AMENDMENT NO. 1 TO COOPERATIVE AGREEMENT NO. 19-1002205

BETWEEN

SAN BERNARDINO COUNTY TRANSPORTATION AUTHORITY
AND

CITY OF SAN BERNARDINO
FOR

PROJECT REPORT AND ENVIRONMENTAL DOCUMENT (PA/ED),

PLANS, SPECIFICATIONS AND ESTIMATE (PS&E), RIGHT-OF-WAY (ROW),

AND CONSTRUCTION PHASES FOR THE INTERCHANGE AT UNIVERSITY PARKWAY AND INTERSTATE 215 (1-215) IN THE CITY OF SAN BERNARDINO I. PARTIES
A. This Amendment No. 1 (AMENDMENT) to Agreement 19-1002205 (AGREEMENT) is made by and between the San Bernardino County Transportation Authority (SBCTA) and the City of San Bernardino (CITY). SBCTA and CITY are each a "Party" and collectively the "Parties" herein.

I. RECITALS
A. In November 2015, Parties entered into Cooperative Agreement No. 16-100335 to to define the roles and responsibilities and funding for improvements for the PA/ED, PS&E, and ROW phases for the interchange at University Parkway and I-215 in the limits of the City of San Bernardino (PROJECT), and
B. Cooperative Agreement No. 16-100335 terminated on June 29, 2018, and C. The Parties entered into AGREEMENT in July 2019 which assumed the terms and conditions of Cooperative Agreement No. 16-100335 and had an effective date of June 30, 2018, and
D. The estimated total cost of PROJECT has increased by $2,509,100 from estimated total of $15,327,916 to $17,837,016, and
E. Parties desire to amend AGREEMENT to define funding responsibilities for the estimated cost increase of PROJECT, and
NOW, THEREFORE, the Parties agree to amend the AGREEMENT as follows:

1. Replace Attachment A in its entirety with the attached Attachment A.1

2. Except as amended by AMENDMENT, all other provisions of the AGREEMENT and amendments thereto shall remain in full force and effect and are incorporated herein by this reference.

3. AMENDMENT is deemed to be included and made part of the AGREEMENT. 1 Amendment No. 1 to 19-1002205

4. The Recitals set forth above are incorporated herein by this reference.

5. AMENDMENT is effective upon execution by SBCTA.
-----SIGNATURES ON FOLLOWING PAGE----..................... 2 Amendment No. 1 to 19-1002205
IN WITNESS WHEREOF, Parties have duly executed
Amendment No. 1 to Agreement 19-1002205 below

SAN BERNARDINO COUNTY CITY OF SAN BERNARDINO

TRANSPORTATION AUTHORITY
By:

Curt Robert D. Field
City Manager
10/9/22 5/16/32
Date: Date:

APPROVED AS TO FORM APPROVED AS TO FORM AND
PROCEDURE:

PP.
tools
14/2022 Sonia R. Carvalho
Assistant General Counsel City Attorney
3 Amendment No. 1 to 19-1002205
Amendment No. 1 to Agreement 19-1002205
Attachment A.1
Project Scope:

Improve traffic operations at the I-215 University Parkway Interchange by improving freeway access to I-215 and improving local traffic flow on University Parkway by reconstructing existing interchange configuration into a Diverging Diamond Interchange (DDI).

Project Cost Estimate and Funding Shares
After application of buy-down funds, Project costs will be split according to the SBCTA Nexus Study with the Public Share at 84.2% and the Development/Local Share at 15.8% Estimated Buy-Down Public Share Development/
Costs Local Share
Project Approval
and Environmental $1,062,176 $939,716 $103,111 $19,349
Document (PA/ED)
Design (PS&E) $1,203,856 $1,103,855 $84,201 $15,800
Right of Way $2,821,400 $612,000 $1,860,315 $349,085
(ROW)
Construction $12,179,584 $3,079,429 $7,662,331 $1,437,824 SBCTA Oversight $570,000 $0 $0 $570,000
TOTAL $17,837,016 $5,735,000 $9,709,958 $2,392,058
Project Milestones
Milestone Actual / (Forecast)
Start of PA/ED 6/2017
Environmental Approval 7/2020
Ready to List (12/2022)
Construction Notice to Proceed (7/2023)
Construction Complete (7/2024)
4 Amendment No. 1 to 19-1002205