DATE: SEPTEMBER 29, 2026
DEPARTMENT: PUBLIC WORKS
FROM: DAVID JACOBS, PUBLIC WORKS DIRECTOR
BY: JENNY DAVILA, PUBLIC WORKS ADMIN SUPERVISOR
TITLE: AMENDMENT NO. 4 TO THE ON-CALL STREETLIGHT MAINTENANCE AGREEMENT WITH ST. FRANCIS ELECTRIC, LLC.
RECOMMENDED MOTION:
A motion to approve a resolution authorizing the City Manager to approve Amendment No. 4 with St. Francis Electric, LLC extending the current agreement for one additional year term ending December 4, 2027, and increasing the annual not-to-exceed amount by $374,000 for a revised annual compensation of $742,595.
EXECUTIVE SUMMARY:
St Francis Electric, LLC has been working with City staff to address and repair streetlight wire theft throughout the City. The contractor has completed Phases 1 and 2 of the repair work and has provided a proposal for Phases 3 and 4. On August 11, 2026, the City Council approved additional funding to support the continued repair efforts. Staff recommends that the City Council authorize the City Manager to execute Amendment No. 4 to the existing agreement with St. Francis Electric, LLC, extending the term through December 2027 and increasing the annual compensation to $742,595. Approval of the amendment will allow the City to proceed with Phases 3 and 4 of the streetlight wire theft repairs.
BACKGROUND:
In October 2023, the City issued a Request for Qualifications (RFQ) on PlanetBids for On-Call Streetlight Maintenance contractors. The City received two complete responses. Following evaluation, Bear Electrical Solutions, LLC and St. Francis Electric, LLC were both selected.
On December 5, 2023, the Salinas City Council awarded the On-Call Streetlight Maintenance Master Service Agreements to both Bear Electrical Solutions, LLC and St Francis Electric, LLC for a term of two-years with an annual not-to-exceed amount of $50,000 per contractor pursuant to Resolution 22850.
Due to increased demand for on-call streetlight maintenance services, the Public Works Department requested City Council for Approval of Amendment No. 1 to increase each agreement’s annual not-to-exceed amount to $100,000 per contractor. The request was approved by City Council under Resolution 23117.
In mid-2025, the City observed a growing number of streetlight outage reports. Upon investigation, staff determined that the streetlight wire was being cut and stolen. The Public Works Department requested quotes from both Bear Electrical Solutions, LLC and St Francis electric, LLC to replace the stolen wiring. Based on the submitted proposals and contractor availability, Amendment No. 2 was executed, increasing St. Francis electric’s overall not-to exceed amount to $250,000.
While Phase 1 of the streetlight wire replacement was being scheduled, additional streetlight wire theft occurred, impacting new locations. St. Francis Electric, LLC submitted a proposal for Phase 2 wire replacement in the amount of $136,595. City Council approved Amendment No. 3, increasing the agreement’s annual not-to-exceed amount to $386,595.
Phases 1 and 2 included the following completed locations:
Sanborn Rd between Fairview Ave and Abbott St (Phase 1) Work St between Sanborn Rd and John St (Phase 1)
Roy Diaz St between Airport Blvd and Freeway (Phase 1)
E. Alisal between Work St and N. Madeira Ave (Phase 1)
Wood St between San Benito St and Santa Maria St (Phase 1) Independence Blvd between Constitution Blvd and Lexington St (Phase 2) Front St from E. Alisal St to E. Markert St – both sides (Phase 2) E. Market from Pajaro St to Market Way (Phase 2)
E. Market St between Sherwood Dr and King St (Phase 2)
Laurel Extension between Sanborn Rd and Natividad Rd. (Phase 2) On August 11, 2026, City Council approved the reallocation of $374,000 in funding to CIP 9267 – Streetlight installation to continue the streetlight wire replacement work associated with Phases 3 and 4. The Public Works Department is requesting that City Council authorize the City manager to execute Amendment No. 4 to the Agreement with St. Francis Electric, LLC. extending the Agreement term through December 2027 and increasing the Agreement’s not-to-exceed amount by the previously approved $374,000, for a total annual not-to-exceed amount of $742,595.
Phases 3 and 4 include the following locations (not listed in order of importance):
Constitution Blvd between Beacon Hill & Boronda Rd
Nantucket Blvd between Declaration Blvd & Constitution Blvd Williams Rd between Quilla St & Boronda Rd
Quilla St between Williams Rd & Paloma St
Abbott St between Maple St & E Romie Ln
Sanborn Rd between Del Monte & Kilbreth Ave
E. Market St between Mederia Ave & Sanborn Rd
Abbott St between John St & Rossi Circle
Rossi between Qual Run & Rossi Circle
Rossi St between E. Lake St & Sansome St
Bernal between N Main & Maryal Dr
Work St between Work Circle & Sanborn Rd
Freedom Pkwy between E Alisal & Tuscany
El Dorado Dr between Boronda Rd & Buckingham Way
Market St between Sherwood Dr & Ivy St
CEQA CONSIDERATION:
Not a Project.
CALIFORNIA GOVERNMENT CODE §84308 APPLIES:
No, because this contract was subject to a competitive bidding process.
STRATEGIC PLAN INITIATIVE:
This item relates to the current City Council Goal of Infrastructure. An increase in compensation and an extension to the Master Service Agreement will contribute to the efficient and effective process to complete emergency work that benefits the community’s safety and wellbeing.
DEPARTMENTAL COORDINATION:
The Public Works Department worked alongside the City Legal Department and the City Finance Department in the Amendment No. 4 review process.
FISCAL AND SUSTAINABILITY IMPACT:
Fund
General Ledger Number (Operating/CIP)
General Ledger Account Name
Remaining Budget Appropriation
Amount Requested
5800
50.9267-63.6010
Outside Services - Other Outside Services
$443,070
$374,000
Approval of Amendment No. 4 will increase the annual not-to-exceed amount of the On-Call Streetlight Maintenance Agreement with St. Francis electric, LLC by $374,000, for a revised annual not-to-exceed amount of $742,595. This increase will not result in an increase to the City’s overall budget, as funding has been allocated within an existing Capital Improvement Project (CIP) budget. The additional funding will support the timely completion of critical streetlight repairs that contribute to public safety and reliable operation of the City’s streetlight infrastructure.