Cities Index.
Agenda, first session

San Bruno City Council
July 25, 2023

Document
Agenda, first session
Meeting
July 25, 2023
Body
San Bruno City Council
Original file
20.2 MB
Text extracted from the city's file for reading and search. Open the original on www.sanbruno.ca.gov. That file is the official record.

SAN BRUNO

RECREATION & AQUATIC
CENTER
City Council Update
e
July 25, 2023
AGENDA

1. Construction Update and Look Ahead Schedule
a) Project Information Update
b) Completed To Date
c) Schedule Update (Public Outreach)
d) What’s Happening the Next 30 Days and Beyond?
e) Adopted Projects Update
I. City Parkway and Crystal Spring Intersection
II. Beckner Shelter Road Projects
f) Change Order and Project Budget Update
g) Project Overview and Outlook

2. Questions
SAN BRUNO RECREATION & AQUATIC CENTER 07-25-2023 3 Construction Update and Look Ahead Schedule
Start Date: September 2021
Project Completion: End of 2023
Estimated Cost Completed To Date: 70.81% (June 2023)
EarthCam Link: https://share.earthcam.net/RecCenterBuild/rec_center_build/camera/view_1

PROJECT INFORMATION
Multivista Aerial Photo on 07/06/23
Multivista Aerial Photo on 03/03/23
SAN BRUNO RECREATION & AQUATIC CENTER 07-25-2023 4 COMPLETED TO DATE (Through 07/24/23)
March 27, 2023
July 24, 2023
Construction Update and Look Ahead Schedule

SAN BRUNO RECREATION & AQUATIC CENTER 07-25-2023 5 Construction Update and Look Ahead Schedule

COMPLETED TO DATE (APRIL - JULY)

GYMNASIUMNATATORIUM

NATATORIUM
• Pool plumbing
• Pool shell and stairs
• Pool gutter
• Bathroom Walls - CMU
• Party Room - CMU walls and framing
underway

GYMNASIUM
• Exterior wall sheathing
• Waterproofing spray is ongoing
• Interior wall framing
• MEPs 90% complete
• Mechanical Roof Curbs
• Roofing Insulation is ongoing

BUILDING UPDATE

OUTDOOR POOL
• Pool Plumbing
• Pool Piping Backfill
• Pool Bottom rebar and concrete
• Pool wall rebar and shotcrete
• External Plumbing ongoing

OUTDOOR POOL
SAN BRUNO RECREATION & AQUATIC CENTER 07-25-2023 6

COMPLETED TO DATE (JULY)
Construction Update and Look Ahead Schedule

PG&E CONDUIT

TRENCHING

CREEK REPAIR
AND

MODIFICATION

SOFT SOIL WORKOUTDOOR

POOL SHELL
CURING

EXTERIOR WALL

SHEATHING AND

WATERPROOFING
SPRAY

PEDESTRIAN

BRIDGE WORK

BEGINNING

MECHANICAL

ROOF CURBS

AND VAPOR

BARRIER

EXTERNAL

FRAMING AND

SHEATHING
ROOF

INSULATION
WORK

BEGINNING

OUTDOOR

POOL PIPING

BACKFILLED

PEDESTRIAN

BRIDGE WORK

BEGINNING
SAN BRUNO RECREATION & AQUATIC CENTER 07-25-2023 7 Construction Update and Look Ahead Schedule
ONSITE UPDATE: EXTERIOR WALLS

COMPLETED TO DATE (APRIL - JULY)
EXTERIOR SHEATHING – GYMNASIUM
WATERPROOFING SPRAY – GYMNASIUM

KEY MAP
Completed
• Exterior wall framing
• Exterior wall sheathing
• Water Proofing Spray is
ongoing

RENDERING - WEST

RENDERING - EAST
SAN BRUNO RECREATION & AQUATIC CENTER 07-25-2023 8 Construction Update and Look Ahead Schedule
ONSITE UPDATE: ROOF

COMPLETED TO DATE (APRIL - JULY)

KEY MAP
21 3
2 - VAPOR BARRIER INSTALLATION – FLAT ROOF
3 - INSULATION DELIVERY
2 - POURED FLAT ROOF
1 - EXTERIOR WALL FRAMING AT

MECHNICAL ROOF
1 - EXTERIOR WALL SHEATHING AT

MECHNICAL ROOF
Completed
• Flat Roof Poured
• Mechanical Roof Curbs Poured
• Vapor Barrier Installation
• Exterior Wall Sheathing at
Mechanical Roof
• Roof Insulation is ongoing
• Solar PV coordination
SAN BRUNO RECREATION & AQUATIC CENTER 07-25-2023 9 Construction Update and Look Ahead Schedule

SOLAR PV

SOLAR PV PLACEMENT

EXAMPLE OF BALLAST-

MOUNTED SOLAR PANELS

SOLAR PV UPDATE
SAN BRUNO RECREATION & AQUATIC CENTER 07-25-2023 10 Construction Update and Look Ahead Schedule
ONSITE UPDATE: NATATORIUM

COMPLETED TO DATE (APRIL - JULY)

INDOOR POOL EXCAVATION

INDOOR POOL PLUMBING

INDOOR POOL REBAR

KEY MAP

RENDERING - NORTHEAST
Completed
• Pool inspection
• Pool plumbing
• Indoor Pool Shell – in curing

POOL STAIRS AND PARTY ROOM WALLS

POOL BOTTOM SHELL CURING
SAN BRUNO RECREATION & AQUATIC CENTER 07-25-2023 11

KEY MAP
Construction Update and Look Ahead Schedule

COMPLETED TO DATE (MAY - JULY)
OFFSITE UPDATE: OUTDOOR POOL

OUTDOOR POOL EXCAVATION

OUTDOOR POOL EXCAVATION

OUTDOOR POOL PLUMBING TRENCH REBAROUTDOOR POOL PLUMBING TRENCH Completed
• Pool excavation
• Pool plumbing and Backfill
• Pool Bottom Rebar
• Pool Bottom Concrete
• Pool Wall Rebar
• Pool Bottom Curing - ongoing
SAN BRUNO RECREATION & AQUATIC CENTER 07-25-2023 12 Construction Update and Look Ahead Schedule

COMPLETED TO DATE (JULY)
OFFSITE UPDATE: OUTDOOR POOL
2 - POOL BOTTOM CURING

KEY MAP
1 2 - OUTDOOR POOL REBAR AND POOL

BOTTOM POUR
2 - OUTDOOR POOL PLUMBING FILL
1 – POOL PIPING
1 – POOL PIPING

BACKFILL
2 SAN BRUNO RECREATION & AQUATIC CENTER 07-25-2023 13 Construction Update and Look Ahead Schedule
OFFSITE UPDATE: PG&E

CONDUIT TRENCHING TO TRANSFORMER PAD

A - TRANSFORMER PAD

B - RETAINING WALL

COMPLETED TO DATE (JULY)

CONDUIT TRENCHING FROM BUILDING
PG&E Schedule

1. Received PG&E Plans – 5/16/23

2. Completed - Preconstruction
Meeting (6/8/23)

3. (In Progress) - Contractor
installing PG&E substructures and
transformer/pad

4. (1st week of August) - PG&E
Inspection (mandrill testing) and
transformer/ pad inspection

5. (TBD) - City Building Inspection
and tagging for meter

6. (TBD) - PG&E to confirm meter
release and to schedule for
power

7. (TBD) – Power Service Drop

KEY MAP

5. RETAINING
WALL

1. ELECTRICAL LINE

2. VAULT LOCATED

IN PARKING LOT

3. TRANSFORMER
PAD

4. STREET ELECTRIC
POLES
A
B
SAN BRUNO RECREATION & AQUATIC CENTER 07-25-2023 14 Construction Update and Look Ahead Schedule
OFFSITE UPDATE:CREEK REPAIR AND MODIFICATION
COMPLETED TO DATE (JUNE – JULY)

CREEK REPAIR AND MODIFICATION

1. Biologist, Hydraulics Engineer and
Hydrogeomorphologist

2. Erosion Damage Repair completed
• Bigger rocks were placed
• Rock Slope Protection
reconfigured to control
water flow

3. Landscape work to begin soon

STORM DAMAGE - BANK EROSION

COMPLETED REPAIR AND MODIFICATION

BEFORE THE STORM
SAN BRUNO RECREATION & AQUATIC CENTER 07-25-2023 15

SCHEDULE UPDATE
2023 2024
Q1 Q2 Q3 Q4 Q1
Activity No. Work Description
1A Demo, Shoring, Grading, and Landscape
1B Pools (Indoor and Outdoor)
1C Building (Natatorium and Gymnasium)
2A City Park Way (Creek and Park)
2B City Park Way (Roadway)
2C City Park Way (Water, Sewer & Storm)
3 Crystal Springs Road (Water)
4 Parking Lot
Construction Update and Look Ahead Schedule
Pools
Building
Site Work
Landscaping and
pedestrian bridges
Top Lift Paving, Final
Delineation And
Signages

HVAC, MEP ,
Roofing, CMU Walls
Street
Realignment
Parking Lot
Onsite Utilities (Water,
Sewer & Storm), Trash
And Generator
Enclosure, PG&E
Transformer Pad
Creek
Restoration
Wall Framing,
MEPs, and
Plumbing
Rain
Extension
Days
Rain Impacted Days
Progress WorkRain Impacted Days Rain Extension DaysRemaining WorkLegend Water service &
trench restoration
completed
SAN BRUNO RECREATION & AQUATIC CENTER 07-25-2023 16 Construction Update and Look Ahead Schedule

PUBLIC OUTREACH
• Project Website is regularly updated
• Portable Changeable Message Boards will be used for Future Road Closures • Detour Signs will be placed as needed
• Communicate with Google Navigation system as needed
• Field Contact Numbers are available on all project signs and City Website • Daily onsite representative is available at the trailer office • Calls and emails are being answered and addressed
• City Park Way daytime closure will continue for landscaping work SAN BRUNO RECREATION & AQUATIC CENTER 07-25-2023 17 Construction Update and Look Ahead Schedule
WHAT’S HAPPENING THE NEXT 30 DAYS AND BEYOND?

ONSITE WORK
• Exterior Waterproofing Spray
• Roofing Insulation
• Natatorium
• Indoor Pool Work
• Party Room CMU Walls
• Interior
• Wall sheathing
• Continue MEPs
• Elevator Shafts

WATERPROOFING OF EXTERIOR WALLS

PARTY ROOM CMU WALLS

ROOFING INSULATION

INDOOR POOL COMPLETION

INTERIOR WALL SHEATHING
SAN BRUNO RECREATION & AQUATIC CENTER 07-25-2023 18 Construction Update and Look Ahead Schedule
WHAT’S HAPPENING THE NEXT 30 DAYS AND BEYOND?

OFFSITE WORK
• Outdoor Pool Curing
• Wading Pool Excavation And
Plumbing
• PG&E Work
• Conduits
• Inspection
• Transformer Pad
• Retaining Wall
• Irrigation & Bioswale
• Creek
• Pedestrian Bridge Work

BUILDING
WORK

PG&E WORK

OUTDOOR

POOL SHELL
CURING

PEDESTRIAN

BRIDGE WORK

BEGINNING
WADING
POOL
WORK

PEDESTRIAN

BRIDGE WORK

BEGINNING

BIOSWALES
AND

IRRIGATION
SAN BRUNO RECREATION & AQUATIC CENTER 07-25-2023 19 Crystal Springs / Oak Street / City Park Way Intersection Improvement Project Update

INCREASED TURNING

RADIUS TO ACCOMODATE

RECOLOGY GARBAGE

TRUCKS TURNING RIGHT

STREET PARKING

STREET PARKING

TEMPORARY SIDEWALK

COORDINATED WITH RAC

PROJECT
FUNDING SOURCES:

Measure A & G Fund
(RAC)
PROJECT BUDGET:
$800,000.00

SIGNAL POLE AND

FOUNDATION DETAIL TO

SHOW DEPTH AND SIZE
Per Vehicle Code, the City Engineer or T.E. to
recommend the conclusion of the
intersection control study. Memorandum to
be issued.

Bidding and Award
October 2023June 2023Aug 3, 2022
Traffic Engineer (T.E.)
presented intersection
traffic control
alternatives to
(TSPC)Traffic Safety and
Parking Committee
Sept 2022
Designer proceeded
with the TSS design
preparation
July-September
2023Aug 10, 2022 Mar 2023
Final Design to be
completed (90%)
Final Design Completed
Signal
Poles Procurement
Coordination
Advertise Project To
Receive Bids Completion Target
December 2023
Construction NTP

PROJECTS
Design and
Management
Consultant
Agreements
Topographic
Surveying
Design
Development Complete Design
Request Quote or
Process as Change
Order
Begin
Construction
Complete
Construction
Repaving and
Parking Lot
Striping
August 2023
(Estimated)
September
2023
(Estimated)
October 2023
(Estimated)
November 2023
(Estimated)
ADA Bridge August 2023
(Estimated)
October 2023
(Estimated)
November 2023
(Estimated)
December
2023
(Partially)
TBD (Permit
Conditions)
Picnic Area #14
ADA Path
September
2023
(Estimated)
November 2023
(Estimated)
December 2023
(Estimated) TBD TBD
Ongoing Completed
Construction Update and Look Ahead Schedule

BECKNER SHELTER ROAD PROJECTS
1 2
3 1 2 3
SAN BRUNO RECREATION & AQUATIC CENTER 07-25-2023 21 Change Order Report
Owner Request

13.49%
Unforeseen and
Unknown Conditions

39.03%
Value Engineering
-1.10%
Resolution of
Discrepancies in the
Design

42.87%
Public Safety &
Convenience

5.72%
$2,744,598.12 (6.38%) APPROVED

CHANGE ORDER TO DATE

6.03% ($2,594,273.31) of the

COMPLETED CHANGE ORDER

WORK TO DATE
Construction Update and Look Ahead Schedule

SAN BRUNO RECREATION & AQUATIC CENTER 07-25-2023 22 0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Project Soft Cost Construction Project Contingency
Pre Construction Construction Remaining Balance
Construction Update and Look Ahead Schedule
Project Budget Update
Total Project Budget:
• $62,290,228.00
Total Expenses To Date:
• $43,228,662.54 (69.40%)

SOFT COSTS
• Design (Group 4)
• Environmental
• Project Manager (Consor)
• Construction Manager (Griffin Structures)
• Geotechnical, T&I, Waterproofing,
Commissioning Services
• Lara Field Parking Lot
• Traffic Signals, Sewer, Water, Sidewalk,
CityNet Fiber
• Temporary Space During Construction
• Furniture Fixtures and Equipment
• Electronic systems and special equipment
• Utility company connection and services
• Fees/ Administration/ Business Plan
• Additional Crystal Springs Tree Removal
• Beckner Shelter Projects
Pre-Construction Phase Cost Total:
• $6,770,384.00
Construction Phase Cost To Date:
• $36,458,278.54
Total:
$43,031,000.00
Total:
$4,945,990.00
Total:
$14,313,238.00

30.01%

22.69%

47.30%

29.19%

70.81%

44.51%

55.49%

SAN BRUNO RECREATION & AQUATIC CENTER 07-25-2023 23

OVERVIEW AND OUTLOOK
Available Contingency Balance of 44.51% to complete
the remaining 29.19%
or $12.5 M worth of work.

Contingency Spent: 55.49%
Work Remaining: 29.19%
• BUILDING STRUCTURES
• CITY PARKWAY/UTIL
• CREEK IMPROVMENTS
• PARKING LOT
• BUILDING INTERIOR
• EXTERIOR WALL FRAMES
• M.E.P /HVAC
• INDOOR POOL

PLUMBING
• CRYSTAL SPRING UTILITY
• CREEK RESTORATION
• CREEK LANDSCAPING
• PEDESTRIAN BRIDGE
• PARKING LOT
• BUILDING INTERIOR FRAMES
• M.E.P /HVAC - ROUGH
• INDOOR POOL EXCAVATION
• PG&E POWER & GAS
• INDOOR POOL SHELL
• OUTDOOR POOL
• BUILDING EXTERIORS
• CITY PARKWAY/UTIL
• CREEK RESTORATION
• CREEK LANDSCAPING
• PG&E GAS & ELECTRIC
• PARKING LOT
• BUILDING INTERIOR FRAMES
• M.E.P /HVAC - EQUIPMENT

INSTALLATION
• ELECTRICAL PANEL BOARDS
• ARCHITECTURAL WALL

FINISHES AND ROOF
• BUILDING ROOF
• BUILDING INTERIORS
• M.E.P/HVAC/ELEVATOREQUIPMENT

INSTALLATION/TESTING
• POOL PLUMBING AND MECHANICAL

INSTALLATION/TESTING
• SITE LANDSCAPING
and FURNISHING
• ROTARY PAVILLION
• FURNITURE FIXTURE & EQUIPMENT
(FF&E)
• PEDESTRIAN BRIDGE
• COMPLETE COMMISSIONING
• CITY STAFF OCCUPANCY
• CITY FACILITY STAFF TRAINING
• DEDICATION PLANNING
66% Completed Spring 2023 Summer 2023 Winter 2023/2024Fall 2023 Schedule

SAN BRUNO RECREATION & AQUATIC CENTER 07-25-2023 24

THANK YOU
sanbruno.ca.gov/RecCenterBuild

• 4th of July presents safety challenges
• Use of illegal fireworks before, during and after the 4th of July • Noise, animal impacts, PTSI residents, risk of injury, etc. • Fire hazards
• Large, unruly gatherings
• Increased alcohol use
• Expansive education, prevention and enforcement operations annually • Funded by Safe and Sane Fireworks sales
• Does not stop rampant illegal fireworks use
• This is not stoppable, only reduceable
• Average number of fireworks-related calls for service on July 4th • San Mateo: 122
• East Palo Alto: 131
• South San Francisco: 188
• Daly City: 95
• None of these Cities allow safe and sane fireworks
• None of these Cities have a funding source for large-scale enforcement • Generally do NOT respond to fireworks complaints
• Pacifica: 104
• Only other SM County City allowing safe and sane fireworks use/sales • Enforcement efforts similar to San Bruno
• Funded with fees imposed on safe and sane firework sales • All Police Department personnel ordered to work
• Robust Incident Action Plan created and approved
• Joint Fire/Police PSA created and disseminated
• Fireworks Safety Postcard to all residents
• Safety meetings with all booth operators
• Educational flyers provided with every fireworks sale • Informational warning notices to all City Facilities
• Advance police contact at known violation locations
• Use of data to focus resource deployment
• Dedicated enforcement details prior to 4th

• All SBPD personnel ordered to work
• 55 staff (Officers, Dispatchers, Clerks, CSOs)
• 40 sworn and 15 non-sworn
• Many worked 16 consecutive hours
• All beats staffed as usual, plus dedicated
enforcement units deployed
• Marked and unmarked units
• Uniformed and plain clothes personnel
• Undercover surveillance
• Drones/UAS
• Dedicated Fire Department Staff
• Dedicated Parks Department Staff
• Dedicated Public Works Department Staff
• SBPD handled 255 calls for service on the 4th of July • 22 fewer than in 2022
• Peak activity period – 8:30pm to 11:15pm
• 144 calls were fireworks related
• 35 fewer than last year
• Most reports vague and marginally workable
• Officers must “on-view” violations to cite
• Observationally…
• Illegal fireworks lighter this year than most years
• Fewer unruly gatherings/parties than typical
• $1,000 Administrative Citation
• Citing Officer must directly observe a specific
person committing a specific violation
• Officer must then safely detain the violator
• Municipal Code infraction doesn’t justify
compromised safety
• Violator must be cited, not physically arrested
• Only evidence in plain view can be seized
• Resident-provided video can help identify
suspects, but cannot replace “in presence” legal
requirement
• Person(s) in control of a gathering can be cited
• Must prove knowledge (warning)
2023 2022 2021 2020 2019 2018 2017 2016 2015
Admin Cites 26 25 17 38 21 25 22 11 11
Arrests 4 2 2 2 0 1 0 0 0
• 26 Administrative Citations issued this year
• 1 more than last year
• Second most ever issued
• About 8/hour during peak period
• Of the 26 people cited 16 were San Bruno residents
• About 181 pounds of live illegal fireworks seized
• 155 pounds over the annual average
Department Nature Cost
Police Department Public Service Announcement (PD & FD) $972.49 Community Services Additional Staff/Equipment on the 4th $7,598.90 Fire Department Fire Marshal Administrative and Inspection Hours $2,358.66 Fire Department 4th of July Staffing and Logistics $16.709.40 Police Department 4th of July Staffing and Logistics $49,239.55 Police Department Pre and Post 4th Education and Enforcement / Logistics $14,677.43 Public Works Cleanup Costs (Labor & Equipment) $7,597.04 Total $99,153.47
NOTE: Costs covered by fees collected from Safe & Sane Firework sales Cities without such sales have no funding source for these operations

4th of July Staffing
• Fire Chief
• 1 Additional BC
• All fire prevention staff on duty
• Education / Enforcement
• 1 extra ALS Type VI Engine Company
• (3 Engines, 1 Truck in the city)
11 Calls for Service
• San Bruno Fire Department handled 26 calls
for service on the 4th of July a slight decrease
from last year
• Peak activity period – 8:30pm to 11pm
• Three calls were fireworks related (3)
12 Calls for Service
• San Bruno Fire Department noticed an increase in fire related calls during the week leading up to July 4th
Date Fireworks related Total Calls
June 13 - June 19 0 107
June 20 - June 26 0 93
June 27 – July 3rd 2 92
July 4th - July 5 5 50
13 Observations
• Illegal fireworks use was consistent with prior years • Education and Prevention was critical
• Weed abatement efforts were made prior to the 4th
San Bruno Public Works and San Bruno Parks Department
Contract for weed abatement during the year
• No injuries from July 4th activities
14 EXTEND INTERIM

AUTHORITY FOR MASTER FEE

SCHEDULE

CITY COUNCIL MEETING
JULY 25, 2023

PETER GILLI

COMMUNITY DEVELOPMENT DIRECTOR
AGENDA
I. Objective
II. Background
III. Extension
IV. Tonight’s Recommended Action
V. Questions
2 OBJECTIVE
• Hold Public Hearing
• Consider Adoption of a Resolution to extend the interim authority for the Master Fee Schedule for Fiscal Year 2023-24 previously adopted as an urgency measure effective July 1, 2023
3 BACKGROUND
4 BACKGROUND
5 1
2 3
7/25 - Recommended
Extension (4/5 vote)
8/12
6/13 - City Council
Adopted Master Fee
Schedule Resolution
(unanimous vote)
6/27 - City Council
Adopted Urgency
Resolution (unanimous
vote)
60 day period before effective date
6/13
6/27
7/1
7/25
7/27
Updated Fees
effective
Updated Fees effective
Master Fee Schedule in
effect
Gap for new
fees

EXTENSION
6 EXTENSION
7 1
2 3
7/25 - Recommended
Extension (4/5 vote)
8/12
6/13 - City Council
Adopted Master Fee
Schedule Resolution
(unanimous vote)
6/27 - City Council
Adopted Urgency
Resolution (unanimous
vote)
60 day period before effective date
6/13
6/27
7/1
7/25
7/27
Updated Fees
effective
Updated Fees effective
Master Fee Schedule in
effect
Gap for new
fees
TONIGHT’S

RECOMMENDED
ACTION
8 TONIGHT’S RECOMMENDED
ACTION
9 • Hold Public Hearing
• Consider Adoption of a Resolution to extend the interim authority for the Master Fee Schedule for Fiscal Year 2023-24 previously adopted as an urgency measure effective July 1, 2023
10 PROVIDE FEEDBACK ON ECONOMIC

DEVELOPMENT PROGRAM

CITY COUNCIL MEETING
JULY 25, 2023

MARIA LANGBAUER

ECONOMIC DEVELOPMENT MANAGER

OBJECTIVE
Conduct a study session and provide feedback on Economic Development program
2 SAN BRUNO

INFORMATION
• Approximately 16,500 jobs
• Approximately 24,00 employed
residents
• Sales Tax revenue estimate of $12.7
million in Fiscal Year 2023-24
• Transit Occupancy Tax revenue
estimate of $2.9 million in Fiscal Year
2023-24
3 BACKGROUND
4 Economic Development
Strategic Plan
1997
General Plan with an Economic
Development Chapter
2009
Transit Corridor Specific
Plan
2013
San Mateo Avenue Conceptual
Streetscape Plan & Downtown
Parking Management Plan
2019

KEY CITY ECONOMIC DEVELOPMENT

INITIATIVES
5 Initiated work on the
new New Hyundai and
Genesis Dealership
2020
Bayhill Specific Plan and Google (YouTube) Office
Development, and Initiation of the Tanforan
Redevelopment Project
2021
New City Permit Software System
and Economic Development
Manager
2023

FEEDBACK ON ECONOMIC

DEVELOPMENT PROGRAM
6 WHY COMMUNITIES INVEST IN

ECONOMIC DEVELOPMENT
7 Source: California Association for Economic Development

ECONOMIC DEVELOPMENT GOALS
City economic development programs can accomplish a wide range of goals:
 Job creation
 Businesses
 Develop vibrant communities
 Increase City revenue
 Facilitate new development
8 JOB CREATION
• Creating new jobs
• Different types of employment or incomes in the community 9 New Auto Dealership

BUSINESSES
Business creation, attraction, retention, and expansion 10 VIBRANT COMMUNITIES
A vibrant community can generate activity levels that will attract people to shop, dine, and visit
11 Vision for the Downtown Streetscape

CITY REVENUE
By bringing in new sales, property, and transit occupancy tax and other revenue
12 Local Hotel
Local retail stores

FACILITATE NEW DEVELOPMENT
Including the redevelopment of vacant or underutilized properties 13 The Aperture, a new housing project
New office project under construction
TONIGHT’S COUNCIL

DISCUSSION AND FEEDBACK
Conduct a study session and provide feedback on Economic Development program
14 15

← All documents from this meeting