Attachment 3 - Change Order No. 2 with Mandeville Modular

Mayor and City Council
November 5, 2025

Document
Attachment 3 - Change Order No. 2 with Mandeville Modular
Meeting
November 5, 2025
Body
Mayor and City Council
Original file
673 KB
Text extracted from the city's file for reading and search. Open the original on sanbernardino.primegov.com. That file is the official record.

Powered by Merlin Al
Project Change Order ID
SB Navigation Center - Hope Campus MMI-CO-0002
Title Order Value
Material Cost escalation for structural steel $1,239,668.00 Request Date Requested By (Customer)
03/10/2025 & City of San Bernardino
Description
Project has experience a material price increase due to the city not meeting critical deadlines on the design lock to allow material procurement to procced. Multiple notifications were sent to the city and the city's designated consultant to inform them of the potential imapct on pricing due to the critical delay. Please see attached notification.

SCHEDULE IMPACT
Starting Date Original End Date
12/16/2024 01/15/2026
New End Date
Additional Days
04/09/2026
Impact Notes

COST BREAKDOWN
Original Updated Mark-
Description Unit Unit Cost Sub Total
Quantity Quantity Up (%)
0 $ 0% $
CHASSIS END CAPS 8 8 pc $19850.00 0% $158800.00
CHANNEL 10 X 20# A-36 2 DAY linear
168 168 $62.60 0% $10516.80
LEAD TIME ARO DUAL GRADE feet
CHANNEL 12 X 20.7# A992 A-992 linear
4-6 WEEK LEAD TIME ARO 240 240 $61.55 0% $14772.00
feet
16GA GALV "CS" 4 X 1 5/8 X 8' 6 linear
1310 1310 $12.91 0% $16918.65
1/2" feet
linear
16GA GALV "DLT" 4 X 1 1/2 X 10' 1150 1150 $13.59 0% $15628.50 feet
20GA "SDLT" TRACK 2 1/2" X 1 linear
1298 1298 $13.52 0% $17548.96
1/4" X 20" feet
MGB-18-TGS-01 MegaBoard
110 110 each $95.00 0% $10450.00
3/4'X48"x 96"(18X1219x2438mm)
Shear Strips 16GA 26 26 pcs $28.43 0% $739.18
16 GA Galvanized Sheets 4'X 8' 52 52 sq feet $84.00 0% $4368.00 5/8" 4X12' FC TYPE X NATIONAL
73 73 each $15.36 0% $1121.28
GYPSUM

NEW/MODIFIED TASKS
Title Serial Number Status Actual Start Expected Start Estimated Start Estimated End

MISCELLANEOUS ITEMS
Description Cost
Material price increase $1239668.00

APPROVAL LISTI
Signature Status Date
City of San Bernardino VIEWED Invalid Date