BID TABULATION FOR
PR22-001, PR22-003: Newmark and Speicher field lighting BID OPENING: 08/31/23 @ 2:30PM
FILE: Project: PR22-001, PR22-003: Newmark and Speicher field lighting Item
No. BID ITEM DESCRIPTION Estimated
Quantity Unit
BID SCHEDULE Unit Price Total Unit Price Total Unit Price Total SCHEDULE NO. 1 Newmark

1.1 MOBILIZATION 1 LS 10,000.00$ 10,000.00$ 50,000.00$ 50,000.00$ 10,000.00$ 10,000.00$

1.2 DEMOLITION AND REMOVAL OF EXISTING SPORTS POLES 4 EA 3,500.00$ 14,000.00$ 4,000.00$ 16,000.00$ 5,000.00$ 20,000.00$

1.3 FURNISH AND INSTALL SPORTS LIGHT POLES AND LIGHTS 9 EA 46,306.22$ 416,755.98$ 35,000.00$ 315,000.00$ 48,000.00$ 432,000.00$

1.4 FURNISH AND INSTALL SPORTS POLE CONCRETE FOOTINGS 9 EA 9,774.00$ 87,966.00$ 4,500.00$ 40,500.00$ 11,000.00$ 99,000.00$

1.5 FURNISH AND INSTALL MUSCO CONTROL CABINETS 1 EA 15,176.00$ 15,176.00$ 12,000.00$ 12,000.00$ 19,000.00$ 19,000.00$

1.6 SALVAGE EXISTING SKYLOGIX CONTROL AND INSTALL IN NEW CABINET 1 EA 6,000.00$ 6,000.00$ 5,500.00$ 5,500.00$ 31,000.00$ 31,000.00$

1.7 WIRE TERMINATION AT ALL LIGHTING POLES 18 EA 525.00$ 9,450.00$ 150.00$ 2,700.00$ 300.00$ 5,400.00$

1.8 FURNISH INSTALL PARKING LOT LIGHTING POLE & FOOTING 9 EA 6,639.00$ 59,751.00$ 2,500.00$ 22,500.00$ 10,000.00$ 90,000.00$

1.9 FURNISH AND INSTALL NO. 3 1/2 PULL BOX PER CITY OF SAN BERNARDINO STANDARD DRAWING SL-2 7 EA 1,073.00$ 7,511.00$ 325.00$ 2,275.00$ 1,700.00$ 11,900.00$

1.1 FURNISH AND INSTALL NO. 5 PULL BOX PER CITY OF SAN BERNARDINO STANDARD DRAWING SL-2 13 EA 1,073.00$ 13,949.00$ 325.00$ 4,225.00$ 1,700.00$ 22,100.00$

1.11 FURNISH AND INSTALL NO. 6 PULL BOX PER CITY OF SAN BERNARDINO STANDARD DRAWING SL-2 7 EA 1,073.00$ 7,511.00$ 325.00$ 2,275.00$ 2,500.00$ 17,500.00$

1.12 FURNISH AND INSTALL 2" SCHEDULE 80 PVC CONDUIT 3,500 LF 15.53$ 54,355.00$ 110.00$ 385,000.00$ 22.00$ 77,000.00$

1.13 FURNISH AND INSTALL 2-1/2” SCHEDULE 80 PVC CONDUIT 1,500 LF 25.37$ 38,055.00$ 110.00$ 165,000.00$ 26.00$ 39,000.00$

1.14 FURNISH AND INSTALL #12 CONDUCTOR 2,000 LF 2.29$ 4,580.00$ 0.32$ 640.00$ 2.00$ 4,000.00$

1.15 FURNISH AND INSTALL #10 CONDUCTOR 4,000 LF 2.85$ 11,400.00$ 0.50$ 2,000.00$ 2.00$ 8,000.00$

1.16 FURNISH AND INSTALL #8 CONDUCTOR 3,000 LF 2.47$ 7,410.00$ 0.90$ 2,700.00$ 3.00$ 9,000.00$

1.17 FURNISH AND INSTALL #6 CONDUCTOR 2,000 LF 3.22$ 6,440.00$ 1.44$ 2,880.00$ 4.00$ 8,000.00$

1.18 FURNISH AND INSTALL #2 CONDUCTOR 5,500 LF 3.83$ 21,065.00$ 3.20$ 17,600.00$ 7.00$ 38,500.00$

1.19 FURNISH AND INSTALL #4/0 CONDUCTOR 1,300 LF 12.73$ 16,549.00$ 9.20$ 11,960.00$ 15.00$ 19,500.00$

1.2 FURNISH AND INSTALL #250 CONDUCTOR 1,300 LF 13.47$ 17,511.00$ 10.60$ 13,780.00$ 17.00$ 22,100.00$

1.21 NEW SWITCHGEAR WITH METER 1 LS 23,870.00$ 23,870.00$ 24,000.00$ 24,000.00$ 51,000.00$ 51,000.00$

1.22 NEW CONCRETE PAD FOR SWITCHGEAR 1 LS 2,900.00$ 2,900.00$ 8,500.00$ 8,500.00$ 14,000.00$ 14,000.00$

1.24 UTILITY TRANSFORMER PAD 1 LS 4,765.00$ 4,765.00$ 1,800.00$ 1,800.00$ 10,000.00$ 10,000.00$

1.25 UTILITY SECONDARY CONDUIT 15 LF 127.00$ 1,905.00$ 60.00$ 900.00$ 250.00$ 3,750.00$

1.26 WIRE CONNECTIONS AT SWITCHGEAR 1 LS 7,750.00$ 7,750.00$ 1,500.00$ 1,500.00$ 6,000.00$ 6,000.00$

1.27 TRENCHING AND BACKFILL 500 LF 13.65$ 6,825.00$ 100.00$ 50,000.00$ 50.00$ 25,000.00$

1.28 PATCH AND REPAIR OF SITE TURF AREAS 1,500 LF 4.65$ 6,975.00$ 3.25$ 4,875.00$ 17.00$ 25,500.00$

1.29 PATCH AND REPAIR OF SITE ASPHALT AREAS 800 LF 52.00$ 41,600.00$ 40.00$ 32,000.00$ 75.00$ 60,000.00$

1.3 WATER POLLUtION CONTROL, BEST MANAGEMENT PRACTICES 1 LS 1,500.00$ 1,500.00$ 2,500.00$ 2,500.00$ 3,000.00$ 3,000.00$

1.31 Project signs 1 EA 2,000.00$ 2,000.00$ 1,500.00$ 1,500.00$ 2,000.00$ 2,000.00$ Sub Total 925,524.98$ 1,202,110.00$ 1,183,250.00$ SCHEDULE NO. 2 Speicher

2.1 MOBILIZATION 1 LS 10,000.00$ 10,000.00$ 35,000.00$ 35,000.00$ 10,000.00$ 10,000.00$

2.2 FURNISH AND INSTALL SPORTS LIGHT POLES AND LIGHTS 6 EA 65,184.67$ 391,108.02$ 35,000.00$ 210,000.00$ 73,000.00$ 438,000.00$

2.3 FURNISH AND INSTALL SPORTS POLE CONCRETE FOOTINGS 6 EA 9,666.67$ 58,000.02$ 4,500.00$ 27,000.00$ 11,000.00$ 66,000.00$

2.4 FURNISH AND INSTALL MUSCO CONTROL CABINETS 1 EA 15,176.00$ 15,176.00$ 12,000.00$ 12,000.00$ 20,000.00$ 20,000.00$

2.5 FURNISH AND INSTALL SKYLOGIX CONTROL AND INSTALL IN NEW CABINET 1 EA 6,000.00$ 6,000.00$ 5,500.00$ 5,500.00$ 28,000.00$ 28,000.00$

2.6 WIRE TERMINATION AT ALL LIGHTING POLES 6 EA 525.00$ 3,150.00$ 150.00$ 900.00$ 400.00$ 2,400.00$

2.7 FURNISH AND INSTALL NO. 3 1/2 PULL BOX PER CITY OF SAN BERNARDINO STANDARD DRAWING SL-2 5 EA 1,073.00$ 5,365.00$ 325.00$ 1,625.00$ 2,000.00$ 10,000.00$

2.8 FURNISH AND INSTALL NO. 5 PULL BOX PER CITY OF SAN BERNARDINO STANDARD DRAWING SL-2 7 EA 1,073.00$ 7,511.00$ 325.00$ 2,275.00$ 2,500.00$ 17,500.00$

2.9 FURNISH AND INSTALL 2" SCHEDULE 80 PVC CONDUIT 3,000 LF 15.53$ 46,590.00$ 110.00$ 330,000.00$ 23.00$ 69,000.00$

2.1 FURNISH AND INSTALL 2-1/2” SCHEDULE 80 PVC CONDUIT 200 LF 25.37$ 5,074.00$ 110.00$ 22,000.00$ 41.00$ 8,200.00$

2.11 FURNISH AND INSTALL #10 CONDUCTOR 3,700 LF 2.85$ 10,545.00$ 0.50$ 1,850.00$ 2.00$ 7,400.00$

2.12 FURNISH AND INSTALL #8 CONDUCTOR 13,000 LF 2.47$ 32,110.00$ 0.90$ 11,700.00$ 3.00$ 39,000.00$

2.13 FURNISH AND INSTALL #4 CONDUCTOR 3,100 LF 4.05$ 12,555.00$ 2.20$ 6,820.00$ 6.00$ 18,600.00$

2.14 FURNISH AND INSTALL #1 CONDUCTOR 600 LF 5.82$ 3,492.00$ 1.80$ 1,080.00$ 9.00$ 5,400.00$

2.15 FURNISH AND INSTALL #6 CONDUCTOR 200 LF 3.22$ 644.00$ 1.44$ 288.00$ 5.00$ 1,000.00$

2.16 NEW SWITCHGEAR WITH METER 1 LS 37,396.00$ 37,396.00$ 28,210.00$ 28,210.00$ 56,000.00$ 56,000.00$

2.17 WIRE CONNECTIONS AT SWITCHGEAR 1 LS 3,590.00$ 3,590.00$ 1,500.00$ 1,500.00$ 7,000.00$ 7,000.00$

2.18 NEW CONCRETE PAD FOR SWITCHGEAR 1 LS 2,900.00$ 2,900.00$ 8,500.00$ 8,500.00$ 16,000.00$ 16,000.00$

2.19 UTILITY SECONDARY CONDUIT 300 LF 127.00$ 38,100.00$ 20.00$ 6,000.00$ 85.00$ 25,500.00$

2.2 TRENCHING AND BACKFILL 500 LF 13.65$ 6,825.00$ 100.00$ 50,000.00$ 60.00$ 30,000.00$

2.21 PATCH AND REPAIR OF SITE TURF AREAS 1,600 LF 4.65$ 7,440.00$ 3.25$ 5,200.00$ 25.00$ 40,000.00$

2.22 PATCH AND REPAIR OF SITE ASPHALT AREAS 400 LF 52.00$ 20,800.00$ 40.00$ 16,000.00$ 90.00$ 36,000.00$

1.23 WATER POLLUtION CONTROL, BEST MANAGEMENT PRACTICES 1 LS 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 2,700.00$ 2,700.00$

1.24 Project sign 1 EA 2,000.00$ 2,000.00$ 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ Sub Total 727,871.04$ 786,448.00$ 955,200.00$ TOTAL BID SCHEDULE 1,988,558.00$ 1,653,396.02$

LOW BIDDER
FEC Electric Inc.
3RD LOW
Ace Electric Inc.
2ND LOW
Southern Contracting Company
2,138,450.00$