Cities Index.
Attachment 3 - Funding Table

Mayor and City Council
June 17, 2026

Document
Attachment 3 - Funding Table
Meeting
June 17, 2026
Body
Mayor and City Council
Original file
112 KB
Text extracted from the city's file for reading and search. Open the original on sanbernardino.primegov.com. That file is the official record.

67.2% 32.8%
SR-210 Del Rosa Interchange Engineers Estimate Escalated 4% for 6 years 7/8/2025 TOTAL MSI CITY OTHER 1.04 15,000,000.00$
Project Report and Environmental Approval*,** 2,200,000$ 1,478,400$ 721,600$ 1.04 15,600,000.00$ Plans, Specifications, and Estimates 1,500,000$ 1,008,000$ 492,000$ 1.04 16,224,000.00$ Right of Way Acquisition 610,000$ 409,920$ 200,080$ 500,000$ 610,000$ 1.04 16,872,960.00$ Construction & Construction Management 35,650,000$ 3,823,680$ 31,826,320$ 24,607,601$ 31,000,000$ 1.04 17,547,878.40$ SBCTA Project Management 400,000$ -$ 400,000$ 1.04 18,249,793.54$ TOTAL 40,360,000$ 6,720,000$ 33,640,000$ Escalated Total 40,360,000$ *includes PID phase and Caltrans oversight fee
**assumes CE for environmental document

64.3% 35.7%
I-215 Palm Avenue Interchange Engineers Estimate Escalated 4% for 6 years 6/25/2025 TOTAL MSI CITY OTHER
Project Report and Environmental Approval*,** 3,300,000$ 2,121,900$ 1,178,100$ Plans, Specifications, and Estimates 3,500,000$ 2,250,500$ 1,249,500$ Right of Way Acquisition -$ -$ -$ 500,000$ 608,326$ Construction & Construction Management -$ -$ -$ 71,173,000$ 86,592,873$ SBCTA Project Management 500,000$ -$ 500,000$ TOTAL 7,300,000$ 4,372,400$ 2,927,600$ -$ Escalated Total 115,801,499$ 25% factor for ROW and CON support *includes PID phase and Caltrans oversight fee
**assumes EIR for environmental document
Cooperative Agreement with City of San Bernardino
Cooperative Agreement with City of San Bernardino

67.2% 32.8%
SR-210 Del Rosa Interchange

63.0% 28.0% 9.0% 32.8%
CITY HIGHLAND COUNTY Local Total
Project Report and Environmental Approval*,** 2,200,000$ 1,478,400$ 454,608$ 202,048$ 64,944$ 721,600$ Plans, Specifications, and Estimates 1,500,000$ 1,008,000$ 309,960$ 137,760$ 44,280$ 492,000$ Right of Way Acquisition 500,000$ 336,000$ 103,320$ 45,920$ 14,760$ 164,000$ Construction & Construction Management -$ -$ -$ -$ -$ -$ SBCTA Project Management 400,000$ -$ 252,000$ 112,000$ 36,000$ 400,000$ TOTAL 4,600,000$ 2,822,400$ 1,119,888$ 497,728$ 159,984$ 1,777,600$ *includes PID phase and Caltrans oversight fee
**assumes CE for environmental document
Cooperative Agreement with City of San Bernardino - No Construction

TOTAL MSI

← All documents from this meeting