Attachment 5-Construction Cost and Cash Flow Forecast

Mayor and City Council
September 4, 2024

Document
Attachment 5-Construction Cost and Cash Flow Forecast
Meeting
September 4, 2024
Body
Mayor and City Council
Original file
132 KB
Text extracted from the city's file for reading and search. Open the original on sanbernardino.primegov.com. That file is the official record.

SR‐210 Waterman Cost to Date Forecast at
Completion Forecast Balance Forecast at
Completion Forecast Balance
7/16/2024 TOTAL MSI CITY OTHER TOTAL TOTAL TOTAL CITY CITY Project Report and Environmental App 207,285$ 169,559$ 37,726$ -$ 207,285$ 207,285$ -$ 37,726$ 0$ Plans, Specifications, and Estimates 501,848$
410,512$
91,336$
-$
412,618$
501,848$
-$
91,336$
(0)$

Right of Way Acquisition -$
-$
-$
-$
-$
-$
-$
-$
-$

Construction & Construction Managem 7,126,734$ 5,829,668 $ 1,297,066 $ -$ 21,979$ 8,900,392$ (1,773,658)$ 1,619,871$ (322,805)$ SBCTA Project Management 200,000$
-$
200,000$
-$
108,821$
200,000$
-$
200,000$
-$

TOTAL 8,035,867$ 6,409,739$ 1,626,128$ -$
750,703$
9,809,525$ (1,773,658)$ 1,948,934$
(322,806)$

$0 R/W pending from CTD
$0 Non-participating MSI expenditures
$0 Misbilled expenditures
Construction Cost with Lowest Apparent Bid
KCS/CM support $827,949
$7,992,443
$8,820,392

81.80% 18.20%

TOTAL MSI CITY TOTAL MSI CITY
Project Report and Environmental App 207,285$ 169,559$ 37,726$ -$ 0$ (0)$ Plans, Specifications, and Estimates 501,848$
410,512$
91,336$
-$
(0)$
0$

Right of Way Acquisition -$
-$
-$
-$
-$
-$

Construction & Construction Managem 8,900,392$ 7,280,521$ 1,619,871$ 1,773,658$ 1,450,853$ 322,805$ SBCTA Project Management 200,000$ -$ 200,000$ -$ -$ -$ TOTAL 9,809,525$ 7,860,591$ 1,948,934$ 1,773,658$ 1,450,852$ 322,806$ Proposed Cooperative Agreement 22-1002720 - Amendment 2 Difference from Amendment 1 CON capital (draft 100% PSE estimate) w/10%
contingency
Cooperative Agreement 22‐1002720 ‐ Amendment 1