Change Order Summary
Document Number: MMI-CO-0013
Project Information
Project Name
MMI-PRJ-93424
Change Order ID
MMI-CO-0013
Title
SB Navigation Center - Hope Campus
Order Value
$137,130.00
Project Address
796 E. 6th Street San Bernardino, California 92410
Client/Owner
SB Navigation Center - Hope
Campus
Contractor
Mandeville Modular
Change Order Details
Description
Individual sleeping units panel and water heater cabinet modification - Caused by Civil Drawings Deviation Reason for Change
**Modification to Sleeping Unit Utility Cabinet (Electrical Panel and Water Heater Enclosure)** Modification of the utility cabinet assembly on the exterior of the individual sleeping modules is required as a direct result of the City of San Bernardino's deviation from the original civil engineering plans developed and coordinated by Mandeville Modular. The City's revisions to finished floor elevations, site grading, and module placement have altered the required relationship between the modular units and the site utilities, resulting in the need to redesign and reconfigure the cabinet housing the electrical distribution panel and water heater. The revised cabinet design requires modifications to framing, dimensions, access clearances, utility routing, electrical panel location, plumbing connections, structural supports, finish materials, and associated manufacturing details to maintain compliance with applicable building codes, serviceability requirements, and HCD-approved modular construction standards. These changes also require updates to production drawings, engineering coordination, fabrication documentation, and factory manufacturing processes. This work is outside the original scope of work and is solely attributable to the City's decision to depart from the Mandeville Modular- designed civil plans. Accordingly, all engineering, redesign, material, fabrication, and associated labor costs required to implement these cabinet modifications constitute additional work and are the responsibility of the Owner through this Change Order.

SCHEDULE IMPACT
Start Date
12/17/2024
New End Date
01/07/2027
Original End Date
12/31/2026
Additional Days
7 days
Impact Notes

COST BREAKDOWN
Description Qty Unit Unit
Cost
Markup
% Markup Amount
LGS Framing 3265.0 EACH $35.00 20% $22,855.00 $137,130.00 Base Cost $114,275.00
Markup $22,855.00

MODIFIED TASKS
Task Name Serial Number Start Date Est Start Date Est End Date

MISCELLANEOUS
Description Amount
Signature ___________________________sign_here