Quantity Unit Unit Price Total Price Unit Price Total Price Unit Price Total Price Unit Price Total Price Unit Price Total Price 1 Mobilization LS 1 6,500.00$ 6,500.00$ 2,500.00$ 2,500.00$ 2,500.00$ 2,500.00$ 6,500.00$ 6,500.00$ 2 Temporary Removal of any existing equipment, bleachers, doors and relocate them back at the original location after theflooring completion
LS 1 6,000.00$ 6,000.00$ 10,000.00$ 10,000.00$ 10,000.00$ 10,000.00$ 18,000.00$ 18,000.00$ 3 Removal and disposal of the existing flooring and/or any unclassified debris, any unused material beneath the flooring at the gym
SF 8510 1.55$ 13,190.50$ 4.06$ 34,550.60$ 7.55$ 64,250.50$ 2.00$ 17,020.00$ 4 Remediation of any existing damages and/or depression due to imperfections in the substrate floor flatness and/or the leveling
LS 1 7,000.00$ 7,000.00$ 33,820.00$ 33,820.00$ 20,000.00$ 20,000.00$ 45,000.00$ 45,000.00$ 5 Relocate the pole sleeves as per the project specifications and special provisions EA 12 600.00$ 7,200.00$ 1,500.00$ 18,000.00$ 575.00$ 6,900.00$ 600.00$ 7,200.00$ 6 Relocate all the existing power plugs/sockets to the same as the original. LS 1 1,400.00$ 1,400.00$ -$ -$ -$ -$ 850.00$ 850.00$ 7 Furnish and install a new fixed resilient, First-grade maple wood gym floor including the skirting. SF 8510 16.25$ 138,287.50$ 17.13$ 145,805.00$ 30.00$ 255,300.00$ 25.00$ 212,750.00$ 8 Painting the new gym floor, marking layout and dimensions to be same as the original marking and painting (basketball court striping, volleyball striping, Pickleball striping etc.).

LS 1 4,500.00$ 4,500.00$ 11,625.00$ 11,625.00$ 15,000.00$ 15,000.00$ 7,500.00$ 7,500.00$ 9 Design and Installation of Parks and Water Bond Act of 2018 (Proposition 68) Sign LS 1 1,500.00$ 1,500.00$ 500.00$ 500.00$ 49.50$ 49.50$ 4,800.00$ 4,800.00$ HUR Flooring California Flooring McWil Sports Surfaces, INC. Geary Floors, Inc. Coastal Construction
Team
$185,578.00 $370,851.00 $256,800.60 $374,000.00 $319,620.00 $185,578.00 $370,851.00 $256,800.00 $374,000.00 $319,620.00 $0.00 $0.00 $0.60 $0.00 $0.00

BID RANKING

TOTAL BID AMOUNT INDICATED BY BIDDER

BID TABULATION

1. BID TABULATION
PROJECT NAME: [Rudy Hernandez Community Center - Gym Flooring Replacement] PROJECT NO: [RFP F-24-1004]
Bid Item and Description
HUR Flooring
Van Nuys , CA
Coastal Construction Team
Encino, CA
California Flooring
Winnetka, CA El Cajon, CA
Geary Floors, Inc.McWil Sports Surfaces, INC.

Gardena, CA

TOTAL BID AMOUNT CALCULATED BASED ON UNIT PRICES

CALCULATION CORRECTIONS TO BID AMOUNT SUBMITTED BY CONTRACTOR BASED ON CALCULATED BID AMOUNT S:\ENGINEERING\RFCA's\2024 All\6.5.24\Rudy Hernandez Community Center Gym Flooring Replacement\Attachment 2 - Bid TabulationBID TABULATION 1 of 1