EXHIBIT A

CONSTRUCTION COSTS OF SHELTER IMPROVEMENTS
Animal Shelter Estimated Cost/Project Percentage of Each Item Item Square
Feet
Linear
Feet
Cubic
Yard Each Cost Project
Percentage
Kennels (270) 8,017 $2,186,080.00 60%
Electrical Wiring (120V) 3,000 $31,200.00 1%
Electrical Wiring (240V) 3000 $33,000.00 1%
Copper Water Pipes 1,430 $11,154.00 0%
Concrete Foundation 4,350 $33,495.00 1%
Grading 4,785 $31,102.50 1%
Sewer Line 911 $284,687.50 8%
Sewer Line Back Fill 911 $14,271 0%
24' x 60' Modular Building $172,703.66 5%
Curb and Gutter 534 $52,065.00 1%
Tree Removal (5) 5 $22,750.00 1%
Excavation 1,812 $108,720.00 3%
ADA Ramps 4 41600 1%
Lights 35 $11,375 0%
Design (Architect and
Engineering Fees) $151,710.17 4%
Contingency (Unforseen
Underground Utilities) $455,130.52 13%

Total $3,641,044 100%
*Additional Costs for the City of San Bernardino $358,956 100% Grand Total $4,000,000
Contribution Amount by Partner
*San Bernardino (53.5% of Costs) $2,306,915
Fontana (24% of Costs) $873,851
Rialto (14% of Costs) $509,746
Colton (7% of Costs) $254,873
Grand Terrace (1% of Costs) $36,410
Loma Linda (.5% of Costs) $18,205
Grand Total $4,000,000