Attachment 3-Construction Cost and Cash Flow Forcast

Mayor and City Council
April 3, 2024

Document
Attachment 3-Construction Cost and Cash Flow Forcast
Meeting
April 3, 2024
Body
Mayor and City Council
Original file
170 KB
Text extracted from the city's file for reading and search. Open the original on sanbernardino.primegov.com. That file is the official record.

81.80% 18.20%
Phase Estimated Cost Buy-Down
Funds SBCTA Share CITY Share Cost to Date
(thru Jan 2024)
Project Approval and
Environmental Document
(PA/ED)
$190,000 $0 $155,420 $34,580 $103,946 $1,191,676
Design (PS&E) $460,000 $0 $376,280 $83,720 $0
Right of Way (ROW) $0 $0 $0 $0 $3,778
Construction $4,835,000 $0 $3,955,030 $879,970 $98,870
SBCTA Oversight $400,000 $0 $0 $400,000 $206,594
TOTAL $5,885,000 $0 $4,486,730 $1,398,270
2/12/2024 29.23% 70.77%
Current Coop Costs Forecast Total Coop
Difference*
City Contribution
Per Coop
Forecast City
Contribution
City Contribution
Difference* SBCTA per Coop Forecast SBCTA SBCTA Difference PA/ED 190,000 $                  207,285 $                  (17,285) $                    34,580 $                  37,726 $               (3,146) $                 155,420$              169,559 $                     (14,139) $ PS&E 460,000 $                  501,848 $                  (41,848) $                    83,720 $                  91,336 $               (7,616) $                 376,280$              410,512 $                     (34,232) $ ROW ‐ $                           ‐ $                           ‐ $                            ‐ $                        ‐ $                     ‐ $                       ‐ $                       ‐ $                              ‐ $ Construction 4,835,000 $               7,126,734 $               (2,291,734)$              879,970 $               1,297,066$         (417,096) $             3,955,030$           5,829,668 $                  (1,874,638)$ Oversight 400,000 $                  200,000 $                  200,000 $                   400,000 $               200,000 $            200,000 $              ‐ $                       ‐ $                              ‐ $ TOTAL 5,885,000$               8,035,867 $               (2,150,867)$              1,398,270$            1,626,128 $         (227,858)$             4,486,730$           6,409,739.1$              (1,923,009.1)$ *positive values are savings Conservative Estimate
KCS/CM support $827,949 KCS/CM support $827,949
$6,298,785 $4,929,825
$7,126,734 $5,757,774
Expenditure Summary
Prior  FY and
FY 23/24 to date
Remaining
FY 23/24 FY 24/25 FY 25/26 FY 26/27 FY 25/26 Future FY Total PE** $103,946 $16,054 $8,156 $906 $0 $129,062
R/W $0 $0 $0 $0 $0 $0
CON*** $3,778 $419,422 $524,320 $349,546 $0 $1,297,066
SBCTA Oversight $96,871 $10,000 $46,565 $37,252 $9,313 $200,000 Total $204,594 $445,476 $579,040 $387,704 $9,313 $0 $1,626,128 * FY is 7/1-6/30
Preliminary Engineering (PE)
CON capital (draft 100% PSE
estimate) w/20% contingency
SR‐210 Waterman Avenue Interchange ‐ SBCTA Forecast and Cash Flow Funding Table in Cooperative Agreement Expenditures to Date DIF/ City Funds DIF/City Funds Balance from
Actuals and CoopPhase
CON capital (draft 100% PSE estimate)
w/10% contingency
Right of Way (ROW)
Construction
SBCTA Oversight
TOTAL
**SBCTA combined PA/ED and PS&E into one phase (PE - Preliminary Engineering) There were advance PS&E design work completed during PA/ED phase and coded as PA/ED work because the environmental City Funds ‐ FY* Cash Flow Forecast Proposed