The Highland Dynasty LLC Team
The Team
Schneider Commercial Real Estate, Kathleen & Al Steward 41 years experience in Real Estate Development & Commercial Real Estate
CBD Investment Inc./Coldwell Banker Dynasty, Mario Chang 41 years experience in Financing, Real Estate Development & Commercial Real Estate
ICON Inc. General Contractors, Patrick Hopkins
40 years experience in General Contracting
Highland Dynasty LLC was created specifically for this project.
Highland Freeway Center Goals and Objectives
• Serve the community and contribute to the local economy • Provide local employment opportunities
• Leverage experience with the City to streamline planning & development • Work with stakeholders including Yaamava’ and Soccer Complex, as well as adjacent apartment complex and residential areas • Address key issues:
• Freeway access and Highland off-ramp
• Impacts to adjacent neighborhood
• Future adjacent site uses
• Generate significant sales tax revenue to City
• Security
Colton
Experience - Area Shopping Centers
Redlands
Yucca Valley
Hemet
(Schneider Real Estate & Gatlin/Berger Developments fee-based) Experience - City of San Bernardino Projects
Jack in the Box Popeyes
3265 Little League Drive 3255 Little League Drive
Experience - City of San Bernardino Projects
7-Eleven
3154 Kendall Drive
Dairy Queen
3164 Kendall Drive
Starbucks
3194 Kendall Drive
Experience - City of San Bernardino Projects
Walmart
4210 E. Highland Avenue
Family Dollar
1137 Baseline St
Experience - City of San Bernardino Projects
AMC Theater Conversion
201 E Airport Drive
Arrowhead Regional Clinic
1499 E Highland Avenue
27,500 sf Office
1955 S Hunts Lane
Retail/Restaurant
Sierra & Highland
Experience - City of San Bernardino Projects
LA Fitness (55,000 sf)
1035 Parkford Drive
Experience - City of San Bernardino Projects
Arden Guthrie Proposed Project - Highland Home Center
Tenant focus on home
improvement, home
furnishings/appliances,
grocery, restaurant &
related services
Possible tenants: Home
Depot, Grocery,
Cabinets to Go, Floor &
Décor, Lumber
Liquidators, Ashley,
Harbor Freight, etc.
Arden Guthrie Proposed Project - Highland Home Center
Focus Areas -
• New off-ramp
Highland
Avenue
• 24/7 Private
Security
• Axon Fusus –
SBPD Camera
Sharing
Proposed Work Plan & Schedule
**Note: The work for the 4 major tasks can be performed concurrently, resulting in an estimated completion schedule of 24 to 30 months. Project schedules can vary as a result of multiple factors that are known to delay projects, including but not limited to required legal notification and publishing procedures, technical deliverables delayed through public comments and other requests for analysis, availability of public hearing dates, requests for extensions by public agencies and other interested parties, legal challenges and other.
Financial Proposal, Revenue & Sales Tax Projections
Estimated Project Costs Sales Volume
Sales Tax Projections
Major anchor tenant will be approximately 131,000 sf. They will purchase ten acres of the property, and they will develop their own store, along with on-sites and off-sites.