Animal Shelter Estimated Cost/Project Percentage of Each Item Item Square Feet Linear Feet Cubic Yard Each Cost Project Percentage Kennels (270) 8,017 $2,186,080.00 55%
Electrical Wiring (120V) 3,000 $31,200.00 1%
Electrical Wiring (240V) 3000 $33,000.00 1%
Copper Water Pipes 1,430 $11,154.00 0%
Concrete Foundation 4,350 $33,495.00 1%
Grading 4,785 $31,102.50 1%
Sewer Line 911 $284,687.50 7%
Sewer Line Back Fill 911 $14,271 0%
24' x 60' Modular Building $172,703.66 4%
7' Hight Security Fence 1,300 $285,610.00 7%
Electric Fence 7,000V 1,300 $13,520.00 0%
Curb and Gutter 534 $52,065.00 1%
Tree Removal (5) 5 $22,750.00 1%
Excavation 1,812 $108,720.00 3%
ADA Ramps 4 41600 1%
Lights 35 $11,375 0%
Design (Architect and Engineering Fees) $166,666.67 4%
Contingency (Unforseen Underground Utilities) $500,000.02 13% Grand Total: $4,000,000 100%