Change Order Summary
Document Number: MMI-CO-0014
Project Information
Project Name
MMI-PRJ-93424
Change Order ID
MMI-CO-0014
Title
SB Navigation Center - Hope Campus
Order Value
$308,250.00
Project Address
796 E. 6th Street San Bernardino, California 92410
Client/Owner
City of San Bernardino
Contractor
Mandeville Modular
Change Order Details
Description
Project Demobilization and Re-mobilization
Reason for Change
Factory line demobilization. and re-mobilization

SCHEDULE IMPACT
Start Date
12/17/2024
New End Date
12/31/2026
Original End Date
12/31/2026
Additional Days
0 days
Impact Notes

COST BREAKDOWN
Description Qty Unit Unit Cost Markup
% Markup Amount
Factory Line
Demobilization

1.0 EACH $256,875.00 20% $51,375.00 $308,250.00
Base Cost $256,875.00
Markup $51,375.00

MODIFIED TASKS
Task Name Serial Number Start Date Est Start Date Est End Date

MISCELLANEOUS
Description Amount