ID Task Name Duration Start Finish Predecessors
1 PS&E 198 days Wed 6/21/23 Fri 3/22/24
2 Draft 95% PSE submittal 0 days Wed 6/21/23 Wed 6/21/23 3 SBCTA/City Review 27 days Wed 6/21/23 Thu 7/27/23 2
4 Prepare 100% PSE 19 days Fri 7/28/23 Wed 8/23/23 3
5 Caltrans EP screencheck review 30 days Thu 8/24/23 Wed 10/4/23 4 6 Start Caltrans EP Review 0 days Wed 10/4/23 Wed 10/4/23 5 7 Caltrans EP Review 90 days Thu 10/5/23 Wed 2/7/24 6
8 Resolve Comments 22 days Thu 2/8/24 Fri 3/8/24 7
9 Prepare Final Set and Approve 10 days Mon 3/11/24 Fri 3/22/24 8 10 RTL 0 days Fri 3/22/24 Fri 3/22/24 9
11 Construction 14 days Thu 12/14/23 Wed 1/3/24
12 MVSS Approve IFB Release 0 days Thu 12/14/23 Thu 12/14/23 13 Board Approve IFB Release 0 days Wed 1/3/24 Wed 1/3/24 12 14 Coop Amendment 54 days Thu 1/18/24 Wed 4/3/24
15 Prepare and review coop
amendment
35 days Thu 1/18/24 Wed 3/6/24
16 City Approve coop amendment 0 days Wed 3/20/24 Wed 3/20/24 15 17 Board Approve coop amendment 0 days Wed 4/3/24 Wed 4/3/24 16 18 Advertisment Period 24 days Tue 4/9/24 Mon 5/13/24
19 Release IFB 0 days Tue 4/9/24 Tue 4/9/24 10FS+10 days,13,1 20 Pre‐Bid Meeting 0 days Tue 4/16/24 Tue 4/16/24 19FS+5 days 21 Questions Due 0 days Thu 4/25/24 Thu 4/25/24 20FS+7 days 22 Responses to Questions 0 days Thu 5/2/24 Thu 5/2/24 21FS+5 days 23 Bid Opening 0 days Mon 5/13/24 Mon 5/13/24 22FS+7 days 24 Bid Analysis 17 days Tue 5/14/24 Wed 6/5/24 23
25 Award 0 days Wed 6/5/24 Wed 6/5/24 24
26 Insurance, CPM, NTP 44 days Thu 6/6/24 Tue 8/6/24 25 27 Begin Work 402 days Wed 8/7/24 Thu 2/19/26 26
28 Construction 120 days Wed 8/7/24 Tue 1/21/25
29 End Construction 0 days Tue 1/21/25 Tue 1/21/25 28
30 Safety Review and Closeout 22 days Wed 1/22/25 Thu 2/20/25 29 31 Partial ROM 0 days Thu 2/20/25 Thu 2/20/25 30
32 Plant Establishment* 262 days Wed 1/22/25 Thu 1/22/26 29 33 Landscape Inspection 10 days Fri 1/23/26 Thu 2/5/26 32 34 ROM 0 days Thu 2/5/26 Thu 2/5/26 33
35 CCA 0 days Thu 2/19/26 Thu 2/19/26 34FS+10 days
198 days PS&E
6/21 Draft 95% PSE submittal
27 days SBCTA/City Review
19 days Prepare 100% PSE
30 days Caltrans EP screencheck review
10/4 Start Caltrans EP Review
90 days Caltrans EP Review
22 days Resolve Comments
10 days Prepare Final Set and Approve
3/22 RTL
14 days Construction
12/14 MVSS Approve IFB Release
1/3 Board Approve IFB Release
54 days Coop Amendment
35 days Prepare and review coop amendment
3/20 City Approve coop amendment
4/3 Board Approve coop amendment
24 days Advertisment Period
4/9 Release IFB
4/16 Pre-Bid Meeting
4/25 Questions Due
5/2 Responses to Questions
5/13 Bid Opening
17 days Bid Analysis
6/5 Award
44 days Insurance, CPM, NTP
120 days Construction
1/21 End Construction
22 days Safety Review and Closeout
2/20 Partial ROM
262 days Plant Establishm e
10 days Landscape Ins p
2/5 ROM
2/19 CCA
M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J 023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026 Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
SR-210 Waterman Construction Phase Schedule
Project: SR-210 Watermand CM
Date: Mon 2/12/24
shment*
Inspection
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029 Half 1, 2030 Half 2, 2030 Half 1, 2031 Half 2, 2031 Half Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
SR-210 Waterman Construction Phase Schedule
Project: SR-210 Watermand CM
Date: Mon 2/12/24
F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S 1, 2032 Half 2, 2032 Half 1, 2033 Half 2, 2033 Half 1, 2034 Half 2, 2034 Half 1, 2035 Half 2, 2035 Half 1, 2036 Half 2, 2036 Half 1, 2037 Half 2, 2037 Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
SR-210 Waterman Construction Phase Schedule
Project: SR-210 Watermand CM
Date: Mon 2/12/24
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M Half 1, 2038 Half 2, 2038 Half 1, 2039 Half 2, 2039 Half 1, 2040 Half 2, 2040 Half 1, 2041 Half 2, 2041 Half 1, 2042 Half 2, 2042 Half 1, 2043 Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
SR-210 Waterman Construction Phase Schedule
Project: SR-210 Watermand CM
Date: Mon 2/12/24