DATE: SEPTEMBER 1, 2026
DEPARTMENT: PUBLIC WORKS
FROM: DAVID JACOBS, P.E., L.S., PUBLIC WORKS DIRECTOR BY: ADRIANA ROBLES, P.E., C.F.M., CITY ENGINEER JONATHAN HERNANDEZ, ASSISTANT ENGINEER TITLE: PROJECT ACCEPTANCE OF THE COVENTRY STREET AND VICTOR STREET TRAFFIC CALMING DEVICES, CIP NO. 9163 RECOMMENDED MOTION:
A motion to approve a Resolution accepting the Coventry Street and Victor Street Traffic Calming Devices, CIP No. 9163 for maintenance and responsibility.
EXECUTIVE SUMMARY:
On August 12, 2025, City Council awarded a contract to Teichert Construction in the amount of $297,839 for the construction of the Coventry Street and Victor Street Traffic Calming Devices, CIP No. 9163. Construction began on March 9, 2026, with the contract having a total of 40 working days. Throughout the project, there was a total of three (3) contract change orders that resulted in an increase of total project costs to $336,904.61, as well as an extension of contract working days to 50 days. On April 24, 2026, the project was considered substantial complete with final punch list items completed on July 14, 2026.
BACKGROUND:
On March 7, 2023, and April 9, 2024, City Council approved a Resolution approving the Neighborhood Traffic Calming Plan for Victor Street and Coventry Street. As part of the plans, a traffic circle on Coventry Street and a raised crosswalk on Victor Street were to be constructed. Due to low interest from contractors bidding on these projects individually, City staff combined the raised crosswalk and traffic circle projects into one, with the intention of adding more incentives to contractors and receiving more bids. On June 3, 2025, the City advertised the project using its On-Call Class A Contractor Services Agreement and opened bids on July 1, 2025, receiving one (1) proposal from Teichert Construction in the amount of $297,839.
On August 12, 2025, the Salinas City Council approved a Resolution (Attachment 3) awarding a construction contract to Teichert Construction in the amount of $297,839 for the construction of the Coventry Street and Victor Street Traffic Calming Devices, CIP No. 9163. Construction began on March 9, 2026, with the contract having a total of 40 working days. During construction, several unforeseen conditions lead to three (3) contract change orders issued, increasing the total project costs to $336,904.61, and increasing the contract working days to 50 days. A summary of the contract change orders are listed below:
Contract Change Order Summary
Coventry Street and Victor Street Traffic Calming Devices, CIP No. 9163 No.
Description
Amount
1 Extension of new concrete sidewalk and placement of 6” of aggregate base along with stabilization fabric $19,513.59
2 Increase in grading area
$11,246.02
3 Adjustment of existing water valve to new grade
$8,306
Contract Change Order Sub-Total
$39,065.51
Original Contract Amount
$297,839
Final Contract Amount
$336,904.51
On April 24, 2026, the project was considered substantial complete, with the final punch list items completed on July 14, 2026.
CEQA CONSIDERATION:
Categorical Exemptions. The City of Salinas has determined that the project is exempt from the California Environmental Quality Act (CEQA) Guidelines (Section 15300 et al, Class 1) because the project involves maintenance to existing streets as identified in Categorical Exemption Class 1; Section 15301(c)(d).
CALIFORNIA GOVERNMENT CODE §84308 APPLIES:
No.
STRATEGIC PLAN INITIATIVE:
This action supports the City Council goal of “Infrastructure” and “Public Safety” because the project constructs infrastructure that increases public safety by reducing speeds in residential neighborhoods.
DEPARTMENTAL COORDINATION:
The Public Works Department manages and inspects construction projects. The Public Works Department and Finance Department manage the project accounting.
FISCAL AND SUSTAINABILITY IMPACT:
The project was completed within its approved budget, and the construction contract with Teichert Construction will be paid for through CIP 9163. The City of Salinas requires contractors to submit certified payroll reports as part of its Labor Compliance Program prior to payment; at the time of this report the City is still working with the contractor to receive all certified payroll reports to issue full payment of the project. This project was funded through Measure X.
Fund
General Ledger Number (Operating/CIP)
General Ledger Account Name
Remaining Budget Appropriation
Amount Requested
n/a
n/a
n/a
n/a
n/a
ATTACHMENTS: