951-782-0707 1770 lowa Avenue #100
rickengineering.com Riverside, CA 92507
RICK
Revised: January 10, 2025
December 9, 2024
Boules Ghaly, EIT
Public Works-Engineering Division
City of San Bernardino
210 N. E. Street, 2n° Floor SAN LUIS OBISPO SANTA CLARITA PHOENIX TUCSON LAS VEGAS DENVER San Bernardino, CA
SUBJECT: TASK ORDER NUMBER 003 FOR ENGINEERING SERVICES
PLEASANT HILL DRIVE STORM DRAIN
REC JOB #16749-K
Dear Boules,
As we discussed, you would like Rick Engineering Company (RICK) to provide civil engineering services for the City of San Bernardino. The city is interested in investigating the current condition of the drainage system within an existing easement between Baldridge Canyon Drive and a Flood Control channel to the west, assess the impact of the erosion on the property at 3480 Pleasant Hill Drive, and develop a design solution to address the issue to prevent further damage.
The project anticipates replacement for up to 250 LF of concrete and corrugated metal pipe storm drain between Baldridge Canyon Drive and a Flood Control channel. It is anticipated that the existing inlet structures that picks up flow from Baldridge Canyon Drive will be maintained. The RiVeRSIDE SACRAMENTO
ibutary area to be analyzed hydrologically is anticipated to be up to 25 acres in size. Th lydrologic analysis will also consider tributary flows from the curb inlet located approximately 45 feet to the east on Palm Ave which is understood to be tributary to the lateral system, but investigation and consideration of repairs/replacement for the section of storm drain east of Baldridge Canyon Drive is not included with this scope of work.
We recommend the city perform video inspection of the existing storm drain pipe, if not already ORANGE done so, to determine the extent of pipe replacement. It is assumed that the city or the city's contractor has performed or can perform this service. Video inspection is not included with this scope of work.
The scope of work is described in detail below.
SCOPE OF WORK
ick Engineering Company "Consultant" agrees to perform the following listed services for th ompensation stated below in Section I\
Engineering Services
A. Research
Consultant will conduct research with the City of San Bernardino, County of San Boules Ghaly-City of San Bernardino
Pleasant Hill Drive Storm Drain Task Order Number 003
Revised: January 10, 2025; December 9, 2024
Bernardino, and other governing agencies for existing plans and maps of the adjacent area to be used for the design of the project. Fees required by the governing agencies for the existing plans/maps are not included with the scope anc assumed to be paid by the client.
Consultant will prepare a CAD file based on the boundary survey described below showing the existing utilities discovered in the research.
B. Right of Way and Boundary Analysis
Consultant will research available record maps, centerline tie sheets and benchmark information from the City of San Bernardino for the project site.
Research will be used to establish horizontal and vertical control for the establishment of the required topographic survey and the limits of the SCFCD easements and area of concern for Storm Drain Design. Field Survey search for and data collect existing controlling centerline monumentation. Analyze field located monuments compared with the record mapping, and complete centerline survey analysis with only certain adjacent public right of ways as needed. Note that the use and reliance of existing monuments of record is required to complete this task. If monuments of record do not exist in the field, an additional scope and fee Property lines, Centerlines and rights-of-way will be determined based on record mapping and field survey. Title report to be provided by the client.
C. Existing Topography
Consultant will provide a field survey of surface improvements; a full topo of the Flood Control District easement north of Lots 8 and 9 of Tract Map No. 4986, between Baldridge Canyon Drive going West to the Flood control Channel West of Lots 9 and 10 of said Map. The survey will include a full topo of the said channel, 50 feet North of and South of the said easement. Topo will include grades with spot elevations; spot elevations to define the existing ground; any observable utility surface appurtenances, including locating any existing Storm Drain improvements, adjacent property fences, natural flowlines, and trees.
Deliverable will be a CAD file. Topo will be 1' contours at 40 scale.
Basis of bearings will be a local centerline bearing, based on record mapping.
Vertical information will be based on available City benchmarks being NAVD 88.
Fees are based upon current prevailing wage for field crews.
D. Design Development
Consultant will conduct a site visit to investigate the current condition of the drainage system, assess the impact of the erosion for the property at 3480 Pleasant Hill Drive, and develop a design solution to address the issue. Site visit will include taking pictures of the current condition and can be provided to the City. licp.rickeng.com/projects|C_RIV_G\16749\16749K_RO\2024\San_Bernardino_SD_Pleasant_Hill Revised_2024_1209_agreement R on-call list_task_order_3.docx
RICK
Boules Ghaly-City of San Bernardino
Pleasant Hill Drive Storm Drain Task Order Number 003
Revised: January 10, 2025; December 9, 2024
E. Storm Drain Plans
Consultant will prepare one (1) set of storm drain plans (approximately 250 LF) to replace the existing deteriorated CMP pipe from the catch basin at Baldridge Canyon Drive and the existing earthen flood control channel to the west. A new headwall, rip rap and grading to repair the eroded slope within the city's storm drain easement at the outlet point to the channel and a maximum of 25-feet south of the outlet point on the channel (1,100 SF area/130 CY earthwork assumed) would be proposed. The plans to be set at a scale of 1"=40' and include plan and profile views. Scope assumes coordination with San Bernardino Flood Control District will be necessary for the regrading in the eroded area and installation of rip rap within lans will be submitted to the City of San Bernardino at 30%, 60%, and final Submittal will include the storm drain plans and bond estimate of the propose improvements.
30% submittal is intended only to get clearance from the City of San Bernardino on the horizontal alignment of the system. Vertical design may not be provided at this Scope assumes that all storm drain structures will be prepared per standard plans and no structural design/details for system will be required.
Scope does not include any existing utility relocation plans if any conflicts are found during design/construction. Traffic Control plans are not included with this scope and fee.
It is recommended that a geotechnical engineer review the site and make replacemen. This is not cludesed our dice an the trenching for the storm drain Specifications are per separate scope item below.
Final Drainage Study Letter Report
Consultant will prepare and submit to the City of San Bernardino one (1) drainage study letter report in support of the proposed work to investigate, repair, and/or replace an existing storm drain lateral to the Baldridge Creek flood control channel.
The area where repairs are anticipated to be required is understood to extend east from the existing curb inlets on Baldridge Canyon Drive (approximately 250 lineal feet). Included are rational method hydrology (modified rational method) for the tributary area (up to 25 acres), hydraulic capacity calculations to support replacement of the existing storm drain (as necessary), drainage study map, anc the letter report. The hydrologic analysis will also consider tributary flows from the curb inlet located approximately 450 feet to the east on Palm Ave which is licp.rickeng.com/projects|C_RIV_G\16749\16749K_RO\2024\San_Bernardino_SD_Pleasant_Hill Revised_2024_1209_agreement R on-call list_task_order_3.docx
RICK
Boules Ghaly-City of San Bernardino
Pleasant Hill Drive Storm Drain Task Order Number 003
Revised: January 10, 2025; December 9, 2024
understood to be tributary to the lateral system, but investigation and consideration of repairs for the section of storm drain east of Baldridge Canyon Drive is not year storm event in accordance with the San Bernardino County Hydrology Manual (dated August 1986).
The Drainage Study letter report will be submitted to the City of San Bernardino at 30% and 60% stages of design and then will be considered as final with the third submittal.
G. Meetings, Management, and Coordination
Consultant will attend meetings and coordinate with client, client's other consultants and agencies during the final engineering phase. Scope includes project management time. Actual time constraint is unknown. A budget of twenty-five (25) hours has been assumed for this task.
H. Direct Expenses
Reimbursable expenses include copying, printing, report binding, delivery, mailing, and mileage expenses incurred for the items described within the scope of work of this proposal. These expenses will be on a time and materials basis for a not-to- exceed amount below. Scope includes one (1) title report assumed at $750.
1. Specifications and Estimate
Consultant will prepare and provide technical specifications to the City of San Bernardino at 60% and final submittal following the Standard Specifications fo Public Works Construction ("Greenbook"). Consultant will also provide an opinio f probable cost and bid schedule based on the signed improvement plans. Scop s only for specifications for the improvement plans covered in this proposal. An additional scope to plans may require additional scope for specifications.
ASSUMPTIONS
1. The project will be awarded as a single prime contract for construction. Phased design and/or issue of early documents are not required.
2. The City will distribute bidding documents and prepare and administer the contract, including front end specifications, for construction.
3. Plans will be submitted electronically to the City.
4. The city's contracted representative will coordinate and submit deliverables for the processing and approvals of applicable construction permits.
5. Agency review is limited to City of San Bernardino Public Works. Changes to the plans due to reviews by agencies not listed above will be prepared under a separate agreement.
6. All Services not listed in scope of services above are excluded. licp.rickeng.com/projects C_RIV_G\16749\16749K_RO\2024\San_Bernardino_SD_Pleasant_Hill Revised_2024_1209_agreement R on-call list_task_order_3.docx
RICK
Boules Ghaly-City of San Bernardino
Pleasant Hill Drive Storm Drain Task Order Number 003
Regiss January 10, 2025; December 9, 2024
COMPENSATION
We propose to provide the above-described services for a fixed fee of $57,300 broken down as follows:
SERVICES FEE
A. Research $1,500
B. Right of Way and Boundary Analysis $6,500
C. Existing Topography $8,700
D. Design Development $4,500
E. Storm Drain Plans $14,100
F. Final Drainage Study $9,000
G. Meetings, Management, and Coordination $5,700
H. Direct Expenses $2,300
Specifications and Estimate $5,000
TOTAL FIXED FEE $57,300
SERVICES NOT INCLUDED
The following items may be required but are not included in the scope of work outlined above.
Additional authorization will be required for these services.
A. Changes in scope of design directed and authorized by Client, in writing, after the start of working drawings. In this case, the amount of extra work shall be that required to bring the revised work to the same stage of completion as the original work, at the time of the change order. In the event the Client desires any changes to the above scope of work, the terms and conditions indicated in Sections Ill and IV are subject to revision.
B. Work of a general or promotional nature not connected with the actual design, approval, or construction of the project.
C. Design and approval of a water or sewer net analysis, booster stations, pressure- reducing stations, sewer pump stations, reclaimed water systems or other utility systems, and the legal descriptions or plat preparations thereof.
D. Administration, processing, or negotiations to obtain approvals and/or signatures from third parties for such items as Letters of Permission, easements, access roads, driveways, etc.
E. Video inspection of existing storm drain
F. Aerial Topography
G. Traffic Control Plans
H. Revisions/relocations of any existing utilities
I. Revisions/relocation to existing street improvements J. Traffic Analysis
licp.rickeng.com/projects|C_RIV_G\16749\16749K_RO\2024\San_Bernardino_SD_Pleasant_Hill Revised_2024_1209_agreement R on-call list_task_order_3.docx
RICK
Boules Ghaly-City of San Bernardino
Pleasant Hill Drive Storm Drain Task Order Number 003
Revised: January 10, 2025; December 9, 2024
K. 3-D grading model
_. Detention Analysis - This is not anticipated to be required since the post-project condition drainage characteristics are anticipated to be similar compared to the pre-project condition M. WQMP - This should not be required as the project is not anticipated to be considered a Priority Project. Instead, it is considered to fall under the category of a routine maintenanc activity to maintain original line and grade, hydraulic capacity, and/or original purpose of the facility. If a WQMP is requested by the City of San Bernardino, a separate scope and fee may be required.
N. HCOC/HMP analysis - This should not be required as the project is not anticipated to be considered a Priority Project.
O. SWPPP - This is not anticipated to be required as the project is anticipated to disturb less than an acre of area. If requested, a separate scope and fee may be required.
P. Off-site Drainage Analysis - Flows tributary to the project area will be analyzed with the drainage analysis included in the Drainage Study task item above. However, off-site flows that are conveyed in the storm drain system upstream and downstream of the project will not be analyzed.
Q. Geotechnical Investigation
R. Critical Course Sediment Yield Analysis
S. Alternative Compliance
T. FEMA - The project improvements will be outside of the FEMA floodplain/floodway limits; therefore, any submittals/processing thru FEMA should not be applicable.
U. Environmental work of any nature
V. LOMR/CLOMR
W. Any surveying or mapping tasks other than those noted above X. Easements
Y. Construction staking
Z. Construction Administration
AA. Processing with Caltrans, Department of Fish and Game, Coastal Commission or the Corps of Engineers
BB. Preparation of bid packages
CC. Construction observation services
DD. Storm water collection and analysis services
EE. As-built measurements
FF. Dry utility coordination/design
GG. Existing utility study
HH. Structural Calculations
licp.rickeng.com/projects|C_RIV_G\16749\16749K_RO\2024\San_Bernardino_SD_Pleasant_Hill Revised_2024_1209_agreement R on-call list_task_order_3.docx
RICK
Boules Ghaly-City of San Bernardino
Pleasant Hill Drive Storm Drain Task Order Number 003
Revised: January 10, 2025; December 9, 2024
Any other services performed at the direction of the Client, which are not defined in the above-listed services, shall be in addition to those set forth in Item I!! of this agreement.
We will begin our services following acceptance of this task order for engineering services.
Please provide the appropriate City of San Bernardino contract for execution.
Sincerely,
RICK ENGINEERING COMPANY
Richard O'Neill, R.C.E. No. 63285, LEED AP, QSD
Associate Principal
licp.rickeng.com/projects C_RIV_G\16749\16749K_RO\2024\San_Bernardino_SD_Pleasant_Hill Revised_2024_1209_agreement R on-call list_task_order_3.docx