Cities Index.
Rpt.docx

Salinas City Council
September 9, 2025

Document
Rpt.docx
Meeting
September 9, 2025
Body
Salinas City Council
Original file
93 KB
Text extracted from the city's file for reading and search. Open the original on legistar2.granicus.com. That file is the official record.

DATE: SEPTEMBER 9, 2025
DEPARTMENT: PUBLIC WORKS DEPARTMENT
FROM: DAVID JACOBS, P.E., L.S., PUBLIC WORKS DIRECTOR
BY: PHAVANA ARAMKUL, JUNIOR ENGINEER
ADRIANA ROBLES, P.E., C.F.M., CITY ENGINEER
TITLE: 2024 PAVEMENT CRACK TREATMENT ON VARIOUS STREETS PROJECT CIP 9981 RECOMMENDED MOTION:

A motion to approve a Resolution accepting the 2024 Pavement Crack Treatment on Various Streets Project, CIP No. 9981 for maintenance and responsibility.

EXECUTIVE SUMMARY:

On November 12, 2024, the City Council awarded the 2024 Pavement Crack Treatment on Various Streets Project, CIP No. 9981, to Carter Enterprises Group Inc DBA Pavement Rehab Company via Resolution No. 23155 for a contracted amount of $ 505,888. Construction began on February 24, 2025, with an allowance of 25 working days for project completion. Pavement Rehab Company has completed pavement maintenance for 41 road segments under this contract, including one deductive contract change order, for a grand total of $465,206.55. Substantial completion was on April 11, 2025.

BACKGROUND:

On May 7, 2024, the City Council established the Pavement Management and Street Selection Policy (Resolution No. 22953) to strategically distribute funding to address pavement deterioration. The policy identified crack treatment as a stop gap/maintenance strategy to prevent water migration into existing pavements. On June 25, 2024, the City Council approved the 5-Year Pavement Preservation Street List (Resolution No. 23031). This list identified the streets that were to receive pavement treatment (maintenance or rehabilitation) in the coming years. In an effort to prevent the selected streets from deteriorating more rapidly, crack treatment was identified as a lower cost effort to provide a short-term protection from water intrusion into the pavement subsurface.

On July 22, 2024, the City Engineer approved the project specifications and authorized the call for bids for the crack treatment project. However, due to a miscalculation that would have allowed for negotiation of the contract unit pricing and would have jeopardized the competitive bid process, bids were rejected on October 22, 2024, via Resolution No. 23135.

The City Engineer approved the revised project plans and specifications on October 4, 2024. On October 25, 2024, City staff opened bids at a public meeting held via Zoom meeting. The lowest responsive and responsible bidder Carter Enterprises Group Inc. dba Pavement Rehab Company submitted a bid that was below the engineer’s estimate and was awarded a contract for $505,888 on November 12, 2024, via Resolution No. 23155.

The 2024 Pavement Crack Treatment on Various Streets Project, CIP 9981 called for pavement crack treatment on various streets. Exhibit A, attached to this report, provides the project location map and Table No. 1 below, identifies the street segments that received pavement crack treatment.

Table 1. Street Maintenance Segments
Street Name
Begin
End

N DAVIS RD

W ROSSI ST

FREEWAY ON/OFF RAMP

CONSTITUTION BLVD

E LAUREL DR

BEACON HILL DR (S)

N MAIN ST

HARDEN PKWY
SANTA CLARA AVE / US 101 ON RAMP

S SANBORN RD

ABBOTT ST
RAILROAD Overpass (PCC START/END)

S SANBORN RD
RAILROAD Overpass (PCC END)

E ALISAL ST

E BLANCO RD

ABBOTT ST
CITY LIMIT (1,725’) E/O LA MESA WAY

ABBOTT ST
CITY LIMITS (1,322' E/O Harris Rd)

S SANBORN RD

BORONDA RD

N MAIN ST

FREEWAY ON/OFF RAMP

GREEN ST

DEL MONTE AVE

GARNER AVE
SKY PL

ALMA AVE
END

CORTEZ ST

NEW DEAL ST
END

ACOSTA ST

TOWT ST
2ND AVE

WIREN ST

WILLIAMS RD
N. END

BARDIN CIR

BARDIN WAY (N)

BARDIN WAY (S)

BARDIN WAY

BARDIN CIR (N)

WILLIAMS RD

VIA PARAISO

LOS PALOS DR

LA MESA DR

PARAISO CT

VIA PARAISO (N)

VIA PARAISO (S)

SAN MARINO WAY

E ROMIE LN

SANTA CRUZ AVE

LA MIRADA DR

SAN BRUNO WAY

LA MESA DR

SAN ANGELO DR

SANTA CRUZ AVE

LA MESA DR

PEACH DR

CALLE CEBU

COMMISSION ST
SUN ST

CALLE CEBU

E MARKET ST

RIANDA ST

GRIFFIN ST

PRADER ST

RIANDA CIR

PRADER ST
END

MURPHY ST

E ALISAL ST
END

PRADER ST

RIANDA ST

E ALISAL ST
Street Name
Begin
End

NEIL ST

MERCED ST

GRIFFIN ST

MERCED ST

E MARKET ST
END

SEMINOLE WAY

SHAWNEE WAY

CHEROKEE DR

DURAN ST

CHEROKEE DR

SEVILLE ST

DURAN CIR

CHEROKEE DR
END

EBRO CIR

CHEROKEE DR
END

CACERAS CIR

CHEROKEE DR
END

BARCELONA CIR

CHEROKEE DR
END

ARAGON CIR

CHEROKEE DR
END

TYLER ST
N 4TH ST

W LAUREL DR

HOLLY ST

RIDER AVE
END
ELM DR

RIDER AVE
END
GEE ST

RIDER AVE
END

PACIFIC AVE

GARNER AVE

DEL MONTE AVE

RIDER AVE
GEE ST

GARNER AVE

ATHERTON WAY

MILLBRAE ST

CAMBRIAN DR

ATHERTON WAY

CAMBRIAN DR

MILLBRAE ST

LEXINGTON DR

INDEPENDENCE BLVD

LITTLE RIVER DR
Table 2 summarizes the project’s measurable outputs.

Table 2 Project Summary
Construction Activity Description
Quantity
Unit
Pavement Crack seal
~ 15
Miles
One (1) contract change order (CCO), for a credit of $40,681.45 was issued for a total construction cost of $465,206.55. No working days adjustment was issued for the deduction of East and West Laurel Drive. Contract change orders were approved in accordance with Department Policy 75-1, revised December 4, 2018.

Table 3: Contract Change Orders
Contract Change Order
Description
Working Days
Change Order Amount
Cumulative Contact Total
Contract
Base Bid 1
25 $505,888.00
CCO 1
Removal of W Laurel Dr & E Laurel Dr from project.
0 $40,681.45
$40,681.45
TOTAL
25 $40,681.45
$465,206.55
The project was substantially completed on April 11, 2025.

The construction methods and materials met the Project Specifications as set forth by the contract documents and the project has been deemed complete.

CEQA CONSIDERATION:

Categorically exempt: The City of Salinas has determined that the project is exempt from the California Environmental Quality Act (CEQA) Guidelines (Section 1530l(c), Class 1), because the project proposes maintaining existing roadways, crosswalks, signage, and pavement striping.

Furthermore, the project does not qualify for any of the exceptions to the categorical exemptions found at CEQA Guidelines Section 15300.2 as all exceptions do not relate to the project scope of work for this project.

CALIFORNIA GOVERNMENT CODE §84308:

No, this project was advertised and competitively bid and is therefore exempt from California Government Code §84308.

STRATEGIC PLAN INITIATIVE:

This project relates to the Council’s Goals of Infrastructure by maintaining the City’s existing roadways.

DEPARTMENTAL COORDINATION:

Public Works staff and Finance staff have worked together on the funding of the 2024 Pavement Crack Treatment on Various Streets Project CIP 9981.

FISCAL AND SUSTAINABILITY IMPACT:

Accepting the 2024 Pavement Crack Treatment on Various Streets Project (CIP 9981) for maintenance and responsibility has no fiscal impact. The project which was funded through Gas Tax, was constructed within its allocated budget and contingencies.

Fund
CIP
Appropriation
Appropriation
Name
Total Appropriation
Amount for recommendation
FY 25-26 CIP Budget Page
Last Budget Action (Date, Resolution)
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
ATTACHMENTS:

Resolution
Exhibit A Location Map
Before/After Photos
Page | 3
Page | 1

CITY OF SALINASCOUNCIL STAFF REPORTCITY OF SALINASCOUNCIL STAFF REPORT

CITY OF SALINAS

COUNCIL STAFF REPORT

CITY OF SALINAS

COUNCIL STAFF REPORT

← All documents from this meeting