RESOURCE

Page 1 of 2 ends

January 13, 2025

PROPOSAL
TO: ESTIMATING DEPARTMENT
RE: City of Hope School-796 6* St. San Bernardino
Abatement
RE Proposal No. 7853-1
Resource Environmental, Inc. is pleased to provide this bid proposal for furnishing all labor, materials, equipment, disposal, and notifications to perform the following scope of work in accordance with all applicable local, state, and federal rules and regulations.

Resource is a licensed demolition and abatement contractor (Classes A, B, C-21, C-22, D-63, ASB, HAZ) with over 17 years of experience. Resource takes pride in its ability to provide the most competitive pricing, accomplished by the capacity to self-perform all work listed below.

Bid Documents/Information
• Hazardous Material Report: Comprehensive Report performed by L.Y. Environmental, Inc.

Dated July 8, 2022
Scope of Work-Regulated Building Materials
Asbestos
• All asbestos materials and quantities per survey.
• Plaster material in the walls of the Art Area approx. ~3,500 SF. • Acoustical Ceiling Material of Art Area and Workshop approx. ~4,500 SF. • 9x9 Green/Brown Floor Tile and Mastic Material of the Art Area approx. ~200 SF. 9x9 Red/Brown Floor Tile and Mastic Material of the Art Area approx. ~1,800 SF. 9x9 Brown Floor Tile and Mastic Material of the Art Area approx. ~500 SF. • Floor Tile and Mastic Material (Bottom Layer) of the Art Storage approx. 90 SF.

Lead/ Other Regulated Building Materials
• None
Conditions/Assumptions
• AQMD 10 working day notification is required before work is to start. • Safe off of all utilities is by others. Resource will assist with local agencies. • This proposal is based on a 40-hour week.

Prevailing Wages are included.
• This proposal is based on ONE mobilization. Additional mobilizations will be an added cost. • Bonds are not included. If required, Resource's bond rate is 1.25%. • Dump fees are based on current rates as of the extended date of this proposal. • Delays due to others or beyond Resource's control shall constitute additional schedule extensions and stand by cost and appropriate general condition cost. • This proposal is extended to (30) Thirty Days from the date of submission.

HAZARDOUS MATERIAL ABATEMENT • DEMOLITION • PLANT DECOMMISSIONING ASSET RECOVERY • UST REMOVAL • SOIL REMEDIATION AND STABILIZATION www.ResourceEnvironmental.com
License No. 864417
DIR Registration #1000003121
SB-PW #56165

RESOURCE

Page 2 of 2 ends

Owner/Agent/Prime Contractor Responsibilities
The owner/agent/prime contractor is responsible for:
• Permits to be obtained by owner. Resource will assist. • Safe-off/disconnection/capping/protection of all utility systems. • Layouts/Survey/Staking for any saw cutting or grade points, if applicable.

Pedestrian canopy, Temporary and permanent fencing, if applicable. • Site security if required for any reason other than protection of Resource equipment.

Temporary water, Power & SWPPP's
All sampling, testing and analysis, which may be required.

Anticipated Completion Schedule/Scheduling of Work
10 Days
Exclusions
Any abatement not part of survey, franchise haulers and fee, signs, all utility disconnects or caps, isolations or rerouting of utilities, barricades, pedestrian canopies, compaction testing, shoring, layouts, surveying, staking, engineering, UST's, and any new construction work.

Pricing Schedule
Abatement $ 94,700
Thank you for the opportunity to provide this bid proposal. Please contact me at (562) 468-7000 to answer any questions.

Respectfully submitted,
Alberto Sanchez Jr
[email protected]
Resource Environmental, Inc.

ACCEPTANCE
Company:

Name and Title:

Signature:

Date:

Purchase Order No.

HAZARDOUS MATERIAL ABATEMENT • DEMOLITION • PLANT DECOMMISSIONING ASSET RECOVERY •UST REMOVAL • SOIL REMEDIATION AND STABILIZATION www.ResourceEnvironmental.com
License No. 864417
DIR Registration #1000003121
SB-PW #56165

RESOURCE

Page 1 of 3 ends

January 13, 2025

PROPOSAL
TO: ESTIMATING DEPARTMENT
RE: City Of Hope School - 796 6th St. San Bernadino
RE Proposal No. 7853
Resource Environmental, Inc. is pleased to provide this bid proposal for furnishing all labor, materials, equipment, disposal, and notifications to perform the following scope of work in accordance with all applicable local, state, and federal rules and regulations Resource is a licensed demolition and abatement contractor (Classes A, B, C-21, C-22, D-63, ASB, HAZ) with over 17 years of experience. Resource takes pride in its ability to provide the most competitive pricing, accomplished by the capacity to self-perform all work listed below.

Bid Documents/Information
•Demolition Specifications/Plans: N/A (Site walk with Richard Miller) Scope of Work-Demolition
Demolition
Roughly 20,000 Sqft of building demolition "School of Hope" All above grade only will be demolished and off-hauled. Slabs and foundations are to remain.

All building materials will be segregated as demolition work progresses. : All known demolition debris (trash, concrete and metal) located within the limits of demolition shall be sized, loaded hauled and disposed of to a designated landfill, transfer station and/or recycling facility.

Site will be left clean with no remaining debris within the limits of demolition. : All metals, wood and salvageable equipment will be loaded, hauled and recycled for added value to the project.

Conditions/Assumptions
AQMD 10 working day notification is required before work is to start. • The removal of unknown and/or buried structures, utilities, rocks and/or debris has not been included in this scope of work.

Safe off of all utilities is by others. Resource will assist with local agencies. • Concrete slabs are not including in this proposal
Footings are not included in this proposal
All salvageable materials such as, non-ferrous metals, equipment and salvageable materials is the property of Resource. All above located at the time of the walk have been included in this proposal and any missing items shall constitute a change of condition to the contract This proposal is based on a 40-hour week.

Prevailing Wages are included.

HAZARDOUS MATERIAL ABATEMENT • DEMOLITION • PLANT DECOMMISSIONING ASSET RECOVERY • UST REMOVAL • SOIL REMEDIATION AND STABILIZATION www.ResourceEnvironmental.com
License No. 864417
DIR Registration #1000003121
SB-PW #56165

RESOURCE

Page 2 of 3 ends

• This proposal is based on one mobilization. Additional mobilizations will be an added cost. • Bonds are not included. If required, Resource's bond rate is 1.25%. • Dump fees are based on current rates as of the extended date of this proposal. • Delays due to others or beyond Resource's control shall constitute additional schedule extensions and stand by cost and appropriate general condition cost. • This proposal is extended to (30) Thirty Days from the date of submission.

Owner/Agent/Prime Contractor Responsibilities
The owner/agent/prime contractor is responsible for:
• Permits to be obtained by owner. Resource will assist. • Safe-off/disconnection/capping/protection of all utility systems. • Layouts/Survey/Staking for any saw cutting or grade points, if applicable. • Pedestrian canopy, if applicable.

Site security if required for any reason other than protection of Resource equipment.

Temporary water. (Resource will pull a temporary construction meter) Temporary and permanent fencing, if applicable. - N/A
SWPPP's. (Resource will provide waddles and gravel bags for temp BMP's) All sampling, testing and analysis, which may be required.

Anticipated Completion Schedule/Scheduling of Work
5 working days
Exclusions
• Any abatement not part of survey, franchise haulers and fee, signs, all utility disconnects or caps, isolations or rerouting of utilities, petro mat under asphalt, barricades, pedestrian canopies, unknown sub surface structures and/or conditions, compaction testing, shoring, de- watering, off-site and ROW work, soil stabilization, drying of soils, structural or utility backfill, import or export of soils/base, contaminated soils, layouts, surveying, staking, grading (rough grade/made safe is included), engineering, UST's, and any new construction work.

Pricing Schedule
Demolition $ 82,500
Abatement
Thank you for the opportunity to provide this bid proposal. Please contact me at (562) 468-7000 to answer any questions.

Respectfully submitted,
Steven Scherbarth
[email protected]
Resource Environmental, Inc.

HAZARDOUS MATERIAL ABATEMENT • DEMOLITION • PLANT DECOMMISSIONING ASSET RECOVERY • UST REMOVAL • SOIL REMEDIATION AND STABILIZATION www.ResourceEnvironmental.com
License No. 864417
DIR Registration #1000003121
SB-PW #56165

RESOURCE

Page 3 of 3 ends

ACCEPTANCE
Company:

Name and Title:

Signature:

Date:

Purchase Order No.