JMA ENGINEERING INC. FEE PROPOSAL
SIERRA WAY STORM DRAIN
CIVIL ENGINEERING - SURVEYING - PLANNING CITY OF SAN BERNARDINO, CA MARCH 3, 2025
SCINDEEN INT
TASKS PERSONNEL HOURS
2-Man
Sr. Project Field Crew Engineering
Professional Project Survey Crew
CADD Supervisor Aide
Engineer Manager Engineer P.L.S. (Prevailing
Wage) Clerical
Hourly Rate IS. 170S 150S 135 5 115 5 149 S 379 S
Task 1.0 - Project Management
1.0 Project Management 4 40 8 $ 1,280
TOTAL Task 1 1,280
$
Task 3.0 - 65% Design Plans, Specifications and Cost Estimate
3.3 San Bernardino County Flood Control Permit 20 $
2,810
3.5 - 65% Complete Design Meeting 10 $ 1,480
TOTAL Task 3 I$ 4,290
Task 4.0 - 95% Design Plans, Specifications and Cost Estimate
4.1 - 95% Plans, Specifications, and Cost Estimate 4 32 32 32] 13,480 TOTAL Task 4 100 S
13,480
Task 5.0 - Final Design Plans, Specifications, and Cost Estimate
5.1 Final Plans, Specifications, and Cost Estimate 4 24 24 24| 10,280 TOTAL Task 5 76 8
10,280
Task 6.0 Post Design Services
6.1 Pre-Bid Construction Meeting, Bid Opening, and Construction 18 $ 2,620
5.2 Field Meetings design clarifications 18 $ 2,620
TOTAL Task 6 5,240
TOTAL Tasks 1-6 $ 34,570
TOTAL HOURS 20 60| 250
GRAND TOTAL FEE 34,570
Neet time for Potential resular meetings.