Appeal 24-02 of Appeal 24-01 for Development Permit Type-D 21 -18, 19, 20, and 21
Presented by: Community Development and Housing Department Background
• Mar 16, 2023: Permit Type-D 21-08, 19, 20, and 21 submitted. • Feb 14, 2024: D/ERC holds hearing, receives opposition, approves project.
• Feb 27, 2024: SAFER files Appeal 24-01.
• Apr 9, 2024: Planning Commission denies Appeal 24-01, upholding project.
• Apr 22, 2024: SAFER files Appeal 24-02.
Aerial Map
Flores Street
Location/Zoning Map
Project Considerations
Hardt and Brier Business Park Project is proposed as five (5) service commercial buildings.
The buildings are designed as an open campus concept as to not incorporate an institutional presence.
Project Considerations
• Access: Multiple buildings have driveways and parking spaces on Hardt St, including ADA and bicycle parking.
• Traffic: Traffic impact from the projects is predicted to be minimal by 2025.
• Landscape: Projects will have diverse landscaping, exceeding code requirements.
• CEQA: Proximity of projects led to a study and mitigation measures; invalidation would affect all projects.
Project Plans
Conceptuals
A
D1-D2C
B
Recommendation
1. Adopt a Resolution denying Appeal 24-02, thereby upholding the Planning Commission’s denial of Appeal 24-01
The Mayor and City Council: