DATE: SEPTEMBER 29, 2025
DEPARTMENT: PUBLIC WORKS
FROM: DAVID JACOBS, PE, LS, PUBLIC WORKS DIRECTOR
BY: ADRIANA ROBLES, PE, CFM, CITY ENGINEER JONATHAN HERNANDEZ, ASSISTANT ENGINEER TITLE: PROJECT ACCEPTANCE OF THE CLOSED CIRCUIT TELEVISION (CCTV) OF SANITARY SEWER PROJECT RECOMMENDED MOTION:

A motion to approve a Resolution accepting the Closed Circuit Television (CCTV) of Sanitary Sewer Project for maintenance and responsibility.

EXECUTIVE SUMMARY:

On December 5, 2023, the City of Salinas awarded a contract to National Plant Services, Inc. in the amount of $547,512.02 for the CCTV of Sanitary Sewer Project. The work included the cleaning of sanitary sewer pipelines, and manhole and sewer line CCTV inspections. The project began on May 28, 2024, and was completed within contract time and budget on June 16, 2025.

BACKGROUND:

On March 11, 2021, President Biden signed the American Rescue Plan Act (ARPA) providing local agencies, including the City of Salinas, with funding to respond to the COVID-19 pandemic and support economic recovery. On September 14, 2021, City Council approved a plan to allocate these funds across four government service areas: Public Facilities, Public Infrastructure, Investments in Water and Sewer, and Homelessness. Based on these guidelines, staff determined that CCTV of Sanitary Sewer Project qualified for ARPA funding under the “Investments in Water and Sewer” category.

The City utilizes CCTV for pipeline video inspection to evaluate and assess the condition of underground pipelines. Video inspections aid in determining the condition of an existing pipeline, allowing staff to better define the scope, scale, and cost of repairs and/or rehabilitation work needed.

The City contracted Wallace Group using its Master Service Agreement for Professional Services for the preparation of specifications and bid documents, monitoring and review of sewer video inspections. On November 7, 2023, the City received four (4) bids through an electronic competitive bidding process, National Plant Services, Inc. (NPS) being the lowest bidder. On December 5, 2023, the Salinas City Council awarded a contract to NPS for the CCTV of Sanitary Sewer Project in the amount of $547,512.02 through Resolution No. 22861. The scope of work included the cleaning of sewer lines, management and disposal of debris removed from sewers, sewer line and manhole CCTV inspections, traffic control, and development of GIS report based on predetermined reporting standards.

A total of 240 working days were estimated for the work. During the project, one (1) contract change order was issued granting an additional working day, for a total of 241 working days. The project began on May 28, 2024, and was deemed completed on June 16, 2025, within contract time and budget.

Measurable Outputs
Table 1 summarizes the Project’s measurable outputs.

Table 1. Project Output Summary
Construction Activity
Quantity
Unit
Clean & CCTV 6” Diameter Sewer Pipe Inspection
96,745
LF
Clean & CCTV 8” Diameter Sewer Pipe Inspection
38,874
LF
Clean & CCTV 10” Diameter Sewer Pipe Inspection
9,625
LF
Clean & CCTV 12” Diameter Sewer Pipe Inspection
5,694
LF
Clean & CCTV 15” Diameter Sewer Pipe Inspection
4,212
LF
Clean & CCTV 18” Diameter Sewer Pipe Inspection
1,443
LF
Sewer Manhole Inspections
348
EA
Funding
This project was paid for by the ARPA Fund as it was identified to be categorized under the “Investment in Water and Sewer” government service area.

Project Closeout
The project was deemed completed on June 16, 2025. The construction methods and materials met the Project Specifications. Staff recommend acceptance of the project for maintenance and responsibility.

CEQA CONSIDERATION:

Categorical Exemptions. The City of Salinas has determined that the project is exempt from the California Environmental Quality Act (CEQA) Guidelines (Section 15301, Class 1) because the project involves the maintenance of existing public facilities/utilities with no expansion of use.

CALIFORNIA GOVERNMENT CODE §84308 APPLIES:

No. This project was advertised and competitively bid.

STRATEGIC PLAN INITIATIVE:

This action supports the City Council goal of Infrastructure as the project involved the inspection and cleaning of existing underground sanitary sewer infrastructure.

DEPARTMENTAL COORDINATION:

The Public Works Department managed and inspected the project. The Public Works Department and Finance Department manage the project accounting.

FISCAL AND SUSTAINABILITY IMPACT:

The project was completed within its approved budget. The construction contract with NPS will be paid for through CIP 9010.

Fund
General Ledger Number (Operating/CIP)
General Ledger Account Name
Remaining Budget Appropriation
Amount Requested
n/a
n/a
n/a
n/a
n/a
ATTACHMENTS:

Resolution
Page | 1
Page | 1

CITY OF SALINAS

COUNCIL STAFF REPORT