Pavement Rehabilitation for 36 Centerline Miles in the City of San Bernardino Complete List for Phase I, II, III (2026-2028)
PAVEMENT IMPROVEMENT FOR 10.3 CENTERLINE MILES
TABLE 1 – PHASE I
# Street Name From To Council
Ward Project Period Maintenance
District
2025
PCI Proposed Treatment
1 NORTHPARK BLVD MOUNTAIN DR H ST 4 PHASE I - 2026 1 12 Reconstruct Surface 2 NORTHPARK BLVD H ST MOUNTAIN DR 4 PHASE I - 2026 1 8 Reconstruct Surface 3 34TH ST E ST D ST 7 PHASE I - 2026 2 61 Reconstruct Surface 4 34TH ST D ST ARROWHEAD AVE 7 PHASE I - 2026 2 48 Reconstruct Surface 5 35TH ST E ST D ST 7 PHASE I - 2026 2 9 Reconstruct Surface 6 35TH ST F ST E ST 5 PHASE I - 2026 2 17 Reconstruct Surface 7 35TH ST D ST ARROWHEAD AVE 7 PHASE I - 2026 2 16 Reconstruct Surface 8 PERSHING AVE MARSHALL BLVD 33RD ST 7 PHASE I - 2026 3 68 Reconstruct Surface 9 PERSHING AVE 33RD ST 34TH ST 7 PHASE I - 2026 3 60 Reconstruct Surface 10 PERSHING AVE 34TH ST 35TH ST 7 PHASE I - 2026 3 9 Reconstruct Surface 11 PERSHING AVE 35TH ST 36TH ST 7 PHASE I - 2026 3 7 Reconstruct Surface 12 PERSHING AVE 36TH ST THOMPSON PL 7 PHASE I - 2026 3 7 Reconstruct Surface 13 PERSHING AVE THOMPSON PL EDGERTON DR 4 PHASE I - 2026 3 5 Reconstruct Surface 14 34TH ST ARROWHEAD AVE MOUNTAIN VIEW AVE 7 PHASE I - 2026 3 47 Reconstruct Surface 15 NORTHPARK BLVD F ST MAYFIELD AVE 4 PHASE I - 2026 3 22 Reconstruct Surface 16 NORTHPARK BLVD MAYFIELD AVE F ST 4 PHASE I - 2026 3 17 Reconstruct Surface 17 PERSHING AVE 41ST ST 43RD ST 4 PHASE I - 2026 3 9 Reconstruct Surface 18 PERSHING AVE 43RD ST 46TH ST 4 PHASE I - 2026 3 10 Reconstruct Surface 19 14TH ST WALL AVE BELLE ST 2 PHASE I - 2026 7 8 Reconstruct Surface 20 14TH ST SEPULVEDA AVE WALL AVE 2 PHASE I - 2026 7 8 Reconstruct Surface 21 15TH ST LUGO AVE SEPULVEDA AVE 2 PHASE I - 2026 7 10 Reconstruct Surface 22 15TH ST WALL AVE BELLE ST 2 PHASE I - 2026 7 8 Reconstruct Surface 23 15TH ST SEPULVEDA AVE WALL AVE 2 PHASE I - 2026 7 9 Reconstruct Surface 24 15TH ST SIERRA WAY LUGO AVE 2 PHASE I - 2026 7 1 Reconstruct Surface 25 SEPULVEDA AVE 17TH ST 18TH ST 2 PHASE I - 2026 7 12 Reconstruct Surface 26 SEPULVEDA AVE 13TH ST 14TH ST 2 PHASE I - 2026 7 19 Reconstruct Surface 27 SEPULVEDA AVE 15TH ST 16TH ST 2 PHASE I - 2026 7 15 Reconstruct Surface 28 SEPULVEDA AVE 14TH ST 15TH ST 2 PHASE I - 2026 7 21 Reconstruct Surface 29 SEPULVEDA AVE 16TH ST 17TH ST 2 PHASE I - 2026 7 15 Reconstruct Surface 30 WALL AVE 13TH ST 14TH ST 2 PHASE I - 2026 7 17 Reconstruct Surface 31 WALL AVE 14TH ST 15TH ST 2 PHASE I - 2026 7 18 Reconstruct Surface 32 WALL AVE 15TH ST 16TH ST 2 PHASE I - 2026 7 8 Reconstruct Surface 33 F ST 7TH ST 8TH ST 1 PHASE I - 2026 7 16 Reconstruct Surface 34 F ST 8TH ST 9TH ST 1 PHASE I - 2026 7 25 Reconstruct Surface 35 8TH ST G ST F ST 1 PHASE I - 2026 7 17 Reconstruct Surface 36 7TH ST VICTORIA AVE H ST 1 PHASE I - 2026 8 58 Thin Mill (2.0") and Overlay + BR 37 7TH ST H ST G ST 1 PHASE I - 2026 8 57 Thick Mill (2.5") and Overlay + BR 38 CHURCH ST E ST D ST 1 PHASE I - 2026 8 32 Thin Mill (2.0") and Overlay + BR 39 CRESCENT AVE 6TH ST 7TH ST 1 PHASE I - 2026 8 51 Thick Mill (2.5") and Overlay + BR 40 F ST 6TH ST 7TH ST 1 PHASE I - 2026 8 46 Thin Mill (2.0") and Overlay + BR 41 F ST 5TH ST 6TH ST 1 PHASE I - 2026 8 21 Thin Mill (2.0") and Overlay + BR 42 SPRUCE ST H ST G ST 1 PHASE I - 2026 8 23 Thick Mill (2.5") and Overlay + BR 43 SPRUCE ST CUL-DE-SAC (W) H ST 1 PHASE I - 2026 8 38 Thick Mill (2.5") and Overlay + BR 44 VICTORIA ST F ST E ST 1 PHASE I - 2026 8 13 Thick Mill (2.5") and Overlay + BR 45 VICTORIA ST 7TH ST KNUCKLE (W/ H ST) 1 PHASE I - 2026 8 61 Thin Mill (2.0") and Overlay + BR 46 VICTORIA ST KNUCKLE (W/ H ST) H ST 1 PHASE I - 2026 8 56 Thin Mill (2.0") and Overlay + BR 47 BRYANT ST LUGO AVE ALLEN ST 1 PHASE I - 2026 8 19 Reconstruct Surface 48 BRYANT ST ALLEN ST WATERMAN AVE 1 PHASE I - 2026 8 10 Reconstruct Surface 49 KINGMAN ST SEPULVEDA AVE INTEROCEAN AVE 1 PHASE I - 2026 8 23 Reconstruct Surface 50 KINGMAN ST INTEROCEAN AVE WATERMAN AVE 1 PHASE I - 2026 8 38 Reconstruct Surface 52 RIALTO AVE EUCALYPTUS AVE PEPPER AVE 3 PHASE I - 2026 9 28 Reconstruct Surface 53 RIALTO AVE PEPPER AVE MERIDIAN AVE 3 PHASE I - 2026 9 42 Reconstruct Surface 54 RIALTO AVE MERIDIAN AVE VIA SAN CARLOS 3 PHASE I - 2026 9 13 Reconstruct Surface 55 RIALTO AVE MERIDIAN AVE PEPPER AVE 6 PHASE I - 2026 9 45 Reconstruct Surface 56 RIALTO AVE VIA SAN CARLOS MERIDIAN AVE 6 PHASE I - 2026 9 15 Reconstruct Surface 57 RIALTO AVE PEPPER AVE CITY LIMITS (675' W/
PEPPER ST) 6 PHASE I - 2026 9 10 Reconstruct Surface
58 RIALTO AVE VIA SAN CARLOS RR TRACKS 3 PHASE I - 2026 9 31 Reconstruct Surface 59 RIALTO AVE RR TRACKS VIA SAN CARLOS 6 PHASE I - 2026 9 5 Reconstruct Surface 60 ANDREWS LN KIMBERLY CT ERIN WAY 3 PHASE I - 2026 10 35 Thick Mill (2.5") and Overlay + BR 61 BEVERLY DR WIER RD ERIN WAY 3 PHASE I - 2026 10 42 Thick Mill (2.5") and Overlay + BR 62 CARL PL KIMBERLY CT ERIN WAY 3 PHASE I - 2026 10 72 Thin Mill (2.0") and Overlay + BR 63 CAROL WAY HERITAGE LN MELISSA WAY 3 PHASE I - 2026 10 29 Thick Mill (2.5") and Overlay + BR 64 COMMERCIAL RD DARTMOUTH RD WATERFORD ST 3 PHASE I - 2026 10 67 Thin Mill (2.0") and Overlay + BR 65 COMMERCIAL RD WATERFORD ST FOXCROFT WAY 3 PHASE I - 2026 10 69 Thin Mill (2.0") and Overlay + BR 66 COMMERCIAL RD HUNTS LN DARTMOUTH RD 3 PHASE I - 2026 10 53 Thin Mill (2.0") and Overlay + BR 67 COMMERCIAL RD FOXCROFT WAY WATERMAN AVE 3 PHASE I - 2026 10 67 Thin Mill (2.0") and Overlay + BR 2 | P a g e
68 ERIN WAY BEVERLY DR CARL PL 3 PHASE I - 2026 10 49 Thin Mill (2.0") and Overlay + BR 69 ERIN WAY KIMBERLY CT BEVERLY DR 3 PHASE I - 2026 10 48 Thick Mill (2.5") and Overlay + BR 70 FOXCROFT WAY HERITAGE LN COMMERCIAL DR 3 PHASE I - 2026 10 49 Rubberized Cape Seal + 3% BR 71 HARWICK DR HUNTS LN ANNAPOLIS CIR 3 PHASE I - 2026 10 25 Thick Mill (2.5") and Overlay + BR 72 HARWICK DR ANNAPOLIS CIR WIER RD 3 PHASE I - 2026 10 25 Thick Mill (2.5") and Overlay + BR 73 HERITAGE LN HUNTS LN JACKSON RD 3 PHASE I - 2026 10 18 Thick Mill (2.5") and Overlay + BR 74 HERITAGE LN JACKSON RD FOXCROFT WAY 3 PHASE I - 2026 10 17 Thick Mill (2.5") and Overlay + BR 75 HERITAGE LN FOXCROFT WAY WIER RD 3 PHASE I - 2026 10 21 Thick Mill (2.5") and Overlay + BR 76 KIMBERLY CT ERIN WAY CARL PL 3 PHASE I - 2026 10 37 Thick Mill (2.5") and Overlay + BR 77 MANCHESTER LN FOXCROFT WAY MELINDA LN 3 PHASE I - 2026 10 45 Rubberized Cape Seal + 3% BR 78 MANCHESTER LN MELINDA LN MELISSA WAY 3 PHASE I - 2026 10 43 Rubberized Cape Seal + 3% BR 79 MELINDA LN YOUNG CT MANCHESTER LN 3 PHASE I - 2026 10 43 Rubberized Cape Seal + 3% BR 80 MELISSA WAY CAROL WAY MANCHESTER LN 3 PHASE I - 2026 10 23 Thick Mill (2.5") and Overlay + BR 81 MOLLY DR WIER RD ERIN WAY 3 PHASE I - 2026 10 30 Thin Mill (2.0") and Overlay + BR 82 YOUNG CT CAROL WAY CUL-DE-SAC 3 PHASE I - 2026 10 48 Rubberized Cape Seal + 3% BR
3 | P a g e
PAVEMENT IMPROVEMENT FOR 11 CENTERLINE MILES
TABLE 2 – PHASE II
# Street Name From To Council
Ward Project Period Maintenance
District
2025
PCI Proposed Treatment
1 ACORN CIR WISTERIA AVE CUL-DE-SAC 5 PHASE II - 2027 1 65 Rubberized Cape Seal + 3% BR 2 ASHLEY CT OHIO AVE CUL-DE-SAC 5 PHASE II - 2027 1 83 Crack Seal + Slurry Seal 3 ASHTON CT REDWOOD ST CUL-DE-SAC 5 PHASE II - 2027 1 93 Crack Seal + Slurry Seal 4 AUBREY PL BELMONT AVE CUL-DE-SAC 5 PHASE II - 2027 1 85 Crack Seal + Slurry Seal 5 AUBREY PL MACLAY ST BELMONT AVE 5 PHASE II - 2027 1 58 Rubberized Cape Seal + 3% BR 6 AZALEA AVE BEECHWOOD AVE OHIO AVE 5 PHASE II - 2027 1 72 Crack Seal + Slurry Seal 7 BEECHWOOD AVE PINE AVE OHIO AVE 5 PHASE II - 2027 1 68 Rubberized Cape Seal + 3% BR 8 BELMONT AVE PINE AVE CUL-DE-SAC 5 PHASE II - 2027 1 60 Rubberized Cape Seal + 3% BR 9 BRENDA LN OHIO AVE VENTURA AVE 5 PHASE II - 2027 1 75 Crack Seal + Slurry Seal 10 BRENDA LN REDWOOD ST OHIO AVE 5 PHASE II - 2027 1 73 Crack Seal + Slurry Seal 11 BRIARWOOD CT BRENDA LN VENTURA AVE 5 PHASE II - 2027 1 73 Crack Seal + Slurry Seal 12 BRIARWOOD CT AZALEA AVE CUL-DE-SAC 5 PHASE II - 2027 1 78 Crack Seal + Slurry Seal 13 CINCINNATI CT BRENDA LN CUL-DE-SAC 5 PHASE II - 2027 1 74 Crack Seal + Slurry Seal 14 HONEYSUCKLE LN IRVINGTON AVE SUNFLOWER AVE 5 PHASE II - 2027 1 37 Thin Mill (2.0") and Overlay + BR 15 HONEYSUCKLE LN POPPY DR ROSEMARY LN 5 PHASE II - 2027 1 67 Rubberized Cape Seal + 3% BR 16 HYATT RD MACLAY ST SHEPHERD DR 5 PHASE II - 2027 1 61 Rubberized Cape Seal + 3% BR 17 LAURA LN IRVINGTON AVE MIMOSA DR 5 PHASE II - 2027 1 63 Thin Mill (2.0") and Overlay + BR 18 MACLAY ST BELMONT AVE AUBREY PL 5 PHASE II - 2027 1 58 Rubberized Cape Seal + 3% BR 19 MACLAY ST IRVINGTON AVE SHEPHERD DR 5 PHASE II - 2027 1 58 Thick Mill (2.5") and Overlay + BR 20 MIMOSA DR WALNUT AVE LAURA LN 5 PHASE II - 2027 1 62 Thin Mill (2.0") and Overlay + BR 21 PERIWINKLE DR ROBIN LN HONEYSUCKLE LN 5 PHASE II - 2027 1 68 Rubberized Cape Seal + 3% BR 22 POPPY DR PINE AVE VERBENA LN 5 PHASE II - 2027 1 73 Crack Seal + Slurry Seal 23 REDWOOD ST BEECHWOOD AVE AZALEA AVE 5 PHASE II - 2027 1 73 Crack Seal + Slurry Seal 24 REDWOOD ST PINE AVE BRENDA LN 5 PHASE II - 2027 1 87 Crack Seal + Slurry Seal 25 ROBIN LN PERIWINKLE DR ROSEMARY LN 5 PHASE II - 2027 1 70 Crack Seal + Slurry Seal 26 ROBIN RD IRVINGTON AVE CUL-DE-SAC 5 PHASE II - 2027 1 39 Thin Mill (2.0") and Overlay + BR 27 ROSEMARY LN WALNUT AVE HONEYSUCKLE LN 5 PHASE II - 2027 1 69 Rubberized Cape Seal + 3% BR 28 SHEPHERD DR HYATT RD PINE AVE 5 PHASE II - 2027 1 54 Rubberized Cape Seal + 3% BR 29 SHEPHERD DR IRVINGTON AVE HYATT RD 5 PHASE II - 2027 1 49 Rubberized Cape Seal + 3% BR 30 SUNFLOWER AVE MACLAY ST SHEPHERD DR 5 PHASE II - 2027 1 61 Rubberized Cape Seal + 3% BR 31 SUNFLOWER AVE VERBENA LN HONEYSUCKLE LN 5 PHASE II - 2027 1 33 Thin Mill (2.0") and Overlay + BR 32 VENTURA AVE BRIARWOOD CT CUL-DE-SAC 5 PHASE II - 2027 1 70 Crack Seal + Slurry Seal 33 VERBENA LN SUNFLOWER AVE POPPY DR 5 PHASE II - 2027 1 32 Thin Mill (2.0") and Overlay + BR 34 WISTERIA AVE WALNUT AVE BELMONT AVE 5 PHASE II - 2027 1 66 Rubberized Cape Seal + 3% BR 35 HIGHLAND AVE CENTRAL AVE PEPPER DR 4 PHASE II - 2027 4 53 Reconstruct Surface 36 HIGHLAND AVE STATE HOSPITAL CENTRAL AVE 4 PHASE II - 2027 4 15 Reconstruct Surface 37 HIGHLAND AVE PEPPER DR ORANGE ST 4 PHASE II - 2027 4 11 Reconstruct Surface 38 HIGHLAND AVE ORANGE ST PALM AVE 4 PHASE II - 2027 4 18 Reconstruct Surface 39 HIGHLAND AVE ORANGE ST PEPPER DR 4 PHASE II - 2027 4 17 Reconstruct Surface 40 HIGHLAND AVE CENTRAL AVE STATE HOSPITAL 4 PHASE II - 2027 4 19 Reconstruct Surface 41 HIGHLAND AVE PALM AVE ORANGE ST 4 PHASE II - 2027 4 43 Reconstruct Surface 42 HIGHLAND AVE PEPPER DR CENTRAL AVE 4 PHASE II - 2027 4 28 Reconstruct Surface 43 HIGHLAND AVE REAL JOURNEY (SHOPPING
CNTR) VICTORIA AVE 4 PHASE II - 2027 4 37 Reconstruct Surface 44 HIGHLAND AVE CITY LIMITS (650' W/ STATE
HOSPITAL) STATE HOSPITAL 4 PHASE II - 2027 4 15 Reconstruct Surface 45 HIGHLAND AVE STATE HOSPITAL REAL JOURNEY
(SHOPPING CNTR) 4 PHASE II - 2027 4 27 Reconstruct Surface 46 MUSCUPIABE DR MIRADA RD COLIMA RD (CA-
210) 7 PHASE II - 2027 5 7 Reconstruct Surface
47 MUSCUPIABE DR COLIMA RD (CA-210) MIRADA RD 2 PHASE II - 2027 5 19 Reconstruct Surface 48 MUSCUPIABE DR 27TH ST MIRADA RD 7 PHASE II - 2027 5 8 Reconstruct Surface 49 MUSCUPIABE DR MIRADA RD 27TH ST 2 PHASE II - 2027 5 11 Reconstruct Surface 50 14TH ST PERRIS ST I ST 6 PHASE II - 2027 6 9 Reconstruct Surface 51 14TH ST MASSACHUSETTS AVE PERRIS ST 6 PHASE II - 2027 6 53 Reconstruct Surface 52 14TH ST GARNER AVE MASSACHUSETTS
AVE 6 PHASE II - 2027 6 34 Reconstruct Surface
53 15TH ST PERRIS ST J ST 6 PHASE II - 2027 6 13 Reconstruct Surface 54 15TH ST MASSACHUSETTS AVE PERRIS ST 6 PHASE II - 2027 6 41 Reconstruct Surface 55 15TH ST GARNER AVE MASSACHUSETTS
AVE 6 PHASE II - 2027 6 47 Reconstruct Surface
56 15TH ST J ST I ST 6 PHASE II - 2027 6 9 Reconstruct Surface 57 EVANS ST PERRIS ST J ST 6 PHASE II - 2027 6 35 Reconstruct Surface 58 EVANS ST MASSACHUSETTS AVE PERRIS ST 6 PHASE II - 2027 6 38 Reconstruct Surface 59 EVANS ST J ST I ST 6 PHASE II - 2027 6 10 Reconstruct Surface 60 EVANS ST GARNER AVE MASSACHUSETTS
AVE 6 PHASE II - 2027 6 42 Reconstruct Surface
61 MAGNOLIA AVE J ST I ST 6 PHASE II - 2027 6 57 Reconstruct Surface 62 MAGNOLIA AVE PERRIS ST J ST 6 PHASE II - 2027 6 41 Reconstruct Surface 63 MAGNOLIA AVE GARNER AVE MASSACHUSETTS
AVE 6 PHASE II - 2027 6 25 Reconstruct Surface
64 MAGNOLIA AVE MASSACHUSETTS AVE PERRIS ST 6 PHASE II - 2027 6 30 Reconstruct Surface 65 WATERMAN AVE 4TH ST
CITY LIMITS (140'
N/ MONTEREY
AVE)
1 PHASE II - 2027
8 51 Reconstruct Surface
4 | P a g e
66 WATERMAN AVE RIALTO AVE 2ND ST 1 PHASE II - 2027 8 54 Reconstruct Surface 67 WATERMAN AVE 2ND ST 3RD ST 1 PHASE II - 2027 8 51 Reconstruct Surface 68 WATERMAN AVE 3RD ST 2ND ST 1 PHASE II - 2027 8 39 Reconstruct Surface 69 WATERMAN AVE 2ND ST RIALTO AVE 1 PHASE II - 2027 8 18 Reconstruct Surface 70 WATERMAN AVE 5TH ST 4TH ST 1 PHASE II - 2027 8 25 Reconstruct Surface 71 WATERMAN AVE 4TH ST 3RD ST 1 PHASE II - 2027 8 24 Reconstruct Surface 72 WATERMAN AVE PVMNT CHNGE (1070' N/
VALLEY ST) RIALTO AVE 1 PHASE II - 2027 8 36 Reconstruct Surface 73 WATERMAN AVE RIALTO AVE
PVMNT CHNGE
(1070' N/ VALLEY
ST)
1 PHASE II - 2027
8 37 Reconstruct Surface
74 BELDEN ST LOS ROBLES AVE JEFFERSON ST 3 PHASE II - 2027 9 68 Rubberized Cape Seal + 3% BR 75 BELDEN ST JEFFERSON ST COLLEGE DR 3 PHASE II - 2027 9 71 Rubberized Cape Seal + 3% BR 76 CARDAMON ST MERIDIAN AVE DALLAS AVE 3 PHASE II - 2027 9 74 Crack Seal + Slurry Seal 77 COLLEGE DR SUTTER AVE DALLAS AVE 3 PHASE II - 2027 9 58 Rubberized Cape Seal + 3% BR 78 COLLEGE DR BELDEN ST MERIDIAN AVE 3 PHASE II - 2027 9 61 Rubberized Cape Seal + 3% BR 79 DALLAS AVE RANDALL AVE CARDAMON ST 3 PHASE II - 2027 9 69 Crack Seal + Slurry Seal 80 DALLAS AVE LOS ROBLES AVE PLEASANT WAY 3 PHASE II - 2027 9 76 Crack Seal + Slurry Seal 81 DALLAS AVE PLEASANT WAY COLLEGE DR 3 PHASE II - 2027 9 61 Crack Seal + Slurry Seal 82 ESPERANZA ST BELDEN ST MERIDIAN AVE 3 PHASE II - 2027 9 56 Rubberized Cape Seal + 3% BR 83 JEFFERSON AVE BELDEN ST MERIDIAN AVE 3 PHASE II - 2027 9 66 Rubberized Cape Seal + 3% BR 84 LASSEN AVE PLEASANT WAY CUL-DE-SAC 3 PHASE II - 2027 9 65 Rubberized Cape Seal + 3% BR 85 LASSEN AVE LOS ROBLES AVE CUL-DE-SAC 3 PHASE II - 2027 9 59 Rubberized Cape Seal + 3% BR 86 LOS ROBLES AVE BELDEN ST MERIDIAN AVE 3 PHASE II - 2027 9 69 Rubberized Cape Seal + 3% BR 87 LOS ROBLES AVE MERIDIAN AVE DALLAS AVE 3 PHASE II - 2027 9 58 Rubberized Cape Seal + 3% BR 88 MARVIN DR LOS ROBLES AVE PLEASANT WAY 3 PHASE II - 2027 9 72 Rubberized Cape Seal + 3% BR 89 PLEASANT CT BELDEN ST CUL-DE-SAC 3 PHASE II - 2027 9 68 Rubberized Cape Seal + 3% BR 90 PLEASANT WAY SUTTER AVE DALLAS AVE 3 PHASE II - 2027 9 49 Rubberized Cape Seal + 3% BR 91 PLEASANT WAY MERIDIAN AVE SUTTER AVE 3 PHASE II - 2027 9 49 Rubberized Cape Seal + 3% BR 92 SUTTER AVE LOS ROBLES AVE CUL-DE-SAC (N) 3 PHASE II - 2027 9 73 Crack Seal + Slurry Seal 93 SUTTER AVE PLEASANT WAY COLLEGE DR 3 PHASE II - 2027 9 59 Rubberized Cape Seal + 3% BR
5 | P a g e
PAVEMENT IMPROVEMENT FOR 15.3 CENTERLINE MILES
TABLE 3 – PHASE III
# Street Name From To Council
Ward Project Period Maintenance
District
2025
PCI Proposed Treatment
1 31ST PL ROBERTSON AVE CUL-DE-SAC 5 PHASE III - 2028 2 70 Crack Seal + Slurry Seal 2 31ST ST PICO AVE MIRAMONTE DR 5 PHASE III - 2028 2 67 Rubberized Cape Seal + 3% BR 3 BUSSEY ST HERRINGTON AVE MIRAMONTE DR 5 PHASE III - 2028 2 71 Crack Seal + Slurry Seal 4 BUSSEY ST LITTLE MOUNTAIN DR PICO AVE 5 PHASE III - 2028 2 67 Rubberized Cape Seal + 3% BR 5 HERRINGTON AVE 30TH ST 31ST ST 5 PHASE III - 2028 2 62 Rubberized Cape Seal + 3% BR 6 HERRINGTON AVE 31ST ST MARSHALL BLVD 5 PHASE III - 2028 2 68 Rubberized Cape Seal + 3% BR 7 LOMITA CT ROBERDS AVE CUL-DE-SAC 5 PHASE III - 2028 2 34 Rubberized Cape Seal + 3% BR 8 LOMITA RD HERRINGTON AVE MIRAMONTE DR 5 PHASE III - 2028 2 65 Rubberized Cape Seal + 3% BR 9 PICO AVE 30TH ST BUSSEY ST 5 PHASE III - 2028 2 59 Rubberized Cape Seal + 3% BR 10 ROBERDS AVE 30TH ST BUSSEY ST 5 PHASE III - 2028 2 62 Rubberized Cape Seal + 3% BR 11 38TH ST WATERMAN AVE PARKSIDE DR 7 PHASE III - 2028 3 69 Rubberized Cape Seal + 3% BR 12 39TH ST BROADMOOR BLVD PARKSIDE DR 7 PHASE III - 2028 3 71 Crack Seal + Slurry Seal 13 39TH ST VALENCIA AVE SAN GABRIEL ST 7 PHASE III - 2028 3 70 Crack Seal + Slurry Seal 14 39TH ST KENWOOD AVE VALENCIA AVE 7 PHASE III - 2028 3 68 Rubberized Cape Seal + 3% BR 15 39TH ST 39TH ST (LOOP) 39TH ST (LOOP) 7 PHASE III - 2028 3 70 Crack Seal + Slurry Seal 16 AVERY ST PARKSIDE DR VALENCIA AVE 7 PHASE III - 2028 3 53 Rubberized Cape Seal + 3% BR 17 AVERY ST VALENCIA AVE EAST END 7 PHASE III - 2028 3 54 Rubberized Cape Seal + 3% BR 18 AVERY ST BROADMOOR BLVD PARKSIDE DR 7 PHASE III - 2028 3 70 Crack Seal + Slurry Seal 19 BROADMOOR BLVD RALSTON AVE SONORA ST 7 PHASE III - 2028 3 55 Rubberized Cape Seal + 3% BR 20 BROADMOOR BLVD AVERY ST 39TH ST 7 PHASE III - 2028 3 71 Crack Seal + Slurry Seal 21 ECHO CT PARKSIDE DR CUL-DE-SAC (E) 7 PHASE III - 2028 3 72 Crack Seal + Slurry Seal 22 ECHO CT PARKSIDE DR CUL-DE-SAC (W) 7 PHASE III - 2028 3 71 Crack Seal + Slurry Seal 23 FAIRMOUNT DR MAYWOOD AVE VALENCIA AVE 7 PHASE III - 2028 3 70 Crack Seal + Slurry Seal 24 FREMONTIA DR AVERY CT CUL-DE-SAC 7 PHASE III - 2028 3 69 Rubberized Cape Seal + 3% BR 25 KENWOOD AVE AVERY ST 39TH ST 7 PHASE III - 2028 3 66 Rubberized Cape Seal + 3% BR 26 MAYWOOD AVE PARKSIDE DR VALENCIA AVE 7 PHASE III - 2028 3 71 Rubberized Cape Seal + 3% BR 27 MAYWOOD CT MAYWOOD AVE CUL-DE-SAC 7 PHASE III - 2028 3 71 Rubberized Cape Seal + 3% BR 28 PALMCROFT BLVD PARKDALE DR MAYWOOD AVE 7 PHASE III - 2028 3 68 Rubberized Cape Seal + 3% BR 29 PARKSIDE DR RALSTON AVE 40TH ST 7 PHASE III - 2028 3 70 Crack Seal + Slurry Seal 30 PARKSIDE DR PARKDALE DR ECHO CT 7 PHASE III - 2028 3 70 Crack Seal + Slurry Seal 31 PARKSIDE DR ECHO CT RALSTON AVE 7 PHASE III - 2028 3 69 Crack Seal + Slurry Seal 32 PEPPER TREE LN AVERY ST CUL-DE-SAC 7 PHASE III - 2028 3 61 Rubberized Cape Seal + 3% BR 33 RALSTON AVE PARKSIDE DR VALENCIA AVE 7 PHASE III - 2028 3 57 Rubberized Cape Seal + 3% BR 34 RALSTON AVE VALENCIA AVE SAN GABRIEL ST 7 PHASE III - 2028 3 56 Rubberized Cape Seal + 3% BR 35 RALSTON AVE BROADMOOR BLVD PARKSIDE DR 7 PHASE III - 2028 3 55 Rubberized Cape Seal + 3% BR 36 RALSTON AVE RALSTON AVE (LOOP) RALSTON AVE
(LOOP) 7 PHASE III - 2028 3 49 Rubberized Cape Seal + 3% BR 37 SAN GABRIEL CT 39TH ST CUL-DE-SAC 7 PHASE III - 2028 3 36 Crack Seal + Slurry Seal 38 SAN GABRIEL ST SONORA ST 40TH ST 7 PHASE III - 2028 3 56 Rubberized Cape Seal + 3% BR 39 SAN GABRIEL ST 39TH ST RALSTON AVE 7 PHASE III - 2028 3 55 Rubberized Cape Seal + 3% BR 40 SONORA ST BROADMOOR BLVD PARKSIDE DR 7 PHASE III - 2028 3 60 Rubberized Cape Seal + 3% BR 41 SONORA ST VALENCIA AVE SAN GABRIEL ST 7 PHASE III - 2028 3 54 Rubberized Cape Seal + 3% BR 42 SONORA ST PARKSIDE DR VALENCIA AVE 7 PHASE III - 2028 3 56 Rubberized Cape Seal + 3% BR 43 17TH ST COLWYN AVE DUNDEE AVE 4 PHASE III - 2028 4 38 Thin Mill (2.0") and Overlay + BR 44 17TH ST OLIVE ST BANGOR AVE 4 PHASE III - 2028 4 47 Thin Mill (2.0") and Overlay + BR 45 ATLANTIC AVE OLIVE ST DUNDEE AVE 4 PHASE III - 2028 4 52 Thin Mill (2.0") and Overlay + BR 46 BANGOR AVE 17TH ST ATLANTIC AVE 4 PHASE III - 2028 4 69 Thick Mill (2.5") and Overlay + BR 47 CLIFTON AVE CENTRAL AVE ORANGE ST 4 PHASE III - 2028 4 62 Thin Mill (2.0") and Overlay + BR 48 COLWYN AVE PACIFIC ST ATLANTIC AVE 4 PHASE III - 2028 4 56 Thick Mill (2.5") and Overlay + BR 49 DUNDEE AVE 17TH ST ATLANTIC AVE 4 PHASE III - 2028 4 50 Thick Mill (2.5") and Overlay + BR 50 LILLIAN LN CLIFTON AVE CUL-DE-SAC 4 PHASE III - 2028 4 67 Rubberized Cape Seal + 3% BR 51 OLIVE ST PACIFIC ST ATLANTIC AVE 4 PHASE III - 2028 4 39 Thick Mill (2.5") and Overlay + BR 52 OLIVE TREE LN CLIFTON AVE CUL-DE-SAC 4 PHASE III - 2028 4 70 Rubberized Cape Seal + 3% BR 53 PEPPER CT CLIFTON AVE CUL-DE-SAC 4 PHASE III - 2028 4 69 Rubberized Cape Seal + 3% BR 54 VILLA CT CLIFTON AVE CUL-DE-SAC 4 PHASE III - 2028 4 71 Rubberized Cape Seal + 3% BR 55 28TH ST TURRILL AVE DAVIDSON AVE 2 PHASE III - 2028 5 55 Rubberized Cape Seal + 3% BR 56 28TH ST CUL-DE-SAC (W) TURILL AVE 2 PHASE III - 2028 5 57 Crack Seal + Slurry Seal 57 29TH ST MIRAMONTE DR TURRILL AVE 2 PHASE III - 2028 5 55 Rubberized Cape Seal + 3% BR 58 ALEXANDER AVE LITTLE MOUNTAIN DR DAVIDSON AVE 2 PHASE III - 2028 5 70 Crack Seal + Slurry Seal 59 DAVIDSON AVE OAKWOOD DR COLIMA RD 2 PHASE III - 2028 5 73 Crack Seal + Slurry Seal 60 DAVIDSON AVE 28TH ST OAKWOOD DR 2 PHASE III - 2028 5 71 Crack Seal + Slurry Seal 61 DAVIDSON AVE 27TH ST 28TH ST 2 PHASE III - 2028 5 70 Crack Seal + Slurry Seal 62 GARNER AVE OAKWOOD DR COLIMA RD 2 PHASE III - 2028 5 71 Crack Seal + Slurry Seal 63 MIRADA RD SERRANO RD MUSCUPIABE DR 2 PHASE III - 2028 5 58 Rubberized Cape Seal + 3% BR 64 MIRADA RD MIRAMONTE DR TURRILL AVE 2 PHASE III - 2028 5 70 Crack Seal + Slurry Seal 65 OAKWOOD DR TURRILL AVE DAVIDSON AVE 2 PHASE III - 2028 5 62 Rubberized Cape Seal + 3% BR 66 OAKWOOD DR MIRAMONTE DR TURRILL AVE 2 PHASE III - 2028 5 54 Rubberized Cape Seal + 3% BR 67 SERRANO RD MIRADA RD COLIMA RD 2 PHASE III - 2028 5 70 Crack Seal + Slurry Seal 68 SERRANO RD 27TH ST MIRADA RD 2 PHASE III - 2028 5 71 Crack Seal + Slurry Seal 69 TURRILL AVE 28TH ST OAKWOOD DR 2 PHASE III - 2028 5 55 Rubberized Cape Seal + 3% BR 70 TURRILL AVE OAKWOOD DR COLIMA RD 2 PHASE III - 2028 5 52 Rubberized Cape Seal + 3% BR 71 ADAMS ST SAN CARLO AVE SAN ANSELMO AVE 6 PHASE III - 2028 6 46 Rubberized Cape Seal + 3% BR 72 ADAMS ST SAN ANSELMO AVE MACY ST 6 PHASE III - 2028 6 25 Thin Mill (2.0") and Overlay + BR 73 DONALD ST DUFFY ST SAN ANSELMO AVE 6 PHASE III - 2028 6 70 Crack Seal + Slurry Seal 6 | P a g e
74 DUFFY ST MESA ST SAN ANSELMO CT 6 PHASE III - 2028 6 69 Rubberized Cape Seal + 3% BR 75 DUFFY ST DONALD ST MESA ST 6 PHASE III - 2028 6 69 Rubberized Cape Seal + 3% BR 76 DUFFY ST SAN ANSELMO CT
CITY LIMITS (160'
N/ SAN ANSELMO
AVE)
6 PHASE III - 2028
6 70 Rubberized Cape Seal + 3% BR
77 MESA ST SAN ANSELMO AVE CITY LIMITS (150'
E/ SAN ANSELMO) 6 PHASE III - 2028 6 15 Thin Mill (2.0") and Overlay + BR 78 MESA ST SAN CARLO AVE SAN ANSELMO AVE 6 PHASE III - 2028 6 55 Crack Seal + Slurry Seal 79 MESA ST DUFFY ST SAN CARLO AVE 6 PHASE III - 2028 6 55 Rubberized Cape Seal + 3% BR 80 SAN ANSELMO AVE MESA ST DUFFY ST 6 PHASE III - 2028 6 54 Rubberized Cape Seal + 3% BR 81 SAN ANSELMO AVE DONALD ST ADAMS ST 6 PHASE III - 2028 6 56 Rubberized Cape Seal + 3% BR 82 SAN ANSELMO AVE ADAMS ST MESA ST 6 PHASE III - 2028 6 52 Rubberized Cape Seal + 3% BR 83 SAN ANSELMO CT DUFFY ST CUL-DE-SAC 6 PHASE III - 2028 6 54 Crack Seal + Slurry Seal 84 SAN BENITO CT ADAMS ST CUL-DE-SAC 6 PHASE III - 2028 6 55 Rubberized Cape Seal + 3% BR 85 SAN CARLO AVE MESA ST SAN ANSELMO AVE 6 PHASE III - 2028 6 69 Rubberized Cape Seal + 3% BR 86 SAN CARLO AVE ADAMS ST MESA ST 6 PHASE III - 2028 6 69 Rubberized Cape Seal + 3% BR 87 SAN CARLO CT SAN CARLO AVE CUL-DE-SAC 6 PHASE III - 2028 6 55 Rubberized Cape Seal + 3% BR 88 10TH ST SIERRA WAY WALL AVE 1 PHASE III - 2028 7 21 Thin Mill (2.0") and Overlay + BR 89 10TH ST MOUNTAIN VIEW AVE SIERRA WAY 1 PHASE III - 2028 7 59 Thin Mill (2.0") and Overlay + BR 90 10TH ST WALL AVE WATERMAN AVE 1 PHASE III - 2028 7 34 Thick Mill (2.5") and Overlay + BR 91 11TH ST SEPULVEDA AVE WALL AVE 1 PHASE III - 2028 7 55 Thin Mill (2.0") and Overlay + BR 92 11TH ST MOUNTAIN VIEW AVE SIERRA WAY 1 PHASE III - 2028 7 41 Thin Mill (2.0") and Overlay + BR 93 11TH ST SIERRA WAY SEPULVEDA AVE 1 PHASE III - 2028 7 52 Thin Mill (2.0") and Overlay + BR 94 11TH ST WALL AVE WATERMAN AVE 1 PHASE III - 2028 7 52 Thick Mill (2.5") and Overlay + BR 95 LUGO AVE 11TH ST BASELINE ST 1 PHASE III - 2028 7 61 Thin Mill (2.0") and Overlay + BR 96 OLIVE ST SIERRA WAY WALL AVE 1 PHASE III - 2028 7 68 Thin Mill (2.0") and Overlay + BR 97 OLIVE ST MOUNTAIN VIEW AVE SIERRA WAY 1 PHASE III - 2028 7 51 Thin Mill (2.0") and Overlay + BR 98 OLIVE ST WALL AVE WATERMAN AVE 1 PHASE III - 2028 7 19 Thick Mill (2.5") and Overlay + BR 99 ORANGE ST MOUNTAIN VIEW AVE SIERRA WAY 1 PHASE III - 2028 7 28 Thick Mill (2.5") and Overlay + BR 100 ORANGE ST WALL AVE WATERMAN AVE 1 PHASE III - 2028 7 34 Thin Mill (2.0") and Overlay + BR 101 SEPULVEDA AVE 11TH ST BASELINE ST 1 PHASE III - 2028 7 61 Thin Mill (2.0") and Overlay + BR 102 WALL AVE 10TH ST 11TH ST 1 PHASE III - 2028 7 27 Thin Mill (2.0") and Overlay + BR 103 WALL AVE 11TH ST BASELINE ST 1 PHASE III - 2028 7 25 Thin Mill (2.0") and Overlay + BR 104 COULSTON ST BARRINGTON PL RICHARDSON ST 3 PHASE III - 2028 10 40 Reconstruct Surface 105 COULSTON ST JASMINE CT CURTIS ST 3 PHASE III - 2028 10 19 Reconstruct Surface 106 COULSTON ST CURTIS ST ROSENA AVE 3 PHASE III - 2028 10 12 Reconstruct Surface 107 COULSTON ST TIPPECANOE AVE FERRE ST 3 PHASE III - 2028 10 20 Reconstruct Surface 108 COULSTON ST FERREE ST BARRINGTON PL 3 PHASE III - 2028 10 38 Reconstruct Surface 109 COULSTON ST ROSENA AVE MOUNTAIN VIEW
AVE 3 PHASE III - 2028 10 9 Reconstruct Surface
110 COULSTON ST RICHARDSON ST JASMIN CT 3 PHASE III - 2028 10 46 Reconstruct Surface 111 COULSTON ST JASMIN CT RICHARDSON ST 3 PHASE III - 2028 10 24 Reconstruct Surface 112 COULSTON ST CURTIS ST JASMINE CT 3 PHASE III - 2028 10 37 Reconstruct Surface 113 COULSTON ST ROSENA AVE CURTIS ST 3 PHASE III - 2028 10 27 Reconstruct Surface 114 CURTIS ST COULSTON ST GOULD ST 3 PHASE III - 2028 10 15 Reconstruct Surface 115 DAVIDSON ST FERREE ST RICHARDSON ST 3 PHASE III - 2028 10 12 Reconstruct Surface 116 DAVIDSON ST TIPPECANOE AVE FERREE ST 3 PHASE III - 2028 10 25 Reconstruct Surface 117 DAVIDSON ST RICHARDSON ST CURTIS ST 3 PHASE III - 2028 10 9 Reconstruct Surface 118 ELM AVE COULSTON AVE GOULD ST 3 PHASE III - 2028 10 37 Reconstruct Surface 119 GOULD ST TIPPECANOE AVE FERREE ST 3 PHASE III - 2028 10 30 Reconstruct Surface 120 GOULD ST FERREE ST RICHARDSON ST 3 PHASE III - 2028 10 26 Reconstruct Surface 121 GOULD ST CURTIS ST HARDT ST 3 PHASE III - 2028 10 13 Reconstruct Surface 122 GOULD ST RICHARDSON ST CURTIS ST 3 PHASE III - 2028 10 30 Reconstruct Surface 123 HARDT ST CURTIS ST GOULD ST 3 PHASE III - 2028 10 21 Reconstruct Surface 124 HARDT ST RICHARDSON ST CURTIS ST 3 PHASE III - 2028 10 32 Reconstruct Surface 125 ROSENA AVE COULSTON ST GOULD ST 3 PHASE III - 2028 10 21 Reconstruct Surface