BID OPENING
July 15, 2025
B I D T A B U L A T I O N PROJECT No. 9535
Bid awarded on _______ by City Council to ___________ Drawing No. for the sum of __________ Project Engineer Jonathan Esteban All other bids were rejected and bid bonds returned. Project Manager Jonathan Esteban Dated CONTRACTOR #1 CONTRACTOR #2 CONTRACTOR #3
City Clerk ENGINEER'S
ESTIMATE
ITEM APPROX. UNIT UNIT UNIT UNIT
NO. QUANTITY PRICE TOTAL PRICE TOTAL PRICE TOTAL PRICE TOTAL
BASE BID
1 MOBILIZATION 1 LS 50,000.00$ 50,000.00$ $12,751.00 12,751.00$ $478,500.00 478,500.00$ $150,000.00 150,000.00$ 2 GENERAL CONDITIONS AND REQUIREMENTS (DIVISION 01) 1 LS 585,725.00$ 585,725.00$ $383,426.00 383,426.00$ $463,370.00 463,370.00$ $550,000.00 550,000.00$ 3 ARCHITECTURAL (A-SHEETS) 1 LS 1,419,920.00$ 1,419,920.00$ $1,329,247.00 1,329,247.00$ $1,163,182.00 1,163,182.00$ $1,935,000.00 1,935,000.00$ 4 PLUMBING (P-SHEETS) 1 LS 18,512.00$ 18,512.00$ $0.00 -$ $19,885.00 19,885.00$ $10,000.00 10,000.00$ 5 MECHANICAL HVAC (M-SHEETS) 1 LS 40,161.00$ 40,161.00$ $27,097.00 27,097.00$ $44,220.00 44,220.00$ $40,000.00 40,000.00$ 6 ELECTRICAL (E-SHEETS) 1 LS 12,516.00$ 12,516.00$ $54,590.00 54,590.00$ $65,500.00 65,500.00$ $50,000.00 50,000.00$ 7 CIVIL SITE (C-SHEETS) 1 LS 605,795.00$ 605,795.00$ $649,306.00 649,306.00$ $411,640.00 411,640.00$ $450,000.00 450,000.00$ 8 LANDSCAPE AND IRRIGATION (L-SHEETS) 1 LS 41,448.00$ 41,448.00$ $230,483.00 230,483.00$ $220,685.00 220,685.00$ $100,000.00 100,000.00$ TOTAL BASE BID (ITEMS 1-8)
(FOR COMPARISON ONLY)
1 2
3 4
5 6
7 8
9 10
11 12
13 14
15 16
17 18
19 20
21 22
X
MINORITY/WOMEN BUSINESS CERTIFICATION X X X
BIDDER'S LIST FOR THE CITY OF SALINAS ENGINEERING AND TRANSPORTATION DEPARTMENT X X PUBLIC CONTRACT CODE SECTION 10232 STATEMENT X X X
CONTRACTOR'S CERTIFICATION OF NON-SEGREGATED FACILITIES X X X
DEBARMENT AND SUSPENSION CERTIFICATION
X
X
X
X
X
X
X
X X
X
X
X
X
X
X
X
X
X
X
2,866,982.00$
X
X
X
CWS Construction Group, Inc.
1717 2nd St, Sacramento, CA 95811
John F. Otto, Inc. dba Otto Construction
(916)441-6870
1301 Grant Ave, Ste B, Novato, CA, 94945
(415)209-0229
Marvulli, Inc.
1005 E Childs Ave, Ste A, Merced, CA 95341
(209)233-9474
3,285,000.00$
XEQUAL EMPLOYMENT OPPORTUNITY CERTIFICATION
X
PUBLIC CONTRACT CODE SECTION 10162 QUESTIONNAIRE X
XX
X
X
INSURANCE CERTIFICATION
X X
X
X
NON-LOBBYING CERTIFICATION FOR FEDERAL AID CONTRACTS
DISCLOSURE OF NON-LOBBYING ACTIVITIES X
X
X
NON-COLLUSION DECLARATION OF CONTRACTOR X
PROPOSAL
BIDDER'S STATEMENT OF FINANCIAL RESPONSIBILITY, TECHNICAL ABILITY, AND EXPERIENCE X
SIGNED ADDENDUM NO. 2
X
X
UNITDESCRIPTION
2,686,900.00$
BIDDER'S STATEMENT OF SUBCONTRACTORS - PART I
SIGNED ADDENDUM NO. 1
X
BIDDER'S STATEMENT OF SUBCONTRACTORS - PART II
NON-COLLUSION DECLARATION OF SUBCONTRACTOR
ITEMS TO BE SUBMITTED BY LOW BIDDER AND SECOND LOWEST BIDDDER WITHIN 5 WORKING DAYS AFTER BID OPENING 2,774,077.00$
BIDDER'S BOND
X
X
X
ITEMS TO BE SUBMITTED WITH PROPOSAL ON BID OPENING DATE X
X
SHERWOOD HALL RECREATION CENTER BUILDING IMPROVEMENT CIP NO. 9535 PUBLIC CONTRACT CODE SECTION 10285.1 STATEMENT
AFFIRMATIVE ACTION ACKNOWLEDGEMENT LETTER FOR EXECUTIVE ORDER 11246 X X
SIGNED ADDENDUM NO. 3 X X X
8/6/2025 11:32 AM \\Vsalsvr60\p\p\9535 Sherwood Recreation Center Building Improvement\BID OPERATIONS\Bid Tab\BidTab_Sherwood_9535.xls Page 1 of 2
BID OPENING
July 15, 2025
B I D T A B U L A T I O N PROJECT No. 9535
Bid awarded on _______ by City Council to ___________ Drawing No. for the sum of __________ Project Engineer Jonathan Esteban All other bids were rejected and bid bonds returned. Project Manager Jonathan Esteban Dated CONTRACTOR #1 CONTRACTOR #2 CONTRACTOR #3
City Clerk ENGINEER'S
ESTIMATE
ITEM APPROX. UNIT UNIT UNIT UNIT
NO. QUANTITY PRICE TOTAL PRICE TOTAL PRICE TOTAL PRICE TOTAL CWS Construction Group, Inc.
1717 2nd St, Sacramento, CA 95811
John F. Otto, Inc. dba Otto Construction
(916)441-6870
1301 Grant Ave, Ste B, Novato, CA, 94945
(415)209-0229
Marvulli, Inc.
1005 E Childs Ave, Ste A, Merced, CA 95341
(209)233-9474
UNITDESCRIPTION
SHERWOOD HALL RECREATION CENTER BUILDING IMPROVEMENT CIP NO. 9535 23 24
25 26
27 28
29 30
31 32
33 34
** Document under review
CONTRACTOR SECTION 3 NOTICE X X
MBE/WBE CONTRACTING ANNUAL REPORTING FORM (HUD FORM 2516) X X
CONTRACTOR CERTIFICATION OF APPLICABLE FRINGE BENEFITS X X
SUBCONTRACTOR CERTIFICATION OF APPLICABLE FRINGE BENEFITS X X
CONTRACTOR CERTIFICATION OF UNDERSTANDING AND AUTHORIZATION X X
SUBCONTRACTOR CERTIFICATION OF UNDERSTANDING AND AUTHORIZATION X X SECTION 3 GOALS STATEMENT X X
PROJECT WAGE RATE SHEET (HUD FORM 4720) X X
MINORITY/WOMEN BUSINESS UTILIZATION REPORT X X
CONTRACTOR'S SECTION 3 AFFIRMATIVE ACTION STATEMENT X X
CONTRACTOR DATA UNIVERSAL NUMBERING SYSTEM (D-U-N-S) NUMBER X X
SUBCONTRACTOR CERTIFICATION OF NONSEGREGATED FACILITIES X X 8/6/2025 11:32 AM \\Vsalsvr60\p\p\9535 Sherwood Recreation Center Building Improvement\BID OPERATIONS\Bid Tab\BidTab_Sherwood_9535.xls Page 2 of 2