CONSENT CALENDAR
City of San Bernardino
Request for Council Action
Date: November 19, 2025
To: Honorable Mayor and City Council Members
From: Lynn Merrill, Director of Public Works, Operations & Maintenance Azzam Jabsheh, Deputy Director of Public Works/City Engineer Department: Public Works
Subject: Approving Amendment No. 3 to Cooperative Agreement No. 22-1002720 with the San Bernardino County
Transportation Authority (SBCTA) in the amount of
$65,382, for the State Route 210/ Waterman Avenue
Interchange Project (Ward 7)
Recommendation:
It is recommended that the Mayor and City Council of the City of San Bernardino, California, adopt Resolution No. 2025-391:
1. Authorizing the Director of Finance and Management Services to amend the State Route 210/Waterman Avenue Interchange Project budget and the Fiscal Year 2025/26 Capital Improvement Program (CIP) budget in the amount of $65,382. from the Measure I Fund, for a total not-to exceed amount of $2,014,316 and;
2. Authorizing the City Manager to execute Amendment No. 3 to Cooperative Agreement No. 22-1002720 with the San Bernardino County Transportation Authority (SBCTA) for the State Route 210/Waterman Avenue Interchange Project, increasing the City’s not-to-exceed contribution by $65,382 for a total not-to-exceed amount of $2,014,316 and;
3. Authorize the City Manager or designee to expend the contingency fund in the amount of $12,776, if necessary, to complete the project.
City Manager’s Comments
The City Manager concurs with the Public Works Director in recommending approval. 2 2
8 0
Executive Summary
The State Route 210/Waterman Avenue Interchange Project focuses on optimizing traffic flow, improving safety, and enhancing operational efficiency to reduce congestion and improve travel reliability. Amendment No. 3 to Cooperative Agreement No. 22-1002720 is necessary to fund additional project costs related to the extended construction schedule and added night work to minimize impacts to daytime commuters. The total City funding increase of Measure I appropriations in the amount of $65,382 reflects $52,606 in new costs and $12,776 allocated as a contingency for potential costs associated with final project closeout.
Background
The City of San Bernardino, in partnership with the San Bernardino County Transportation Authority (SBCTA), initiated the State Route 210/Waterman Avenue Interchange Project to address congestion, safety, and accessibility concerns at the I-210 Freeway and Waterman Avenue interchange. This critical project aims to improve traffic circulation, reduce delays, and enhance safety for vehicles, pedestrians, and cyclists.
The interchange improvements include adding two southbound left-turn lanes on Waterman Avenue leading to the eastbound on-ramp, widening the eastbound on- ramp to include an approximately 700-foot auxiliary lane, constructing a retaining wall adjacent to the on-ramp, removing the raised median curb on the Waterman Avenue Bridge, and re-striping the intersection at Waterman Avenue and East 30th Street to provide two northbound left-turn lanes. Collectively, these improvements will improve overall operational efficiency, safety, and connectivity between the freeway and surrounding arterial roadways.
On December 15, 2021, the Mayor and City Council approved Resolution No. 2021- 300 and Cooperative Agreement No. 22-1002720 with SBCTA for the design, environmental review, and construction of the project. The agreement established a not-to-exceed amount of $1,398,270 in Measure I funds, consisting of $400,000 from FY 2021/22 and $998,270 from FY 2022/23. SBCTA was designated as the leading agency responsible for project delivery, while the City agreed to fund its proportional share under the SBCTA Nexus formula.
On April 3, 2024, the City Council approved Resolution No. 2024-062, authorizing Amendment No. 1 to Cooperative Agreement No. 22-1002720. This amendment increased the City’s not-to-exceed amount by $227,858 using Measure S funds, bringing the total to $1,626,128. The increase was necessary to address cost escalations related to construction materials, labor, and design refinements identified during the 100% Plans, Specifications, and Estimate (PS&E) review process by Caltrans.
Following the advertisement of construction bids in May 2024, SBCTA received seven bids ranging from $7.2 million to $14 million—substantially higher than the 2 2
8 0
engineer’s estimate. The lowest responsive bid was $1,773,658 above the previously authorized funding amount. To maintain the project schedule and allow SBCTA to award the construction contract, the City Council approved Amendment No. 2 on September 4, 2024. Amendment No. 2 added $322,806 in Measure I funds, increasing the City’s not-to-exceed amount to $1,948,934.
Please see funding table below for details:
This Amendment No. 3 to Cooperative Agreement No. 22-1002720 reflects an additional cost, increasing the City’s total not-to-exceed amount from $1,948,934 to $2,014,316.
Discussion
In July 2025, SBCTA staff notified the City of additional project costs due to the extension of the construction schedule from 120 to 200 working days. The longer duration was necessary to accommodate the procurement of long-lead materials such as traffic signal poles and mast arms and to allow for increased night work to avoid traffic disruptions. These schedule changes increased total project costs by $359,239.
SBCTA will fund $293,857 (81.8 percent), while the City’s share is $65,382 (18.2 percent).
The City’s total not-to-exceed amount under the cooperative agreement will increase from $1,948,934 to $2,014,316. The City’s funding increase consists of two components:
$52,606 to be added to the FY 2025/26 CIP Budget from the Measure I Fund. $12,776 allocated as a contingency for potential Project Report and Environmental Approval activities associated with final project closeout, which may or may not be required.
This action ensures the City maintains its funding commitment to complete the project and satisfies its share of costs under the SBCTA Nexus formula. The total cost increase will be funded entirely from Measure I and will not impact the General Fund.
The project remains consistent with the City’s partnership obligations under the Valley Original FundingMeasure I - FY21/22 $400,000.00
Original Funding Measure I - FY22/23 $998,270.00
Amendment No. 1 - Measure S $227,858.00
Amendment No. 2 - Measure I $322,806.00
Total Not to Exceed $1,948,934.00
Co-Op Agreement Funding Details
2 2
8 0
Interchange Phasing Program and is listed in SBCTA’s 10-Year Delivery Plan and Nexus Study.
Please see updated funding table below:
The cost increases outlined in this amendment will be funded through Measure I.
2021-2025 Strategic Targets and Goals
This project is consistent with Key Target No. 3c: Evaluate and Enhance the quality of public safety services. This project will enhance travel path safety for the non- motoring public and contribute to clean and attractive non-motorized infrastructure network designed to support long term economic growth.
Fiscal Impact
There is no General Fund impact associated with this action. Fiscal Year 2025/26 CIP Budget will be amended by $65,382.00 utilizing the Measure I fund balance.
Conclusion
It is recommended that the Mayor and City Council of the City of San Bernardino, California, adopt Resolution No. 2025-391:
1. Authorizing the Director of Finance and Management Services to amend the State Route 210/Waterman Avenue Interchange Project budget and the Fiscal Year 2025/26 Capital Improvement Program (CIP) budget in the amount of $65,382. from the Measure I Fund, for a total not-to exceed amount of $2,014,316 and;
2. Authorizing the City Manager to execute Amendment No. 3 to Cooperative Agreement No. 22-1002720 with the San Bernardino County Transportation Authority (SBCTA) for the State Route 210/Waterman Avenue Interchange Project, increasing the City’s not-to-exceed contribution by $65,382 for a total not-to-exceed amount of $2,014,316 and;
3. Authorize the City Manager or designee to expend the contingency fund in the amount of $12,776, if necessary, to complete the project.
Attachments
Attachment 1 Resolution No. 2025-391
Attachment 2 SBCTA Cooperative agreement
Attachment 3 Construction Cost and cash flow Forecast Previous Not to Exceed cost $1,948,934.00
Amendment No.3 - Measure I $65,382.00
Total New Not- to- Exceed $2,014,316.00
2 2
8 0
Ward:
Seventh Ward
Synopsis of Previous Council Actions:
December 15, 2021 Resolution No. 2021-300 Resolution of the Mayor and City Council approving Cooperative Agreement No. 22-1002720.
April 3, 2024 Resolution No 2024-062 Resolution of the Mayor and City Council approving Amendment No 1. to Cooperative
Agreement No. 22-1002720 with SBCTA.
September 4, 2024 Resolution No. 2024 resolution of the Mayor and City Council approved Amendment No. 2 to Cooperative Agreement No. 22- 1002720 with SBCTA.
CC: Eric Levitt, City Manager