DATE: MARCH 17, 2026
DEPARTMENT: COMMUNITY DEVELOPMENT
FROM: LISA BRINTON, DIRECTOR
THROUGH: GRANT LEONARD, PLANNING MANAGER
BY: JONATHAN MOORE, SENIOR PLANNER
TITLE: 2025 GENERAL PLAN ANNUAL PROGRESS REPORT AND VISION SALINAS 2040 UPDATE RECOMMENDED MOTION:

A motion to approve a Resolution accepting the 2025 General Plan Annual Progress Report and authorizing its submittal to the State of California Department of Housing and Community Development and the Governor’s Office of Land Use and Climate Innovation.

EXECUTIVE SUMMARY:

Sections 65400 and 65700 of the California Government Code mandate that all cities and counties submit an annual report on the status of the General Plan and progress in its implementation to their legislative bodies, the Governor’s Office of Land Use and Climate Innovation (LCI) and the Housing and Community Development Department (HCD) by April 1st of each year. This annual report covers current Salinas General Plan implementation activities during the 2025 calendar year. Accomplishment highlights include the completion of the seven-acre Ensen Community Park at Carr Lake, the construction of a new Hebbron Family Resource Center, and the continued processing of tentative map applications for new neighborhoods in the Future Growth Area, and the release of a Public Review Draft of the 2040 General Plan. Once City Council accepts the General Plan Annual Progress Report, the report is then deemed final.

BACKGROUND:

According to California Government Code Section 65400, staff is required to prepare a General Plan Annual Progress Report (GP APR) for review by the City Council for submittal to LCI and HCD by April 1st of each year. The GP APR provides the City’s legislative bodies and the state with information regarding the implementation of the current General Plan and informs the public of the progress in meeting the community’s goals. The Draft 2025 GP APR is provided as Attachment 1 to this report.

There is no standardized form or format for the preparation of the General Plan APR. The GP APR is to provide information for decision makers to assess how the General Plan was implemented during the reporting period and provide enough information to identify necessary “course adjustments” or modifications to the General Plan and means to improve local implementation. The GP APR is not required to incorporate all General Plan elements. The Housing Element has its own Annual Progress Report that is overseen by HCD and prepared by the Housing Division. 2025 General Plan Accomplishment Highlights
The GP APR lists projects and accomplishments by their corresponding General Plan Element and implemented Goals/Policies. Accomplishment highlights in 2025 include:

Land Use/Community Design Elements
The Permit Center approved over 2,900 permits and conducted more than 20,100 building inspections. Major construction and development projects included issuing planning entitlements for the change of use of a 9,000-square-foot building from retail to a dental office, approving commercial, recreational, and entertainment use for a Dave and Buster’s location, issuing building permits for a new RSD Distribution concrete tilt-up warehouse, permitting a new Chick-fil-A restaurant, and approving the renovation of Fire Station 1.

Completed administrative work related to the Clean California State Beautification Program for the installation of banners, the wrapping of the 20 new trash receptacles with vinyl graphic lamination of community art and photography to be completed in Spring 2026. Continued planning for the installation of two monuments: one at Closter Park, and the second at the Skyway Blvd and E. Alisal roundabout to be completed by September 2026.

Launched a comprehensive Zoning Code Update (ZCU), including development of a community engagement strategy presented to the Planning Commission and City Council. Conducted study sessions with the Planning Commission on the relationship between the General Plan and other City documents and codes, visioning for the ZCU, and recent state law changes.

Conservation/Open Space Element
Implemented the Mills Act program through execution of one contract and completed a draft Historic Context Statement.

Started design concepts and entitlement plans for adaptive reuse/redevelopment projects in the historic Chinatown Neighborhood.

Completed accessibility improvements at the Closter Park Recreation Center.

Continued partnership with Big Sur Land Trust on the development of a new 73-acre park at Carr Lake. Phase I, Ensen Community Park, a 7-acre community park, was completed and transferred to the City for ownership and maintenance in August 2025. Phase II, the restoration area, is currently under construction and is anticipated to open to the public in Summer 2026.

Circulation Element
Completed the Alisal Safe Routes to School project, constructing a Pedestrian Hybrid Beacon (PHB) at Williams Rd between Monte Bella Blvd and Del Monte Ave.

Completed the Main at Lamar Streets Pedestrian Crosswalk enhancement, improving existing pedestrian facilities by installing an overhead Rectangular Rapid Flashing Beacon (RRFB).

Began the update to the Traffic Calming Policy to improve the efficiency of the program.

Safety Element
Partnered with Monterey County Public Health Department to start a 2026-2030 update to the Comprehensive Strategic Plan on Violence Prevention.

SFD expanded its’ youth explorer program from 15 to 25 and recently celebrated the completion of the first cohort’s successful completion of the program.

Led the annual My Life Story Conference for professionals who work with violence and justice system impacted youth and their families to hear from their clients in a conference setting to learn how to improve our practices.

Economic Development Element
Created and staffed a new Deputy Director of Economic Development position.

Developed a 2-Year Economic Development Work Plan.

Re-established ongoing dialogue with economic development shareholders.

Continued Small Business hotline and Business Navigator position which responded to over 300 inquiries.

Visión Salinas 2040 General Plan Update 2025 Progress
Staff conducted multiple General Plan Update study sessions:

City Council – January 27 – Economic Development
Joint City Council/Planning Commission – June 10 – Pre Draft Study Session Planning Commission – October 1 – Study session on General Plan requirements and relation to other local planning documents.

The City completed internal reviews of the final administrative and screen check drafts of the General Plan and worked with the consultant to produce the Public Review Draft Visión Salinas 2040 General Plan, released in December 2025. City leadership and staff continue to meet with SPARC and other economic development shareholders to advance an updated Economic Development Element (EDE). Legal counsel reviewed administrative drafts of the Climate Action Plan (CAP) and the Environmental Impact Report (EIR) for the General Plan and CAP. Staff are also working with the consultant team to address comments on these documents in preparation for their public review drafts. 2026 Efforts and Next Steps
The City hosted a workshop event on the Draft Plan on Saturday, March 7, 2026, from 9:00 AM to Noon, at One Main Street. This event was rescheduled from February because of scheduling conflicts. Staff are also presenting the General Plan at City committees/commissions over the first quarter of the year. 1/21 - Planning Commission
2/2 - Historic Resources Board
2/23 - Public Art Commission
2/26 - Airport Commission
3/11 - Library and Community Services Commission
3/12 - Traffic and Transportation Commission
3/25 - Police Community Advisory Committee
Engagement may extend to additional study sessions, presentations, or pop-ups as necessary. Once this round of outreach is complete, staff will incorporate feedback into a second draft of the General Plan, which would include an updated EDE to be released with the public review draft EIR. The Public Review draft Climate Action Plan may be completed before these documents and released in March. The EIR release will start a mandatory 45-day comment period. Below is a projected timeline for General Plan Update progress in 2026.

Projected General Plan Update Timeline 2026
Q1
Q2
Q3
Q4
Planning Commission and other study sessions
Draft Plan Workshop and continued engagement
Revisions to administrative draft EIR/CAP
Start revisions to Draft Plan
Release draft EIR, CAP, revised GP for 45-day comment period Study sessions on EIR, CAP, and Revised GP
Revise documents following comment period
Publish revised General Plan, CAP, and EIR
Start approval process:

Monterey County Airport Land Use Commission
Planning Commission
Traffic and Transportation Commission
City Council
Planning Commission Consideration
The Planning Commission considered this item on March 4, 2026. They did not have specific comments on the GP APR and they approved a resolution recommending its acceptance and submittal to HCD and LCI.  Staff also presented the GP APR to the Housing and Land Use Committee as an informational item on March 10, 2026.

CEQA CONSIDERATION:

Not a Project.  The City of Salinas has determined that the proposed action is not a project as defined by the California Environmental Quality Act (CEQA) (CEQA Guidelines Section 15378). Any subsequent discretionary projects resulting from this action will be assessed for CEQA applicability.

CALIFORNIA GOVERNMENT CODE §84308 APPLIES:

No.

STRATEGIC PLAN INITIATIVE:

Given that the General Plan acts as the City’s guiding document for future growth and development, many of the projects listed implementing General Plan policies also implement objectives of the 2025 Strategic Plan. Examples include, but are not limited to, the Business Navigator Position, Small Business Hotline, and addition of new economic development staff, all implementing Economic Development objectives 2 and 4. The Alisal Safe Routes to School and Main Street pedestrian projects implement the Infrastructure objective of improving the City’s streets and sidewalks. Multiple playground improvements, the new Hebbron Family Center, and the Ensen Community Park also implement Infrastructure and Youth and Seniors objectives around improving public facilities.

Completing the Visión 2040 General Plan is an objective under City Services. Outreach as part of the General Plan and Zoning Code updates also helps implement the City Services objective of engaging residents and improving communication to the community. The General Plan Update also analyzes the capacity of infrastructure to support future development, implementing Infrastructure objective 4.

DEPARTMENTAL COORDINATION:

Nearly all City departments contributed to this report by describing their General Plan-related accomplishments in 2025. Although General Plan Update is led by Community Development, all departments, the City Council and City Commissions are involved in its preparation.

FISCAL AND SUSTAINABILITY IMPACT:

This report has no direct fiscal impact to the General Fund. The General Plan APR must be submitted within sixty (60) days of the April 1st deadline. Failure to submit the APR on time could make the City ineligible for certain State grant programs.

Fund
General Ledger Number
(Operating/CIP)
General Ledger Account Name
Remaining Budget Appropriation
Amount Requested
N/A
N/A
N/A
N/A
N/A
ATTACHMENTS:

Presentation
Draft 2025 General Plan Annual Progress Report
City Council Resolution
Page | 3
Page | 1

CITY OF SALINASCOUNCIL STAFF REPORTCITY OF SALINASCOUNCIL STAFF REPORT

CITY OF SALINAS

COUNCIL STAFF REPORT

CITY OF SALINAS

COUNCIL STAFF REPORT

← All documents from this meeting