City of San Bernardino
Request for Council Action
Date: December 17, 2025
To: Honorable Mayor and City Council Members
From: Lynn Merrill, Director of Public Works
Department: Public Works
Subject: Approve Amendment No. 2 to the Professional Services Agreement with Miller Architectural Corporation for the Encanto Community Center Improvement Project for
$73,400 and Professional Services Contingencies in the
amount of $26,600. (Ward 1)
Recommendation:
It is recommended that the Mayor and City Council of the City of San Bernardino, California:
1. Approve Amendment No. 2 to the Professional Services Agreement with Miller Architectural Corporation in the amount of $73,400 for the Encanto Community Center Project (Project), increasing the not-to-exceed amount to $329,580, and extending the term to July 31, 2027; and
2. Authorize Professional Services Contingencies in the amount of $33,000 for a total Project professional services budget of $362,580; and
3. Authorize the City Manager or designee to execute all documents with Miller Architectural Corporation; and
4. Authorize the City Manager or designee to expend the contingency fund, if necessary, to complete the project.
City Manager's Comments
The City Manager recommends approval.
3 0
8 0
Executive Summary
Amending the Professional Services Agreement for Encanto Community Center would allow Miller Architectural Corporation to complete the necessary work to bid the project for construction. It will also extend the term through project construction and closeout.
The additional services will be paid for using previously allocated Project funding sources.
Background
The Encanto Community Center is a 24,660 square foot city-owned facility that was constructed in 1968 to support programs focused on providing physical, educational, vocational, rehabilitative, preventative, and recreational services to the community.
Due to the age and condition of the building, the City decided to complete improvements to the facility to address deferred maintenance needs and redesign existing spaces to allow for the restoration and expansion of recreational services at the facility.
On January 20, 2021, the Mayor and City Council adopted Resolution 2021-01 the Mayor and City Council of the City of San Bernardino, California, adopt Resolution No. 2021-1:
oApproving the use of donated funds from the Estate of Sharell Paramo to support a project for renovation of the Encanto Community Center; and oAuthorizing the Director of Finance to appropriate funds in the amount of $2,236,622 from Donations Fund No. 006 to the Encanto Community Center Improvements Project (“Project”) and amend the FY 2020-21 Capital Improvement Plan to include the Project; and
oApproving the award of a Professional Services Agreement with Miller Architectural Corporation for Project design services in the amount of $178,385 from Encanto Community Center Improvements Project Fund No. 006-380-8748.
On November 15, 2023, the Mayor and City Council approved Amendment No 1. To the Professional Services Agreement with Miller Architectural Corporation in the amount of $77,795, increasing the not to exceed amount to $256,180.
Discussion
The Encanto Community Center Project is currently in the final stages of design.
Proposed project improvements include, but are not limited to:
Locker room renovation
Multipurpose room remodel/renovation
ADA Accessibility
Staff Office remodel/renovation
Pool equipment relocation
3 0
8 0
Kitchen renovation
Gymnasium renovation
Restroom renovation
As a result of the permitting and review process, more items than previously anticipated will need to be revised in order to meet current code requirements. Additionally, the estimated project cost ($9M to 10M) significantly exceeds the current project budget.
To help proceed with the most critical elements of the project, City staff have directed the design team to prepare a phased approach to the project. This helps provide the flexibility necessary to construct portions of the project separately as additional funding sources are made available.
Amendment No. 2 provides an additional $73,400 to complete the design plans and specifications and extends the term through July 31, 2027. The extended term allows Miller Architectural Corporation to continue to provide their services through the end of the construction and project closeout process. It will also allow Miller Architectural Corporation to remain under contract in anticipation of the next phase of the Project.
An additional $33,000 is recommended for professional services contingencies.
The Project currently has an available Fund balance of $3,179,040.26 from all sources, which is sufficient to cover the cost of the additional professional services and professional services contingency total of $106,400.
Project Fund Balance
Fund Type Available Balance
Donation Fund $2,058,062.15
CDBG-CV 1 Fund $17,893.48
CDBG-CV 3 Fund $856,295.61
Cultural Development Construction $246,789.02
Total Available Balance $3,179,040.26
2021-2025 Strategic Targets and Goals
This project is consistent with Key Target No.1 - Improved Operational & Financial Capacity and Key Target No. 3 - Improved Quality of Life. Renovation of the Encanto Community Center will improve and preserve the existing facility and expand the recreational services available to the overall community.
Fiscal Impact
There is no General Fund impact associated with this item. This item will utilize previously allocated funding provided by Donation, Community Development Block Grant, and Cultural Development Construction Funds.
Conclusion
It is recommended that the Mayor and City Council of the City of San Bernardino, California:
3 0
8 0
1. Approve Amendment No. 2 to the Professional Services Agreement with Miller Architectural Corporation in the amount of $73,400 for the Encanto Community Center Project (Project), increasing the not-to-exceed amount to $329,580, and extending the term to July 31, 2027; and
2. Authorize Professional Services Contingencies in the amount of $33,000 for a total Project professional services budget of $362,580; and
3. Authorize the City Manager or designee to execute all documents with Miller Architectural Corporation; and
4. Authorize the City Manager or designee to expend the contingency fund, if necessary, to complete the project.
Attachments
Attachment 1 Amendment No 2. to the Agreement with Miller Architectural Corporation
Attachment 2 Amendment No 1. to the Agreement with Miller Architectural Corporation
Attachment 3 Professional Services Agreement Miller Architectural Corporation
Attachment 4 Location Map
Ward:
First Ward
Synopsis of Previous Council Actions:
January 20, 2021 Adopted Resolution No. 2021-1: 1. Approving the use of donated funds from the Estate of Sharell Paramo to support a project for renovation of the Encanto Community Center; and 2. Authorizing the Director of Finance to appropriate funds in the amount of $2,236,622 from Donations Fund No. 006 to the Encanto
Community Center Improvements Project (“Project”) and amend the FY 2020-21 Capital Improvement Plan to include the Project; and 3. Approving the award of a Professional Services
Agreement with Mille Architectural Corporation for Project design services in the amount of $178,385 from Encanto
Community Center Improvements Project Fund No. 006-380- 8748.
3 0
8 0
November 15, 2023 Approved Amendment No. 1 to the Professional Services Agreement with Miller Architectural Corporation in the amount of $77,795, for a total contract amount of $256,180 from Encanto Community Center Improvement Project.