Attachment 7
Cost Estimate for Minor Restroom Rehabilitation Efforts The following is a cost estimate for the minor rehabilitation of 23 park restroom facilities across the City of San Bernardino. This estimate accounts for repairs and replacements needed due to extended facility closures and general wear.

Park Renovations Quote (Rough Estimate)
Item Estimated Cost
Lighting (ballasts, bulbs) $15,000
Plumbing (valve kits, wax rings, new
buttons)
$18,000
Partitions (missing or rusted, unsafe
for use)
$20,000
Staff labor $10,000
Estimated Total Cost: $63,000