required documents prior to the work beginning shall not waive the Contractor’s obligation to provide them. The City reserves the right to require complete, certified copies of all required insurance policies, including endorsements, required by these specifications, at any time.

45 Subcontractors
Contractor shall require and verify that all subcontractors maintain insurance meeting all the requirements stated herein, and Contractor shall ensure that City is an additional insured on insurance required from subcontractors. For CGL coverage subcontractors shall provide coverage with a form at least as broad as CG 20 38 04 13.

Maintenance of Insurance
Maintenance of insurance by Contractor as specified shall in no way be interpreted as relieving Contractor of its indemnification obligations or any responsibility whatsoever and the Contractor may carry, at its own expense, such additional insurance as it deems necessary.

Special Risks or Circumstances
City reserves the right to modify these requirements, including limits, based on the nature of the risk, prior experience, insurer, coverage, or other special circumstances.

Surety Bonds
Contractor shall provide the following Surety Bonds:

1. Payment bond

2. Performance bond
The Payment Bond and the Performance Bond shall be in a sum equal to the contract price. Bonds shall be duly executed by a responsible corporate surety, authorized to issue such bonds in the State of California and secured through an authorized agent with an office in California.

46 Attachment BLABOR LAW REQUIREMENTS
(CCR Title 8, Section 16421)
This public works project is subject to compliance monitoring a nd enforcement by the California Department of Industrial Relations (“DIR”). All work shall be i n accordance with wage scales and applicable determinations made by the Director of the DIR, as p rovided by Article 2, Chapter 1, Division 2, Part 7 of the Labor Code of the State of California, commencing with §1771.

Penalties for violations may be applied by the DIR pursuant to the Labor Code §1813 and §1815. The Contractor shall indemnify, hold harmless, and defend the City (with counsel reasonably approved by the City) against any claim for damages, compensation, fines, penal ties, or other amounts arising out of the failure or alleged failure of any person or entity (including C ontractor and its subcontractors) to pay prevailing wages as determined pursuant to Labor Code §1720, an d hereby agrees to, §§1771-1774; to employ apprentices pursuant to Labor Code §1777.5 et seq., and/ or to comply with the other applicable provisions of Labor Code §1720 et seq., §§1771-1774, §1777.5 et seq., and the implementing regulations of the DIR in connection with the scope of work. This indemnifi cation section shall survive the expiration of the Term.

The Federal and State Labor Law requirements applicable to the Agreement are composed of, but not limited, to the following items:

1. Payment of Prevailing Wage Rates : All contractors, including subcontractors, shall pay no less than the prevailing rate of wages (Labor Code §1775), including the rates for holidays and overtime work (Labor Code §§1813 and 1815), to all workers employed in t he execution of the contract (Labor Code §1774), pursuant to Labor Code §§1720-1784. The pre vailing rates are those issued as wage determinations by the DIR, for each craft, classificati on and type of work. The current wage rate information can be found at the DIR’s website at:
https://www.dir.ca.gov/oprl/DPreWageDetermination.htm.

Copies of the prevailing rate of per diem wages are on file at City’s Public Works Department (principal place of office). Contractor shall post a copy of the determination of the Director of DIR of the prevailing rate of per diem wages at each job site.

2. Apprentices: Contractor and subcontractors shall employ registered apprent ices on this public works Agreement pursuant to Labor Code §1777.5. All contractors on this project (prime and subcontractors) are required to submit the Division of Apprenti ceship Standards’ (“DAS”) Public Works Contract Award Information (DAS 140) form to all applicab le apprenticeship committees no later than 10 days before commencing work. Additionally, all contractors are required to request registered apprentices (DAS 142 form).

Penalties for failure to pay prevailing wages (for non -exempt projects) and failure to employ apprentices include forfeitures and debarment under Labor Code §§1775 and 1777.7.

3. Certified Payroll Records : All contractors, including subcontractors, must maintain and file certified payroll records (“CPRs”) pursuant to Labor Code §1776. Additionally, all contractors and subcontractors must furnish certified payroll records into the DIR’s Electronic Certified Payroll Reporting (“eCPRs”) database ( https://services.dir.ca.gov/gsp). Penalties apply to Contractor and any Subcontractors for failure to do so under Labor Code §1777.

47 4. Subcontracting: Contractors are required to list all subcontractors hired to perform work on this public works agreement when that work is in an excess of one-ha l f o f 1 p e r c e n t o f t h e p r i m e contractor’s total bid or ten thousand dollars ($10,000.00), whichever is greater.

See Public Contracts Code §4104.

5. Proper Licensing/Registration : All contractors and subcontractors are required to be properl y licensed, in accordance with the P rovisions of Chapter 9 of Div ision 3 of the Business and Professions Code and subject to the requirements of §4104 of the Public Contract Code. In addition, all contractors including subcontractors must submit proof of current registration to perform public work, pursuant to Labor Code §1771.1. Contractors are required to be properly licensed and to require all subcontractors to be properly licensed. Penalties f or employing workers while unlicensed under Labor Code §1021 and under the California Cont ractors License Law, found at Business and Professions Code §7000 et. seq.

6. Job Site Notices: Contractors are required to post all required notices (poster s) on the job site in an area accessible to all workers, including subcontractors. Posters must be readable and placed in visible areas allowing workers to access the posters before, du ring, and after work shifts. Jobsites with multiple locations must in clude a portable poster board to ensure continued access to the information. Posters placed in f oreman, supervisor, or employee vehicles, in an offsite job trailer, or inside a temporary restroom do not meet the posting requirem ent. Posters may be printed from the DIR’s website at: http://www.dir.ca.gov/wpnodb.html.

7. Nondiscrimination in Employment – Equal Employment Opportunity (“EEO”): Employment discrimination is prohibited, pursuant to Labor Code §1777.6, the Government Code, and Title VII of the Civil Rights Act of 1964.

8. Kickbacks Prohibited : Contractors and subcontractors are prohibited from recapturin g wages illegally by accepting or extracting “kickbacks” from employee wages pursuant to Labor Code §1778.

9. Acceptance of Fees Prohibited: Contractors and subcontractors are prohibited from accepting fees for registering any person for public work or for filling work orders on public works contracts, pursuant to Labor Code §§1779 and 1780.

10. Unfair Competition Prohibited: Contractors and subcontractors are prohibited from engaging i n unfair competition as specified under Business and Professions Code §§17200 - 17208.

11. Workers’ Compensation: Contractors and subcontractors must be properly insured for Workers’ Compensation under Labor Code §1861. Contractor hereby represents that Contractor is aware of the provisions of Section 3700 of the Labor Code, which require every employee to be insured against liability for Workers’ Compensation or to undertake self-insurance in accordance with the provisions of that Code, and Contractor will comply with such p rovisions before commencing the performance of the work of this agreement.

OSHA: Contractors and subcontractors must abide by the Occupational, Safety, and Health Laws and regulations that apply.

48 PUBLIC WORKS CONTRACT AWARD INFORMATION (D.A.S.
140)

49 PART C –

CITY OF SALINAS FORMS AND MEMORANDUM

DOCUMENTS

52 CITY OF SALINAS FRINGE BENEFIT STATEMENT

CONTRACTOR OR SUBCONTRACTOR (Please Print) CONTRA CT NUMBER DATE

DEPARTMENT OF INDUSTRIAL REGISTRATION
NUMBER

CONTRACTORS STATE LICENSE

BOARD NUMBER FEDERAL-AID PROJECT NUMBER
TO: RESIDENT ENGINEER OR DISTRICT LABOR COMPLIANCE OFFICER City of Salinas, Department of Public Works
Cindy Lagman, PW Compliance Officer
200 Lincoln Avenue | Salinas | CA 93901

BUSINESS ADDRESS
Labor Compliance uses the follo wing fringe benefits information (shown or referenced on wage rate determinations) paid to or o n behalf of employees in various crafts or classifications to check payroll or apply to force account work on the above contract.

COMPLETE AND SUBMIT THIS FORM WITH THE FIRST CERTIFIED PAYROLL OR WHEN THERE HAVE BEEN CHANGES.

Classification Fringe Benefit Hourly Amount Name and Address of Plan, Fund, or Program

Effective Date

Subsistence and/or Travel Pay

$
Vacation $

Health and
Welfare $

Pension $

Apprentice or
Training Fees $

Other $

Classification Fringe Benefit Hourly Amount Name and Address of Plan, Fund, or Program

Effective Date

Subsistence and/or Travel Pay
$

Vacation $

Health and
Welfare $

Pension $

Apprentice or
Training Fees $

Other $

Classification Fringe Benefit Hourly Amount Name and Address of Plan, Fund, or Program

Effective Date

Subsistence and/or Travel Pay

$
Vacation $

Health and
Welfare $

Pension $

Apprentice or
Training Fees $

Other $

I certify under penalty of perjury that fringe benefits are paid to the approved Plans, Funds, or Programs listed above.

NAME AND TITLE (PLEASE PRINT)

For individuals with sensory disabilities, this document is ava ilable in alternate formats. For alternate format information, contact the Forms Management Unit at (916) 445-1233, TTY 711, or write to Records and Forms Management, 1120 N Street, MS-89, Sacramento, CA 95814.

STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION FORM EM-2501 (REV 05/2019)

SIGNATURE

BUSINESS TELEPHONE NUMBER

54 [THIS PAGE LEFT INTENTIONALLY BLANK]

55 LOCAL HIRING ADMINISTRATIVE MEMORANDUM 98-2
(Updated 07/20/98)
(Updated 03/01/03)

EFFECTIVE DATE: June 19, 1998

SUBJECT: GUIDELINES FOR IMPLEMENTATION OF

LOCAL HIRING FOR PUBLIC WORKS
(Responsible Department – Public Works)

PURPOSE:

These administrative guidelines implement Salinas City Code Cha pter 12, Article IV (the “Ordinance”).

The terms used in these Administrative Guidelines shall be defined as in the Ordinance.

GENERAL POLICY AND PROCEDURE:

A. PERSONS SUBJECT TO GUIDELINES:

These guidelines apply to all Contractors and Subcontractors wh o provide labor or materials for any Public Works Contract that is subject to competitive bidding re quirements, unless prohibited by state or federal law.

B. LOCAL HIRING GOAL:

The Contractor shall make a good faith effort to hire qualified individuals, including any Subcontractor’s work force, who are residents of the Monterey B ay area, so that no less than 50% of the Contractor’s total construction workforce, including any Su bcontractor work force, measured in labor work hours, shall be comprised of Monterey Bay Area residents. The documentation required by these Guidelines is intended to show the Contractor’s, and Subc ontractor’s, good faith efforts towards that goal.

C. PERSONS WHO ARE LOCAL HIRES:

The local hiring goal applies to any “qualified individual” who is in a certified state or federally approved apprenticeship program in an applicable trade or has b ecome a journeyperson in his or her applicable trade with 5 years’ experience or more.” In order to be considered a “local hire” each qualified individual must either:

1. Reside in the Monterey Bay Area (Monterey, Santa Cruz, and S an Benito Counties) prior to the advertisement of the competitive bid on the Public Works Contract, or,

2. Be hired through a local hiring hall that has jurisdiction o ver all or part of the Monterey Bay Area.

D. GOOD FAITH EFFORT:

A good faith effort on the part of the Contractor or Subcontrac tor shall include a review of the current local hire requirements and exis ting staffing for compliance wi th the requirements. If they are not in compliance, or need to do additional hiring for the project, th e Contractor or Subcontractor shall, at a minimum, perform all of the following hiring and documentation efforts:

56 1. Advertise for qualified Monterey Bay Area residents in trade papers and newspapers that have a general circulation within the area;

2. Contact local recruitment sources to identify qualified indi viduals who are Monterey Bay Area residents (Public Works Administration shall maintain a List of Potential Local Hire Recruitment Sources in the Public Works office for review by any interested party. This list shall not be considered a complete record of all sources, but rather a catal ogue of contacts that may provide referral numbers for assisting Contractors in meeting their local hiring obligations. The list shall be updated periodically.); and

3. Document and submit all efforts to meet the ordinance requir ements on forms available in the Bid documents and at the Salinas Public Works Department.

E. NOTICE TO SUBCONTRACTORS:

The Contractor shall include in all Contracts with Subcontracto rs on City Public Works Contracts the language required by Salinas City Code Section 12-32 (6).

F. REQUIRED DOCUMENTATION:

The Contractor and/or Subcontractor shall complete all of the f ollowing documents and submit them within the time specified:

1. Statement Of Good Faith For Local Hire
Every Contractor participating in a competitive Bid on a Public Works Contract shall include a completed and signed Statement of Good Faith for Local Hire for m, which will be supplied in the Bid, documents. If at any time during the term of the Contr act additional employees or Subcontractors are hired for the project, a revised Statement o f Good Faith For Local Hire form shall be completed, signed, and submitted, including any additional employees or Subcontractors, with the weekly prevailing wage s tatement as required in the Pl ans and Specifications of the project for the week immediately following the addition of employees or Subcontractors.

2. Local Hiring Residency Compliance Form
During the term of the Contract, a Local Hiring Residency Compl iance Documentation form shall be completed, signed and submitted with each weekly prevailing wage statement as required in the Plans and Specifications of the project.

G. TRACKING AND MONITORING:

At the time of Bid opening, all documents and Contract language required in the Proposal and agreement shall be checked for compliance with this Article. Any Subcontractors listed in the Proposal shall also have their Contract submissions checked for the appr opriate documentation and language at that time. The City employees opening the Bids shall also deter mine whether the names of any Contractors, Subcontractors, or Bidders have been disqualified by the City and are not authorized to perform City Contracts. If any Bidder or Subcontractor fails to comply with the good faith local hiring provisions required by the ordinance in its bid submissions prior to awards, the Bidder shall be declared to be a non-responsive Bidder by the City. (See Salinas City Code Section 12-33) H. ENFORCEMENT:

If the inspector and/or Public Works Contract administrator for the project have cause to believe there have been violations to the Local Hiring Ordinance, or any other term of the Contract, there shall be an investigation of the issue. Should the investigation show th at violations have occurred, a written

57 Finding of Noncompliance can be presented to the Contractor and subsequently to the Council, along with a Declaration of Irresponsibility, asking the Council to s upport the findings and issue the Declaration. The Contractor shall be notified at least 10 calendar days prior to the Council meeting and has the right to appeal the findings to the Council. (See Salin as City Code Sections 12-34 through 12- 37)

I. CONFLICT:

In the event of a conflict between the requirements of these Guidelines and the Local Hiring Ordinance, the terms of the ordinance shall prevail.

58 LOCAL HIRING RESIDENCY COMPLIANCE

DOCUMENTATION
In conformance with Article IV in Chapter 12 of the Salinas Mun icipal Code, each Contractor and Subcontractor shall complete and attach this Local Hiring Residency Compliance Documentation to each weekly prevailing wage statement as they are submitted to the City Engineer.

Project Title: Project No.:

For The Pay Period Ending:

Contractor (or Subcontractor ): License No.:

Address: City: State: Zip:

1. For each employee, complete residency compliance information by checking appropriate trade:

Employee Name: Classification/Trade:
** Resident of
Monterey Bay Area:

1. Journeyman __ Apprentice __ Other __
Trade: Yes No

2. Journeyman __ Apprentice __ Other __
Trade: Yes No

3. Journeyman __ Apprentice __ Other __
Trade: Yes No

4. Journeyman __ Apprentice __ Other __
Trade: Yes No

5. Journeyman __ Apprentice __ Other __
Trade: Yes No

6. Journeyman __ Apprentice __ Other __
Trade: Yes No

7. Journeyman __ Apprentice __ Other __
Trade: Yes No
**Resident of Monterey Bay Area = Living in Monterey, Santa Cruz, San Benito Counties or hired through a local hiring hall with jurisdiction over the Monterey Bay Area.

2. Calculate total weekly project local hiring percentage based on all labor work hours reported on prevailing wage statement: ................................................................................................ ________ %

3. I certify that the information contained in this form is true and correct, to the best of my knowledge. (Please sign all pages.) (Submitted under penalty of perjury, Salinas City Code, Section 12-31.)
______________________________________________________________ _____________________ Signature Date
______________________________________________________________ _____________________ Name (Please Print) Title or Position (Please Print)
Page_____ of_____
Revision Date March 2003 This Form May Be Copied as Needed

59 PUBLIC WORKS DEPARTMENT BID PROTEST
City of Salinas
Bidder’s attention is directed to the, “CITY OF SALINAS SPECIAL PROVISIONS SECTION 2 PROPOSAL REQUIREMENTS AND CONDITIONS”, Subsection 2-1.04.

Today’s Date:

Project Title: Bid Opening Date:

Contractor:

Contact Name: Phone:

Address:

City: State: Zip:

Chapter 12-39. - Bid protests of the City Code provides: Any Co ntractor who has submitted a Bid but is not the apparent lowest responsible Bidder on a City Contract m ay file a protest. The Bid protest shall be filed with the City Clerk within three working days of the Bid opening. The City Council shall hear the Bid protest prior to adopting a resolution authorizing the Bid award and execution of the Contract. In cases where the Contract is not executed by the City pursuant to City Council resolution, the Bid protest shall be heard by the City Council prior to the time the City issues a N otice to Proceed or the appropriate City official executes the contract on behalf of the City. The prote sting party may protest the Bid award for the City’s or successful Bidder’s failure to comply with the requirements of this article, the Bid documents, or any other applicable provision of this Code. The City Council s hall sustain a Bid protest only if it finds evidence that award of the Bid would violate the Code or other applicable law. The decision of the Council shall be final.

The Contractor listed above wishes to protest one or more of th e bid processes used to make the determination of the lowest res ponsible Bidder. The following is a statement that describes the circumstances and the issues under protest. (Additional sheet(s) can be attached as needed.) Please be as specific as possible:

The following is a statement that clearly describes the remedy being recommended by the above Contractor. (Additional sheets can be attached as needed.)
Please be as specific as possible:

I certify under penalty of perjury that the information contain ed in this form is true and correct, to the best of my knowledge. (Please include this statement on all pages with an authorized signature.)

Signature in blue ink Name (Please Print)

Title or Position (Please Print) Date
Number of Pages (including those attached)

60 CITY OF SALINAS NOTICE OF POTENTIAL CLAIM
DC-CEM-6201 (REV 7/00)

FOR CITY USE ONLY
Received by Date
(For Resident Engineer)

TO CONTRACT NUMBER DATE

(Resident En gineer)

The particular circumstances of this potential claim are described in detail as follows:

The reasons for which I believe additional compensation may be due:

The nature of the costs involved and the amount of the potential claim are described as follows:
(If accurate cost figures are not available, provide an estimate, or describe the types of expenses involved) The undersigned originator (Contractor or Subcontractor as appropriate) certifies that the above statements are made in full cognizance of the California False Claims Act, Government Code sections 12650-12655.

The undersigned further understands and agrees that this potential claim is to be further considered unless resolved, shall be restated as a claim in response to the State s proposed final estimate in accordance with Section 9-1.07B of the Standard Specifications.

SUBCONTRACTOR or CONTRACTOR
(Circle One)

(Authorized Representative)
For Subcontractor notice of potential claim
This notice of potential claim is acknowledged and forwarded by

PRIME CONTRACTOR
(Authorized Representative)
CEM-6201 (REV. 7/00)

I
□ □ □□
□□ □□
□ □ □□
□□ □□
□□ □□
□□ □ □
Local Assistance Procedures Manual Exhibit 16-B
Subcontracting Request
EXHIBIT 16-B SUBCONTRACTING REQUEST

CONTRACTOR NAME COUNTY ROUTE

BUSINESS ADDRESS CONTRACT NUMBER

CITY AND STATE ZIP CODE FEDERAL-AID PROJECT NUMBER
A. SUBCONTRACTOR B. BID ITEM C. PERCENTAGE OF D. SUB LISTED E. CERTIFIED F. DESCRIBE WORK G. DOLLAR AMOUNT (Name, Business Address, Phone) NUMBER (S) BID ITEM AT BID TIME DBE WHEN LESS THAN BASED ON THE BID SUBCONTRACTED 100% OF WORK IS AMOUNT

SUBCONTRACTED
Yes No Yes No
Yes No Yes No
Yes No Yes No
Yes No Yes No
Yes No Yes No
Yes No Yes No
I certify that:
• The Standard Provisions for labor set forth in the contract apply to the subcontracted work. • If applicable, Form FHWA- 1273 of the Special Provisions has been inserted in the subcontracts and should be incorporated in any lower-tier subcontract. Written contracts have been executed for the above noted subcontracted work.

Contractor's Signature
Date
This section is to be completed by the resident engineer.

1. Total of bid items

2. Contractor must perform with own forces (line 1 X contract req. %) $ $

3. Bid items previously subcontracted (taken from previously approved 16-B)

4. Bid items subcontracted (this request)

5. Total bid items subcontracted (line 3 plus 4)

6. Balance of work contractor to perform (line 1 minus 5) $
$
$
$
Approved
RESIDENT ENGINEER’S SIGNATURE DATE
Copy Distribution : Original-Contractor Copy- Resident Engineer Copy- OCR- [email protected] or fax to (916) 324-1949

Page 1 of 2 ends

January 2018

62 PART D –

SPECIAL PROVISIONS

63 CITY OF SALINAS

PUBLIC WORKS DEPARTMENT

COVENTRY STREET AND VICTOR STREET TRAFFIC CALMING

DEVICES
SECTION 1 SPECIFICATIONS AND PLANS
All work to be done under this Contract shall conform to the ap plicable requirements of the STANDARD SPECIFICATIONS, DESIGN STANDARDS, AND STANDARD PLANS, Latest Edition and subsequent revisions, City of Salinas, Public Works Department, herein ref erred to as the “Standard Specifications”.

The most current approved version of the California Manual of U niform Traffic Control Devices (CA- MUTCD), and the State Standard Plans and Specifications, 2024 Edition.

The listing of certain salient sections from the Standard Speci fications and these Special Provisions shall not in any way relieve the Contractor of complying with each an d every section of the Standard Specifications.

In the event of conflicts or discrepancies among the Contract D ocuments, interpretations will be based on the following priorities:

1. Addenda, if any, with later date having precedence over those of earlier date.

2. These Special Provisions.

3. Standard Specifications.

4. State Standard Specifications.

In the case of an inconsistency between Plans and Specification s or within either Document not clarified by addendum, the more elaborate, greater quantity and better quality of work shall be provided unless Owner elects to proceed with a change order for the work at a reduction or increase, as applicable, in the Contract Price.

Wherever in the Special Provisions, Notice to Bidders, Proposal, Contract, or other Contract documents the following terms are used; the intent and meaning shall be interpreted as follows:

State – California Department of Transportation
Department - City of Salinas
City - City of Salinas
Local Public Agency - City of Salinas
Owner - City of Salinas
Engineer – City Engineer

64 SECTION 2 BIDDING
2-1.01 GENERAL
The Bidder's attention is directed to the Provisions in Section 2, "Proposal Requirements and Conditions", of the Standard Specifications and these Special Provisions for the requirements and conditions which he/she must observe in the preparations of the Proposal form an d the submission of the Bid. The City reserves the right to award or withhold award of the project.

Each proposal shall have listed therein the name and address of each subcontractor to whom the bidder proposes to subcontract portions of the work in an amount in ex cess of one-half of one percent of the total bid or $10,000, whichever is greater, in accordance with the Su bletting and Subcontracting Fair Practices Act, commencing with Section 4100 of the Public Contract Code. The bidder’s attention is invited to other provisions by using unauthorized subcontractors or by making unauthorized substitutions.

In addition, each Proposal shall have listed therein the portio n of work that shall be done by each Subcontractor listed. A sheet for listing the Subcontractor is included in the Proposal.

The Contractor, sub recipient, or Subcontractor shall not discriminate on the basis of a person’s political or religious affiliation or belief, non-affiliation or non-belief, race, color, age, sex, sexual orientation, disability, marital, military status (past or present), and national origin in the performance of this Contract. 2-1.02 APPROXIMATE ESTIMATE
The quantities given in the proposal and contract are approxima te only, being given as a basis for the comparison of bids. The City does not, expressly or by implica tion, agree that the actual amount of work will correspond therewith, and reserves the right to increase or decrease the amount of any class or portion of the work, or to omit portions of the work, as may be deemed necessary or advisable by the Engineer. 2-1.03 EXAMINATION OF PLANS, SPECIFICATIONS, CONTRACT AND SITE OF WORK
The Bidder shall examine carefully the site of work contemplate d, the Plans and Specifications, and the Proposal and Contract Forms, therefore. The submission of a Bid shall be conclusive evidence that the Bidder has investigated and is satisfied as to the conditions t o be encountered, as to the character, quality, and scope of work to be performed, the quantities of materials to be furnished, and as to the requirements of the Proposal, Plans, Specifications, and the Contract.

All questions about the meaning or intent of the Contract Docum ents shall be submitted to the City of Salinas through the project page on the PlanetBids website. Res ponses will be issued by Addenda electronically online through the PlanetBids Vendor Portal webs ite and ONLY to Bidders who are registered Prospective Bidders for this project. Questions received less than 9 calendar days prior to the date of the opening of bids will not be answered. Only questions answered by Addenda will be binding.

Oral and other interpretations or clarifications will be without legal effect.

Bidder is cautioned to make such independent investigation and examination as he/she deems necessary to satisfy himself/herself as to conditions to be encountered in t he performance of the work and with respect to possible local material s ources, the quality, and quantity o f material available from such property, and

65 the type and extent of processing that may be required in order to produce material conforming to the requirements of these Special Provisions.

The availability or use of information described within the Pro visions in Section 2-1.06 is not to be construed in any way as a waiver of the Provisions of the first paragraph of the State Standard Specification in Section 2-1.07 of these Special Provisions, and the Bidder i s cautioned to make such independent investigation and examination as he/she deems necessary to sati sfy himself/herself as to conditions to be encountered in the performance of the work and with respect to possible local material sources, the quality, and quantity of material available from such property and the t ype and extent of processing that may be required in order to produce material conforming to the requirements of these Special Provisions.

No information derived from inspection of records of investigation or compilation thereof made by the City of Salinas or from the City Engineer, or their assistants, shal l in any way relieve the Bidder or Contractor from any risk or from properly fulfilling the terms of the Contract. 2-1.04 DIR REGISTRATION
A Contractor or Subcontractor shall not be qualified to bid on, be listed in a bid proposal, subject to the requirements of Section 4104 of the Public Contract Code or engage in the performance of any contract for public work, as defined in this chapter, unless currently regis tered and qualified to perform public work pursuant to Section 1725.5. It is not a violation of this sect ion for an unregistered contractor to submit a bid that is authorized by Sec tion 7029.1 of the Business and Pr ofessions Code or by Section 10164 or 20103.5 of the Public Contract Code, provided the contractor is registered to perform public work pursuant to Section 1725.5 at the time the contract is awarded.

All Contractors (prime and subs) must possess and maintain such registration with DIR in order to be awarded and to perform work on public works project. The follo wing is the link to DIR’s Contractor Registration searchable database: https://efiling.dir.ca.gov/PWCR/Search.action. 2-1.05 SUBCONTRACTING
The percentage of work a prime contractor is required to self-p erform is thirty percent (30%) of the total bid. Contractor shall adhere to Chapter 4 of the Public Contract Code, “Subletting and Subcontracting Fair Practices Act”. Prime contractor shall submit a “Subcontractor Submittal Form” for subcontractors prior to commencement of work. All subcontractors, no matter the tier, or amount of work they will perform, shall be listed on this form. All subcontractors shall be approved prior to their work commencing.

Each subcontractor shall have an active and valid:
 State Contractor License with a classification appropriate for the work to be performed.  Public Works Contractor registration number with the Department of Industrial Relations.  City of Salinas Business License.

2-1.06 EXAMINATION OF SITE
Before submitting a Bid, each Bidder shall carefully examine th e Plans and Specifications relating hereto.

He/she shall also visit the site if the proposed work and shall fully inform himself/herself as to all the existing conditions relating to t he construction and related la bor so that he/she may fully understand the

66 facilities, difficulties, restrictions attendant on the execution of the work, limitations applying to the work, and he/she shall estimate and include in his/her Bid a sum sufficient to cover the cost of all items which are required to attain the completed conditions contemplated in the project. 2-1.07 BID PROTEST AND BID PROTEST FEE
Bid protests are limited to “Bidders” as defined in the Contrac t Documents. Any Bid protest must be submitted in writing to the City Clerk before 5:00 p.m. (as det ermined by the clock in the City Clerk’s Office) within 3 working days after Bid opening.
a) Any protest of the proposed award of Bid to the Bidder deemed the lowest responsible Bidder must be submitted in writing to the City no later than 5:00 p.m. within 3 working days following the date of the Bid opening. If a Bidder protests more than one Bid, the Bidder shall file a separate protest as to each Bid being protested, complying with this section. b) The initial protest document must contain a complete statement of the basis for the protest. The protest must refer to the specific portion of the document or the specific statute that forms the basis for the protest. The protest must include the name, address, an d telephone number of the person representing the protesting party. The protest must be signed a nd submitted under penalty of perjury.
c) The party filing the protest mus t concurrently transmit a copy of the initial protest document and any attached documentation to the Bidder whose Bid is being pro tested, as well as to all other parties with a direct financial interest that may be adversely affected by the outcome of the protest.

Such parties shall include all other Bidders who appear to have a reasonable prospect of receiving an award depending upon the outcome of the protest. Faxed or emailed copies are acceptable, with confirmation of receipt by the Bidder or person to whom it was sent. d) The protestor must have actually submitted a Bid on the project or have been specifically excluded from submitting a Bid due to an action by the City. A Subcontr actor of a party submitting a Bid on this project may not submit a Bid protest. A party may not rely on the Bid protest submitted by another Bidder, but must timely pursue its own protest. e) The City Council shall hear the Bid protest prior to adopting a resolution authorizing the Bid award and execution of the contract. In cases where the contract is n ot executed by the City pursuant to City Council Resolution, the Bid protest shall be heard by the City Council prior to the time the City issues a Notice to Proceed, or the appropriate City offici al executes the contract on behalf of the City. The decision of the Council shall be final.
f) The protestor shall also submit a non-refundable fee of $1,000.00 per protest via certified check made payable to the City of Salinas to reimburse its costs in r eviewing and investigating the Bid protest. Any protest submitted without the fee shall be returned without further action by the City. g) Any protest not complying with this section shall be returned without further action by the City. h) The procedure and time limits set forth in this paragraph are m andatory, are Bidder’s sole, and exclusive remedy in the event of Bid protest. Bidder’s failure to comply with these procedures

67 shall constitute a waiver of any right to further pursue the Bi d protest, including filing a Government Code Claim or any legal proceedings.

SECTION 3 CONTRACT AWARD AND EXECUTION
The Contractor’s attention is directed to the Provisions in Sec tion 3, “Award and Execution of Contract”, of the Standard Specifications and Section 2 “Bidding”, of thes e Special Provisions for the requirements and conditions concerning award and execution of the Contract.

Certificates of Insurance shall be furnished by the Contractor and shall be returned with the signed Contract and Contract bonds within 15 calendar days after receipt. The Notice to Proceed with the work shall not be issued by the City Engineer until all such documents are submitted.

The Contractor shall have 15 calendar days immediately following award of Contract (not Notice to Proceed) to furnish materials submittals.

In determining the lowest “responsible” Bidder, consideration shall be given to the general competency of Contractor in regard to the work covered by the Proposal. To this end, each Proposal shall be supported by the “Bidder’s Statement of Fina ncial Responsibility, Technical Ability, and Experience” on the form(s) found herein. Failure of the Bidder to provide requested infor mation in a complete and accurate manner shall be considered non-responsive resulting in rejection of th e Bid. Additionally, the City of Salinas reserves the right to disqualify or refuse to consider a Propos al if a Bidder is in default for any of the following reasons:
a) Lack of competency and adequate machinery, plant, and other equ ipment, as revealed by the documents requested.
b) Uncompleted work, which in the judgment of the City Engineer, might hinder or prevent the prompt completion of additional work if awarded.
c) Failure to comply with any regulation of the City of Salinas d) Default under previous Contracts.

If awarded, this Contract shall be awarded to the responsible B idder submitting the lowest Bid who meets the financial and technical requirements. The City of Salinas r eserves the right to withhold award of Bid for 90 calendar days from the Bid opening date.

The Contract shall be executed by the successful Bidder and sha ll be returned, together with the Contract bonds, to the Agency so that it is received within 10 working days, not including Saturdays, Sundays and legal holidays, after the Bidder has received the Contract for execution. Failure to do so shall be just cause for forfeiture of the proposal guaranty. The executed Contract documents shall be delivered to the following address: City of Salinas, Attn: City Clerk, 200 Lincoln Avenue, Salinas CA 93901.

68 SECTION 4 SCOPE OF WORK
The work in general, shall include furnishing all labor, materials, tools, equipment, and incidentals required for the construction in accordance with the Plans and these Spe cial Provisions for the work herein, for the COVENTRY STREET AND VICTOR STREET TRAFFIC CALMING DEVICES.

The work, in general, shall include the construction of one (1) traffic circle, one (1) raised crosswalk, furnishing and installation of detectable warning surfaces, cur b drains, drainage channels, street signs on new poles/posts, removal of exis ting pavement markings, removal of existing asphalt concrete pavement, removal of existing concrete ramps, sidewalk, curb and gutter, installation of new concrete sidewalk, curb and gutter, installation of new p avement striping and markings, and all incidental and appurtenant improvements and restorations specified in accordance with the Plans and these Special Provisions.

Such other items or details not mentioned above, but that are r equired by the Plans and Specifications, Standard Specifications, or these Special Provi sions shall be performed, placed, constructed, and/or installed for a complete project. Payment s hall be included in the various items of work and no additional compensation shall be made.

Except for authorized changes in the work, payment for said com plete-in-place finished work or improvement will be made only on the basis of the Contract item of work listed in the Proposal. All other work, including the furnishing of labor, materials, tools, equi pment and incidentals, provided for in these Plans and Specifications and Contract, or required for the prop er completion of the work as a whole, for which no separate payment has been provided shall be an obligat ion of the Contractor and payment therefore shall be considered included in the price paid for the various items of work listed in the Proposal and no additional compensation shall be made.
4-1.01 BID ITEM DESCRIPTION
This section covers details of individual items of the Base Bid to ensure that it is clear as to what is to be included in each item. The costs submitted with each item are to reflect the work to be completed under the bid item only. Payment of all of the following items shall be f or actual materials installed on the job and for the actual work accomplished.

ITEM 1 – MOBILIZATION
Mobilization shall consist of preparatory work and operations, including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for the establishment of all offices, buildings, and other facilities necessary for w ork on the project; and for all other work and operations which must be performed , or costs incurred prior to beginning work on the various contract items on the project site. Payment for mobilization shall include all labor, materials, tools, equipment, and other appurtenances required for a complete-in-place mobilizati on as indicated within these Special Provisions and as shown on the Plans. Payment shall be included in the Contract unit price paid per Lump Sum (LS) for “MOBILIZATION” as listed in the Proposal no additi onal compensation shall be allowed, therefore.

ITEM 2 – TEMPORARY TRAFFIC CONTROL

69 Payment for all temporary traffic control shall include full co mpensation for furnishing labor, materials, tools, equipment; notifying all affected property owners, resid ents, businesses, City of Salinas Police and Fire Departments, City of Salinas, Republic Services (garbage company), MST (Monterey-Salinas Transit), effected school districts, and ag encies; implementation, instal lation and removal of all temporary traffic control, including all required temporary construction signs and posts, city furnished financing signs, lights, barricades, delineators, removal at end of project, necessary m ounting hardware, and other appurtenances required for a complete-in-place temporary traffic control as indicated within these Special Provisions and as shown on the Plans. Payment shall be included in the Contrac t unit price paid per Lump Sum (LS) for “TEMPORARY TRAFFIC CONTROL” as listed in the Proposal and no additional compensation shall be allowed, therefore.

ITEM 3 – FURNISH AND INSTALL TRAFFIC CIRCLE, COMPLETE-IN-PLACE Payment for the construction of a traffic circle shall include furnishing all labor, materials, tools, and equipment for the removal and disposal of existing asphalt concrete, removal of existing pavement striping and markings, construction surveying and staking, adjustment of sanitary sewer manhole, placement and compaction of aggregate base, dowel reinforcements, concrete fo rm work, pouring and finishing of concrete, placement of backfill with top soil, installation of new signs and posts, installation of new pavement striping and markings, and other appurtenances required for a complete-in-place installation of a traffic circle. Payment shall be included in the Contract unit price paid per Lump Sum (LS) for “FURNISH AND INSTALL TRAFFIC CIRCLE” as listed in the Proposal and no ad ditional compensation shall be allowed, therefore.

ITEM 4 – FURNISH AND INSTALL RAISED CROSSWALK, COMPLETE-IN-PLACE Payment for the construction of raised crosswalk shall include furnishing all labor, materials, tools, and equipment for the removal and disposal of existing asphalt conc rete, removal and disposal of existing concrete pedestrian ramps, removal and disposal of concrete sidewalk and concrete curb and gutter, grading, construction surveying and stakin g, concrete form work, placeme nt and compaction of aggregate base, dowel reinforcements, pouring and finishing of concrete sidewalk and concrete curb and gutter, placement of Type “A” HMA, installation of detectable warning surfaces, r elocation of existing signs, removal and disposal of existing poles, installation of new signs and posts , installation of new pavement striping and markings, installation of curb drains and drainage channels, in stallation of cobble splash pad, and other appurtenances required for a complete-in-place installation of a raised crosswalk. Payment shall be included in the Contract unit price paid per Lump Sum (LS) for “FURNISH AND INSTALL RAISED CROSSWALK” as listed in the Proposal and no additional compensation shall be allowed, therefore. 4-1.02 COMPLETE-IN-PLACE
Complete-in-place means that pay ment shall be full compensation for all work necessary to complete the portion of the Contract in its entirety to the satisfaction of the City Engineer, in accordance with the requirements of the Contract. When the basis of payment states the work shall be paid for complete-in- place it shall be the Contractor’s responsibility to determine the elements necessary to complete the work.

When the basis of payment includes a list of elements associate d with the complete-in-place work, the list shall not be construed to limit the work to the listed elements.

70 4-1.03 CHANGES IN WORK
Changes and extra work shall be in accordance with Section 4-1. 05, “Changes and Extra Work”, of the State Standard Specifications.

The Engineer reserves the right to make such alterations, devia tions, additions to or omissions from the Specifications, including the right to increase or decrease the quantity of any item or portion of the work or omit any items or portion of the work, as may be deemed by the Engineer to be necessary or advisable, and to require such extra work as may be determined by the Engineer to be necessary for the proper completion or construction of the whole work contemplated.

Contractor to submit list of required equipment and minimum per sonnel required to complete the work, prior to authorization of any “Time and Material/Force Account” work.

For work done on a “Time and Materials” or “Force Account” basi s, Contractor shall submit all required documents for a specific change within ten (10) calendar days of completing the work.

Outstanding proposals at the end of the project: The Contractor shall submit all outstanding proposals, in the specified format, within ten (10) calendar days of the date established as “Substantial Completion”. The City reserves the right to not process any proposals received a fter that date unless specifically agreed in advance.
4-1.04 CHANGED CONDITIONS
a. Differing Site Conditions

1. During the progress of the work, if subsurface or latent physical conditions are encountered at the site differing materially from those indicated in the contr act or if unknown physical conditions of an unusual nature, differing materially from thos e ordinarily encountered and generally recognized as inherent in the work provided for in the contract are encountered at the site, the party discovering such conditions shall promptly noti fy the other party in writing of the specific differing conditions before the site is disturbed and before the affected work is performed.

2. Upon written notification, the engineer will investigate the co nditions, and if it is determined that the conditions materially differ and cause an increase or decrease in the cost or time required for the performance of any work under the contract, an d adjustment, excluding anticipated profits, will be made and the contract modified in writing accordingly. The engineer will notify the contractor of the determination whether or not an adjustment of the contract is warranted.

3. No contract adjustment which results in a benefit to the contra ctor will be allowed unless the contractor has provided the required written notice.

4. No contract adjustment will be allowed under this clause for any effects caused on unchanged work. (This provision may be omitted by the Local Agency, at their option.) b. Suspensions of Work Ordered by the Engineer

71 Suspensions of work shall be in accordance with Section 8-1.06 “Suspensions” of the State Standard Specifications.
c. Significant Changes in the Character of Work

1. The Engineer reserves the right to make, in writing, at any time during the work, such changes in quantities and such alterations in the work as necessary to satisfactorily complete the project.

Such changes in quantities and alterations shall not invalidate the contract nor release the surety, and the contractor agrees to perform the work as altered.

2. If the alterations or changes in quantities significantly chang e the character of the work under the contract, whether such alterations or changes in are in themselves significant changes to the character of the work or by affecting other work cause such other work to become significantly different in character, an adjustment, excluding anticipated profit, will be made to the contract.

The basis for the adjustment shall be agreed upon prior to the performance of the work. If a basis cannot be agreed upon, then an adjustment will be made either for or against the contractor in such amount as the engineer may determine to be fair or equitable.

3. If the alterations or changes in quantities do not significantly change the character of the work to be performed under the contract, the altered work will be pa id for as provided elsewhere in the contract.

4. The term “significant change” shall be construed to apply only to the following circumstances:
 When the character of work as altered differs materially in kin d or nature from that involved or included in the original proposed construction; or  When a major item of work, as defined elsewhere in the contract, is increased in excess of 125 percent or decreased below 75 percent of the original co ntract quantity. Any allowance for an increase in quantity shall apply only to that portion in excess of 125 percent of original contract item quantity, or in case of decre ase below 75 percent, to the actual amount of work performed.
4-1.05 ITEMS NOT LISTED
Items of labor and materials which are not specifically listed in the Proposal and these Special Provisions as pay items, but which are shown and/or mentioned o n the Plans or are required to be done to complete the overall project, shall be considered inclu ded in other pay items, and no additional compensation will be allowed, therefore.

SECTION 5 CONTROL OF WORK
5-1.01 PERMITS AND LICENSES
The Contractor and approved Subcontractor(s) shall obtain all n ecessary licenses (a valid City of Salinas business license), a valid, current, and in good standi ng Class A (General Engineering) contractor’s license issued by the California Contractor’s State License Board (CSLB) depending on the type of work the contractor is approved for, and a City of Salinas Transportation permit if

72 necessary (including State Permit, if applicable), and any other permits required for the project prior to the commencement of construction.

All City encroachment permit f ees for work performed under this agreement will be waived by the City of Salinas.

Should the permit require specialty testing, payment for necessary materials, and specialty testing including testing results and reports are outside the scope of this Contract and shall be provided by the City of Salinas.

The costs for any re-testing as a result of failed tests shall be borne by the Contractor and no additional compensation shall be allowed, therefore. All testing labs and certified testers shall be approved by the City Engineer prior to retesting.

The City of Salinas will provide the appropriate material testing for this project.

The Contractor shall comply with all requirements of the Division of Industrial Safety and the Department of Industrial Relations.
5-1.02 NOTICE OF POTENTIAL CLAIM
Section 5-1.43 “Potential Claims and Dispute Resolution”, of the State Standard Specifications is amended to read:

Section 5-1.43 Potential Claims and Dispute Resolution – The C ontractor shall not be entitled to the payment of any additional compensation for any act, or fail ure to act, by the City Engineer, including failure or refusal to issue a change order, or for th e happening of any event, thing, occurrence, or other cause, unless he/she shall have given the City Engineer due written notice of potential claim as hereinafter specified. Compliance with this section shall not be a prerequisite as to matters within the scope of the protest Provisions in Section 4-1.05, “Changes and Extra Work”, or the notice Provisions 4.106, “Differing Site Conditions”, or Section 8-1.10, “Liquidated Damages”, nor to any claim which is based on difference in measurements or errors of computation as to Contract quantities.

The written notice of potential claim shall be submitted to the City Engineer prior to the time that the Contractor performs the work given rise to the potential cl aim for additional compensation, if based on an act or failure to act by the City Engineer, or in all other cases within 15 calendar days after the happening of the event, things, occurrence, or other cause, giving rise to the potential claim.

It is the intention of this section that differences between the parties arising under and by virtue of the Contract are brought to the attention of the City Engineer at the earliest possible time in order that such matters may be settled, if possible, or other appropr iate action promptly taken. The Contractor hereby agrees that he/she shall have no right to add itional compensation for any claim that may be based on such act, failure to act, event, thing or occurrence for which no written notice of potential claim as herein required was filed.

Should the Contractor, in connection with or subsequent to the assertion of a potential claim, request inspection and copying of documents or records in the p ossession of the City that pertain

73 to the potential claim, contractor shall make its records of the project, as deemed by the City to be pertinent to the potential claim, available to the City for inspection and copying.

Submission of a claim, properly certified, with all required su pporting documentation, and written rejection or denial of all or part of the claim by owner, is a condition precedent to any action, proceeding, litigation, suit, or demand for arbitration by Contractor. 5-1.03 CLAIMS
Submission of a claim, properly certified with all required supporting documentation, and written rejection or denial of all or part of the claim by the City Engineer, is a condition precedent to any action, proceeding, litigation, suitor demand for arbitration by Contractor. The C ontractor's attention is directed to Section 9-

1.07B “Final Payment and Claims” of the Standard Specifications.

Payment for graffiti, if required, shall be borne by the Contractor, and no additional compensation shall be allowed therefore.
5-1.04 DISCREPANCIES
Should the Contractor at any time discover any discrepancy or m istake in a drawing or Specification, any variation between dimension on dr awings and measurements at sit e, or any lack of dimensions or other information he/she shall report at once to the Engineer for cor rection and shall not proceed with work affected thereby until such correction has been made.
5-1.05 COORDINATION AND COOPERATION
The Contractor shall schedule operations to cooperate and work harmoniously with City forces, Utility Companies, affected property owners and tenants, other Contract ors, and the City of Salinas during the execution of this Contract; coordinating all activities to prev ent unnecessary conflicts, delays, and disruptions to the progress of the project. Scheduling of cons truction activities should be in conformance with Caltrans Construction Site BMP SS-1 (“Scheduling”), with every effort made to perform the Grading and Clearing and Grubbing operations during dry season (May 1 – Sept 30).

The construction progress schedule under Section 8-1.04 of the Standard Specifications is required of this Contract and such schedule shall show the coordination between the Contractor and utility companies to minimize delays to the overall progress of the work.
5-1.06 WORK TO BE DONE BY OTHERS
Miscellaneous items of work not included under the various Prop osal items and as shown on the Plans, "N.I.C." and/or "By Others", will be done by others and is not a part of this Contract.

No additional compensation will be afforded for scheduling or rescheduling of work to allow for the work by others. However, time extension will be granted if Contractor's overall progress is impeded by the work of others.

Work to be done by others shall include but is not limited to relocations and adjustments of utility company facilities shall be performed by various utility companies, if necessary and as required.

74 5-1.07 UTILITY DETERMINATION
The Contractor shall coordinate with the utility companies to l ocate and mark all utility mains and service laterals, including depth within the project area. Contractor shall make full determination of all underground utilities in order to prevent damage or disruption to the existing services during construction.

The Contractor shall contact the Underground Service Alert (“U. S.A.”), telephone number 811, 48 hours in advance before performing any trenching or excavation work.

Contractor shall adhere to all U .S.A.-North rules and regulatio ns. Contractor shall be responsible for protecting all utility facilities (MH lids, water valves, gas valves, etc.).

The Contractor is hereby notified that some utility conflicts, if any, may exist at the start of construction.

The Contractor shall be prepared to schedule his/her work aroun d these conflicts. While the Contractor shall be granted time extensions without penalty for utility de lays if such delays impede his/her overall progress, no extra payment will be made for utility delays, exc ept as provided in these Special Provisions and the Provisions in Section 8-1.07, “Delays”, of the State Standard Specifications. Such time extensions will furnish evidence that his/her overall progress is being de layed. Minor reassignment of work forces or equipment, which may be in conflict with utility's work, shall not be construed as delay in the Contractor's progress.

Utility company's work, if any, shall be done concurrently with this project and shall include work within the street right-of-way. The Contractor shall schedule and coo rdinate his/her installations with the utility companies to avoid any conflicts which may impede the overall p rogress of the project. All removals, installations, and relocations of conflicting underground and above ground utilities shall be executed by the respective utility companies at their expense.

The utilities shown on the Plans are for reference only and are based on utility company records. Known conflicts have been investigated and approximate cover indicate d on Plans, if any. The Contractor shall prosecute the work exercising reasonable care not to damage any such facilities. If the Contractor, while performing the work, discovers facilities not identified on the Plans, he/she shall immediately notify the utility company and the City Engineer in writing within 72 hours.

The Contractor's attention is directed to the existence of cert ain underground facilities that may require special precautions to be taken by the Contractor to protect the health, safety and welfare of workers and of the public. Facilities requiring special precautions include, but are not limited to: natural gas pipelines, underground telephone, cable TV and electric supply system conductors or cables either directly buried or in duct or conduit. The Contractor shall notify the City Engineer at least 24 hours prior to performing any work in the vicinity of such facilities.

Repair of pipes due to accidental or convenience removals (incl uding equipment conflicts) shall be at the expense of the Contractor and no additional compensation will be allowed. 5-1.08 COORDINATION AND COOPERATION WITH UTILITY COMPANIES AND

OTHER CONTRACTORS
The Contractor shall be required to cooperate and work harmonio usly with the public utility companies, other Contractors, affected property owners/tenants and the Cit y of Salinas during the execution of this Contract.

75 Prior to any work, the Contractor shall submit a schedule for his/her work reflecting coordination with other Contractors, if any, and utility companies. All work shall be c oordinated to minimize delays to the overall progress of work.
5-1.09 CONSTRUCTION EASEMENTS
Any work to be done on private properties or requiring access through private properties shall not be done until the City has acquired easements or right-of-entry from the property owner. Prior to starting such work, the Contractor shall verify with the City Engineer that such authority has been granted.

The Contractor will confine their operations within the limitat ions of construction easements or limits as shown on the drawings. If the Contractor's operations result in damage to plantings or any other privately- owned facility outside the limitations of the construction easements or public right-of-way, the Contractor shall, at their expense, repair such damage or indemnify the owner of the damaged property.

If the Contractor negotiates with property owners for use of la nd for construction ope rations outside the limits of the construction easements, he/she shall do so at their own risk and the City will assume no liability for such use of private property. All agreements between the Contractor and private property owners shall be in writing. The Contractor shall commence no work outside t he construction easements until copies of such agreements are furnished to the City.
5-1.10 SOUND CONTROL REQUIREMENTS
The Contractor shall comply with all local sound control and noise level rules, regulations, and ordinances which apply to any work performed pursuant to the Contract.

Each internal combustion engine, used for any purpose on the jo b or related to the job, shall be equipped with a muffler of a type recommended by the manufacturer. No i nternal combustion engine shall be operated on the project without said muffler.

Full compensation for conforming to the requirements of this section shall be considered as included in the prices paid for the various Contract items of work involved and no additional compensation will be allowed, therefore.
5-1.11 GRAFFITI
The Contractor shall remove all graffiti from any equipment and/or structures (any type), new or existi ng within the limits of project within 24 hours daily throughout the contract. The Contractor shall not bring any equipment to the project site with graffiti on it.

Payment for graffiti remediati on, if required, shall be borne b y the Contractor, and no additional compensation shall be allowed, therefore.
5-1.12 WATER POLLUTION CONTROL COMPLIANCE
The Contractor’s attention is directed to the provisions in Sec tion 14-9.02, “Air Pollution Control” and Section 13, “Water Pollution Control”, of the State Standard Specifications. No mud, asphalt, concrete, or cement slurry resulting from saw cutting is allowed to drain into the City’s catch basins.

76 A. The Contractor shall abate dust nuisance by cleaning, sweeping, and sprinkling with water during all phases of construction including weekends, holidays, and any other times as directed by the City Engineer. The use of water or other materials that results in m ud on the public streets shall not be permitted as a substitute for sweeping. The Contractor shall su bmit a contact phone number. The Contractor shall respond to dust control abatement requests wit hin four (4) hours of receiving notification. Should the Contractor fail to respond to such not ice, the City shall cause to have the abatement completed by any available construction team and deduct that cost from any funds due to the Contractor. Payment for dust control abatement and sweeping shall be considered as included in the contract price paid for by the various items of work involved and no additional compensation shall be allowed, therefore.

B. Construction site erosion and sediment control BMP’s must be in place prior to commencement of construction. The requirements of the State’s CGP are intended to be implemented on a year round basis, not just during rainy season (Oct 1 – Apr 30). Acceptable pollution control protection around existing area drains shall be in conformance with Caltrans Stor m Drainage Inlet Protection BMP (“SC-10”).

C. Protection of storm drain inlets and/or adjacent waterways shal l be in place at all times during construction. Tracking of mud, sediment, concrete washout, tras h or other construction-related materials or wastes are not allowed to be discharged in the pub lic right of way, on private streets, or into the City’s storm drain s ystem. Any such discharges shal l be cleaned up at the end of the current work shift in which the discharge occurred, or at the end of the current workday, whichever comes first.
5-1.13 CONTRACTOR RESPONSIBILITIES FOR MAINTAINING TRAFFIC For Traffic Maintenance, the Contractor’s attention is directed to Section 7-1.03, “Public Convenience” and 12-4.02C(9), “Flagging”, of the State Standard Specifications and these Special Provisions. Nothing in these Special Provisions shall be construed as relieving the Contractor from their responsibility as provided in said Section 12-4.02C(9). Contractor shall provide delineators for traffic safety:

A. Whenever immediate action is re quired to prevent impending inju ry, death, or property damage, and precautions which are the Contractor's responsibility have not been taken and are not expected to be taken, the City may, after reasonable attempts to notify the Contractor, cause such precautions to be taken and shall charge the cost thereof against the Contr actor, or may deduct such cost from any amount due or becoming due from the City. City action or in action under such circumstances shall not be construed as relieving the Contractor of their surety from liability.

B. The Contractor shall notify the Police, Fire, Traffic, Monterey -Salinas Transit, Engineering Department of jurisdictional agencies involved, affected property owners and businesses, and news media (radio, TV, newspaper) at least 10 calendar days in advance of any work that will delay traffic. The Contractor shall cooperate with local authorities relative to handling traffic through the area and shall make their own arrangements relative to keeping the working area clear of parked vehicles.

The Contractor shall also be responsible for compliance with additional public safety requirements which may arise during constructi on. They shall exercise specia l caution against dangerous

77 conditions, and shall provide, in stall, and maintain temporary barricades and fencing as may be necessary to protect the public. All construction traffic contr ol devices shall be in place and operational prior to beginning work or different phases through out the contract. During construction and within the area of work barricades, signs, lights, flashers, and other safety devices shall be used by the Contractor to direct vehicular and pedestr ian traffic. During any day between 9:00 a.m. and 4:00 p.m., the Contractor may limit traffic to one lane in each direction with approved traffic control measures, unless otherwise directed by the City Engineer.

During construction and within the area of work barricades, signs, lights, flashers and other safety devices shall be used by the Contractor to direct vehicular and pedestrian traffic. The Contractor shall maintain pedestrian and two-way vehicular traffic at all times. Full closure of any streets will not be allowed unless approved by the City Engineer. Traffic safety devices shall be in good repair at all times. Traffic safety devices in need of repair o r paint shall be removed immediately from the project on order of the Project Inspector. Upon comple tion of work, the Contractor shall promptly remove all signs and warning devices.

C. Personal vehicles of the Contractor’s employees shall not be pa rked on the traveled way or shoulders, including any section closed to public traffic.

Whenever vehicles or equipment are parked within six feet of a traffic lane, the shoulder area shall be closed with florescent traffic cones or portable delineators placed on a taper in advance of the parked vehicles or equipment and along the roadway at 25-foot intervals to a point not less than 25 feet past the last vehicles or piece of equipment. A minimum o f 9 cones or portable delineators shall be used for the taper. A W20-1 (Road Work Ahead) or C24 (Shoulder Work Ahead) sign shall be mounted on a telescoping flag tree with flags. The flag tre e shall be place whereas directed by the City Engineer.

D. Where work is to be performed on private properties (removal and construction of walks, driveway, etc.), the City Engineer will obtain written permission for right-of-entry from the respective owner prior to performing the work. No work shall be commenced by the Contractor until such permission has been granted and until notified by the City Engineer. The Contractor shall be responsible for any and all property damage a nd public liability resulting from their operation on said private properties.

E. Unless otherwise directed by the City Engineer, the Contractor shall at all times maintain vehicular and pedestrian access to all properties fronting City streets. Two-way traffic shall be maintained at all times. The Resident City Engineer shall determine if tempor ary driveways will be necessary within the limits of work during construction. Traffic shall be maintained on one-half of the street at all times.

F. Contractor shall provide delineators for traffic safety until s uch time as all cat tracking has been performed. Cat tracking shall be completed within 8 hours of completed paving/resurfacing at the respective location and shall be maintained in a legible and traffic safety manner by the Contractor until final striping or pavement markings are in place.

Payment - The cost of furnishing all flagmen and police officer s, maintaining traffic as described herein and under the State Standard Specifications in Section 7-1.03, "Public Convenience"," 7-1.04, "Public

78 Safety," and Section 12-4.02C(9), "Flagging", and for complying with the Provisions of these Special Provisions shall be included in t he various items of work liste d in the Proposal, and no additional compensation shall be allowed, therefore.
5-1.14 DEWATERING
Reserved.
5-1.15 INSPECTIONS AND CONTROL OF WORK
In all cases where inspection of the work is required and/or where portions of the work are specified to be performed under the direction a nd/or inspection of the City Eng ineer, the Contractor shall notify the City Engineer at least 48 hours in advance of the time such inspection and/or direction is required.

The Contractor’s attention is directed to Section 6-2 of the St andard Specifications. In addition to the requirements of said section, the Contractor’s representative shall notify the Engineer daily of the following day’s proposed work schedule in order to plan for appropriate inspections. The Contractor’s Representative shall also submit a daily report of the day’s construction activity for review and approval. The daily report shall contain the name, classification, and detailed task listing, of all personnel and equipment, including all Subcontractors, at work that day.

All work and materials shall be subject to inspection at all times by representatives of the City Engineer.

Before starting work, the Prime Contractor shall assign a representative to:

1. Receive the City Inspector/Engineer's orders

2. Implement the City Inspector/Engineer's orders

3. Supervise the workers

4. Coordinate the Subcontractors' work

Payment for submitting the Contractor’s daily report and notification of the next day work schedule under this section shall be considered included in the various contract prices, and no additional compensation shall be allowed, therefore.
5-1.16 CLOSING

OF UNINSPECTED WORK
Contractor shall not allow nor cause any of his work to be cove red or enclosed until it has been inspected and approved by the City Engineer. Should any of his work be enclosed or covered before such inspection and approval he shall uncover the work at his own expense, and after inspection, make all repairs necessary to restore his work to its original condition.
5-1.17 AREAS FOR CONTRACTOR’S USE
The street right-of-way shall be used only for purposes that ar e necessary to perform the required work.

The Contractor shall not occupy the right-of-way or allow others to occupy the right-of-way, for purposes, which are not necessary to perform the required work, unless authorized in writing by the City Engineer. 5-1.18 OPEN AND/OR TRENCH EXCAVATIONS DEEPER THAN FOUR FEET

BELOW THE SURFACE
The Contractor shall promptly and before the following conditio ns are disturbed, notify the City Engineer in writing of any:

79 (1) Material that the Contractor believes may be material that is hazardous waste, as defined in Section 25117 of the Health and Safety Code, which is required to be removed to a Class I, Class II or Class III disposal site in accordance with the existing law.
(2) Subsurface or latent physical conditions at the site differing from those indicated. (3) Unknown physical conditions at the site of any unusual nature, different materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the Contract.

Should the conditions materially differ or do involve hazardous waste, any additional work will be at Section 4-1.05 “Changes and Extra Work” of the State Standard Specifications.

Your attention is directed to Section 9.1.22 “Arbitration”, of the State Standard Specifications. In the event of a dispute as to whether the conditions materially differ or do involve hazardous waste, the Contractor shall continue to proceed with all work to be performed under t he Contract and shall retain all rights provided either by Contract or by law which pertain to the resolution of any dispute or protest. 5-1.19 PRESERVATION OF PROPERTY
The Contractors attention is directed to the Provisions in Sect ion 5-1.36, “Property and Facility Preservation”, of the State Standard Specifications, and these Special Provisions.

Existing trees, shrubs, and other plants, that are not to be removed and are injured or damaged by reason of the Contractor’s operations, shall be replaced by the Contractor in accordance with the requirements within the Provisions in Section 5-1.39C “Landscape Damage” of the State Standard Specifications.

Damaged or injured plants shall be removed and disposed of outs ide the City of Salinas right-of-way in accordance with the Provisions in Section 14-10 of the State Standard Specifications. At the option of the Contractor, removed trees and shrubs may be reduced to chips. The chipped material shall be spread within the highway right-of-way at locations designated by the City Engineer.

Replacement planting of injured or damaged trees, shrubs, and other plants shall be completed not less than 5 working days prior to completion of project, and acceptance of the Contract . Contractor shall provide a 120-day landscape maintenance period for all replacement trees, shrubs, and other plants. 5-1.20 FINAL INSPECTION AND CLEANUP
At the completion of the work, a final inspection will be made by the City Engineer. The Contractor will be responsible for final cleanup of the project area in accorda nce of the Provisions with Section 4-1.13 of the State Standard Specifications.

SECTION 6 CONTROL OF MATERIALS
6-1.01 GENERAL
Attention is directed to the Provisions in Section 6, “Control of Materials”, of the Standard Specifications and these Special Provisions.

80 All materials required to complete the work under this Contract shall be furnished by the Contractor except when otherwise specified herein. Contractor shall provide a schedule of value for all lump sum i tems of work as listed in the Proposal. The schedule of values shall be used for any addition and/or deletion to that particular item of work.
6-1.02 RELATIVE COMPACTION/MATERIAL TESTING
Wherever relative compaction is specified to be determined by Test Method No. Calif. 216 or Test Method No. Calif. 231, the relative compaction shall be determined by Test Method No. 231, in accordance with the Provisions in Section 6-2 of the State Standard Specifications. All tests and frequency of tests shall be in accordance with the Standard Specifications and 2021 Quality Assurance Program. Contractor attention is directed to the Special Provisions in Section 5-1.20B, “Perm its, Licenses, Agreements, and Certifications”, of the State Standard Specifications, concerni ng special testing. Payment for necessary materials and special testing including testing results and rep orts is outside the scope of this Contract and shall be provided by the City of Salinas.
6-1.03 SUBSTITUTIONS
Reference in these Specifications to any article, device, produ ct, material, fixture, form or type of construction by name, make or catalog number is to be interpreted only as establishing a standard of quality, and not to be construed as limiting competition. In such cases, the Contractor may, at their option, use any article, device, product, material, fixture, form, or type of c onstruction equal to that specified. The City Engineer is the final judge of acceptability of proposed substitute and the Contractor proposing substitution shall furnish, at their expense, any data, samples, test, etc., as required by the City Engineer to determine quality of the proposed substitutions.

In addition, all proposed substitutions shall be:

1. Submitted within 10 calendar days following award of the Contract as approved by City Council

2. Proven to the City Engineer to be equal or superior to the specified item in all respects

3. Accompanied by shop drawings and/or complete descriptive information.

All dimensional or functional changes, or changes to other work, which is required by, or are a result of, an acceptable substitution shall be the sole and complete responsibility of the Contractor and shall be made at no additional cost to the City of Salinas.

The Contractor shall make no substitutions of materials or equi pment without written approval of the City Engineer.

SECTION 7 HEALTH AND SAFETY
7-1.01 CONTRACTOR’S RESPONSIBILITY FOR SAFETY
The Contractor certifies that he is experienced and qualified t o anticipate and meet the safety and health requirements of this Project. For informational purposes only the Contractor shall submit to the City a copy of his Injury and Illness Prevention Program. The Contractor shall be responsible for initiating, maintaining and supervising all safety precau tions and programs in connecti on with the Work. This requirement will

81 apply continuously 24 hours a day every day until final acceptance of the Work and shall not be limited to normal working hours. The duties of the City, Engineer and Inspector do not include review of the adequacy of the Contractor’s safety measures in, on, or about the site and vicinity.

A. Safety Officer: The Contractor shall designate a fully traine d and responsible member of his organization at the site whose duty shall be prevention of hazards and accidents and who shall have the authority to direct work for the Contractor.

B. Safety Supervisor: The Contractor shall designate Safety Superv isors for each work site. One Safety Supervisor may be the Safety Officer. The other Safety S upervisors shall work for the Safety Officer. Each shall be fully trained for the type of work being performed and shall have authority to direct the Contractor’s work.
7-1.02 SAFETY MEASURES
The Contractor shall comply with all laws, ordinances, codes, r ules, regulations, and lawful orders of any public authority having jurisdiction for the safety of persons or property or to protect them from damage, injury, or loss. The Contractor shall maintain copies of all do cuments mentioned or referenced in this Section readily available at the site until the work is completed. In the event the Contractor fails to observe any of the necessary safety provisions, the Owner may stop the work and direct the Contractor to comply with the applicable provisions or may order the necessary work to be done by others. All impacts, both monetary and time-related, associated with stoppage of the work in order to comply with the City's directives pertaining to safety requirements, and all costs of having the necessary work done by others shall be borne by the Contractor.
7-1.03 CONFINED SPACE SAFETY
Work performed in or about wastewater facilities, including but not limited to manholes, pipes, tanks, basins, and structures, carries with it the high potential for exposure of workers a nd other persons to hazardous conditions. The Contractor is required to be especially alert to these conditions. These conditions may include, but are not limited to, exposure to hydrogen sulfi de, carbon dioxide, methane, carbon monoxide and other gases; exposure to atmospheres containing in sufficient oxygen to support the human life; exposure to wastewater (sewage) which may contain bacteriological, chemical, and other constituents harmful humans; working in conditions where engulfment or entrapment of personnel may occur (such as in trench excavation); and working in structures with uneven or slippery surfaces and with difficult and limited access. Many of these environments are classified as “c onfined spaces” in the Federal National Institute of Occupational Safety and Health (NIOSH) regulations and/or the State of California’s General Industry Safety Orders. The Contractor shall be fully familiar with, and shall strictly adhere to and comply with, the applicable sections of these documents pertaining to confined spaces. In the event of a conflict between applicable requirements, the more restrictive shall app ly. Solely as an aid to the Contractor, and without assuming any liability for their completeness or for determining if they are the regulations that are currently in effect, the Owner h as included excerpts from the S tate of California General Industry Safety Orders which the City believe are applicable to the Works. Thes e excerpts consist of State of California, Administrative Code, Title 8, General Industry Safety Orders, Articles 107 and 108 are found at the end of these Specifications (provided by the Owner).

82 7-1.04 PERSONAL HYGIENE
Persons involved in the work may be exposed to disease-producin g organisms in wastewater. The Contractor shall require his/her personnel to observe proper hy gienic precautions, including washing of hands and other exposed portions of the body with disinfecting soap and water before eating or smoking.

Contractor shall provide Port-a-Potty for all workers at his/her expense. 7-1.05 PUBLIC SAFETY AND CONVENIENCE
Attention is directed to Section 7-1.03 “Public Convenience” of the State Standard Specifications, and these Special Provisions. Safe and adequate pedestrian zones and cros sing of work shall be maintained at all times. The Contractor shall conduct his/her work so as to insur e the least possible obstruction to traffic, inconvenience to the general public in the vicinity of the work, and to insure the protection of persons and property. No road or street shall be closed to the public exce pt with the permission of the City Engineer and the proper governmental authority. Fire hydrants on or adjacent to the work shall be accessible to fire- fighting equipment. Temporary Provisions shall be made by the Contractor to insure the use of sidewalks, private and public driveways, and proper functioning of gutters, sewer inlets, drainage ditches and culverts, irrigation ditches, and natural water courses.
7-1.06 WARNINGS AND BARRICADES
The Contractor shall provide and maintain barricades, guards, temporary bridges and walkways, watchmen, night lights and danger signals illuminated from sunset to sunr ise, and all other necessary appliances and safeguards to protect the work, life, property, the public, excavations, equipment, and materials. Barricades shall be of substantial construction and shall be painted such as to increase their visibility at night. Suitable warning signs shall be placed and illuminated at night as to show in advance where construction, barricades, or detours exist. Guard rails shall be provided for bridges or walkways over or adjoining excavations, shafts and other openings, and locations where injury may occur. 7-1.07 FIRE PREVENTION
A. Fire Extinguishers and Hoses: The Contractor shall furnish and maintain fully charged fire extinguishers of the appropriate type, supplemented with tempor ary fire hoses wherever an adequate water supply exists, at the places where burning, weld ing, or other operations that may cause a fire are being performed.

B. Flammable, Hazardous, or Toxic Materials: Solvents, gasoline, and other hazardous materials may be in the wastewater (sewage); and therefore, the work site may be hazardous to open flame, sparks, or unventilated occupancy. The Contractor shall take measures to insure his personnel observe proper safety precautions when working in these areas. Only a working supply of flammable, hazardous, or toxic materials shall be permitted in or on any o f the permanent structures and improvements, and shall be removed there from at the end of each day's operations. The Contractor shall store flammable, hazardous, or toxic materials and waste separate from the Work and stored materials for the Works in a manner that prevents spontaneous combustion or dispersion; none shall be placed in any sewer or drain piping nor buried on the City's or other property. The Contractor shall maintain a current and up-to-date copy of all laws, ordin ances, codes, rules, regulations, and lawful orders of any regulatory authority having jurisdiction of control over flammable, hazardous or toxic materials, and at his/her expense shall comply with sa id laws, ordinances, codes, rules, regulations, and lawful orders.

83 7-1.08 SAFETY HELMETS, CLOTHING AND EQUIPMENT
The Contractor shall not permit any person for whom he/she is r esponsible or liable to enter or remain on the site of the Work unless the person is equipped with and wea ring a safety helmet, other protective clothing, and safety equipment as required and shall discharge from the site all persons not so equipped.

The Contractor shall post conspi cuous signs at the appropriate locations warning the public and persons engaged upon the work of this requirement.
7-1.09 HAZARDOUS AREAS
The Contractor shall not permit or allow any person or persons to enter any pipe or space containing hazardous or noxious substances or gases; or where there is an insufficient amount of oxygen to sustain life and consciousness; or any other hazardous area unless equipped with lawful and appropriate safety equipment and life supporting apparatus, and unless those entering are continually monitored and guarded by and in communication with other persons outside the space or area who are equipped in the same way, can give an alarm to others for assistance, and initiate immediate rescue operations in the event of mishap. 7-1.10 EMERGENCIES
A. Work During an Emergency: The Contractor shall perform any and all operations and shall furnish any materials and equipment necessary during an emergency endan gering life or, property and, in all cases, shall notify the City Engineer of the emergency as soon as practicable, but shall not wait for instruction before proceeding to properly protect both life and property. Any additional compensation or extension of Contract Time by the Contractor on account of an emergency shall be applied for to the City.

B. Representatives for Emergencies: The Contractor shall file with the Owner a written list giving names, addresses, and telephone numbers of at least two of his/ her representatives who can be contacted at any time in case of emergency. The representative s shall be fully authorized and equipped to correct unsafe or i nconvenient conditions on short notice. The Contractor shall promptly notify the Owner of all changes in the listing. 7-1.11 SUBMITTALS
Prior to receiving Notice to Proceed, the Contractor shall submit to the City Engineer the following:
1) Safety Best Management Practices Plan
2) Detailed Traffic Control Plan
3) Safe Construction Operation Plan
4) A copy of his/her Injury and Illness Prevention Program Manual 5) A list of safety equipment he/she shall maintain on site 6) The names of his/her Safety Officer and Safety Supervisor(s) wh o shall be responsible for maintaining safety at each work site.
7) Proof of current safety training for all individuals who shall be working on the site.

84 8) A description of any job-specific measures he/she shall be using which are not contained in his/her manual.

The City shall maintain these materials for record purposes. 7-1.12 IMPLEMENTATION
It is the Contractor’s responsibility to follow his/her own saf ety program and provide one or more designated Safety Supervisor(s) at each work site.
7-1.13 PAYMENT
No separate payment shall be made for maintaining health and safety and it shall be considered as included in the prices paid for the various Contract items of work as li sted in the Proposal and no additional compensation shall be allowed, therefore.

SECTION 8 LEGAL RELATIONS AND RESPONSIBILITY
8-1.01 LAWS
Contractor shall comply with laws, regulations, orders, and dec rees applicable to the project. Indemnify and defend the City against any claim or liability arising from the violation of a law, regulation, order, or decree by you or your employees. Immediately report to the City Engineer a discrepancy or inconsistency between the Contract and a law, regulations, order, decree. If the City incurs any fines or penalties because of the Contractor’s failure to comply with the law, regulation, order, or decree, the City shall deduct the amount of the fine or penalty. Immediately notify the City Engineer, if a regulatory agency requests access to the job site or to records. Submit a list of documents provi ded by the agency and issued enforcement actions.
8-1.02 GENERAL
Contractor shall comply with provisions of Section 7, “Legal Re lations and Responsibility to the Public” of the State Standard Specifications.

Contractor shall exercise special caution against dangerous con ditions and provide temporary barricades and fencing as may be necessary to protect the public. During c onstruction within the area of work, barricades, signs, lights, flashers, and other safety devices shall be used by the Contractor to direct vehicle and pedestrian traffic.

The Contractor shall comply with the requirements of CAL-OSHA, the applicable provisions of local, state, and federal regulations governing the project work.

The Contractor shall provide necessary safeguards and shall exe rcise caution against injury or defacement of any existing site improvements and plantings. The Contracto r shall be responsible for any damage resulting from their operations and shall repair or replace such damage at their own expense. No trucks or vehicles of any kind shall be allowed to pass over area unless adequate protection is provided. Unless designated otherwise, all existi ng improvements shall be repair ed or replaced, in kind, at the Contractors expense.

Temporary ramps, backfill, or covers for incomplete trenching/b ackfill operations shall also be furnished by the Contractor at the end of each day’s work for the protection of vehicular and pedestrian traffic.

85 The Contractor shall be responsible for any damage to the work which occurs before final acceptance.

Contractor to securely cover all openings into the systems and protect all apparatus, equipment, or appliance, both before and after being set in place, to prevent obstructions in the pipes and breakage, misuse, or disfigurement of the apparatus, equipment, or appliance. Con tractor shall be responsible for damage to all existing utilities, whether they are indicated on the drawings.

Unless otherwise directed by the City Engineer, the Contractor shall at all times maintain vehicular access to all IWWF facilities.
8-1.03 PUBLIC CONTRACTS CODE 9204 PUBLIC WORKS PROJECT
Contract Dispute Procedures
Sections 9204(e) and (g) of the California Public Contract Code (“PCC”) provides that the text or a summary of PCC 9204, effective January 1, 2017, shall be included in the plans and specifications for any public works projects that may g ive rise to a claim under this section and that Section 9204 applies to contracts for public works projects entered into on or after Ja nuary 1, 2017. In accordance therewith, City of Salinas hereby provides notice and includes the statutory text:
9204. (a) The Legislature finds and declares that it is in the best interests of the state and its citizens to ensure that all construction bus iness performed on a public wor ks project in the state that is complete and not in dispute is paid in full and in a timely manner.
(b) Notwithstanding any other law, including, but not limited t o, Article 7.1 (commencing with Section 10240) of Chapter 1 of Part 2, Chapter 10 (commencing with Sect ion 19100) of Part 2, and Article 1.5 (commencing with Section 20104) of Chapter 1 of Part 3, this se ction shall apply to any claim by a contractor in connection with a public works project.
(c) For purposes of this section:
(1) “Claim” means a separate demand by a contractor sent by reg istered mail or certified mail with return receipt requested, for one or more of the following:
(A) A time extension, including, without limitation, for relief from damages or penalties for delay assessed by a public entity under a contract for a public works project. (B) Payment by the public entity of money or damages arising fr om work done by, or on behalf of, the contractor pursuant to the contract for a public works project and payment for which is not otherwise expressly provided or to which the claimant is not otherwise entitled. (C) Payment of an amount that is disputed by the public entity. (2) “Contractor” means any type of contractor within the meaning of Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Code who ha s entered into a direct contract with a public entity for a public works project.
(3) (A) “Public entity” means, without limitation, except as pr ovided in subparagraph (B), a state agency, department, office, division, bureau, board, or commission, the California State University, the University of California, a city, including a charter city, county, including a charter county, city and county, including a charter city and county, district, special district, public authority, political subdivision, public corporation,

86 or nonprofit transit corporation wholly owned by a public agenc y and formed to carry out the purposes of the public agency.
(B) “Public entity” shall not include the following:
(i) The Department of Water Resources as to any project under the jurisdiction of that department. (ii) The Department of Transportation as to any project under the jurisdiction of that department. (iii) The Department of Parks and Recreation as to any project under the jurisdiction of that department. (iv) The Department of Corrections and Rehabilitation with resp ect to any project under its jurisdiction pursuant to Chapter 11 (commencing with Section 7000) of Title 7 of Part 3 of the Penal Code. (v) The Military Department as to any project under the jurisdiction of that department. (vi) The Department of General Services as to all other projects. (vii) The High-Speed Rail Authority.
(4) “Public works project” means the erection, construction, alteration, repair, or improvement of any public structure, building, road, or other public improvement of any kind. (5) “Subcontractor” means any type of contractor within the mea ning of Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Cod e who either is in direct contract with a contractor or is a lower tier subcontractor.
(d) (1) (A) Upon receipt of a claim pursuant to this section, t he public entity to which the claim applies shall conduct a reasonable review of the claim and, within a period not to exceed 45 days, shall provide the claimant a written statement identifying what portion of the cl aim is disputed and what portion is undisputed. Upon receipt of a claim, a public entity and a contractor may, by mutual agreement, extend the time period provided in this subdivision.
(B) The claimant shall furnish reasonable documentation to support the claim. (C) If the public entity needs approval from its governing body to provide the claimant a written statement identifying the disputed portion and the undisputed portion of the claim, and the governing body does not meet within the 45 days or within the mutually agreed to extension of time following receipt of a claim sent by registered mail or certified mail, return receipt requested, the public entity shall have up to three days following the next duly publicly noticed meeting of the governi ng body after the 45-day period, or extension, expires to provide t he claimant a written statement identifying the disputed portion and the undisputed portion.
(D) Any payment due on an undisp uted portion of the claim shall be processed and made within 60 days after the public entity issues its written statement. If the pu blic entity fails to issue a written statement, paragraph (3) shall apply.
(2) (A) If the claimant disputes the public entity’s written re sponse, or if the public entity fails to respond to a claim issued pursuant to this section within the time pres cribed, the claimant may demand in writing

87 an informal conference to meet and confer for settlement of the issues in dispute. Upon receipt of a demand in writing sent by registered mail or certified mail, return receipt requested, the public entity shall schedule a meet and confer conference within 30 days for settlement of the dispute. (B) Within 10 business days following the conclusion of the mee t and confer conference, if the claim or any portion of the claim remains in dispute, the public entity shall provide the claimant a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed. Any payment due on an undisputed portion of the claim shall be processed and made within 60 days after the public entity issues its written statement. Any disputed portion of the claim , as identified by the contractor in writing, shall be submitted to nonbinding mediation, with the public entity and the claimant sharing the associated costs equally. The public entity and claimant shall mutually ag ree to a mediator within 10 business days after the disputed portion of the claim has been identified in writing. If the parties cannot agree upon a mediator, each party shall select a mediator and those mediator s shall select a qualified neutral third party to mediate with regard to the disputed portion of the claim. Each party shall bear the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator. If mediation is unsuccessful, the parts of the claim remaining in dispute shall be subject to applicable procedures outside this section.
(C) For purposes of this section, mediation includes any nonbin ding process, including, but not limited to, neutral evaluation or a dispute review board, in which an independent third party or board assists the parties in dispute resolution through negotiation or by issuance of an evaluation. Any mediation utilized shall conform to the timeframes in this section.
(D) Unless otherwise agreed to by the public entity and the contractor in writing, the mediation conducted pursuant to this section shall excuse any further obligation under Section 20104.4 to mediate after litigation has been commenced.
(E) This section does not preclude a public entity from requiri ng arbitration of disputes under private arbitration or the Public Works Contract Arbitration Program if mediation under this section does not resolve the parties’ dispute.
(3) Failure by the public entity to respond to a claim from a contractor within the time periods described in this subdivision or to otherwise meet the time requirements of this section shall result in the claim being deemed rejected in its entirety. A claim that is denied by reas on of the public entity’s failure to have responded to a claim, or its failu re to otherwise meet the time requirements of this section, shall not constitute an adverse finding with regard to the merits of the claim or the responsibility or qualifications of the claimant.
(4) Amounts not paid in a timely manner as required by this sec tion shall bear interest at 7 percent per annum.
(5) If a subcontractor or a lower tier subcontractor lacks lega l standing to assert a claim against a public entity because privity of contract does not exist, the contract or may present to the public entity a claim on behalf of a subcontractor or lower tier subcontractor. A subcontractor may request in writing, either on their own behalf or on behalf of a lower tier subcontractor, that the contractor present a claim for work which was performed by the subcontractor or by a lower tier subcontra ctor on behalf of the subcontractor. The

88 subcontractor requesting that the claim be presented to the pub lic entity shall furnish reasonable documentation to support the claim. Within 45 days of receipt o f this written request, the contractor shall notify the subcontractor in writing as to whether the contractor presented the claim to the public entity and, if the original contractor did not present the claim, provide the subcontractor with a statement of the reasons for not having done so.
(e) The text of this section or a summary of it shall be set forth in the plans or specifications for any public works project that may give rise to a claim under this section. (f) A waiver of the rights granted by this section is void and contrary to public policy, provided, however, that (1) upon receipt of a claim, the parties may mutually agree to waive, in writing, mediation and proceed directly to the commencement of a civil action or binding arbitration, as applicable; and (2) a public entity may prescribe reasonable change order, claim, and dispute resol ution procedures and requirements in addition to the provisions of this section, so long as the cont ractual provisions do not conflict with or otherwise impair the timeframes and procedures set forth in this section. (g) This section applies to contracts entered into on or after January 1, 2017. (h) Nothing in this section shall impose liability upon a publi c entity that makes loans or grants available through a competitive application process, for the failure of an awardee to meet its contractual obligations. (i) This section shall remain in effect only until January 1, 2 027, and as of that date is repealed, unless a later enacted statute that is enacted before January 1, 2027, deletes or extends that date. 8-1.04 LABOR NONDISCRIMINATION
Attention is directed to the following Notice that is required by Chapter 5 of Division 4 of Title 2, California Code of Regulations and the City’s Federal Mandated Disadvantage Business Enterprise (“DBE”) Program.

NOTICE OF REQUIREMENT FOR NONDISCRIMINATION PROGRAM
(GOV. CODE, SECTION 12990)
Contractor attention is called to the “Nondiscrimination Clause ”, set forth in the Provisions in Section 7-

1.021(2), “Nondiscrimination”, of the Standard Specifications, which is applicable to all nonexempt State Contracts and Subcontracts, and to the “Standard California Non discrimination Construction Contract Specifications” set forth therein. The Specifications are appl icable to all nonexempt state construction Contracts and Subcontracts of $5,000.00 or more.

Furthermore, the prime Contractor or Subcontractor shall not di scriminate on the basis of race, color, national origin, or sex in the performance of this Contract. F ailure by the Contractor to carry out these requirements is a material breach of this Contract, which may r esult in the termination of this Contract or such other remedy, as recipient (i.e., the City of Salinas) deems appropriate. 8-1.05 WAGE DETERMINATION
All wage scales shall be in accordance with applicable determin ations made by the Director of the Department of Industrial Relations (“DIR”) of the State of California, as provided by Article 2, Chapter 1, Division 2, Part 7 of the Labor Code of the State of California , commencing with Section 1771. In accordance with Section 1773.2 of the Labor Code, copies of the aforesaid determinations of the Director

89 of the DIR are available on the website address http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm They shall apply to the Construction Contract and all Subcontractors thereunder.

The wage rates determined by the Director of DIR and published in the Department of Transportation publication entitled General Preva iling Wage Rates refer to exp iration dates. If the published wage rate does not refer to a predetermined wage rate to be paid after the expiration date, said published rate of wage shall be in effect for the life of this Contract. If the published wage rate refers to a predetermined wage rate to become effective upon expiration of the published wage rate and the predetermined wage rate is on file with the DIR, such predetermined wage rate shall become effecti ve on the date following the expiration date and shall apply to this Contract in the same manner as if it had been published in said publication. If the predetermined wage rate refers to one or more additional expiration dates with additional predetermined wage rates, which expiration dates occur during the life of thi s Contract, each successive predetermined wage rate shall apply to this Contract on the date following th e expiration date of the previous wage rate.

If the last of such predetermined wage rates expires during the life of this Contract, such wage rate shall apply to the balance of the Contract.

The "Statement of Compliance" and "Payroll Report" shall be on forms furnished by the City. Reduced copies of the “Statement of Compliance” and “Payroll Report” fo rms are attached in Part “C” of these Specifications. No other forms shall be accepted.

All contractors and subcontractors must furnish certified payro ll records directly to the Labor Commissioner (aka Division of Lab or Standards Enforcement) on a weekly basis and in the format prescribed by the DIR, which may include electronic submission. 8-1.06 PUBLIC SAFETY
The Contractor shall concern himself with public safety at all times during the life of this contract. Work area shall be clearly identified. Public access through the project shall be by means of well-established and delineated corridors (see traffic control item). Materials shal l be stockpiled in such a manner as to assure no hazard to the public. Tools and equipment shall be likewise kept locked and out of reach. Work area shall be kept free of garbage and other waste.

The Contractor shall provide for the safety of the traffic and the public in accordance with the Provisions in Section 7-1.09, “Public Safety”, of the Standard Specifications and these Special Provisions. 8-1.07 PUBLIC CONVENIENCE
Attention is directed to Section 7-1.08 “Public Convenience” of the Standard Specifications, and these Special Provisions. Safe and adequate pedestrian zones and cros sings of work shall be maintained at all times.
8-1.08 PROTECTION OF SITE
The Contractor shall take all necessary precautions to prevent damage to the adjacent fencing, roadway, utilities, buildings, and other existing improvements, etc., du ring the progress of their work and shall be required to make any repairs resulting from their negligence, and no additional compensation shall be made.

90 Attention is directed to Section 7-1.08, “Public Convenience”, and 7-1.09, “Public Safety”, of the Standard Specification, and these Special Provisions. Safe and adequate pedestrian zones and crossings of work shall be maintained at all times unless otherwise approved by the City Engineer. 8-1.09 DISPOSAL OF MATERIAL
If the Contractor elects to dispose of materials at locations other than those where arrangements have been made by the City, the Contractor shall make arrangements for di sposing of the materials outside the right of way and shall pay all costs involved. Arrangements shall inc lude, but not be limited to, entering into agreements with property owners and obtaining necessary permits, licenses, and environmental clearances.

Before disposing of any material outside the right of way, the Contractor shall furnish to the Engineer satisfactory evidence that the Contractor has entered into agre ements with the property owners of the site involved and has obtained the permits, licenses and clearances.

In those instances, in which the Department has compiled “Materials Information” as referred to in Section 2-1.07, “Job Site and Document E xamination”, of the State Stand ard Specifications, the compilation will include the documents setting forth the arrangement made with some of the property owners for the disposal of material on those owner’s properties.

The Contractor is cautioned to make such independent investigat ion and examination as the Contractor deems necessary to be satisfied as to the quantity and type of materials which may be disposed of on the property and the rights, duties and obligations acquired or und ertaken under the arrangement with the property owner.

Notwithstanding that the Contractor may elect to dispose of mat erials on any such property owner’s property, no material may be disposed of on that property unless the Contractor has first either:
1) Executed a document that will guarantee to hold the owner harml ess from all claims for injury to persons or damage to property resulting from the Contractor's o perations on the property owner's premises and also agree to conform to all other provisions set forth in the arrangement made between the Department and the pr operty owner. The document wil l be prepared by the Engineer for execution by the Contractor, or
2) Entered into an agreement with t he owner of the disposal site o n any terms mutually agreeable to the owner and the Contractor; provided that the Contractor shal l furnish to the Engineer a release, in a form satisfactory to the Engineer, executed by the owner, relieving the Department of any and all obligations under the Department's arrangement with the owner.

SECTION 9 PAYMENT
9-1.01 BEGINNING OF WORK, TIME OF COMPLETION, LIQUIDATED DAMAGES

AND TEMPORARY SUSPENSION OF WORK
The Contractor’s attention is directed to the Provisions of Sec tion 8, “Prosecution and Progress”, Section 8-1.02, “Schedule”, Section 8-1.04, “Start of Job Site Activiti es”, and Section 8-1.10, “Liquidated Damages” of the State Standard Specifications and the following Provisions:

91 The Contractor shall begin the work within 15 calendar days after the Notice to Proceed by the City Engineer and the Contractor sha ll diligently prosecute the work to completion on or before the expiration of 40 Working Days . This does not include the allotted 30 calendar days for mater ial submittals, the ordering, and receiving of materials.

A working day shall be any day other than a legal holiday, Satu rday, Sunday, or designated non-workday on which the normal working forces of the Contractor should proceed with regular work for at least 6 hours toward completion of the Contract. If the Contractor schedules work on designated non-work day(s) such as weekend or holidays, the Contractor shall reimburse the C i t y o f S a l i n a s f o r i n s p e c t i o n services rendered by the City of Salinas or its consultant.

The Contractor shall pay to the City of Salinas the sum of $1,300.00 per day for each and every calendar day delay in finishing the work in excess of the time of completion prescribed above.

Before work may begin, a pre-construction conference/virtual meeting shall be held with the City Engineer or their designee for the purpose of discussing with the Contra ctor the scope of work, Contract Plans, Specifications, existing conditions, materials to be ordered, equipment to be used, and all essential matters pertaining to the prosecution of and the satisfactory completion of the project as required. The Contractor’s representative at this conference/virtual meeting shall include all major superintendents for the work and may include major Subcontractors.

Section 8-1.04B of the State Standard Specifications is amended by adding the following:

The Contractor shall notify the City Engineer, in writing, of t heir intent to begin work at least 5 calendar days in advance before work is begun for this project. The notice shall be delivered to City Engineer’s Office and shall specify the date the Contractor intends to start. If the project has more than one location of work, a separate notice shall be given for each location.

Section 8-1.04B is further amended to read:

Notice in writing of the Contractor’s intention to start work p rior to approval, specifying the date on which he/she intends t o s t a r t , s h a l l b e g i v e n t o t he City Engineer at least 5 calendar days in advance.

The Contractor shall immediately comply with written order of t he City Engineer to suspend work wholly or in part in accordance with the Provisions in Section 8-1.06 of the State Standard Specifications and these Special Provisions.
9-1.02 SCHEDULE OF VALUES
The Schedule of Values shall conform to the Provisions in Secti on 9-1.16B, of the State Standard Specifications, and these Special Provisions.

The City Engineer shall be furnish ed a Schedule of Values for e ach Contract Lump Sum item of work described within these Special Provisions and where noted in these Special Provisions.

92 The Schedule of Values shall be submitted to the City Engineer for approval within 15 calendar days after the Contract has been approved. The Schedule of Values shall be approved, in writing, by the City Engineer before any partial payment for any of the lump sum items of work shall be made. 9-1.03 MEASUREMENT AND PAYMENT
Payment for all labor, materials, tools, equipment and other ap purtenances required for the proper, substantial and complete-in- place project construction for COVENTRY STREET AND VICTOR STREET TRAFFIC CALMING DEVICES as shown on the Plans and/or outlined in these Special Provisions.

Except for authorized changes in the work, payment for said com plete-in-place finished work or improvement shall be made only on the basis of the Contract ite m of work listed in the Proposal. The various Contract item prices paid for the work required, for COVENTRY STREET AND VICTOR STREET TRAFFIC CALMING DEVICES , complete-in-place, including full compensation for furnishing all labor, materials, tools, equipment, and incident als, for doing all the work provided in these Plans and Specifications and Contract, or required for the prop er completion of the work as whole, for which no separate payment has been provided shall be a suppleme ntary obligation for the Contractor item of work listed in the Proposal.
9-1.04 PROGRESS PAYMENTS AND RETENTION
The Contractor's attention is directed to Section 9, “Measureme nt and Payment” of the Standard Specifications.

The City shall retain 5% of such estimated value of the work done and 5% of the value of materials so estimated to have been furnished and delivered and unused and f urnished and stored as aforesaid as part security for the fulfillment of the Contract by the Contractor.

The Contractor shall submit Subcontractor and/or supplier’s wai ver of liens as required under Civil Code Article 8122-8138. The waiver sha ll be "conditional" before pay ment and "unconditional" after payment.

The unconditional waivers ensure that all subcontractors are promptly paid.

As provided in Section 22300 of the Public Contract Code and Se ction 10263 of the Government Code, Contractor may request that any retention to be withheld during the course of a project is paid to an escrow agent at the Contractor's expense. Should the Contractor make such request, it will be required that an appropriate Escrow Agreement as provided in said government cod es be fully executed prior to any payment of retention withheld or to be withheld. The City Engi neer or their delegate is authorized to execute said Escrow Agreement on behalf of the City.

The Contractor shall submit the progress payment pay application to the Engineer for review and approval.

The Engineer shall review it within seven (7) calendar days of receipt. The Engineer shall either deny and return the progress payment pay application to the Contractor f or correction or recommend approval and forward it to the City for processing. The required attachment s to the monthly progress payment pay application shall include:

93 a. Certified Payroll Reports : All current payroll reports and statement of compliance for t he Contractors and all subcontractors (to be completed through the l a s t d a y o f w o r k i n t h e p a y application)
b. Daily Reports : All current Daily Reports for the Contractor, all Subcontract ors, and owner operators. Daily reports shall contain the name, classification , and detailed task listing of all personnel and equipment, includi ng all subcontractors and owner operators (to be completed through the date of pay application)
c. Quantity Calculations : Certified quantity calculations to justify all pay quantities and amount requested.
d. Monthly Schedule: The Contractor shall submit an updated, revised construction schedule to the Engineer with each pay application.
e. Unconditional Waiver of Lien Releases : The Contractor shall submit Subcontractor and/or supplier’s waiver of liens as re quired under Civil Code Article 8122-8138. The waiver shall be “conditional” before payment and “unconditional” after payment on forms set forth in the statute.

Failure to provide any of the documents as listed above will re sult in the Engineer returning the monthly pay application to the Contractor with no action.

Payment for all labor, materials, tools, equipment, and other a ppurtenances required for the proper, substantial, and complete-in-place for the project as shown on the Plans and/or outlined in these Special Provisions.
9-1.05 PROMPT PROGRESS PAYMENT TO SUBCONTRACTORS
A prime Contractor or Subcontractor shall pay any Subcontractor not later than 7 calendar days of receipt of each progress payment in accordance with the Provision in Se ction 7108.5 of the California Business and Professions Code concerning prompt payment to Subcontractor s. The 7 calendar days are applicable unless a longer period is agreed to in writing between the Cont ractor and the City Engineer. Any delay or postponement of payment over 30 calendar days may take place only for good cause and with the City Engineer prior written approval. Any violation of Section 7108.5 shall subject the violating Contractor or Subcontractor to the penalties, sanction, and other remedies of that Section. Federal law (49 CFR 26.29) requires that any delay or postponement of payment over 30 calendar day of receipt of each payment may take place only for good cause and with the City’s prior written approval. These requirements shall not be construed to limit or impair any contractual, administrative, or judicial remedies otherwise available to the prime Contractor or Subcontractor in the event of a dispute inv olving late payment or nonpayment by the prime Contractor, deficient subcontract performance, or noncompliance by a Subcontractor. This Provision applies to both Contractors and Subcontractors.
9-1.06 PROMPT PAYMENT OF FUNDS WITHHELD TO SUBCONTRACTORS The City of Salinas shall hold re tainage from the prime Contrac tor and shall make prompt and regular incremental acceptances of portions, as determined by the City of Salinas, of the Contract work, and pay retainage to the prime Contractor based on these acceptances. The prime Contractor, or Subcontractor, shall return all monies withheld in retention from all Subcontractors within 7 calendar days for construction

94 contracts and 15 calendar days for consultant contracts after r eceiving payment for work sati sfactorily completed and accepted including incremental acceptances of portions of the Contract work by the City of Salinas. Any delay or postponement of payment may take place o nly for good cause and with the City Engineer prior written approval. Any violation of this provision shall subject the violating prime Contractor or Subcontractor to the penalties, sanctions, and other remedies specified in Section 7108.5 of the California Business and Professions Code and Section 10262 of the California Public Contract Code for construction contracts, and Section 3321 of the California Civil Code for co nsultant contracts. This requirement shall not be construed to limit or impair any contractual, administrative, or judicial remedies otherwise available to the prime Contractor or Subcontractor in the event of a disp ute involving late payment or nonpayment by the prime Contractor; deficient subcontractor performance and/or noncompliance by a Subcontractor. 9-1.07 INCREASE OR DECREASE QUANTITY
The City reserves the right to increase or decrease the quantit y specified in the Proposal, as deemed necessary, by more than 25% and eliminate any item or work without the adjustment of Contr act Unit Prices.
9-1.08 COMPENSATION ADJUSTMENTS FOR OIL PRICE INDEX FLUCTUATIONS There shall be no compensation adjustments for oil price fluctuations for this project. 9-1.09 ARBITRATION
Contractor attention is directed to Section 9-1.22 “Arbitration,” of the State Standard Specifications. In the event of a dispute as to whether the conditions materially diff er or do involve hazardous waste, the Contractor shall continue to proceed with all work to be perfor med under the Contract and shall retain all rights provided either by Contract or by law which pertain to the resolution of any dispute or protest.

Arbitration shall be initiated by a Complaint in Arbitration ma de in compliance with the requirements of said regulations. A Complaint in Arbitration by the Contractor shall be made not later than 180 calendar days after the date of service in person or by mail on the Contractor of the final written decision by the Department of the claim.

SECTION 10 CONSTRUCTION DETAILS
SECTION 10-1 GENERAL
10-1.01 ORDER OF WORK
All work under this project shall be scheduled, coordinated and executed as necessary to permit construction to be completed within the constraints of the project. The Contractor and utility companies shall coordinate and schedule their operations to minimize disruptions or delays . The utility company's Contractors shall perform their utility work prior to overlay, new road section, rough grading, clearing and grubbing.

All operations shall be coordina ted to eliminate any possibilit y of damage, or unnecessary removal, replacements and/or modifications to existing facilities or to facilities constructed under this project.

The Contractor shall not begin work until all materials are on hand, unless approved otherwise by the City Engineer.

95 The Contractor shall submit a Traffic Control Plan of his/her proposed construction operation together with a diagram indicating his/her layout for traffic control. This Plan shall be subject to the approval of the City Engineer and shall be submitted at least 10 calendar days prior to the beginning of any construction of any work. No work shall begin until the Plans have been approved by the City Engineer.

The Plan shall show the type of location of advanced warning signs for construction phasing, construction, scheduling, details, lane closures and other items deemed neces sary by the City Engineer and shall be in accordance with the Provisions in Section 7 "Legal Responsibilities" of these Special Provisions. 10-1.02 BASELINE SCHEDULE
A baseline schedule shall be prepared by the Contractor for this Contract and shall conform to the Provisions in Section 8-1.02C(6) "Baseline Schedule" of the State Standard Specifications and shall be delivered to the City Engineer at the pre-construction meeting. No work shall begin until the Baseline Schedule has been approved by the City Engineer.

Such baseline schedule (bar chart type or other) shall show coo rdination of major portions of the work including utility relocations/adjustments and other related work by others.

The Contractor shall schedule operations in cooperation with ot her Contractors and the utility companies to avoid unnecessary conflicts, delays, and disruptions to the progress of this project. Attention should be given to scheduling of all land disturbance activities in dry season (May 1 – Sept 30). 10-1.03 PROGRESS SCHEDULE
A progress schedule shall be prepared by the Contractor for thi s Contract and shall conform to Section 8-

1.02 “Schedule” of the State Standard Specifications, as applic able, and shall be delivered to the City Engineer at the pre-construction meeting. No work shall begin until the Baseline Schedule has been approved by the City Engineer.

Such progress schedule (bar chart type or other) shall show coo rdination of major portions of the work including utility relocations/adjustments and other related work by others.

The progress schedule shall be amended as necessary if progress varies significantly from the schedule and at a minimum, every four weeks.

The Contractor shall schedule operations in cooperation with ot her Contractors and the utility companies, as applicable, to avoid unnecessary conflicts, delays, and disruptions to the progress of this project. 10-1.04 WORKMANSHIP
All work performed under this Contract shall be of the highest quality of the trade and the Contractor shall employ only workers who are skilled and thoroughly familiar with the type of improvements proposed. 10-1.05 WARRANTIES
All equipment furnished by the Contractor shall be guaranteed t o the City of Salinas by the manufacturers for a period of not less than one (1) year following the date of acceptance of all system installations. T he contractor shall immediately repair and/or replace all defectiv e materials and workmanship discovered within one year after acceptance by the City.

96 10-1.06 OBSTRUCTIONS
Attention is directed to Section 8-1.10 “Utility and Non-Highwa y Facilities” and Section 15, Existing Highway Facilities, of the Standard Specifications and these Special Provisions. 10-1.07 UNDERGROUND OBSTRUCTIONS
Other than utility work, the removal and relocation of all unde rground obstructions, including but not limited to sprinkler systems, water mains or electrical conduit s shall also be the responsibility of the Contractor and no additional compensation will be allowed, therefore.

Repair of pipes, electrical conduits and other appurtenances due to accidental or convenience removals shall be at the expense of the Contractor.

Adjust existing utility frames, covers, and manholes to new gra de as shown on the Plans and as specified in Section 15-2.05A, “Frames, Covers, Grates, and Manholes”, of the Standard Specifications.

Payment for the adjustment of utility frames, covers, and manholes shall be included in the prices paid for the various Contract items of work as listed in the Proposal an d no additional compensation shall be allowed, therefore.
10-1.08 SUBMITTALS/DRAWINGS OF RECORD/CRITERIA FOR FURNISHING

PLANS AND SPECIFICATIONS TO CONTRACTOR
The Contractor shall review, stamp, and sign with his/her a pproval and submit, with promptness and in orderly sequence so as to cause no delay in the work or in the work of any Contractor, all shop drawings and samples required by the Contr act Documents or subsequently by the City Engineer as covered by modifications. Shop drawings and samples shall be properly identified as specified, or as the City Engineer may require. At the time of submission, the Contractor shall especially inform the City Engineer in writing of any deviation in the shop drawings or samples from the requi rements of the Contract Documents. (The mere inclusion of the information is not sufficient notice.) Shop drawings, including manufacturer's literature, catalog cuts, or other printed material shall be entitled with the name of the product on each sheet and shall otherwise be identified by listing the particular Division, Section Article or reference of the work pertaining thereto. Differing items shall not be submitted on the same sheet.

By approving and submitting shop drawings and samples, the Contractor thereby represents that he/she has determined and verified all field measurements, field construction criteria, materials, catalog number and similar data, or shall do so, and that he/she has checked and c oordinated each shop drawing and sample with the requirements of the work and the Contract Documents.

Allow two weeks minimum for review. Allow additional time if p rocessing must be delayed to permit coordination with subsequent submittals. Allow one week for reprocessing each submittal.

No extension of Contract time will be authorized because of fai lure to transmit submittals sufficiently in advance of the work to permit processing.

The City Engineer shall review and approve any shop drawings an d samples with reasonable promptness as to cause no delay, but only for conformance with the design concept of the project and with the

97 information given in the Contract Documents. The City Engineer' s approval of a separate item shall not indicate approval of an assembly in which the item functions.

The Contractor shall make any corrections required by the City Engineer and shall resubmit the required number of corrected copies of shop drawings or new samples unti l approved. The Contractor shall direct specific attention in writing or on resubmitted shop drawings to revisions other than the correction requested by the City Engineer on previous submissions. Corrected shop dr awings shall be resubmitted in the same manner as called for above.

The City Engineer's approval of shop drawings or samples shall not relieve the Contractor of responsibility for any deviation from the requirements of the Contract Documents unless the Contractor has specifically informed the City Engineer in writing of such deviation at the time of the submission, and the City Engineer has given written approval to the specified deviation; nor shal l the City Engineer's approval relieve the Contractor form responsibility for errors or omissions in the shop drawings or samples.

No portion of the work requiring a shop drawing submission, inc luding ordering of materials, shall be commenced until the submission h as been approved by the City En gineer. All such portions of the work shall be in accordance with approve d shop drawings and samples. Any work placed without submittals being made shall be replaced by Contractor at his/her own expen se, if directed by the City Engineer.

Whenever work is specified to conform to approved samples on fi le in the City Engineer’s Office, conformance shall be required in all respects and the City Engineer's decision in respect to such conformity shall be final.

Where Specifications require manufacturer's printed installation directions, submit duplicate copies of such directions for approval.

The Contractor shall provide and maintain an up-to-date complet e "RECORD DRAWING" record on a separate set of construction Plans which shall show every chang e from the original drawings and Specifications. Prints for this purpose may be obtained from the City Engineer. This set of drawings is to be kept on the site and to be used only as a record set.

These Plans shall also serve as work progress sheets, and the C ontractor shall make neat and legible annotations thereon daily as the work proceeds, showing the wor k as actually installed. These drawings shall be available at all times for inspection and to be kept in a location designated by the City Engineer.

At the project pre-construction meeting, the City Engineer shal l furnish two sets of the Plans and Specifications to the Contractor and an additional set for each of the listed Subcontractors. If additional sets are requested, the Contractor will be charged for any extra sets requiring reproduction and binding at the rate specified in the Notice to Bidders.

On or before the date of final inspection, the Contractor shall deliver the corrected and completed "RECORD DRAWING" to the City Engineer. Contractor shall furnish in duplicate two binders of all manufacturers' literature brochures, manuals, parts list, instr uctions, etc., for all electrical and mechanical equipment as required to be furn ished and installed by the Cont ractor. Submissions of this literature in a haphazard method will not be acceptable. Failure to submit "RECORD DRAWING" shall be caused to withhold final payment and not accept the project.

98 Record Plans are required under Section 8-1.03 and may be recor ded and submitted via readily readable electronic media such as CD, DVD or USB memory.

The “RECORD DRAWING” shall be accurate and up to date with approval of the City Eng ineer before each progress payment shall be made.
10-1.09 WATERING
Watering, if any, shall conform to the provisions in Section 17, “Watering”, of the Standard Specifications, except that full compensation for developing water supply shall be considered as included in the prices paid for the various Contract items of work involving the use of wat er and no separate payment will be made.

Where applicable, City of Salinas Code Chapter 36A Water Conservation will take priority. 10-1.10 CONSTRUCTION SURVEYS AND STAKING
The Contractor shall provide the appropriate construction staking to establish lines and grades as necessary to permit satisfactory completion of the Contract work. Payment for construction surveys and staking shall be considered as included in the prices paid for the various Co ntract items of work and no additional payment shall be allowed, therefore.
10-1.11 SURVEY MONUMENTS
Contractor shall protect survey monuments on and off the right of way. Upon discovery of a survey monument not identified and located by the City, immediately:

1. Stop work near the monument

2. Notify the Engineer
Do not resume work near the monument until authorized.

Should a monument be disturbed or damaged, the Contractor shall notify the Engineer and shall restore, replace, repair, or reestablish monument or accessories to monu ments. All construction surveying shall be performed by or under the direction of a licensed Land Surveyor or Professional Engineer, who is authorized to practice land surveying, retained or provided for by the Contractor.

The Contractor shall retain a Licensed Surveyor, or a Registere d Engineer authorized to practice land surveying within the State of California to research, locate and reset Survey Monuments, including record monuments that are missing. The Contractor is responsible for t he filing and recording of the Survey Monuments. The Contractor shall provide the City with a final copy of Record of Survey or Corner Record as filed.

City monuments shall be as specified in the Standard Specifications per Section 81.

All costs to the Contractor for protecting, removing, restoring , repairing, or reestablishing monuments or accessories to monuments or costs associated with the preparati on or filing of Corner Records pursuant to Sections 8700 and 8806 of the Bus iness and Professional Code, a nd submitting copies of recorded corner records to the City, shall be included in the prices paid for the various Contract items as listed in the Proposal and no additional compensation shall be allowed, therefore.

99 10-1.12 PROJECT SIGNS
The Contractor shall install furnished signs (City of Salinas financing signs) with new hardware and 4”x 6” pressure treated posts. Signs shall be picked up by the Contractor at a designated location to be named at a later date by the City Engineer. The signs shall be installed in both vehicle directions at the beginning and the end of the project limits. The Contractor shall remove the City signs when requested by the City Engineer and deliver to a designated location.
10-1.13 CONSTRUCTION AREA SIGNS
Reserved.
10-1.14 CLEAN UP
Throughout all phases of construction including suspension of work and until final acceptance of the project by the City of Salinas Council, the Contractor shall keep the w ork site clean and free from rubbish and debris. The Contractor shall also abate dust nuisance by clean ing, sweeping and sprinkling with water, or other means as necessary. The use of water resulting in mud on public street and or City right-of-way shall not be permitted as a substitute for sweeping or other methods.

Failure of the Contractor to comply with the City Engineer’s cl ean up orders may result in an order to suspend the work until the condition is corrected. No additional compensation shall be allowed therefore as a result of such suspension.

At the completion of the work, a final inspection will be made by the City Engineer. The Contractor will be responsible for final cleanup of the project area in accorda nce of the Provisions with Section 4-1.13 of the State Standard Specifications.

Payment for maintaining the work site clean shall be included i n the prices paid for the various Contract items as listed in the Proposal and no additional compensation shall be allowed, therefore. 10-1.15 CONSTRUCTION AND DEMOLITION WASTE REDUCTION

PLAN/RECYCLING
Throughout all phases of construction includin g suspension of work, and un til final acceptance of the project, the Contractor shall keep the work site clean and free from rubbish and debris. Salinas Municipal Code 9-4.1 requires all Constr uction and Demolition (“C&D”) pro jects within the City to divert at least 65% of the C&D debris and 100% of inert materials generated by the project. In addition, all building and demolition project contractors must prepare and submit a C&D Waste Reduction and Recycling Plan prior to commencement of project and a final C&D Waste Reduction and Recycling Report to the City Engineer’s Office upon completion of the project. Further information can be found in the Constr uction and Demolition (C&D) Diversion Requirements and Instructions in Part F of this document.

Failure to submit a “C&D Waste Reduction and Recycling Plan" and file a “C&D Waste Reduction and Recycling Report” may result in non-compliance fees and sha ll be cause to withhold final payment and not accept the project.

The Contractor shall also abate dust nuisance by cleaning, swee ping, and sprinkling with water, or other means, as necessary. The use of water resulting in mud on public streets will not be permitted as a substitute for sweeping or other methods.

100

Failure of the Contractor to comply with the City Engineer's or designee’s clean up orders may result in an order to suspend the work until the condition is corrected. No additional compensation will be allowed as a result of such suspension.

SECTION 10-2 REMOVAL AND DISPOSAL/SALVAGE EXISTING FACILITIES 10-2.01 GENERAL
The Contractor shall remove all appurtenances as shown on Plans . All removed material shall become the property of the Contractor (unless noted otherwise on the Plans ) and shall be disposed of as provided in Section 17-2.03D, “Disposal of Materials”, of the State Standar d Specifications and in accordance with “C&D Waste Reduction and Recycling Report”.

Payment for the removal and dis posal/salvage of existing facilities shall be included in the prices paid for the various Contract items as listed in the Proposal and no add itional compensation shall be allowed, therefore.

All accidental or convenience removals of existing facilities by the Contractor shall be at the expense of the Contractor, and no additional compensation shall be allowed therefore. 10-2.02 REMOVAL OF ASBESTOS AND HAZARDEOUS SUBSTANCES
If applicable, when the presence of asbestos or hazardous substances are not shown on the Plans or indicated in the Special Provisions and the Contractor encounters materials which the Contractor reasonably believes to be asbestos or a hazardous substance as defined in the Provi sions in Section 25914.1 of the Health and Safety Code, and the asbestos or hazardous substance has not been rendered harmless, the Contractor may continue work in unaffected areas reasonably believed to be safe. The Contractor shall immediately cease work in the affected area and report the condition to the City Engineer in writing immediately.

In conformance with the Provisions in Section 25914.1 of the Health and Safety Code, removal of asbestos or hazardous substances including exploratory work to identify and determine the extent of the asbestos or hazardous substance shall be performed by separate Contract.

If delay of work in the area de lays the current controlling operation, the delay shall be considered a right- of-way delay and the Contractor shall be compensated for the delay in conformance with the Provisions in Section 8-1.07. “Delays” and Sec tion 19-1.03B, “Unsuitable Mate rial”, of the State Standard Specifications.

SECTION 11 ITEMS OF CONSTRUCTION
SECTION 11-1 GENERAL
All items of work listed in the Proposal Section shall conform to the Plans, City of Salinas Standard Specifications and Standard Plans, 2024 State Standard Specifications, and these Special Provisions.

The Contractor shall refrain from using diesel fuel or solvents of any kind for cleaning tools and equipment in such a manner as to permit spillage of parkways or other improved areas.

101
SECTION 11-2 EARTHWORK
11-2.01 GENERAL
The work performed in connection with trenching, compaction, ex cavation, backfill, and other earthwork operations shall be in accordance with Section 19, “Earthwork” of the Standard Specifications and these Special Provisions.

Surplus excavation materials including native soil, concrete, a sphalt concrete, concrete base, and subbase material shall become property of the Contractor and shall be d isposed in accordance with the Provisions and State Standard Specifications.

Protection of work shall be from outside sources of water such as runoff from adjacent lands shall be the responsibility of the Contractor; unstable conditions resulting from improper protection shall be the responsibility of the Contractor, and no additional compensation shall be allowed, therefore.

Unless specified otherwise, payment for miscellaneous earthwork operations including saw cutting, pavement removals, trenching and structure excavations , backfi ll, and compaction and disposal shall be included in the prices paid for the various Contract items and no additional compensation shall be allowed, therefore.

The cost of excavation, rough, and final grading to the depths shown on the Plans shall be included in the prices paid for the various Contract items and no additional compensation shall be allowed, therefore. 11-2.02 QUALITY ASSURANCE
The City of Salinas uses a Quality Assurance Program (QAP) to e nsure a material is produced to comply with the Contract. The Contractor may examine the records and reports of tests the City of Salinas performs if they are available at the job site. Schedule work to allow time for QAP. 11-2.03 HAULING
The payment for hauling shall be considered included in the prices paid for the various Contract items listed in the Proposal and no additional compensation shall be allowed, therefore. 11-2.04 GRADE TOLERANCE
Grade tolerance shall conform to the Provisions in Section 19-1 .03, “Grade Tolerance”, of the Standard Specifications.

SECTION 11-3 ASPHALT CONCRETE
11-3.01 GENERAL
Asphalt concrete (AC) shall be placed in accordance with the Pl ans, the applicable Provisions of the State Standard Specifications, and these Special Provisions. The work to be performed shall include but not limited to: removal and disposal of existing AC pavement; preparation of area and subgrade; placement of Class 2 aggregate base materials when required; paint binder, p rime coat, and placing of Type “A” HMA as specified within these Special Provisions.

The AC overlay areas shall be in accordance with the Plans, the applicable Provisions of the City of Salinas Standard Specifications, the applicable Provisions of the State Standard Specifications, and these Special

102
Provisions. Contractor shall rem ove existing asphalt concrete t o the depths as indicated in the Plans.

Contractor shall compact existing aggregate base to 95% relativ e compaction prior to the placement of asphalt concrete.

Pavement restoration due to the trenching and/or excavation operation for the various improvements shall be in accordance with the Plans and these Special Provisions. 11-3.02 PRIME COAT
Prime coat shall be liquid asphalt SC-250. One application of SC-250 prime coat shall be applied at the rate of 0.25 gallons per square yard to all surfaces of base rock which are to be paved with asphalt concrete. 11-3.03 PAINT BINDER
Paint binder shall be RS-1 type asphaltic emulsion per Section 94 of the Standard Specifications. Paint binder shall be applied at a rate of 0.05 gallons per square ya rd per Section 93 and 94 of the Standard Specifications. Paint binder shall be applied to all vertical surfaces of existing pavement, curbs, gutters, and construction joints in the surfacing against which additional m aterial is to be placed to a pavement to be surfaced and as designated by the City Engineer.
11-3.04 TACK COAT
The Engineer calculates the Quantity of asphalt in Tack Coat (QTC) as either of the following:

1. Asphalt binder using the asphalt binder total tons placed as tack coat.

2. Asphaltic emulsion by applying the formula to the asphaltic emulsion total tons placed as tack coat. 11-3.05 ASPHALTIC EMULSION
The Engineer calculates the quantity of asphalt in asphaltic em ulsions, including fog seals and tack coat, using the following formula:

Qe = AETT x (Xe/100)
w h e r e :

Qe = quantity in tons of aspha lt used in asphaltic emulsion AETT = undiluted asphaltic emulsion, total tons placed
Xe = minimum percent residue s pecified in Section 94 based on the type of emulsion used You may determine Xe by submitting daily test results for asphalt residue for the asphaltic emulsion used.

If you choose this option, you must:

1. Take 1 sample for every 200 tons but not less than 1 sample per day in the presence of the Engineer from the delivery truck, at midload from a sampling tap or thief, and as follows:

1.1. Draw and discard the 1st gallon.

103

1.2. Take 2 separate ½ gal samples.

2. Submit the 1st sample at the time of sampling

3. Furnish the 2nd sample with in 3 business days of sampling t o an authorized laboratory that participates in the AASHTO Proficiency Sample Program.

4. Submit test results from the laboratory within 10 business days of the sample date. 11-3.01 REMOVAL

OF ASPHALT CONCRETE PAVEMENT
Existing asphalt concrete pavement shall be sawcut to a straigh t and clean cut where shown on the Plans.

All contaminated water shall be vacuumed and disposed of in an environmentally approved fashion. All asphalt removal shall have vertical surfaces created by saw cutting or any other approved method proposed by the Contractor that results in an acceptable vertical surfac e. Rounded edges of surrounding asphalt concrete areas will not be accepted for placement of AC. Tack c oat and/or prime coat shall be applied to all existing horizontal and vertical surfaces prior to placemen t of asphalt concrete including base material with no additional compensation. Work of this item shall comply with all requirements of the Standard Specifications for subgrade and asphalt concrete.

Saw cut edges damaged during the progress construction shall be re-cut to provide a straight and even line, at no additional cost to the City.

SECTION 11-4 CONCRETE FACILITIES
11-4.01 GENERAL
The furnishing and installation of concrete facilities shall co nform to the applicable provisions in Section 73, “Concrete Curbs and Sidewalk ”, and Section 90, “Portland Co ncrete Cement”, of the Standard Specifications, the Plans, and these Special Provisions. Concre te shall be Class 3 and shall be placed as shown on the Plans.

All contaminated water shall be vacuumed and disposed of in an environmentally approved fashion.

Contractor shall provide sufficient forces to perform the necessary construction of this project in order that all work shall be completed within the time frame established for this project.

Contractor shall contact U.S.A. (Underground Service Alert, tel ephone number 811) 48 hours in advance before performing any trenching or excavation work.

Existing concrete facilities dama ged during construction, conve nience removals, and miscellaneous concrete transitions shall be reconstructed at the expense of the Contractor and no additional compensation shall be made.
11-4.02 REMOVAL AND DISPOSAL OF CONCRETE SIDEWALK, CURB AND GUTTER
Removal and disposal of concrete sidewalk and curb and gutter shall conform to the Provisions in Section 15, “Existing Highway Facilities”, of the Standard Specifications and these Special Provisions.

104
Existing concrete sidewalk, curb and gutter shall be cut to a minimum depth of one and one-half inches (1- 1/2”) with an abrasive type saw at the first scoring line at or beyond the planned joint or as shown on the Plans or as indicated by the City Engineer.
11-4.03 CONSTRUCTION OF CONCRETE SIDEWALK, CURB AND GUTTER Construction of concrete sidewalk, curb and gutter shall conform to the Provisions in Section 73 and 90 of the Standard Specifications and these Special Provisions.

Concrete sidewalk shall be constructed per City of Salinas Standard Plan No. 2R and as shown on the Plans.

Concrete Type “B”, and Type “C” curb and gutter shall be constr ucted per City of Salinas Standard Plan No.1 and as shown on the Plans.

SECTION 11-5 REINFORCEMENT
11-5.01 GENERAL
Dowel and bar reinforcements in concrete shall be No. 4 and shall be placed as shown on the Plans and in accordance with Section 52 of the Standard Specifications.

SECTION 11-6 AGGREGATE BASE
11-6.01 GENERAL
Aggregate base shall be Class 2 and shall conform to the Provis ions in Section 26, “Aggregate Bases”, in the Standard Specifications and these Special Provisions. Base courses shall be three-quarter of an inch (3/4”) maximum aggregate size. All aggregate bases shall be com pacted to 95% relative compaction, Contractor shall prepare soils as necessary to provide a stable subgrade.

SECTION 11-7 THERMOPLASTIC PAVEMENT STRIPING AND MARKINGS 11-7.01 GENERAL
Thermoplastic traffic striping a nd pavement markings shall be a pplied to pavement surfaces as shown on the Plans and as specified on the City of Salinas Standard Specifications, 2024 State Standard Specifications and Standard Plans, and in accordance with these Special Provisions.

Cat tracking is required before permanent pavement striping and pavement markings are placed and shall be approved by the City Engineer before final pavement striping and pavement markings are installed. For traffic safety all cat tracking shall be performed by the Contr actor within 24 hours after the removal of existing pavement striping and markings. Contractor shall insta ll temporary striping immediately after removal of existing pavement mar kings and shall be maintained i n a legible and traffic safety manner by the Contractor until final permanent pavement striping and markings are in place.

Application of thermoplastic pav ement striping and markings sha ll be as specified in Section 84 of the Standard Specifications. Existing surfaces that are to receive the thermoplastic material shall be mechanically wire brushed to remove all dirt and contaminants. Damaged or improper pavement striping and markings shall be immediately removed from the surface it was applied to, at the Contractor’s expense.

All of the equipment used in the application of traffic striping shall produce stripes of uniform quality that conform to the specified requirements.

105
11-7.02 MATERIALS
Traffic stripes and pavement markings must be retroreflective. Traffic stripes shall be alkyd thermoplastic material and glass beads, thermoplastic material shall be “lead free”. Materials used for traffic stripes and pavement markings shall be as specified in Section 84-2.02 of the Standard Specifications.

White thermoplastic stripes and ma rkings shall meet a minimum r etroreflectivity of 700 mcdꞏm -2ꞏlx-1.

Yellow thermoplastic stripes and markings shall meet a minimum retroreflectivity of 500 mcdꞏm -2ꞏlx-1 when measured under ASTM E1710 or ASTM E3320.
11-7.01 REMOVAL OF PAVEMENT STRIPING AND PAVEMENT MARKINGS Removal of existing pavement striping and pavement markings shall be performed by disk grinder or other pre-approved methods by the City Engineer. The contractor shall not use a pavement grinder to remove the striping. All work shall be subject to inspection at all times by the City Engineer.

SECTION 11-8 SIGNS
11-8.01 GENERAL
All work and materials for signs shall conform to the Provision s in Section 56 of the City of Salinas Standard Specifications, and the latest edition of the California Manual of Uniform Traffic Control Devices (CA-MUTCD), and as shown on the Plans. All new sign panels shou ld meet the minimum CA-MUTCD retroreflectivity standards. All signs furnished shall have an ti-graffiti sheeting. The Contractor shall furnish all mounting hardware. Signs shall be constructed of a minimum 0.080 inch thick aluminum alloy. 11-8.02 SIGN POST
New sign posts shall be 2”x 2” s quare tube posts with 7/18 inch knockouts, 1 inch on center, on all four sides. Posts shall be 12 gauge steel 0.105 inch thick and conform to ASTM A1011. Bolts, nuts and washers shall conform to ASTM A 307 and shall be galvanized. The sign p anel shall be upright and level. All hardware shall be tightened securely. All new sign posts shall be plumb and free of vertical or lateral movement. All signs located within a walking area shall have a minimum clearance of 7 feet and new sign posts should be sized accordingly. Unless otherwise noted on Plans or in these Special Provisions. 11-8.03 ANCHORAGE
Anchor sleeve shall be 2 1/4” x 2 1/4” inner diameter and 2 1/2” x 2 1/2” outer diameter square tube posts with 7/18 inch knockouts, 1 inch on center, on all four sides. Anchor Sleeves shall be 7 gauge heavy duty steel and conform to ASTM A1011. Anchor sleeves shall have a minimum length of 36 inches. Sign post shall be placed in the anchorage sleeve with a minimum overlap of 18 inches and bolt connected.

If new signs are to be installed on sidewalk or concrete, the contractor is required to core a 3 inch diameter hole, 36 inches deep through the pavement or existing surface. After placing the anchor sleeve, fill the hole with a concrete mix footing per City of Salinas Standard Specifications (2008), and level off the top of the concrete so that the final surface is flush and level with surrounding area.

All work shall be subject to inspection at all times by the City Engineer.

106
11-8.04 MOUNTING
All new signs shall be affixed to posts with commercial quality galvanized steel bolts, washers and nuts.

The face of the sign panel shall be protected by placing either a fiber or neoprene washer between a metal washer next to the bolt head and sign face. Sign panels larger than 36”x36” shall be mounted with a back brace.

New signs mounted to existing posts shall have a minimum clearance of 7 feet, if located on a sidewalk. If existing post is not high enough, contractor shall notify the City Engineer. Existing sign posts may vary in shape and style, new signs shall be mounted with appropriate fa stening hardware. If an existing post is deteriorated or broken, the contractor shall notify the City En gineer. If existing post is not salvageable, contractor shall install a new post. The sign panel shall be plumb and free of vertical or lateral movement.

All hardware shall be tightened securely.

Straps and saddle brackets for mounting sign panels on lighting standards, sign structure posts, and traffic signal standards must be stainless steel and must conform to the provisions of Section 82 of State Standard Specifications. All work shall be subject to inspection at all times by the City Engineer.

SECTION 11-9 CURB DRAIN AND RECTANGULAR DRAINAGE CHANNEL 11-9.01 GENERAL
Curb drain and rectangular drainage channel shall be Curb-O-Let and shall be installed as shown on the Plans and per manufacturer’s specifications.

SECTION 11-10 DETECTABLE WARNING SURFACE
11-10.01 GENERAL
The Contractor shall furnish and install Armor-Tile Cast-in-Place Inline Dome Tactile Detectable Warning Surface Tile where indicated on the Plans or approved equal by the City Engineer.

SUBMITTALS - The Contractor shall submit manufacturer’s literature describin g products, installation, procedures, and routine maintenance.

The Contractor shall submit 2 tile samples (for verification pu rposes) minimum 6” x 8” of the kind he/she is proposing.

The Contractor shall submit shop plans for products specified s howing fabrication details, composite structural system, plans of tile placement including joints, an d materials to be used as well as outlining installation materials and procedure.

The Contractor shall submit material test reports from qualifie d independent testing laboratory indicating that materials proposed for use in compliance with requirements and meet the properties indicated. All test reports shall be conducted on a cast-in-place tactile tile system as certified by a qualified independent testing laboratory.

The Contractor shall submit copies of the manufacturer’s specified maintenance practices for each type of tactile tile and accessory as required.

107
QUALITY ASSURANCE – Provide cast-in-place tactile tiles and accessories as produced by “Armor- Tile Tactile System” or approved equal by the City Engineer.

The Contractor shall be an experienced installer of cast-in-place tactile tiles (wet set).

Vitrified Polymer Composite (VPC) cast-in-place tiles shall be an epoxy polymer composition with an ultraviolet stabilized coating employing aluminum oxide particl es in the truncated domes. The tile shall incorporate an in-line dome patter of truncated domes 0.2” in h eight, 0.9” diameter at the base, and 0.4” diameter at the top of dome spaced 2.35” nominal as measured o n a diagonal and 1.70” nominal as measured side by side. For wheelchair safety the field area sha ll consist of a non-slip surface with a minimum of 40-90° raised points 0.045” high, per square inch, or approved equal by the City Engineer.

NOMINAL TILE SIZE
Length and Width 24”x48” 24”x60” 36”x48” 36”x60”
Depth 1.400”+/- 5% maximum
Face Thickness 0.1875 +/- 5% maximum
Length and Width +/- 0.5% maximum

Water absorption of VPC tiles when tested by ASTM-D 570 shall not exceed 0.35%.

Slip resistance of VPC tiles when tested by ASTM-C 1028 the com bined wet/dry static co-efficient of friction not to be less than 0.09 on top of domes and field area.

Compressive strength of VPC tile when tested by ASTM-D 695-91 shall not be less than 18,000 psi. Tensile strength of VPC tile when tested by ASTM-D 638-91 shall not be less than 10,000 psi. Flexural strength of VPC tile when tested by ASTM-C293-94 shall not be less than 24,000 psi.

Chemical stain resistance of VPC tile when tested by ASTM-D 543 -87 to withstand without discoloration or staining – 1% hydrochloric acid, urine, calcium chloride, stamp pad ink, gum, and red aerosol paint.

Abrasive wear of VPC tile when tested by BYK-Gardner Tester AST M-D 2468 with reciprocating linear motion of 37 +/- cycles per minute over a 10” travel. The abras ive medium, a 40-grit Norton Metallite sandpaper, to be fixed and levele d to a holder. The combined ma ss of the sled, weight and wood block to be a 3.2 pounds. Average wear depth shall not exceed 0.030 after 1000 abrasion cycles measured on the top surface of the dome representing the average of three measurement locations per sample.

Fire resistance VPC tile when tested by ASTM-G26-95 for 2000 ho urs shall exhibit the following result- deterioration, fading or chalking of surface of the tile.

Gardner Impact to geometry “GE” of the standard when tested by ASTM-D 5420-93 to have a mean failure energy expressed as a function of specimen thickness of not les s than 450” lbf/in. A failure is noted if a hairline fracture is visible in the specimen.

108
Accelerated weathering of VPC tile when tested by ASTM-G26-95 f or 2000 hours shall exhibit the following result-deterioration, fading or chalking of surface of the tile.

The VPC cast-in-place tiles embedded in concrete shall meet or exceed the following test criteria:

Accelerated aging and freeze thaw test of VCP tile when tested to ASTM-D 1037 shall show no evidence of cracking, delamination, warpage, checking, blistering, color change, loosening of tiles, or other defects.

Salt and spray performance of VPC tile and adhesive system when tested to ASTM-B 117 shall not show any deterioration or other defects after 100 hours of exposure.

Embedment flange spacing shall be 3.0” minimum to 3.1” maximum center-to-center spacing.

DELIVERY, SPACING, AND HANDLING – Tile shall be suitably packaged or crated to prevent damage in shipment or handling. Sturdy wrappings shall protect finished surfaces and part number shall identify tile type.

SITE CONDITIONS – Maintain minimum temperature of 40°F in spaces to receive tactile tiles for at least 48 hours prior to installations, and for not less than 48 hours after installation. Store tactile tile material in spaces where they will be installed for at least 48 hours befor e beginning installation. Subsequently, maintain minimum temperature of 40°F in areas where work is completed.

The use of water for work, cleaning, dust control, etc. shall n ot be allowed to come into contact with the passengers and/or public. Provide barricades or screens to protect passengers and/or public.

Disposal of any liquids or other materials of possible contamin ation shall be made in accordance with federal, state, local laws, and ordinances.

Cleaning materials shall have code acceptable low VOC solvent c ontent and low flammability if used on site.

GUARANTEE – Cast-in-place tactile tiles (wet set) shall be guaranteed in writing by manufacturer for a period of 5 years from date of final completion and acceptance of the project from the City of Salinas. The guaranteed replacement shall incl ude defective work, breakage, deformation, fading, and chalking of finishes and loosening of tiles.

The Vitrified Polymer Composite (VPC) Cast-in-Place Tactile Til e (wet set) shall be Armor-Tile manufactured by Engineered Plastics Incorporated or approved equal by the City Engineer. The VPC shall be free from blemishes. The color shall be yellow conforming to the Federal Standard 595B and color no. 33538 and shall be homogeneous throughout the tile.

INSTALLATION – During all concrete pouring and tile installation procedures ensure adequate safety guidelines are in place and that they are in accordance with these Special Provisions.

The cast-in-place tactile tile shall be one piece, if it cannot be achieved the Contractor shall get approval from the City Engineer to use more than one piece of cast-in-place tactile tile prior to installation.

109
The specifications of the concre te sealants, structural adhesiv es, fasteners, epoxy chalking, and related materials shall be in strict accordance with these Special Provisions and the guidelines set by their respective manufacturers.

The physical characteristics of t he concrete shall be consisten t with these Special Provisions while maintaining a slump range of 4 to 7 to permit solid placement o f the cast-in-place tile system. An overly wet mix shall cause the cast-in-place system to float, therefore, under these conditions suitable weight such as 2 concrete blocks or sandbags (25 pounds) shall be places on each tile.

The concrete pouring and finishing operations require typical mason’s tools, however, a 4’ long level with electronic slope readout, 25 pounds weights, vibrator, a large white rubber mallet, and small sledge hammer with 2” x 6” x 20” wood tamping plate are specific to the installation of the cast-in-place system.

The concrete shall be poured and finished, true, and smooth to the required dimensions and slope prior to tile placement. Immediately after furnishing the concrete, the electronic level shall be used to check that the required slope is achieved. The tile shall be placed true and square to the curb edge in accordance with the Plans and Special Provisions. The cast-in-place tiles shall be tamped or vibrated into the fresh concrete to ensure that the field level of tile is flush to the adjacent concrete surface. The Plans indicate that the tile field level (base of truncated dome) is flush to adjacent surfa ces to permit proper water drainage and eliminate tripping hazards between adjacent finishes. The toler ance for elevation differences between tile and adjacent surface is 1/16”.

Immediately after tile placement, the tile elevation is to be checked to adjacent concrete. The tile elevation and slope should be set consistent with the Plans to permit water drainage to curb as the design dictates.

While concrete is workable a steel trowel shall be used to trow el the concrete around the tile perimeter to the field level of the tile.

During and after the tile installation and the concrete curing stage, it is imperative that there is no walking, leaning or external force placed on the tile to rock the tile, causing a void between the underside of the tile and concrete.

Following the curing of the concrete, the protective plastic wr ap shall be removed from the tile face by cutting the plastic with a sharp knife tight to the concrete/tile interface. If concrete bleeding occurs, a wire brush shall clean the residue without damage to the tile surface.

CLEANING AND PROTECTING – The Contractor shall protect the tile against damage during construction period to comply with tactile tile manufacturer’s specification.

The Contractor shall clean tactile tiles for the final time not more than 4 days prior to date scheduled for final inspection prior to the f inal acceptance for maintenance by the City of Salinas. Clean tactile tile by method specified by the manufacturer and/or the City Engineer.

110
SECTION 11-11 COBBLE SPLASH PAD
11-11.01 GENERAL
Cobble splash pad shall be placed in accordance with the Specia l Provisions and as shown on the Plans.

Cobbles shall be 4”- 6” in diameter, rounded, washed, and free of debris. Cobbles shall be placed to a minimum of 6” depth.

111
PART E– CONSTRUCTION BEST MANAGEMENT PRACTICES
(BMPS), CONSTRUCTION AND DEMOLITION DIVERSION

REQUIREMENTS, AND OTHER MISCELLANEOUS

INFORMATION

112
[THIS PAGE LEFT INTENTIONALLY BLANK]
TH E FOLLOW ING BMPs MUST BE PROPE RLY USED AT ALL CONSTRUC TION SITES TO PROTECT STORM DRAINS AND MINIMIZE POLLU- The City of Salinas Stormwater Management Program prohibits pollu tant discharges at work sites from flowing into storm drains and polluting neighborhood creeks, rivers, and the ocean. To comply with the law and kee p your project on schedule, make sure proper BMPs are in place and functioning. Sites must be checked and maintained daily. The following BMPs are required; they are not all-inclusive.

Prior tostaginganymaterialsor equipmentintheright-of-way (suchas dump- stersor trucks), pleasecontact the applicablelocal jurisdictiontolearnof any temporary encroachmentpermit or trafficcontrol requirements necessary for right-of-way stagingand loading areas, applicable stormwater BMPsand safetyplanreviewrequirements. Provide astabilizedvehiclepathwithcon- trolled accesstoprevent trackingof dirt offsite. Properlysizesiteentrance BMPsfor anticipatedvehicles.

Allpaint andstuccomaterial storedonthesitemust becontained and covered. It isillegaltodump unused paint or stuccointhesewer or stormdrainsystem. Donotwashoutbrushesinthe streetor dump anyresiduesinthestormdrain. Paint brushesandsprayguns must be washed/cleaned out intoahazardousmaterialsdrumor backintothe originalcontaineranddisposed of properly.

Gravel bags, siltfencesand strawwattles(weighted down) areaccept- ableperimeter controls, andmust beusedtosurround theentiresite.

Avoidrunning over perimeter controlswithvehicles or heavy equipment astheycandamagethematerials. Keep extraabsorbentmaterials and/or wet-dryvacuumonsitetoquicklypickupunintended spills.

Constructionmaterial must bestoredon siteat all times. Building materialsshouldalways be covered when not inusetopreventrunoff caused bywindor rain. Flooding must alsobeprevented by monitor- ingthesitebefore, during, and after rainevents toensure thatBMPs arefunctioning andthattherearenosafetyissues.

Alwayscover dumpsters witharollback tarp. Areasarounddump- stersshouldbeswept daily. Perimeter controlsarounddumpster areasshouldbeprovidedifpollutants areleakingor dischargingfrom thedumpster.

BMPssuchastarps andgravel bagsshouldbeimplemented toprevent materialsand residuefromentering intothestormdrainsystem.

The disposal of “wet”constructionmaterialsshouldbehandled inthe washoutarea. Thisincludespaint, stucco, and concrete. Useaberm withanimperviousliner tocontainwet materialsandprevent runoff in nearby areas. The washoutareamust becheckedandmaintained daily toensurecompliance. Alldriedmaterialsmust bedisposed of at the landfill.

Moundsof dirt or gravel shouldbestoredon siteand sprayed daily withwater topreventexcessivedust. Duringtherainyseason
(October 15th— April 15th) thesematerialsshouldbe covered. For thoseareas that areactiveandexposed, awet weathertriggered action planincluding additionalBMPsshould beinplacetoprotect thesite during arainevent. Sitesmust haveadequate trackingcontrol topre- ventthetransport of dirt/gravel fromthesite.

Allearthmoving equipmentshouldbe stored on site. Maintenance of any equipmentshouldbe conducted on site, and mud tracks anddirt trailsleft by equipment leading to and fromthe site should be cleaned upimmediately.

Stormdrains must be protectedat all timeswithperimeter con- trols, suchas gravel bags. Sandbagsaretypically not usedfor inlet protectionbecause they donotpermitflow-through.Re- placeruptured or damaged gravel bagsandremovethedebris
fromtheright-of-way immediately.

Questions? Contact the City of Salinas Public Works Department 831- 758- 7988 or 831- 758- 7194
Photo courtesy of the City of San Diego
Remember... C I T Y O F SALINAS

As a Resident or Business Operator

• What we do on land affects the
quality of water we drink and use in
so many ways.

• Many small sources of pollution
add up to cause big water quality
problems.

• Pressure washing or hosing
down sidewalks or driveways
contribute to water pollution .

Mop, sweep or use other dry methods
to clean pavement or grounds around
your home or business.

• Excessive runoff from land-
scape irrigation can result in water
pollution by carrying fertilizers,
pesticides or silt offsite to local water
ways. Regularly inspect your irrigation
system to prevent excessive runoff.
• Trash and Debris dumped or left to
accumulate on residential or business
grounds can wind up local waterways.

Dispose of trash properly. Keep areas
clean and free of trash and debris.

• Natural things such as soil, leaves,
grass clippings, and pet waste ca n
cause water pollution.

• Waste dumped into storm
sewers goes into creeks and
waterways without treatment.

• Automobiles and other vehicles
cause water pollution as well as air
pollution

Everyone can make a difference!
Reporting of Illegal
Dumping or Suspicious
Discharges:

Reporting will, in great part, rely on
participation from the public.

Residents who observe illegal dumping or
observe pollutants within waterways or
storm sewers should contact the City of
Salinas, Environmental & Maintenance
Services Office.

Dial (831) 758-7233,
Monday – Thursday
8 a.m. - 5:00 p.m.

Or call 911 after hours, weekends or
holidays to report a stormwater violation.

For non-emergencies use the internet
inquiry form located on the City’s website
address below.

http://www.ci.salinas.ca.us/contact.cfm

This program will succeed with strong
public participation.

Illicit Discharge
Detection &
Elimination

S T O R M W A T E R

P O L L U T I O N

P R E V E N T I O N

Report Illicit Discharges
and Illegal Dumping
Phone: 831-758-7233
or
Dial 911
For Emergency Reporting

City of Salinas - Public Works Department
Environmental & Maintenance Services
426 Work Street, Salinas, Ca. 93901
Non-Emergency Web Contact::
http://www.ci.salinas.ca.us/contact.cfm

What is an
Illicit Dischar g e?

An illicit discharge is defined as
“any discharge into a municipal storm
sewer system that is not composed en-
tirely of stormwater”. Some of the pollut-
ants that fall into this broad category are:

• Car wash wastewater

• Gas and motor oil

• Grass clippings

• Household cleansers

• Paints

• Pesticides

• Pet waste

• Solvents

• Weed killer

Sometimes these pollutants are
carried through the storm drainage system
by rain, wind, or improper disposal into
Salinas Waterways. This can result in
serious health and water quality problems.

In addition, wildlife and the overall
appearance of the creek or waterway is
adversely affected by illicit discharges.

Six Easy Ways That
You Can Keep Illicit
Discharges Out of Our
Local Creeks

There are simple steps that we can take
to solve the problems that our local waterways
face. It is up to YOU, the homeowner and busi-
ness owners who call Salinas home, to clean it up
and to help keep it clean!

1. Used oil, antifreeze, and batteries can
be recycled. Clean up any spills immedi-
ately—kitty litter or sawdust will absorb the
spill. Be sure to sweep these up as well.

2. Wash your car on the grass so that water,
detergent, and dirt will be filtered by the
soil. Better yet, take your car to a com-
mercial car wash, where the dirty water is
sent to the wastewater treatment plant.

3. Empty bottles of house-
hold cleansers, pesti-
cides, and weed killer
should be disposed of
according to label direc-
tions.

4. Grass clippings in the street should be
swept up aft er each mowing. Grass clip-
pings left in the street are
being washed down into the
storm sewers and end up in
the local waterways where
they have the potential to
cause algae blooms.

5. Many ho usehold products, including
paints, paint thinners, and solvents
can be taken free of charge to Salinas
Valley Solid Waste Authority, Household
Hazardous Waste drop-off site at 128
Sun St. Salinas, CA 93901, (831) 775-
3000. Paint brushes used with water
based paint can
be rinsed in the sink.

If you have a small
amount of left-over
paint in a can, stuff it
loosely with newspaper, let the paint
dry out completely and put it in the
trash.

6. When walking your pet use a bag or use
a scooper to clean up your pet’s
waste. In order to keep animal waste
from contaminating our community,
anyone who walks a pet should properly
dispose of waste by picking it up, wrap-
ping it, and either placing it into the
trash or flushing it UNWRAPPED!

Construction
Sediment from excavation and other
construction projects is the most common
pollutant washed from work sites.

Sediment entering the waterways through
storm drains harms aquatic life and
disrupts the food chain upon which both
fish and people depend.

Erosion Control General Practices
• Keep all construction debris away
from the street, gutter and storm
drain. Look for and clean up material
that may have traveled away from
your property.
• Keep materials out of the rain by
storing them indoors or outdoors with
a secure roof or plastic sheeting.
• Schedule grading and excavation
projects for dry weather.
• Cover excavated material and
stockpiles of asphalt and sand with
plastic tarps.
• Prevent erosion by planting fast -
growing annual and perennial grasses.

These will shield and bind soil.

Recycling & Hazardous Waste Disposal:

Sun Street Transfer Station
Salinas Valley Solid Waste Authority
(831) 424-5520
139 Sun Street
Salinas, 93901

To Report a Spill, Illegal Dumping or a
Clogged Storm Drain Call:
(831) 758-7233
City of Salinas
Department of Public Works
Maintenance Division

Look for all o ther pamphlets for storm
drain protection guidelines:

❑ Automotive Maintenance & Car
Care
❑ Equipment Rentals
❑ Food Service Industry
❑ Fresh Concrete & Mortar
Application
❑ General Construction & Site
Supervision
❑ Heavy Equipment & Earthmoving
Activities
❑ Landscaping, Gardening & Pest
Control
❑ Mobile Washers and Cleaners
❑ Painting
❑ Roadwork & Paving
❑ Swimming Pool, Jacuzzi &
Fountain Maintenance

For more information about sto rm drain
protection or additional pamphlets, call:
(831) 758-7233
City of Salinas
Department of Public Works
Maintenance Division

Stormwater
Best Management
Practices (BMPs):

Repair and Remodeling

Safe Environmental Habits and
Procedures for:

❑ Landscaping
❑ Painting
❑ Remodeling
❑ Home Owners

Permit Center
65 West Alisal St., Suite 101
Salinas, California 93901
(831) 758-7251
Water Pollution Prevention
It’s Up to Us

Only “rain” is allo wed in our storm drain
system. Rain, industrial and household
water mixed with urban pollutants creates
stormwater pollution. The pollutants
include:

Urban runoff pollution (oil and other
automotive fluids, paint and construction
debris, yard and pet wastes, pesticides
and litter).
• Flows through the storm drain to the
Salinas River and the Reclamation
Ditch that takes water and debris
straight from Salinas streets to the
Monterey Bay Marine Sanctuary.
• Contaminates our rivers and ditches,
harms aquatic life and increases the
risk of flooding by clogging gutters
and catch basins.
• Oil and grease, for example, clog fish
gills and block oxygen from entering
the water. If oxygen levels in the
water become too low, aquatic
animals may be harmed and/or die.

Household Hazardous Waste Disposal
• Household toxics —such as common
household cleaners, paint products
and motor oil —can pollute our rivers
and poison the groundwater if not
disposed of as hazardous waste.
• Take your household chemicals and
toxics to the local Household
Hazardous Waste Facility.

Concrete & Masonry
Fresh co ncrete and mortar application
materials can wash down or blow into the
street, gutter or storm drain.
• Do not mix up more fresh concrete or
cement than you will use.
• Store bags of cement and plaster
under cover. Protect these materials
from rainfall, runoff and wind, away
from gutters and storm drains.
• Never dispose of cement washout or
concrete dust onto driveways, streets,
gutters or storm drains.

Painting
Paints and solvents contain chemicals that
are harmful to aquatic life. Toxic
chemicals can come fro m liquid or solid
products or from cleaning residues on
rags. It is especially important to prevent
these chemicals from entering storm
drains.

Paint Cleanup
• Never clean brushes or rinse paint
containers into a street, gutter or
storm drain.
• For oil-based paints, paint out brushes
to the extent possible. Clean with
thinner and then filter and reuse
thinner.
• For water -based paints, paint out
brushes to the extent possible, then
rinse in the sink.
• When thoroughly dry, used brushes,
empty paint cans (lids off ), rags and
drop cloths may be disposed of as
trash.

Paint Removal
• Chemical paint stripping residue,
including saturated rags, is a
hazardous waste and should be taken
to a household hazardous waste
collection event.
• Chips and dust from marine paints or
paints containing lead or tributyl tin
are also hazardous wastes. Sweep
them up and save them for a
hazardous waste collection event.

Paint Recycling
• Reuse leftover paint for touch -ups or
recycle it at a local household
hazardous waste collection event.

Landscaping & Gardening
• Intensive gardening and landscaping
increase the likelihood that garden
chemicals and soil will wash into
storm drains. Pesticides and
herbicides not only kill garden
invaders, they also harm insects,
poison fish and contaminate grou nd
and river water.
• Use organic or non -toxic fertilizers
and pesticides. Do not fertilize or use
gutters or storm drains.
• Store pesticides, fertilizers and
chemicals in a covered area to
prevent runoff.
• Do not blow, sweep, hose or rake
leaves into the stre et, gutter or storm
drain.
• Place clippings and pruning waste in
approved containers for pick up.
• Conserve water by using drip
irrigation, soaker hoses or micro-spray
systems.

120

POLE DETAIL

NTS

POLE DETAIL
NTS

POLE DETAIL

122

126
ATTACHMENT A: CITY OF SALINAS HOLIDAY SCHEDULE

127

128

PART F – QUALITY ASSURANCE PROGRAM