ATTACHMENT 2

CITY OF SAN CLEMENTE

PROFESSIONAL CONSULTANT SERVICES AGREEMENT

1. PARTIES AND DATE.

This Agreement is made and entered into this
referred to herein as "Party" and collectively as "Parties."

2. RECITALS.

2.1 Consultant.

Consultant desires to perform and assume responsibility for the provision of certain professional Engineering and Design consulting services required by the City on the terms and conditions set forth in this Agreement. Consultant represents that it is experienced in providing professional Engineering and Design consulting services to public clients, is licensed in the State of California, if applicable, and is familiar with the plans of City.

2.2 Project.

City desires to engage Consultant to render such professional Engineering and Design consulting services for the Recycled Water Quality Improvement Project for City of San Clemente Utilities ("Project") as set forth in this Agreement.

3. TERMS.

3.1 Scope of Services and Term.

General Scope of Services. Consultant promises and agrees to furnish to the City all labor, materials, tools, equipment, services, and incidental and customary work necessary to fully and adequately supply the professional Labor Compliance and Monitoring consulting services necessary for the Project ("Services"). The Services are more particularly described in Exhibit "A" attached hereto and incorporated herein by reference. All Services shall be subject to, and performed in accordance with, this Agreement, the exhibits attached hereto and incorporated herein by reference, and all applicable local, state and federal laws, rules and regulations.

3.1.2 Term. The term of this Agreement shall be from 10/05/2022 to 12/30/2024, unless earlier terminated as provided herein. Consultant shall complete the Services within the term of this Agreement, and shall meet any other established schedules and deadlines.

3.2 Responsibilities of Consultant.

3.2.1 Independent Contractor; Control and Payment of Subordinates. The Services shall be performed by Consultant or under its supervision. Consultant will determine the means, methods and details of performing the Services subject to the requirements of this Agreement. City retains Consultant on an independent contractor basis and not as an employee. 1 55452.01100131193624.5
Consultant retains the right to perform similar or different services for others during the term of this Agreement. Any additional personnel performing the Services under this Agreement on sagans shat have onto over the conduct of consultant al Consultant's officers, employees, or agents, except as set forth in this Agreement. Consultant shall pay all wages, salaries, and other amounts due such personnel in connection with their performance of Services under this Agreement and as required by law. Consultant shall be responsible for all reports and obligations respecting such additional personnel, including, but not limited to: social security taxes, income tax withholding, unemployment insurance, disability insurance, and workers' compensation insurance.

3.2.2 Schedule of Services. Consultant shall perform the Services expeditiously, within the term of this Agreement, and in accordance with the Schedule of Services set forth in Exhibit "B" attached hereto and incorporated herein by reference. Consultant represents that it has the professional and technical personnel required to perform the Services in conformance with such conditions. In order to facilitate Consultant's conformance with the Schedule, City shall respond to Consultant's submittals in a timely manner. Upon request of City, Consultant shall provide a more detailed schedule of anticipated performance to meet the Schedule of Services.

3.2.3 Endorsement on PS&E/ Other Data. Consultant shall sign all plans, specifications, estimates (PS&E) and engineering data furnished by Consultant, and where appropriate will indicate Consultant's authorized signature and professional registration number.

3.2.4 Conformance to Applicable Requirements. All work prepared by Consultant shall be subject to the approval of City.

3.2.5 Substitution of Key Personnel. Consultant has represented to City that certain key personnel will perform and coordinate the Services under this Agreement. Should one or more of such personnel become unavailable, Consultant may substitute other personnel of at least equal competence upon written approval of City. In the event that City and Consultant cannot agree as to the substitution of key personnel, City shall be entitled to terminate this Agreement for cause. As discussed below, any personnel who fail or refuse to perform the Services in a manner acceptable to the City, or who are determined by the City to be uncooperative, incompetent, a threat to the adequate or timely completion of the Project or a threat to the safety of persons or property, shall be promptly removed from the Project by the Consultant at the request of the City. The key personnel for performance of this Agreement are as follows: Dhiru Patel.

Principal Civil Engineer, or his/her designee, to act as its representative in all matters pertaining to the administration and performance of this Agreement ("City's Representative"). City's Representative shall have the power to act on behalf of the City for review and approval of all products submitted by Consultant but not the authority to enlarge the Scope of Work or change the total compensation due to Consultant under this Agreement. The City Manager shall be authorized to act on City's behalf and to execute all necessary documents which enlarge the Scope of Work or change the Consultant's total compensation subject to the provisions contained in Section 3.3 of this Agreement. Consultant shall not accept direction or orders from any person other than the City Manager, City's Representative or his/her designee.

3.2.7 Consultant's Representative. Consultant hereby designates Dhiru Patel, Principal, or his/her designee, to act as its representative for the performance of this Agreement 2 55452.01100\31193624.5
('Consultant's Representative"). Consultant's Representative shall have full authority to represent and act on behalf of the Consultant for all purposes under this Agreement. The Consultant's Representative shall supervise and direct the Services, using his/her best skill and attention, and shall be responsible for all means, methods, techniques, sequences, and procedures and for the satisfactory coordination of all portions of the Services under this Agreement.

3.2.8 Coordination of Services. Consultant agrees to work closely with City staff in the performance of Services and shall be available to City's staff, consultants and other staff at all reasonable times.

3.2.9 Standard of Care; Performance of Employees. Consultant shall perform all Services under this Agreement in a skillful and competent manner, consistent with the standards generally recognized as being employed by professionals in the same discipline in the State of California. Consultant represents and maintains that it is skilled in the professional calling necessary to perform the Services. Consultant warrants that all employees and subconsultants shall have sufficient skill and experience to perform the Services assigned to them. Finally, Consultant represents that it, its employees and subconsultants have all licenses, permits, qualifications and approvals of whatever nature that are legally required to perform the Services, and that such licenses and approvals shall be maintained throughout the term of this Agreement.

As provided for in the indemnification provisions of this Agreement, Consultant shall perform, at its own cost and expense and without reimbursement from the City, any services necessary to correct errors or omissions which are caused by the Consultant's failure to comply with the standard of care provided for herein. Any employee of the Consultant or its sub-consultants who is determined by the City to be uncooperative, incompetent, a threat to the adequate or timely completion of the Project, a threat to the safety of persons or property, or any employee who fails or refuses to perform the Services in a manner acceptable to the City, shall be promptly removed from the Project by the Consultant and shall not be re-employed to perform any of the Services or to work on the Project.

3.2.10 Laws and Regulations. Consultant shall keep itself fully informed of and in compliance with all local, state and federal laws, rules and regulations in any manner affecting the performance of the Project or the Services, including all Cal/OSHA requirements, and shall give all notices required by law. Consultant shall be liable for all violations of such laws and regulations in connection with Services. If Consultant performs any work knowing it to be contrary to such laws, rules and regulations, Consultant shall be solely responsible for all costs arising therefrom. Consultant shall defend, indemnify and hold City, its officials, directors, officers, employees, agents, and volunteers free and harmless, pursuant to the indemnification provisions of this Agreement, from any claim or liability arising out of any failure or alleged failure to comply with such laws, rules or regulations.

3.2.11 Safety. Consultant shall execute and maintain its work so as to avoid injury or damage to any person or property. In carrying out its Services, the Consultant shall at all times be in compliance with all applicable local, state and federal laws, rules and regulations, and shall exercise all necessary precautions for the safety of employees appropriate to the nature of the work and the conditions under which the work is to be performed. Safety precautions, where applicable, shall include, but shall not be limited to: (A) adequate life protection and lifesaving equipment and procedures; (B) instructions in accident prevention for all employees and subconsultants, such as safe walkways, scaffolds, fall protection ladders, bridges, gang planks, confined space procedures, trenching and shoring, equipment and other safety devices, equipment and wearing apparel as are necessary or lawfully required to prevent accidents or injuries; and (C) adequate facilities for the proper inspection and maintenance of all safety 3 55452.01100\31193624.5

3.2.12 Insurance. Consultant agrees to procure and maintain, at Consultant's expense all insurance specified in Exhibit "C" attached hereto and by this reference incorporated herein. Consultant shall require all subconsultants to carry the same policies and limits of insurance that the Consultant is required to maintain, unless otherwise approved in writing by the City.

3.3 Fees and Payments.

3.3.1 Compensation. Consultant shall receive compensation, including authorized reimbursements, for all Services rendered under this Agreement at the rates set forth in Exhibit "D" altached hereto and incorporated herein by reference. The total compensation shall not exceed nine hundred five thousand two hundred seven ($905,207.00) without written approval of the City Council or City Manager as applicable. Extra Work may be authorized, as described below, and if authorized, will be compensated at the rates and manner set forth in this Agreement.

3.3.2 Payment of Compensation. Consultant shall submit to City a monthly invoice which indicates work completed and hours of Services rendered by Consultant. The invoice shall describe the amount of Services provided since the initial commencement date, or since the start of the subsequent billing periods, as appropriate, through the date of the invoice.

City shall, within 30 days of receiving such invoice, review the invoice and pay all non-disputed and approved charges thereon. If the City disputes any of Consultant's fees, the City shall give written notice to Consultant within thirty (30) days of receipt of an invoice of any disputed fees set forth therein.

Reimbursement for Expenses. Consultant shall not be reimbursed for any expenses unless authorized in writing by City, or included in Exhibit "D" of this Agreement.

3.3.4 Extra Work. At any time during the term of this Agreement, City may request that Consultant perform Extra Work. As used herein, "Extra Work" means any work which is determined by City to be necessary for the proper completion of the Project, but which the Parties did not reasonably anticipate would be necessary at the execution of this Agreement.

Consultant shall not perform, nor be compensated for, Extra Work without written authorization from the City.

3.3.5 Rate Increases. In the event that this Agreement is renewed pursuant to Section 3.1.2, the rate set forth in Exhibit "D" may be adjusted each year at the time of renewal as set forth in Exhibit "D."

3.3.6 Labor Code Requirements.

Prevailing Wages. Consultant is aware of the requirements of California Labor Code Section 1720, et seq., and 1770, et seg., as well as California Code of Regulations, Title 8, Section 16000, et seq., ("Prevailing Wage Laws"), which require the payment of prevailing wage rates and the performance of other requirements on "public works" and "maintenance" projects. if the Services are being performed as part of an applicable "public works" or "maintenance" project, as defined by the Prevailing Wage Laws, and if the total compensation is $1,000 or more, Consultant agrees to fully comply with such Prevailing Wage Laws. Consultant shall make copies of the prevailing rates of per diem wages for each craft, classification or type of worker needed to execute the Services available to interested parties upon request, and shall post copies at the Consultant's principal place of business and at the project site. Consultant shall defend, indemnify and hold the City, its officials, officers, employees, 4 55452 01100\31193624.5
agents, and volunteers free and harmless from any claim or liability arising out of any failure or alleged failure to comply with the Prevailing Wage Laws.

3.3.6.2 Registration. If the Services are being performed as part of an applicable "public works" or "maintenance" project, in addition to the foregoing, then pursuant to Labor Code sections 1725.5 and 1771.1, the Consultant and all subconsultants must be registered with the Department of Industrial Relations ("DIR"). Consultant shall maintain registration for the duration of the project and require the same of any subconsultants. This project may also be subject to compliance monitoring and enforcement by the DIR. It shall be Consultant's sole responsibility to comply with all applicable registration and labor compliance requirements, including the submission of payroll records directly to the DIR. Notwithstanding the foregoing, the contractor registration requirements mandated by Labor Code sections 1725.5 and 1771.1 shall not apply to Services performed on a public works project that is exempt pursuant to the small project exemption specified in Labor Code sections 1725.5 and 1771.1.

3.4 Accounting Records.

3.4.1 Maintenance and Inspection. Consultant shall maintain complete and accurate records with respect to all costs and expenses incurred under this Agreement. All such records shall be clearly identifiable. Consultant shall allow a representative of City during normal business hours to examine, audit, and make transcripts or copies of such records and any other documents created pursuant to this Agreement. Consultant shall allow inspection of all work, data, documents, proceedings, and activities related to the Agreement for a period of four (4) years from the date of final payment under this Agreement.

3.5 General Provisions.

3.5.1 Termination of Agreement.

3.5.1.1 Grounds for Termination. City may, by written notice to Consultant, terminate the whole or any part of this Agreement at any time, with or without cause, by giving written notice to Consultant of such termination, and specifying the effective date thereof, at least seven (7) days before the effective date of such termination. Upon termination, Consultant shall be compensated only for those services which have been adequately rendered to City, and Consultant shall be entitled to no further compensation. Consultant may not terminate this Agreement except for cause
Effect of Termination. If this Agreement is terminated as provided herein, City may require Consultant to provide all finished or unfinished Documents and Data and other information of any kind prepared by Consultant in connection with the performance of Services under this Agreement. Consultant shall be required to provide such document and other information within fifteen (15) days of the request.

3.5.1.3 Additional Services. In the event this Agreement is terminated in whole or in part as provided herein, City may procure, upon such terms and in such manner as it may determine appropriate, services similar to those terminated.

3.5.2 Delivery of Notices. All notices permitted or required under this Agreement shall be given to the respective parties at the following address, or at such other address as the respective parties may provide in writing for this purpose:
5 55452.01100131193624.5
Consultant: LE + RO, Inc.
1199 South Fullerton Road
City of Industry, CA 91748
ATTN: Dhiru Patel, PE, Chief Executive Officer
City: City of San Clemente
910 Calle Negocio
San Clemente, CA 92673
ATTN: Kiel Koger, PW Director / City Engineer
Such notice shall be deemed made when personally delivered or when mailed, forty-eight (48) hours after deposit in the U.S. Mail, first class postage prepaid and addressed to the party at its applicable address. Actual notice shall be deemed adequate notice on the date actual notice occurred, regardless of the method of service.

3.5.3 Ownership of Materials and Confidentiality.

3.5.3.1 Documents & Data; Licensing of Intellectual Property. This Agreement creates a non-exclusive and perpetual license for City to copy, use, modify, reuse, or sublicense any and all copyrights, designs, and other intellectual property embodied in plans, specifications, studies, drawings, estimates, and other documents or works of authorship fixed in any tangible medium of expression, including but not limited to, physical drawings or data magnetically or otherwise recorded on computer diskettes, which are prepared or caused to be prepared by Consultant under this Agreement ("Documents & Data"). Consultant shall require all subconsultants to agree in writing that City is granted a non-exclusive and perpetual license for any Documents & Data the subconsultant prepares under this Agreement. Consultant represents and warrants that Consultant has the legal right to license any and all Documents & Data.

Consultant makes no such representation and warranty in regard to Documents & Data which were prepared by design professionals other than Consultant or provided to Consultant by the City. City shall not be limited in any way in its use of the Documents & Data at any time, provided that any such use not within the purposes intended by this Agreement shall be at City's sole risk.

3.5.3.2 Confidentiality. All ideas, memoranda, specifications, plans, procedures, drawings, descriptions, computer program data, input record data, information, and other Documents & Data either created by or provided to Consultant in connection with the performance of this Agreement shall be held confidential by Consultant. Such materials shall not, without the prior written consent of City, be used by Consultant for any purposes other than the performance of the Services. Nor shall such materials be disclosed to any person or entity not connected with the performance of the Services or the Project. Nothing furnished to Consultant which is otherwise known to Consultant or is generally known, or has become known, to the related industry shall be deemed confidential. Consultant shall not use City's name or insignia, photographs of the Project, or any publicity pertaining to the Services or the Project in any magazine, trade paper, newspaper, television or radio production or other similar medium without the prior written consent of City.

3.5.3.3 Confidential Information. The City shall refrain from releasing Consultant's proprietary information ("Proprietary Information" unless the City's legal counsel determines that the release of the Proprietary Information is required by the California Public Records Act or other applicable state or federal law, or order of a court of competent jurisdiction, in which case the City shall notify Consultant of its intention to release Proprietary Information.

Consultant shall have five (5) working days after receipt of the Release Notice to give City written notice of Consultant's objection to the City's release of Proprietary Information. Consultant shall 6 55452.01100131193624.5
indemnify, defend and hold harmless the City, and its officers, directors, employees, and agents from and against all liability, loss, cost or expense (including attorney's fees) arising out of a legal action brought to compel the release of Proprietary Information. City shall not release the Proprietary Information after receipt of the Objection Notice unless either: (1) Consultant fails to fully indemnify, defend (with City's choice of legal counsel), and hold City harmless from any legal action brought to compel such release; and/or (2) a final and non-appealable order by a court of competent jurisdiction requires that City release such information.

3.5.4 Cooperation; Further Acts. The Parties shall fully cooperate with one another, and shall take any additional acts or sign any additional documents as may be necessary, appropriate or convenient to attain the purposes of this Agreement.

3.5.5 Attorney's Fees. If either party commences an action against the other party, either legal, administrative or otherwise, arising out of or in connection with this Agreement, the prevailing party in such litigation shall be entitled to have and recover from the losing party reasonable attorney's fees and all other costs of such action.

3.5.6 Indemnification.

3.5.6.1 To the fullest extent permitted by law, Consultant shall defend (with counsel of City's choosing), indemnify and hold the City, its directors, officials, officers, employees, volunteers and agents free and harmless from any and all claims, demands, causes of action, costs, expenses, liability, loss, damage or injury of any kind, in law or equity, to property or persons, including wrongful death, in any manner arising out of, pertaining to, or incident to any alleged acts, errors or omissions, or willful misconduct of Consultant, its officials, officers, employees, subcontractors, consultants or agents in connection with the performance of the Consultant's Services, the Project or this Agreement, including without limitation the payment of all damages, expert witness fees and attorney's fees and other related costs and expenses. Consultant's obligation to indemnify shall not be restricted to insurance proceeds, if any, received by Consultant, the City, its officials, officers, employees, agents, or volunteers.

If Consultant's obligation to defend, indemnify, and/or hold harmless arises out of Consultant's performance as a "design professional" (as that term is defined under Civil Code section 2782.8), then, and only to the extent required by Civil Code section 2782.8, which is fully incorporated herein, Consultant's indemnification obligation shall be limited to claims that arise out of, pertain to, or relate to the negligence, recklessness, or willful misconduct of the Consultant, and, upon Consultant obtaining a final adjudication by a court of competent jurisdiction, Consultant's liability for such claim, including the cost to defend, shall not exceed the Consultant's proportionate percentage of fault.

3.5.7 Entire Agreement. This Agreement contains the entire Agreement of the parties with respect to the subject matter hereof, and supersedes all prior negotiations, understandings or agreements. This Agreement may only be modified by a writing signed by both parties

3.5.8 Governing Law. This Agreement shall be governed by the laws of the State of California. Venue shall be in Orange County.

3.5.9 Time of Essence. Time is of the essence for each and every provision of this Agreement.

3.5.10 City's Right to Employ Other Consultants. City reserves right to employ 7 55452.01100\31193624.5
other consultants in connection with this Project.

3.5.11 Successors and_Assigns. This Agreement shall be binding on the successors and assigns of the parties.

3.5.12 Assignment or Transfer. Consultant shall not assign, hypothecate, or transfer, either directly or by operation of law, this Agreement or any interest herein without the prior written consent of the City. Any attempt to do so shall be null and void, and any assignees, hypothecates or transferees shall acquire no right or interest by reason of such attempted assignment, hypothecation or transfer.

3.5.13 Construction; References; Captions. Since the Parties or their agerts have participated fully in the preparation of this Agreement, the language of this Agreement shall be construed simply, according to its fair meaning, and not strictly for or against any Party. Any term referencing time, days or period for performance shall be deemed calendar days and not work days. All references to Consultant include all personnel, employees, agents, and subconsultants of Consultant, except as otherwise specified in this Agreement. All references to City include its elected officials, officers, employees, agents, and volunteers except as otherwise specified in this Agreement. The captions of the various articles and paragraphs are for convenience and ease of reference only, and do not define, limit, augment, or describe the scope, content, or intent of this Agreement.

3.5.14 Amendment; Modification. No supplement, modification, or amendment of this Agreement shall be binding unless executed in writing and signed by both Parties.

3.5.15 Waiver. No waiver of any default shall constitute a waiver of any other default or breach, whether of the same or other covenant or condition. No waiver, benefit, privilege, or service voluntarily given or performed by a Party shall give the other Party any contractual rights by custom, estoppel, or otherwise.

There are no intended third party
beneficiaries of 5.16iht into Third-Panny Sumediariese Paries.

3.5.17 Invalidity; Severability. If any portion of this Agreement is declared invalici, illegal, or otherwise unenforceable by a court of competent jurisdiction, the remaining provisions shall continue in full force and effect.

3.5.18 Prohibited Interests. Consultant maintains and warrants that it has not employed nor retained any company or person, other than a bona fide employee working solely for Consultant, to solicit or secure this Agreement. Further, Consultant warrants that it has not paid nor has it agreed to pay any company or person, other than a bona fide employee working Holy for consulat any e, conson parentage ran a gi
contingent upon or resulting from the award or making of this Agreement. For breach or violation of this warranty, City shall have the right to rescind this Agreement without liability. For the term of this Agreement, no member, officer or employee of City, during the term of his or her service with City, shall have any direct interest in this Agreement, or obtain any present or anticipated material benefit arising therefrom.

3.5.19 Equal Opportunity Employment. Consultant represents that it is an equal opportunity employer and it shall not discriminate against any subconsultant, emplayee or applicant for employment because of race, religion, color, national origin, handicap, ancestry, sex or age. Such non-discrimination shall include, but not be limited to, all activities related to 8 55452.01100131193624.5
initial employment, upgrading, demotion, transfer, recruitment or recruitment advertising, layoff or termination. Consultant shall also comply with all relevant provisions of City's Minority Business Enterprise program, Affirmative Action Plan or other related programs or guidelines currently in effect or hereinafter enacted.

3.5.20 Labor Certification. By its signature hereunder, Consultant certifies that it is aware of the provisions of Section 3700 of the California Labor Code which require every employer to be insured against liability for Worker's Compensation or to undertake self-insurance in accordance with the provisions of that Code, and agrees to comply with such provisions before commencing the pertormance of the Services.

3.5.21 Authority to Enter Agreement. Consultant has all requisite power and authority to conduct its business and to execute, deliver, and perform the Agreement. Each Party warrants that the individuals who have signed this Agreement have the legal power, right, and authority to make this Agreement and bind each respective Party.

3.5.22 Counterparts. This Agreement may be signed in counterparts, each of which shall constitute an original.

3.6 Subcontracting.

3.6.1 Prior Approval Required. Consultant shall not subcontract any portion of the work required by this Agreement, except as expressly stated herein, without prior written approval of City. Subcontracts, if any, shall contain a provision making them subject to all provisions stipulated in this Agreement.
9 55452.01100131193624.5
IN WITNESS WHEREOF, the parties hereto have caused this Agreement to be duly executed on the respective dates set forth opposite of their signatures.

CITY OF SAN CLEMENTE
By:_
ATTEST: Its:

Dated: . 20_
CITY CLERK of the City of
San Clemente, California
APPROVED AS TO FORM:

BEST BEST & KRIEGER
City Attorney

APPROVED AS TO AVAILABILITY
OF FUNDING:

Finance Authorization
("CONSULTANT")
By:

Its:

Dated: _ 20
10 55452.01100\31193624.5
EXHIBIT "A"

SCOPE OF SERVICES
DRAFTI
11 55452 01100131193624.5
CITY

CALIFORNIA
City of San Clemente
пола
Engineering Services for

RECYCLED WATER QUALITY IMPROVEMENT PROJECT
August 17, 2022
Proposal by:

C LEE+RO

WATER INFRASTRUCTURE ENGINEERS
1199 South Fullerton Road
City of Industry, CA 91748
626-912-3391 lee-ro.com
LEE+ RO

WATER INFRASTRUCTURE ENGINEERS
Celebrating 40 years
as partners in possibility.
1199 South Fullerton Road
City of Industry, CA 91748
626.912-3391
lee-ro.com August 17, 2022
Mr. Amir K. Ilkhanipour, P.E.

City of San Clemente
Engineering Division
910 Calle Negocio, Suite 100
San Clemente, CA 92673
Confidential
Subject: Recycled Water Quality Improvement Project - Project No. 17407 Dear Mr. likhanipour:

LEE + RO has carefully assembled a team to provide the City of San Clemente (City) with the skills, resources, and relevant experience needed to design the MF & RO facility at CSCWRP successfully. We have thoroughly evaluated the project needs and requirements to ensure we exceed the City's expectations. We offer the City the following benefits:

Exceptionally Qualified Project Team with a Proven Track Record: Our Team is carefully chosen to ensure the City's ultimate project success. We have included Trussell Technologies on our team for the treatment process design. Trussell Technologies enjoys an excellent reputation in high-technology water treatment process design. Kevin Saleh, PE, is proposed as our Project Manager due to his experience on similar projects for the design of micro-filtration and reverse osmosis systems. He will coordinate the work between our process design team and lead engineers.

Availability: Our team is available to begin work on the project immediately upon receipt of your authorization to proceed.

Delivery: We are in a unique position for you on this project to deliver it on time and within budget.

We will be ready for an effective turnover to operations. We know time is essential, and we have a well-defined plan to implement the project.

On behalf of the entire team, we thank you for this opportunity to work with the City staff on this important project. We will be pleased to negotiate our fee and scope with the City if deemed necessary.

Please don't hesitate to contact me at (626) 667-5309 or [email protected] if you have any questions or would like additional information.

Respectfully Submitted,
Dhiru Patel, PE
Chief Executive Officer
LEE + RO, Inc.

LOS ANGELES BAY. AREA SACRAMENTO SAN DIEGO
City of Son Clemente
Recycled Water Quality Improvement Project

CONTENTS
Project Team.. .1

TABLE OF CONTENTS
2 Experience . 8
3 Project Understanding & Approach . 17
4 Project Scope.. 25
5 Project Schedule.. 29
6 Fee..... 30

APPENDICES
Appendix A - LEE + RO Resumes
Appendix B - Trussell Technologies Resumes
Appendix C - Addenda Acknowledgement
( LEE+RO

WATER INFRASTHUCTURE ENGINEERS
lep-ro.Comn
City of San Clemente
Recycled Water Quality Improvement Project

1. PROJECT TEAM
The LEE + RO key staff members chosen for this project have significant experience executing similar services for other municipal agency clients. We have assembled a team that can successfully deliver this complex project to you in the most efficient manner. Mechanical, civil, Exhibit 1-1 electrical, instrumentation and controis (I&C) disciplines are all LEE + RO Organization Chart employees. This will make the LEE + RO team efficient and productive.

The team includes well-known industry sub-consultants because we know this is important to be high in the learning curve for this project and have a solid plan to execute to your schedule.

Principal-In-Charge
Trussell Technology, our sub-consultant, is a national technology expert which brings relevant water recycling experience and an in-depth CALIFORNIA understanding of California regulatory issues. Planning and designing Dhiru water recycling projects is a core business for Trussell Technologies and Patel, PE has been for decades. They will build on this expertise to develop ideas and approaches that save the City's time and money.

Project Manager Technical Advisory & QA/QC Staff
Full resumes for the proposed LEE + RO team members are in Appendix A.

Kevin Eric Mario
Saleh, PE Lovering, PE Manansala, PE
Project Team
Lead Controls Lead Pipeline
Lead Electrical Lead Controls Lead Mechanical Lead Civil Lead Pipeline Lead Structural Michael Shiv Jay Adam Murti James
Assadourian, PE Murti, PE Jung, PE Betsworth. PE Kadiyala, PE/PLS Gingrich, PE Subconsultants
Trussell Technologies | Process & MF/RO Mechanical Design Helix Environmental | Environmental
& LEE+RO

WATER INFRASTRUCTURE ENGINEERS

Page 1 ends

City of San Clemente
Recycled Water Quality Improvement Project
Kevin Saleh, PE I Project Manager
A project manager focused on complete delivery, Kevin Saleh has over 25 years of experience as a civil engineer.

His professional experience includes planning, design, construction management, and construction support services for various public works projects, with specific areas of practice in water and wastewater. He knows how to drive a team and execute a detailed design. He is a detailed, nuts-and-bolts engineer who focuses on a complete and biddable set of documents and has extensive experience coordinating complex electrical, I&C, and mechanical designs in similar facilities. Kevin knows how to bring stakeholders together, discuss technical issues, and drive to a resolution that everyone supports driving efficient delivery.

Kevin's Experience:
• 5 MGD Microfiltration Plant - Design Engineer/Resident Engineer for a 5 MGD Treatment Plant (Cranberry Run Water Treatment Plant, Carroll Count, MD). Kevin was involved in Mechanical and Civil design and Civil Engineer, served as Resident Engineer during the construction from the excavation to the start-up.

CA #90535 RO Plant Expansion - Design, permitting, and construction support for expanding the Groundwater Recovery Plant (GWRP) for the City of San Juan Capistrano from 5 MGD to 7.7 MGD. The expansion project BS, Civil Engineering, upgraded the Reverse Osmosis (RO) plant.

University of Tabriz
1 MGD Tertiary Filtration - Project Engineer responsible for preparing plans, including membrane feed pump station, membrane effluent piping, and technical specifications. Also responsible for engineering services during construction. His duties included reviewing submittals, responding to RFls, weekly site visits, and attending construction meetings to construct a 1 MGD tertiary membrane filtration plant inside the City of Corona's WRF2 facility.
1 MGD RO Plant - Project Engineer and Site Inspector for 1 MGD Glendale Independent Well Water Treatment Plant. Assisted in the feasibility study, permitting, and design and also provided inspection services during the construction
• 30 MGD Sea Water Desalination Plant - Dubai, United Arab Emirates. Project Engineer responsible for assisting with plant layout, hydraulics, and design of finished water tank, pipelines, and pump station. Kevin prepared O&M Manuals for the plant and reviewed submittals and shop drawings.

Jay Jung, PEl Lead Mechanical
Jay Jung has over 15 years of engineering projects in process research and design and water treatment facilities His areas of expertise include experiment setup, pilot or full-scale testing, sampling and data analysis, and development of treatment process trains. He also has considerable experience with feasibility studies, analysis of existing process trains, and preparing a project or preliminary design reports. During the last ten years, Mr.

Jung has been a project engineer responsible for developing plant design criteria, P&IDs, hydraulic profiles, and detailed facility design drawings and specifications. His expertise includes chemical conditioning and chemical handling facilities, disinfection, spent backwash water treatment, granular activated carbon adsorption, and membrane biofiltration.

Jay will supervise the mechanical design team and be responsible for the development of mechanical design drawings. He will also support the project manager in developing design deliverables and coordination with Trussell Technologies.

Civil Engineer,
CA #C75672 Jay's Experience:

PHD, Candidate, • Microfiltration CIP System - Project Manager for engineering design of Microfiltration Clean-In-Place (CIP) University of Southern systems at two West Basin Water District's satellite facilities located at the Exxon-Mobil Refinery in Torrance California (Completed 4 and the British Petroleum Refinery in Carson. The satellite facilities treat Title 22 recycled water using MF Years In Ph.D. Program) followed by RO for boiler and cooling tower applications at the refineries MS, Environmental 5 MGD Tertiary Filtration - Project Engineer for preparation of a preliminary design report and final design Engineering, University services for CVWD's California Title 22 water recycling plant expansion from 2.5 to 5.0 mgd Of Southern California
Condition Assessment of MBR Treatment System - Jay was the Project Manager for the condition MS, Environmental assessment to evaluate the extent of the damages to the Campus Kilpatrick treatment process and electrical Engineering, Yonsei equipment. The short-term and long-term solutions detail the costs of transporting raw wastewater, renting University, Korea treatment equipment, restoring the treatment plant to pre-fire conditions, and upgrading the treatment plant to an MBR treatrent system. An estimated timeline for the design and construction of the wastewater treatment plant improvements is also included.

LEE+ RO

WATER INFRASTOUCTURE ENGINEERS

Page 2 ends

City of San Clemente
Recycled Water Quality Improvement Project
Adam Betsworth, PE | Lead Civil
Adam S. Betsworth is a licensed Civil Engineer with 15 years of civil engineering, design, and construction experience in water and wastewater conveyance systems, including water transmission, trunk sewers, force mains, storage tanks, and pump stations. In his experience, Adam has calculated and resolved complex mathematical and engineering problems and formulas to meet project specifications. Adam is an expert in Civil 3D and presented projects to clients, from concept to 3D model designs using Civil 3D in conjunction with product samples and presentation material. Adam properly understands government rules and regulations as needed to complete projects. He also can draft plans and concepts using Civil 30, LDD, and AutoCAD.

Adam will design the site gradings, paving/re-paving, and any other site civil improvements deemed necessary during the design.

Adam's Experience:

Civil Engineer,
CA #C73790 Utility Relocation - Preparation of utility relocation drawings in anticipation of storm drain construction for Rowland/Homeland MDP Interferences, County of Riverside BS, Civil Engineering,
California State Grading and Storm Drain Installation - Prepared plans for grading design, protecting environmentally Polytechnic University, sensitive areas, and storm drainage for judson Tank Project in Moreno Valley Pomona
City of Beaumont Recycled Water Treatment Plant Improvements Murthy Kadiyala, PE, PLS I Lead Pipeline
With 19 years of experience in various projects in Municipal Water and Wastewater System Planning, Design, and Construction Management, Murthy has helped solve many design challenges. Murthy has provided engineering and construction support services for many Water and Wastewater pipeline installations and rehabilitation projects and helped close them out successfully. He is an expert Water System hydraulic modeler and has also served in the responsible role of a Water and Wastewater Plan Checker for many years. His added knowledge of the service connections to private developments, including land title and encumbrances, has enabled him to identify all required facilities and potential issues early in the design process. His Land Surveying experience helps add a different perspective to projects.

Murthy will do the hydraulic modeling and design the yard piping for this project.

Murthy's Experience:

Civil Engineer,
CA #C73472 Hydraulic Modeling - Provided hydraulic modeling for the various water/wastewater systems Land Surveyor, Pipeline Design - Design engineer for the City of Colton's Waste Water Treatment Plant upgrades and also CA #L9180
managed many other pipeline projects in various pipe sizes and materials MS Civil Engineering,
Michigan State Licensed Land Surveyor - Murthy's knowledge of land surveying will help to accurately locate the utilities University not shown on the site survey map.

LEE+RO

WATER INFRASTROCTURE ENGINEERS

Page 3 ends

City of San Clemente
Recycled Water Quality Improvement Project
Michael Assadourian, PEl Lead Electrical
Michael Assadourian has over 25 years of experience covering electrical and Control systems engineering, design, construction, and project management for water and wastewater treatment plants, pump stations emergency power-generation systems, water conveyance facilities, petrochemical plants, and refineries. He has in-depth knowledge of power distribution and lighting systems, both NEMA and IEC standards-based; motor controls and variable frequency drives; coordination with power & utility companies; and SCADA and radio/ microwave systems. His work experience includes P&ID development, electrical system condition assessment, ETAP analysis, load flow and short-dircuit analysis, and protective device coordination studies. He has extensive experience retrofitting existing plants with new power and controls and resolving construction-related problems.

Michael has provided various construction support services, including equipment & shop drawings review, processing of RFis, resolving construction issues, and electrical system commissioning and start-up.

Electrical Engineer, Michael will supervise the electrical design team and be responsible for the development of electrical design CA #E14390 drawings. He will also support the project manager in developing design deliverables and coordination with Trussell Technologies.

MS, Industrial &
Systers Engineering Michael's Experience:
& Management, Electrical System Condition Assessment - Performed electrical system condition assessment for three University of
wastewater treatment plants for the Elsinore Valley Water District Southern California
Electrical Design - Lead Electrical Engineer for various projects inside the water/wastewater treatment plant
Shiv Murti, PE | Lead Instrumentation & Controls
Shiv Murti has been a SCADA and electrical controls engineer for five water treatment, six pumping plants, and many water distribution control structures for over 25 years. During this period, Shiv has worked on more than 80 projects, including chemical tank farms, chlorination, ozonation of water treatment plants, a solar generation plant, and automation of distribution facilities. Before joining LEE + RO, Shiv worked as a Senior Engineer at the Metropolitan Water District of Southern California for 18 years.

Shiv will support the project manager in coordination with Trussell Technologies P&ID design and developing control system design deliverables.

Shiv's Experience:

Electrical and Controi System reliability Improvement - Lead engineer for MWD treatment facilities Electrical Engineer, reliability improvements
CA #E11391
MS, Electrical
Engineering Indian
Institute of
Technology,
Kharagpur, India
& LEE+RO

WATER INFRASTRUCTURE ENGINEERS

Page 4 ends

City of Son Clemente
Recycled Water Quality Improvement Project
James Gingrich, SE | Lead Structural Engineer
James Gingrich is a California registered structural engineer with more than 30 years of structural analysis, engineering, design, constructability analysis, value engineering, project coordination, and construction management experience. He has been the structural project manager, QA/QC reviewer, and lead structural engineer for planning, investigation and condition assessment, preparation of preliminary & final design, seismic analysis and upgrading, and construction phase engineering services for a wide variety of concrete and steel structures for water conveyance and pumping facilities, water storage, treatment, and distribution facility projects for Metropolitan Water District (MWD) of Southern California. His experience and expertise include rehabilitation & retrofit engineering & designs for existing facilities. His representative experience includes lead designer for the Lake Matthew Outlet Facilities, Colorado River Aqueduct Pumping Plant Seismic Upgrades, and Oxidation Retrofit (Ozone Disinfection) Projects for MWD's Mills Jensen, Weymouth, Skinner, and Diemer Water Treatment Plants Civil Engineer, James will supervise the structural design team and be responsible for the development of structuraldesign CA #C34701 drawings.

Structural Engineer, James' Experience:

CA #S3023
• Structural Design for Various Treatment Plant Upgrades BS, Civil Engineering,
California State
Polytechnic University,
Pomona
Mario Manansala, PE I Technical Advisor
Mario Manansala is an electrical engineer with over 40 years of experience in designing electrical power distribution systems; preparing construction bid documents, including plans and specifications; performing electrical calculations in support of the electrical plans; coordinating construction activities to ensure projects are fully completed efficiently; performing field inspections to ensure work is performed per the design intent. and developing and implementing test procedures so that the design requirements of the installation are met.

He has a broad knowledge of NEC. IEEE, UL, and NFPA codes and standards applicable to electrical system design and operation. Having worked with several electrical manufacturers such as Westinghouse, ABB, and Klockner Moeller, he has a long practical experience with the industrial application of electrical equipment. He will be an excellent technical resource for this project.

Marios' Experience:

Electrical Engineer, WRP 10 improvements Project, Coachella Valley Water District CA #C13693
WRP 7 PLC Replacements Project, Coachella Valley Water District BSEE, Electrical WRP 10 Plant B & Plant C Improvements, Coachella Valley Water District, Palm Desert Engineering.

University of the
Philippines
& LEE+RO
WATER INFRASTRUÇTURE ENGER BERS

Page 3 ends

learn con
City of Son Clemente
Recycled Water Quality Improvement Project
Eric Lovering, PE | QA/QC Manager
Eric Lovering has over 18 years of process mechanical/ electrical/ instrumentation & controls (I&C) system engineering and project management experience with water and wastewater treatment plants, pump stations industrial facilities, and standby power generation, He currently maintains two California PE licenses — "Civil" and "Electrical." Eric has extensive training and hands-on knowledge in civil, hydraulics, mechanical equipment, piping systems, and electrical & control systems. His project experience includes system analysis, alternative studies, vendor selection, engineering, design, construction, PLC programming, start-up & commissioning. trouble- shooting, and O&M consultation. Eric has hands-on experience with pumping equipment, diesel and gas-driven generators, variable frequency drives (VFDs), motor control centers, iow- and medium-voltage power distribution, and I&C systems. He has developed his knowledge of the key factors that play into a successful design that will minimize construction change orders. Backed with our QMS program and coupled with his engineering history.

Eric is a Quality Champion working on City's behalf to bring forth a high quality engineering product. Ownership Civil Engineer,
of Quality keeps Eric engaged and active throughout project lifecycle.

CA #C70807
Erics' Experience:

Electrical Engineer,
CA #E18727 • UV Disinfection System Replacement, South Bay Water Reclamation Plant, City of San Diego BS, Aeronautical • Emergency Generators, Weymouth Water Treatment Plant, Metropolitan Water District of Southern California Engineering,
University Of California, Main Switchgear Building, Weymouth Water Treatment Plant, Metropolitan Davis
Dhiru Patel, PE I Principal-in-Charge
Dhiru Patel has over 30 years of water and wastewater facilities engineering, project management and business management experience. He has managed andoverseen projects involving study, PDR, finaldesign and construction support phases for distribution. conveyance, treatment and supporting facilities for water/wastewater/water reclamation projects. He has extensive experience with project management, plant and process engineering studles, preliminary engineering, final design, construction engineering support, troubleshooting, and operations and maintenance (0&M) support for water and wastewater treatment facilities. Dhiru serves as Principal-in Charge and Project Director for many of our as needed engineering services contracts. As the Principal-in-Charge for this contract, Dhiru will have corporate responsibility for the entire project team's performance Dhirus' Experience:

Hyperion Secondary Effluent Pumping Station (HSEPS) Expansion Project, Hyperion Treatment Plant (HTP), Chemical Engineer,
CA #CH4264 West Basin Municipal Water District (WBMWD), Carson MS, Chemical Mills Water Treatment Plant, Chemical Systems Upgrades, Modules 1 & 2 Rehabilitation and Single Point Engineering, injection Facility Upgrades, Metropolitan Water District of Southern California University of
Southern California Water Treatment Plant Improvements and Rehabilitation Projects. Metropolitan Water District of Southern California, Los Angeies
LEE+RO

WATER INFRASTEUCTURE ENGINEERS

Page 6 ends

City of San Clemente
Recycled Water Quality Improvement Project
Trussell Technologies | Process & MF/RO Mechanical Design Trussell Tech is a California-focused company with unparalleled expertise in California treatment issues and regulations. Our firm has completed projects throughout the State of California for varlous municipal agencies.

Trussell Technologies recognizes the importance of meeting treatment goals and providing the design of a system with ease of operation. The firm understands the drivers and challenges to maximizing water recycling, especially as water conservation and drought impact wastewater's treatability. They are highly experienced at working with wastewater agencies to optimize their operating tacilities and frequently provide operational guidance and support. Listed below are relevant project examples to give additional insight into how we can help the City. The highlighted projects include a reference that can be contacted.

Client Project Recycled Water / Pure Membrane Processes Design Permitting Procurement Commissioning Operation
ESDC
Water Monterey Groundwater
Monterey One Water x
Recharge Project
MF/RO System for South Bay
City or Son Diego x X
Water Reclamation Plant
Padre Dam Municipal East County Advanced Water
Water District Purification Program x
City or San Diego Pure Water Program
City of Oceanside Pure Water Oceanside
Engineering Services for
City of Santa Barbara
Membrane Filtration Facility
San Elijo Joint Powers Process Optimization Plan and
Authorities As-Needed Assistance
Metropolitan Water
Regional Recycled Water Advanced
District of Southern
Purification Center Demonstration
California
Carmel Area Wastewater MF/Ro System Operational and
District As-Needed Technical Support
East Bay Municipat
RARE MF/RO Process Support Projeci
Utilitv District
Helix Environmental | Environmental
Helix is a leader in environmental consulting and natural resource sustainability. Established in 1991, Helix provides a broad range of environmental planning. CEQA/NEPA compliance, cultural resource management, biological resource studies, air quality/CHG consulting, regulatory permitting, acoustics and noise controls, and other environmental studies throughout California and the western United States. Helix has extensive experience helping public and private entities comply with environmental laws and regulations, manage natural and cultural resources, and design and construct sustainable projects. Helix also specializes in habitat restoration and the installation of native habitat.

LEE+ RO

WATER IHFRASTRECTURE ENGINEERS

Page 7 ends

City of San Clemente
Recycled Water Quality Improvement Project

2. EXPERIENCE
Electro-Dialysis Reversal (EDR) Demineralization Facility Expansion Design-Build Project at North City Water Reclamation Plant City of San Diego, CA
Client:

Michael Marks
City of SD Pub. Works
(858) 627-3253
9573 Chesapeake Dr.

San Diego, CA
Completion Date:
2011
Total Cost:
$2.5 Million
LEE + RO's Team:

Eric Lovering
The City of San Diego produces 5.5 mgd (21,000 m3/day) of 300 mg/l TDS EDR water utilizing General Electric' EDR units and produces up to 12 mgd of recycled water by blending. To provide increased reliability, LEE + RO, as design engineer to a design build contractor, designed and commissioned a new $2.5 million EDR No. 6 unit and ancillary facilities. LEE + RO also designed supporting utilities for the future advanced water treatment pilot plant. The new EDR stacks required expansion of the infrastructure including piping & valves, electrical and control systems, and structures housing the new 900 gpm capacity EDR 6 unit and modification to the existing five EDR units. The project also included a new 3,000 gpm capacity vertical turbine feed pump with VFD, new electrical MCC building with HVAC system, new electrical duct banks & power feeders, lighting, modification to existing substation, compressed air system, PLC, and ASCADA system. The EDR facility was commissioned in October 2011. & LEE+RO

WATER ESFRASTRUCTURE ENGINEERS

Page 8 ends

City of San Clemente
Recycled Water Quality Improvement Project
UV Disinfection System Replacement South Bay Water Reclamation Plant City of San Diego, CA
Client:

Manny da Rosa
City of SD Pub. Works
(619) 218-9890
525 B Street
San Diego, CA
Completion Date:
2011
Total Cost:
$2.5 Million
LEE + RO's Team:

Eric Lovering
LEE + RO provided Professional Engineering Design Services for the replacement of the UV disinfection system located at South Bay Water Reclamation Plant (SBWRP). The old Trojan UV4000 systems were beyond their useful life and the existing units no longer met the current energy efficiency standards. The new system designed by LEE + RO reduces the operations and maintenance costs and allows the City to apply for and obtain SDG&E energy credits based on the power savings by using the new system in lieu of the existing system.

The new UV system is more efficient than the old SBWRP UV system and will consume less electricity while providing the same level of disinfection.

The new UV system requires less frequent lamp replacement and will be easier to maintain leading to lower operations and maintenance costs. The new system will allow the City to comply with the Title 22 permit requirements in a more efficient manner by providing better dosage monitoring, a more reliable and maintenance friendly design, faster response to flow changes, and reduction in algae growth.

The new system meets the 100MJ/cm2 MS2 as required by California Title-22 State and also other State Department of Drinking Water requirements.

The existing channel was reutilized for the new system and the walls of the channel were structurally modified to accommodate the new UV system which is smaller than the existing system in overall dimensions. The existing weir gates were replaced with new motorized gates. As part of the design, the process hydraulic profiles were carefully engineered to ensure optimum performance The new system is equipped with multiple modular ballast systems. The project included new power and controls. The new system is equipped with multiple independent feeder breakers, one for each modular ballast systems, at allow for easy maintenance and high runtime. A new outdoor NEMA-3R MCC was provided to feed the new UV system and is located under a canopy. LEE + RO engineered the system so that the modifications required to the existing channels were minimized, which in turn reduced the shut downtime required for construction. & LEE+RO

WATER ENFRASTRUCTURE ENGINEERS

Page 9 ends

City of San Clemente
Recycled Water Quality Improvement Project
Exxon-Mobil and British Petroleum CMF Clean-in-Place Systems West Basin Municipal Water District
Client:

Rajen K. Budhia
West Basin Municipal Water Dist.
(310) 660-6241
17140 Avalon Blvd Ste 210
Carson, CA 90746
Completion Date:
2009
Total Cost:
$740,000

GTRE KO
LEE + RO's Team:

Dhiru Patel
Sal Calderon
Jay Jung
LEE + RO was contracted by West Basin Municipal Water District to provide preliminary design, detailed design, and construction phase services for the design and implementation of skid mounted Continuous Microfiltration (CMF) Clean-In-Place (CIP) systems at two of the District's satellite facilities located at the Exxon-Mobil Refinery in Torrance and the British Petroleum Refinery in Carson. The District's satellite facilities further treat Title 22 recycled water using microfiltration (MF) followed by reverse osmosis for product water to be utilized for boiler and cooling tower applications at the refineries. The existing single CIP system at each facility, consisting of a chemical feeding system using Citric Acid and Caustic, has not been effective in cleaning and protecting the MF units as intended. This project provides a second CIP system at each facility, integrated with the existing CIP systems, to increase the efficiency and protection of the MF treatment process. LEE + RO prepared a Preliminary Design Report after extensive field investigation and review. Detailed engineering and design included preparation of project plans, specifications and an engineer's cost estimate. Equipment includes the CIP tank, pumping and piping system, chemical feeding, instruments and controls, software and program upgrades. Design disciplines required included civil, mechanical, electrical, instrumentation & controls, and process engineering. Construction support services include participation in pre-bid, kick-off, and construction progress meetings, review and responses to RFls and Shop Drawing Submittals, technical support during start-up, and preparation of final record drawings.

LEE+RO

WATER INFRASTRBCTURE ENGINEERS

Page 10 ends

City of San Clemente
Recycled Water Quality Improvement Project
Trussell
MONTEREY ONE WATER 5 MGD MF/RO
Monterey One Water (M1W) - Project Highlights:
• 5 MGD advanced water treatment facility
Pure Water Monterey • Design, procurement, permitting support, and ESDC • Pilot-scale, demo-scale, and full-scale operation and support • Tested 3 different MF membranes and 2 different RO membranes

CLIENT REFERENCE PROJECT DATES TOTAL PROJECT
Paul Sciuto, P.E., M1W General Manager | 2013 VALUE
(831) 645-4600 | present $120 million
[email protected]
Did your firm meet the To meet water supply needs in the region, Monterey One Water
project schedule and consulted Trussell in developing
budget? the Pure Water Monterey project, a
Groundwater Replenishment
Yes Reuse Project. The groundwater
Trussell adhered to the recharge reuse project includes a 12-month design 5 MGD AWPF with pre-ozonation,
schedule and budget, microfiltration, reverse osmosis, UV advanced oxidation, and product water and helped this project stabilization, expandable to 6.5 mgd. Trussell assisted M1W with all technical succeed with its fast aspects of Pure Water Monterey, including pre-design testing, design, paced implementation procurement, permitting support, and engineering services during schedule in order to meet construction. During the pre-design phase, Trussell conducted bench-scale the water needs of the and pilot testing to evaluate Advanced Water Purification Facility treatment community. alternatives, designed and helped operate the Demonstration Facility (a permanent facility with pilot-scale advanced water treatment processes), and Key Staff
Shane Trussell, PE
Eileen Idica, PE
John Kenny, PE
Elaine Howe, PE (NM)
Keel Robinson
Rodrigo Tackaert, PE
LEE+RO

NATER INFRASTRECTURE ENGIMEERS

Page 11 ends

City of San Clemente
Recycled Water Quality Improvement Project
Trussell
NORTH CITY OZONE BAC RETROFIT (1.5 MGD) AND PURE WATER

DEMONSTRATION FACILITY OPERATION
City of San Diego • Pure Project Highlights:
• Final Design and Installation/Construction of 1.5 MGD Ozone/BAC Water San Diego
system to the Pure Water Demonstration Facility
• Operation of the 1 MGD Pure Water Demonstration Facility from 2013 to 2017

CLIENT REFERENCE PROJECT DATES TOTAL PROJECT
Joseph Quicho | 2013 VALUE
(858) 292-6479 | 2017 $5 million
[email protected]
Did your firm meet the Trussell has provided long-term support of the City of San Diego's Pure Water
project schedule and Program, which has a long-term goal of budget? having one-third of San Diego's drinking
water supply (approximately 83 MGD) be
Yes purified potable reuse water. Trussell Tech
Trussell Tech completed has worked with the City at each stage to all work on schedule and implement the Pure Water Program. within budget for each In 2013, Trussell began operating the Pure aspect of this complex, Water Demonstration Facility (PWDF), a 1-MGD production capacity facility cutting edge project. We consisting of micro- and ultrafiltration membranes, reverse osmosis, and an continue to get ultraviolet light with advanced oxidation process. Trussell was also retained to authorized additiona
install the 1.5 MGD ozone and
support contracts, which biologically activated carbon
are completed on budget (BAC) systems as additional
and schedule. treatment processes to the
PWDF. Trussell procured the
systems, as well as designed the
Key Staff ozone pipeline contactor (pictured
above), worked with DSD through
necessary permits, and managed
Shane Trussell, PE on-site construction. Trussell provided final as-builts to the City as a conclusion Brett Faulkner, PE of the design task. In addition, during this period, Trussell conducted extended Aleks Pisarenko testing of the new treatment train, adding to the valuable dataset that would Eileen Idica, PE eventually support the North City Pure Water Facility. Trussell also supported the City in obtaining State grant funding (Prop. 84) for operation and Rodrigo Tackaert, PE maintenance of the PWDF for one year, and hence took over maintenance as John Kenny, PE well during that time period. These efforts have provided invaluable data and information for the Pure Water Program, and demonstrate Trussell's knowledge of membrane treatment of wastewater, from on-the- ground operations and maintenance to State Water Board regulatory permitting to design expertise for San Diego-specific needs.

LEE+RO

WATER ANFRASTROCTURE ENGINEERS

Page 12 ends

City of San Clemente
Recycled Water Quality Improvement Project
Trussell

SULFURIC ACID ADDITION AND ANTISCALANT PRE-

SELECTION PILOT STUDY AT NCWRP PWDF
City of San Diego - Pure Project Highlights:

Water San Diego
North City Pure Water Facility to ensure reliable RO performance CLIENT REFERENCE PROJECT DATES | TOTAL PROJECT
Anthony Van (for sulfuric acid addition) | 2016 VALUE
(858) 292-6492 | 2018 $5 million
[email protected]
and
Joseph Quicho (for antiscalant pre-selection)
(858) 292-6479
[email protected]
Did your firm meet the As part of implementing the City of San project schedule and Diego's Pure Water program, Trussell Tech performed pilot tests to optimize the
budget? design of the future full-scale facility Pure
Water Facility. Two pilot test projects were
Yes conducted.

Trussell and partner's
in the first project, Trussell Tech along with
cost control efficiency
partner consultants designed a new sulfuric acid dosing and storage facility ensured a timely The facility was designed, permitted, and constructed on an expedited schedule and
maintenance of project schedule of only a few months. The purpose of this project was to include budget for these cost- sulfuric acid addition to an existing demonstration plant process to prevent scale formation on the RO membranes and to increase the system recovery saving projects.
from 75% to 85%. The benefit of this work will be additional pure water Key Staff production at the future full-scale facility at a lower cost.

Trussell
Shane Trussell, PE
Celine Trussell, PE independent RO trains to test three different membrane anti-scalan!
Rodrigo Tackaert, PE chemicals. The findings from the
study performed using the pilo
system will allow the City to ge
competitive three
City $1 Million per year in O&M cost at the full-scale Pure Water facility.

LEE+RO

WATER INFRASTRUCTURE ENGINEERS

Page 13 ends

City of San Clemente
Recycled Water Quality Improvement Project
Trussell

PADRE DAM MUNICIPAL WATER DISTRICT ADVANCED

WATER PURIFICATION DEMONSTRATION FACILITY
Padre Dam Municipal Water Project Highlights:
• 100,000 gpd MF/RO/UVAOP demonstration facility
District and the East County
• Design, procurement, ESDC, operation
Advanced Water Purification • Interviews and performance review of membranes used in the Program industry for qualifying the membrane specificatio

CLIENT REFERENCE PROJECT DATES TOTAL PROJECT
Seval Sen, AWP Engineering Manager | 2013 COST
(619) 258-4631 I present $528 million
[email protected]
Did your firm meet the The East County Advanced Water
project schedule and Purification Project is a potable
budget? reuse project in East San Diego
County and is a collaborative
Municipal Water District,
Diego County Sanitation District,
the City of El Cajon, and Helix
Water District. The East County
AWP Project began with efforts by Padre Dam to develop the project concept, including the construction of a 100,000 gpd demonstration facility at the Ray Stoyer Water Reclamation Facility. Trussell led process mechanical design of the demonstration facility for the free chlorine pipeline contactor, membrane filtration system, reverse osmosis system, UV/AOP unit, various water quality Yes instrumentation, and chemical feed systems through final Trussell Tech met all specifications and engineering drawings. scheduled milestones
and remained within The facility was procured through a design-bid-build approach, with Trussell support through construction, and the demonstration facility began operating project. We continue to in March 2015. Trussell Tech investigated several topics at the demonstration get authorized additional facility, including a year of intensive testing for potable reuse feasibility - support contracts, which including MS2 challenge testing to demonstrate free chlorine disinfection are completed on budget reverse osmosis and brine minimization testing - which has led to an and schedule. unprecedented 95% recovery demonstrated through the closed circuit RO configuration, and preformed chloramines - which required modification of the demonstration facility chemical feed systems and control logic in order to reduce membrane permeabilization.

Shane Trussell, PE Trussell Tech has supported Padre Dam and the JPA in utilizing these testing Brett Faulkner, PE results to define the full-scale treatment design through an initial basis of Rodrigo Tackaert, PE
LEE+RO

WATER INFRASTRECTURE ENGINEERS

Page 14 ends

City of San Clemente
Recycled Water Quality Improvement Project
Trussell
San Elijo Water Reclamation Facility Operations Plan, Operational Support, Secondary Improvements, and Recycled Water Expansion
San Elijo Joint Powers Project Highlights:
• Design of MF/RO system for recycled water expansion
Authorities
• Improvement of secondary process and integration of
instrumentation

CLIENT REFERENCE PROJECT DATES TOTAL PROJECT
Mike Thornton, General Manager VALUE
| 2008
(760) 753-6203 I present <$1 million
[email protected]
Did your firm meet the Since 2008, Trussell Technologies has worked with the San Elijo Joint Powers
project schedule and
Authority (SEJPA) on an array of
budget? projects related to secondary process
optimization, recycled water expansion
Yes design, tracer and disinfection studies,
Trussell Tech's long and instrumentation trials and
relationship has integration.
improved the clients
needs in an cost and Trussell Technologies worked with
time efficient manner. SEJPA to develop an operations plan for the whole facility to improve
treatment, eliminate guesswork, and
Key Staff minimize the operating cost of the
SEWRE. Our staff also provided the
Trussell SEJPA with the design for their 0.5
MGD MF/RO demineralization
Shane Trussell, PE
facility, which has been operating
Brett Faulkner, PE reliably over 4 years. Trussell has
Rodrigo Tackaert, PE provided ongoing technical support and operations and maintenance
recommendations for the MF and RO systems. Trussell's recommendations have ensured stable operations and reliable performance of the membrane systems at all times, including during challenging water quality events.

LEE+RO

WATER INFRASTRUCTURE ENGINEERS

Page 15 ends

City of San Clemente
Recycled Water Quality Improvement Project
Trussell
Technical Support of Operation and Maintenance of Tertiary Membrane Filtration at the El Estero Wastewater Treatment Plant
City of Santa Barbara Project Highlights:
• Enhancement of recycled water production
• Improvement of MF system performance

CLIENT REFERENCE PROJECT DATES TOTAL PROJECT
Lisa Arroyo, Wastewater System Manager VALUE
| 2016
(805) 564-5412 I present <$1 million
[email protected]
Did your firm meet the In January of 2016, the City of Santa Barbara (the City) commissioned a 2.5 project schedule and MGD tertiary facility to produce recycled water using membrane filtration (MF).

After experiencing issues with MF production, the City retained Trussell budget?
Technologies to ensure that recycled water requirements are reliably achieved. Trussell Technologies worked with operations staff to optimize the Yes MF system by improving cleaning procedures, backwash sequencing, and Trussell Tech's expertise recommending and implementing modifications to the MF system. Trussell in membrane processes Technologies coordinated discussions between the City, the MF system ensured the City was supplier, and the system integrator to implement modifications and optimize given the support the MF system. Through this effort, the City was able to double their effective needed to increase production through the MF system and meet all recycled water demands. production.

Trussell Technologies has since been
Key Staff providing routine operational support
and as-needed services, which include
weekly analyses of performance and
Trussell water quality data from the secondary
Shane Trussell, PE and tertiary treatment processes.

Brett Faulkner, PE These analyses are presented to the
City in weekly conference calls;
operational recommendations are also
discussed. By continuously working
with El Estero Wastewater Treatment
Plant (EEWTP) operations staff,
feedwater quality has improved
dramatically from the upstream
secondary process, and the tertiary MF
process has been reliably meeting
recycled water demands.

LEE+RO

WATER INFRASTRUCTURE ENGINEERS

Page 16 ends

City of San Clemente
Recycled Water Quality Improvement Project

3. PROJECT UNDERSTANDING
Our Technical Experts Have A Deep Understanding The smooth operation of the WRP of the City's Goals, and the Ability to Achieve Them Reliable MF/RO system with minimal and predictable maintenance The City owns and operates a wastewater collection and treatment • Simple but effective procurement process ensuring proven system within its service area ('City System"), which includes a technology is installed wastewater reclamation plant that provides wastewater treatment and produces recycled water that is compliant with Title 22 (Plant"). • Plug-and-play construction process The Plant currently has excess capacity available for the treatment of • Streamlined permitting processes by providing the proper wastewater.
documentation for approval in the first pass
The City's Reclamation Plant processes include preliminary treatment, primary treatment, activated sludge secondary treatment, and tertiary Technical Approach:
treatment for recycled water. A portion of the existing secondary-treated LEE + RO is pleased to see that the City is taking a forward step to wastewater is sent to the tertiary treatment to produce unrestricted maximize recycled water production by adding a new MF/RO system Title 22 recycled water. The tertiary recycled water contains excessive to the WRP. In doing so, the City follows Trussell's recommendation dissolved solids (1500 mg/L), resulting in end-user irrigation challenges. in the Water Reclamation Plant Efficiency Study Project that a partial The average capacity of the tertiary system is 4.4 MGD, with a peak demineralization process would be required to produce acceptable capacity of 5 MGD
recycled water for the South Orange County Wastewater Authority The City is proposing a Membrane Filtration (MF) and Reverse Osmosis (SOCWA) based on a review of the governing permits. (RO) treatment system to improve the quality of the blended reclaimed Several important considerations will drive the design of the MF/RO water by lowering the total dissolved solids (TDS) to an acceptable level system, as discussed below.
(less than 800mg/L) to meet both City's and SOCWA's permit limits. Costs and Layout for MF & RO Facility at the San Clemente Water Reclamation Design Considerations and Key Points
Plant was developed by Trussell Technologies dated March 14, 2022, describing a two-phase MF/RO implementation approach (Refer to the Review of Available Documents
enclosed Exhibit "A") to maximize recycled water production. The project will blend 1.2 MGD of MF/RO product water with 2.2 MGD of recycled Our team will review available drawings and other documents and water for total product water of 3.0 MGD. This total blend flow accounts show the existing underground utilities on base maps to ensure the for 3.4 MGD of available flow at the WRP and also approximately 0.4 design maintains enough separation between proposed pipelines and/ MGD of brine that would be generated from producing 1.2 MGD of MF or treatment units and existing utilities. If needed, we will identify and and RO permeate. The 3.0 MGD blend would result in a TDS of less than request that the City pothole the utility for the exact depth, size, and 800 mg/L. location.

We have assembled an exceptionally qualified team to provide design Location of Blending System
engineering, bidding support, and construction support services to the City of San Clemente (City) for the construction of a new Membrane The MF/RO product water shall be blended with the existing filtration Filtration (MF) and Reverse Osmosis (RO) treatment system at the City's discharge to lower the distribution system's TDS. Our team will evaluate Water Reclamation Plant (WRP). We understand the challenges that high the alternative locations of manifold and static mixer and discuss with salinity poses to many recycled water facilities in California and the the City's Operation to find the best option. valuable role recycled water usage plays in achieving water reliability and security. Our team is prepared to develop a design that ensures a Water Quality Assessment simple, effective, and reliable MF/RO system for the City and supports No team has as much experience as we do with tailoring designs to the bid and construction phases to ensure project success. The new deal with wastewaters of different qualities. The selection of key MF/RO system will treat a portion of the WRP's secondary effluent to design criteria (e.g., flux and recovery) highly depends on wastewater improve the quality of the blended reclaimed water by lowering the total quality. While this may seem obvious, there are multiple examples dissolved solids and other mineral content. This will provide the City across the state where this pitfall was not avoided. As a result, drastic with a reliable source of non-potable, "purple pipe" water. Our team adaptations have been required after installation to alleviate the design will leverage its knowledge of the local environment to provide the City flaws. Trussell currently has multiple contracts focused on overcoming with an MF/RO demineralization facility that addresses permit limits operational limitations caused by poorly designed MF/RO facilities. across all the recycled water users and member agencies. Both Trussell Technologies and LEE + RO have worked with the City on past projects Our team will design an MF/RO system that works from the beginning, avoiding costly redesign and headaches during operation. Our team's and we are committed to delivering a high-quality and cost-effective knowledge of the local environment will be used to design an MF/RO demineralization facility while prioritizing the following:

LEE+RO

WATER INFRASTROCIURE ENGINEERS

Page 17 ends

City of San Clemente
Recycled Water Quality Improvement Project
system that meets limits in the City's Master Reclamation Permit and collective experience--which includes Santa Barbara, Monterey One SOCWA's Master Recycling Permit. Water, San Elijo JPA, and Padre Dam Municipal Water District, as well as pre-selection for the City of San Diego's North City Pure Water Fa- Membrane Selection cility-to guide the City through the available membrane options, their features, and associated benefits or issues, as illustrated in the figure Our team knows membranes. Because of our operating experience, we below. This discussion will inform the membrane selection and help bal- know which membranes provide the best protection against fouling and ance performance goals and cost.
the greatest resistance to fiber breakages. We will pull from our vast "Universal" Membrane
Past
System area
Material Type (PVDF Installations,
vs. PES, ceramic) Low pressure vS.
high rejection
References
Manufacturing method
(NIPs vs. TIPs) Fouling and
Warranty chemical resistance
Offerings
Cleaning
regimes MF Expert RO Expert
Feedwater, Pre-Treatment, and Cleaning Strategies The team will also evaluate the need for sulfuric acid as a pre-treatment for the RO system. Sulfuric acid increases the solubility of common The membranes are not the only determining factor for reliable scalants such as calcium phosphate. It is necessary for high-recovery performance and operability. Feedwater and pre-treatment design (e.g., applications like potable reuse. A high RO recovery is not attractive for strainers and chemical addition) can be just as important, especially for this project because demineralization is the objective. Therefore, we wastewater treatment. The alum dosage as a coagulant to the filter feed would promote an acid-free design to save costs, lower safety risks, and at the WRP results in the filter effluent having high membrane scaling reduce chemical management needs. Operating at a lower recovery potential. Additionally, Trussell's review of operational data from the also lowers the frequency of cleanings and increases system uptime.

Water Reclamation Plant Efficiency Study shows that the tertiary filters have limited solids holding capacity and experience rapid headloss The use of chloramines will be necessary for this application to control buildup. Therefore, the team intends to use secondary effluent as the biological fouling. Chloramines will be formed upon the addition of feedwater for the MF/RO facility. Using secondary effluent will lower the sodium hypochlorite to the MF feedwater due to the presence of filter loading rate and thus ease operational limitations reported by the ammonia in the non-nitrified secondary effluent. An evaluation will be City. We have a good understanding of operating MF systems on non- made if preformed chloramines can be implemented at the site. The nitrified secondary effluent from several plants that produce recycled advantage of using preformed chloramines is to limit the formation of water in southern California. This experience will be used to provide potentially harsh brominated oxidants that can lower RO membrane the City with design criteria that reliably achieve the water quality goals lifespan. This is achieved using RO permeate as the carrier water to and provides predictable operation. The benefits of implementing this form chloramines in a small side-stream line. RO membranes effectively optimal pretreatment include, but are not limited to: 1) reduce the rate reject the precursors (e.g., bromide) that can lead to the formation of of fouling in RO filters, the permeability of filters remains high, and as these harsh oxidants when combined with sodium hypochlorite. Our a result, the system remains energy efficient, 2) increase in disinfection partners at Trussell have the knowledge and past design experience capacity by removing the viruses in pretreatment, and 3) a significant on how to design a simple yet effective preformed chloramine solution rejection of contaminants. for the City.

LEE+RO

WAIER INFRASTRUCTURE ENGINEERS

Page 18 ends

City of San Clemente
Recycled Water Quality Improvement Project
The cleaning regime is also key for MF/RO systems based Evaluation of Existing Site and Layout experiences supporting the San Elijo Water Reclamation Plant and the City of Santa Barbara's El Estero Wastewater Treatment Plant. Our MF/ It is important to thoroughly vet the project site location to minimize RO facility design will involve considerations for types of chemicals, disturbances during the construction of the MF/RO facility. Our team will tanks for cleaning solutions/neutralization, and procedures for perform a field visit to verify the survey map with the site conditions backwash, maintenance cleans, and clean-in-place. We can anticipate and add the existing electrical manhole, etc., to the site survey map. We and design for many challenges (e.g., rapid fouling, frequent cleans, have included potholing to the scope as an optional task to locate any integrity issues) that may come up during operations, but we also know underground utilities within the project site (if needed). that not every challenge can be anticipated. To address this, we include There are also architectural and noise ordinances that the designer must flexibility in our design (e.g., chemicals for different cleaning strategies) abide by. As part of the feasibility study, the team will conduct a detailed to empower the City with the operational tools to address future water site visit and interview the City's Operations Staff to fully evaluate the quality challenges as they arise.
facility location regarding availability of electrical power, accessibility for Instrumentation chemical deliveries, free space available inside the chemical building and utilization of existing infrastructure. A proposed layout for the MF/ MF and RO systems are highly automated processes, so any weak link RO facility is provided on the next page. It is a refined version of the in the instrumentation design can jeopardize the City's reclaimed water preliminary layout included in Trussell's March 2022 Communication on goals. We prioritize selecting and placing quality monitors, instruments, Cost and Layout. valves, and other ancillary equipment based on our experience with The layout includes the following features:
testing, comparing, and evaluating multiple options in the field including hands-on operational experience at the North City Pure Water • Strategic placement of equipment to take advantage of existing Demonstration Facility since 2013. An effective treatment process is 30-inch secondary effluent lines for MF feed and RO concentrate useless if its performance cannot be monitored and demonstrated to tie-ins the regulators.
• Placement of equipment to not disturb the existing access road, Erosion Control and Prevention of Run-off to the Site and electrical duct bank, and sodium hypochlorite lines Electrical Room
• RO skid placement to allow sufficient space for membrane element removal from the south
• Multiple trains (2 MF/UF trains and 2 RO trains) to allow for operational flexibility while conserving footprint with a double-train RO skid
• Redundancy in equipment where most needed, including two duty and one automatic standby strainer
• Chemical usage includes sodium hypochlorite, sulfuric acid fif needed), citric acid, caustic soda, sodium bisulfite, and antiscalant with space for redundant chemical transfer pumps
• Use available area in the existing chemical building for electrical. noise emitting equipment, and chemical skids and tanks
The adjacent slope soil erosion and runoff toward the existing building and proposed MF/RO site could be an issue. As the photo shows, water intrusion into the electrical room is possible. Our design team will look into this issue and recommend corrective actions such as grading design for the area between the building and the toe of the slope, extending the V-ditch, catch basin, etc.

The MF/RO concrete pad will be set 6-inch above the ground elevation, and the site will be graded to let the runoff discharge to the stormwater & LEE+RO

WATER IUFRASTRBCTURE ENGINEERS

Page 19 ends

=
TRENCH pe
LEE+ RO

MAIER ISTAASIBULIURE ENSINEERS
Exhibit 3 - 1 - Overall Site Plan LEE+RO
18115/361 1883324/773181 81/TW
City of San Cemente
Recycled Water Quelty Improvement Profect
Exhibit 3 - 2 - Site Plan 3D Layout With Canopy • LEE+RO

VALEN INTEASTRSCTUEE ENCINTERS
leero.com
Cissol Son Clemense
Recycied Water Quality improvement Project
Exhibit 3 - 3 - Site Plan 3D Layout Without Canopy LEE+RO

NETTE IS RASTRIART (NERFERS
irere.com
City of San Clemente
Recycled Water Quality Improvement Project
Production Capacity Considerations Third Party Process Design Review The water quality produced by a RO system used as a sidestream is suf- Third-party design review helps ensure the process design meets or ex- ficient to lower the overall tertiary effluent TDS needed to meet both the ceeds quality, safety, performance, and code compliance requirements.

City's and SOCWA's permit limits and meet goals for other constituents such as sulfate and chloride. A preliminary analysis indicates that poten- Maintenance of Current Standards tially 1.2 MGD of RO permeate would be required to provide 3.0 MGD of Our library of engineering standards, including standard plans, details, recycled water with a TDS less than 800 mg/l. The preliminary sizing specifications, and cost-estimating criteria, are frequently updated to assumes 97% TOS rejection by RO membranes, 1,300 mg/L secondary ensure the design team constantly incorporates changes in regulations effluent TDS, and a safety factor on the blended TDS to ensure steady and new technologies and lessons from previous projects into the de- distribution to the City's recycled water users. The intended acid-free RO sign effort. design considers 75% recovery such that approximately 0.4 MGD would be wasted from the MF/RO system, with RO concentrate sent via outfall Project Management and MF backwash water to the primary influent.

LEE + RO's project manager will conduct project management activities Construction Staging to ensure adherence to scope, schedule, and budget; promote effi- cient communication between team members, the City, and others as The contractor staging area will be considered during the design and required; and implement an effective quality assurance/quality control identified on the plans to ensure that the Operations Staff will have ac- (QA/QC) program. Our project manager will be the point of contact with cess to the facility during the construction and avoid future conflicts and the City and will have full technical and administrative responsibility for potential change orders due to access restraints. the Project. Our project manager's responsibility is to meet with the City regularly, ascertain the goals, incorporate them into the Project prompt- Constructability Review iy, and communicate them to the project team members to develop a superior product within the budget and schedule. He will work with our Contract documents will be developed, including construction plans, QA/QC Manager to ascertain that the Project is reviewed before any special provisions, and cost estimates. The industry experts and our milestone submittal and is of decent quality. construction management team will review these documents for con- structability to avoid potential construction issues. Preparation of a Management Plan is one of the first tasks undertak- en for the Project. The Management Plan will define project roles and responsibilities, communicate management philosophy, and establish Quality Control and Management project procedures and policies. Specifically, our plan includes:

Approach • Project policies and procedures will cover document control, lines of communications among the project team members and the Dis- Quality Assurance trict, sign-off procedures, report formats, and billing instructions.

Although LEE + RO maintains a library of checklists for "quality by in- • The project performance plan identifies specific work scopes on a spection," experience has taught us that the most reliable path to quality task-by-task basis and assigns schedules and budgets to each task is to engineer quality into our design process. Policies supporting this establishing the base for subsequent contro!. include the following:

Proactive Listening to Clients
Our goal is to give our clients what they want. To achieve this, LEE + RO has developed a library of questions to make it easy for our clients (especially operators and end-users) to clarify preferences and expec- tations at the start of the design process. Further, our design memo- randums and specifications are set up in tabular format to make them accessible for clients to review in light of their preferences.

Experienced Design Teams
No amount of "quality by inspection" will deliver quality if the team lacks the requisite experience. Our core project team (including sub-consul- tants) has been on similar projects for years and combines over a cen- tury of experience in civil, structural, mechanical, process, and electricall engineering
6 LEE+RO

WAIER IUFRASTROCTURE ENGINEERS

Page 23 ends

City of San Clemente
Recycled Water Quality Improvement Project
Key Elements of our Project Management Plan are:

KEY ELEMENTS OF PROJECT MANAGEMENT
Project Identification Work Program Projeci Management Technical Execution V Listen to the Client / Establish Work Plan and V Progress reporting V Project Execution Schedule
/ Ascertain project Needs V Establish Work Breakdown Comparison of Progres V Internal Quality Control Structure (WBS) leporting with WBS an
Resources Loaded Schedule
/ Identify Problem/Constraints V Resource Determination • Resolution of Discrepancies V Review Schedule Review and Adjustment i V Identification of Impacts) lan and Schedut
/ Review Budget V Establish Project Milestones V Development of Mitigation(s) / Site Review V Continuous Coordination
/ Data Review
/ Determine Expectations
/ Determine Approvai Process
/ Establish Scope of Technical Services
16 LEE+RO

WATER ERFRASTRBCTURE ENGINEERS

Page 24 ends

City of San Clemente
Recycled Water Quality Improvement Project

4. PROPOSED SCOPE OF SERVICES
The LEE + RO team looks forward to partnering with the City on this Our project manager will meet with the City virtually or in person important project. We have prepared the scope of services as outlined to report the project progress monthly. The other design lead in the City's e-mail and have indicated additions to that scope herein. engineers and/or sub-consultants may be invited to the meetings In addition, LEE + RO has summarized the deliverables and our key to address the City's questions or concerns. assumptions for each task which are listed below. The labor and fee LEE + RO will prepare the agenda and minutes of the meeting estimates are outlined in our fee exhibit and are aligned with the scope The meeting minutes will be submitted to the City for review of work based on the information below.
within three working days after each meeting.

Deliverables: Agenda, meeting/workshop material, minutes/notes for each meeting.

1. PROJECT MANAGEMENT
LEE + RO will conduct project management activities, including 3. REVIEW OF EXISTING DOCUMENTS monitoring scope, schedule, and budget. As discussed in the Following the Notice to Proceed, LEE + RO will request available pre-proposal meeting, the City anticipates a maximum duration for site record drawings, existing reports, influent flow, load char- the design phase to be approximately 12 months
acteristics, existing filtration effluent alignment, and all other This task includes general project coordination between the relevant information for review to get familiar with the site before Engineer, City, and others as required. LEE + RO will organize, the kick off meeting and field visit. administer, and supervise the work of project team members, including oversight of all in-house project personnel and adminis- 4. FEASIBILITY STUDY trative support for allocating resources necessary to meet project objectives. Our team will review and analyze data provided by the City to confirm the sizing of the MF/RO system for the removal of total The project management activities include: dissolved solids from the recycled water to an acceptable level (less than 800mg/L) to meet both City's and other stakeholder's • Monthly status reports permit limits. Data will also inform the operability of the MF/RO • Monthly PM meetings system in terms of conveyance, storage, pumping requirements, chemical usage, and cleaning frequency. The information will be • Monthly invoices used to prepare a Preliminary Design Report (PDR) related to the process, chemicals, electrical loads, and tie-ins for feed, product, • Team coordination/communications and waste streams. As part of the PDR, we will size the MF/RO • Quality Assurance / Quality Contro! for deliverables system, provide site layout, piping, and chemical system design, and describe connections and how the system will operate. • Action/decision log (or comparable issue resolution process) The City desires to isolate the electrical costs of the Recycled • Third-party quality control coordination (if approved as an Water operation and processing from the plant's other opera- optional service) tions and processes. Our team will evaluate the installation of a sub-meter of the WRP main electric line or coordinate with the The QC process will be documented in a standard LEE + RO QC power supplier to install a new transformer and meter for this new review spreadsheet. facility.

Deliverables: Monthly invoices and progress reports

5. PRELIMINARY, PROGRESS, AND FINAL PLANS,

2. PROJECT MEETINGS AND FIELD VISITS SPECIFICATIONS, AND ENGINEER'S OPINION

OF PROBABLE COST
LEE + RO anticipates that three field visits will be necessary to review existing site conditions; the first visit will evaluate available Our team will develop the preliminary design drawings (30% De- space inside the chemical building, and the second meeting with sign) and advance them to the 60% and 90% design stages. The the City's electrical and control staff to understand the available project specifications and the engineer's opinion of the probable capacity, possibility of using the existing MCCs, and the City Stan- construction cost will be submitted at the 60% and 90% progress dards to follow for the electrical and control design. The third visit stages and for the 100% / Final bid documents. will support the feasibility study drafted by Trussell Technologies.

Disciplines will organize drawings in an industry-standard format The project kick-off meeting could be held on-site and combined (see table below). The drawing list submitted herein will be updat- with the first field visit.
ed at 30% design and developed throughout the design phase.

LEE+ RO

WATER INFRASTRBCTURE ENGINEERS

Page 25 ends

City of San Clemente
Recycled Water Quality Improvement Project
LEE + RO will prepare an Opinion of Probable Construction Costs Our team will prepare a competitive pre-selection document (OPCC) for the feasibility study and update the OPCC in conjunc- set for major equipment packages to be issued upon the City's tion with each subsequent design deliverable, 60% (AACE Class concurrence with the feasibility study recommendations. Assume 4), 90% (AACE Class 4), and 100% / Final (AACE Class 3). All OPCCS two preselection packages: (1) pumping systems; (2) filter systems. will conform with the American Association of Cost Engineering The pre-selected equipment will serve as the basis for the final (AACE) cost estimating standards. design. Pre-selected equipment and pre-approved submittals with negotiated fixed prices will be incorporated into the final design The City will prepare the front-end documents (notice inviting bids, bid documents, contract documents, and general condi- tions); LEE + RO will review front-end documents and conform LEE + RO will be responsible for Division 01 and technical speci- front-end documents with the project technical requirements. fications. Specifications will follow the Construction Specification Our team will provide supplemental information and any special Institute (CSI) format. contract requirements in a project-specific Special Conditions document (e.g., pre-selection of equipment, project constraints, Our team will prepare a control narrative at the 60% design stage, intermediate milestones). describing how MF/RO system will operate and interface with the San Clemente WRP for recycled water production.

Sheet Completed MF / RO MF/RO
Drawing Drawing Title
Number 30% 60/90%
General
T-1 TITLE SHEET, VICINITY AND LOCATION MAPS LEE + RO X
T-2 2 INDEX OF SHEETS, LEGEND, AND ABBREVIATIONS LEE + RO T-3 GENERAL NOTES LEE + RO
T-4 DESIGN CRITERIA AND EQUIPMENT SUMMARY TT
T-5 5 HYDRAULIC PROFILE LEE + RO
T-6 PROCESS FLOW SCHEMATIC TT X
Demolition
D-1 DEMOLITION PLAN 1 (OVERALL) LEE + RO X
D-2 8 DEMOLITION SECTIONS AND PHOTOS LEE + RO
D-3 9 DEMOLITION DETAILS LEE + RO
Civil and Yard Piping
C-1 10 OVERALL SITE & HORIZONTAL CONTROL PLAN LEE + RO X C-2 11 SITE GRADING AND BMP PLAN LEE + RO
C-3 12 CIVIL DETAILS LEE + RO
C-4 13 YARD PIPING PLAN LEE + RO
C-5 14 PIPING PROFILES LEE + RO
C-6 15 BLENDING STATION PIPING PLAN AND SECTIONS LEE + RO X Architectural
A-1 16 PRE-FABRICATED ROOF ARCHITECTURAL PLAN, ELEVATION, AND DETAILS LEE + RO Structural
S-1 17 GENERAL STRUCTURAL NOTES 1 LEE + RO
5-2 18 RO / MF AREA STRUCTURAL PLAN LEE + RO
S-3 19 RO / MF AREA STRUCTURAL SECTIONS LEE + RO X
S-4 20 RO / MF AREA STRUCTURAL SECTIONS - 2 LEE + RO
S-5 21 RO / MF AREA DETAILS - 1 LEE + RO
LEE+RO

WATER INFRASTRBCTURE ENGINEERS

Page 26 ends

City of San Clemente
Recycled Water Quality Improvement Project
Sheet Completed MF/RO MF / RO
Drawing Drawing Title
Number By 30% 60/90%
5-6 22 RO / MF PRE-FABRICATED ROOF STRUCTURAL PLAN AND DETAILS LEE + RO S-7 23 RO / MF PRE-FABRICATED ROOF STRUCTURAL DETAILS LEE + RO 5-8 CHEMICAL CONTAINMENT AREA STRUCTURAL MODIFICATIONS PLAN LEE + RO 5-9 CHEMICAL CONTAINMENT AREA STRUCTURAL SECTIONS LEE + RO S-10 CHEMICAL CONTAINMENT AREA STRUCTURAL DETAILS LEE + RO S-11 PIPE SUPPORT SECTIONS AND DETAILS LEE + RO
S-12 28 STRUCTURAL TYPICAL DETAILS - 1| LEE + RO
Mechanical
M-1 29 PIPING AND VALVE SCHEDULE LEE + RO
M-2 30 RO / MF AREA EQUIPMENT LAYOUT TT X
M-3 31 RO / MF AREA EQUIPMENT SECTION TT
M-4 32 RO / MF AREA PROCESS PIPING PLAN TT X
M-5 33 FEED LINE MODIFICATION PLAN LEE + RO
M-6 34 WASTE LINE MODIFICATION PLAN LEE + RO
M-7 35 PRODUCT LINE MODIFICATION PLAN LEE + RO X X
M-8 MECHANICAL DETAILS LEE + RO
M-9 37 MECHANICAL DETAILS LEE + RO X
M-10 38 CHEMICAL STORAGE AREA - MECHANICAL PLAN TT
M-11 39. CHEMICAL STORAGE AREA MECHANICAL SECTIONS 1 TT X M-12 40 MF FILTRATE TANK - PLAN AND SECTION TT
M-13 41 RO / MF MISCELLANEOUS DETAILS 1 TT
Electrical and Security
E-1 42 ELECTRICAL LEGENDS AND GENERAL NOTES LEE + RO X
E-2 43 SITE ELECTRICAL PLAN LEE + RO X X
E-3 44 SINGLE LINE DIAGRAM AND MCC ELEVATION LEE + RO X E-4 CONDUIT AND CABLE SCHEDULES - 1 LEE + RO
E-5 46 CONDUIT AND CABLE SCHEDULES - 2 LEE + RO
E-6 47 SITE LIGHTING PLAN LEE + RO X
E-7 CONTROL BLOCK DIAGRAMS - 1 LEE + RO
E-8 49 CONTROL BLOCK DIAGRAMS - 2 LEE + RO
E-9 50 RO / MF AREA GROUND LEVEL POWER PLAN 1 LEE + RO
E-10 51 RO / MF AREA GROUND LEVEL POWER PLAN 2 LEE + RO E-11 52 GROUNDING PLAN LEE + RO
E-12 53 ELECTRICAL DETAILS-1 LEE + RO
LEE+RO

WATER EHFRASTROCTURE ENGINEERS

Page 27 ends

City of San Clemente
Recycled Water Quality Improvement Project
Sheet Completed MF / RO MF / RO
Drawing Drawing Title
Number 30% 60/90%
Instrumentation
1-1 54 INSTRUMENTATION AND CONTROL LEGEND 1 TT X
1-1 55 INSTRUMENTATION AND CONTROL LEGEND 2 TT X
1-3 56 MF SYSTEM (WITH FEED SYSTEM AND AUTOSTRAINERS) X X 1-4 57 MF CIP PUMPS, TANKS AND HEATER (WITH BACKWASH SUPPLY SYSTEM) TT 1-5 58 MF FILTRATE STORAGE AND RO TRANSFER PUMPS TT X
1-6 59 RO FEED PUMPING AND MF COMPRESSED AIR AND AIR SCOUR SYSTEMS TT X 1-7 60 RO SKIDS TT X
1-8 RO CIP AND FLUSH SYSTEMS TT X
1-9 62 CHEMICAL FEED SYSTEMS 1 TT X
1-10 63 CHEMICAL FEED SYSTEMS 2
1-11 64 CHEMICAL FEED SYSTEMS 3 TT X
1-12 65 CHEMICAL FEED SYSTEMS 4
1-13 66 INSTRUMENT DETAILS 1 TT
1-14 67 NETWORK DIAGRAMS - 1 LEE + RO
1-15 68 CONTROL SCHEMATICS - 1 LEE + RO
1-16 69 TYPICAL CONTROL PANELS - 1 LEE + RO
1-17 70 CONTROL PANELS - 1 LEE + RO

6. CEQA DOCUMENT 7. GRANT APPLICATION ASSISTANCE
The scope of work provided below is based on our understand- Our team will work with the City's consultant to secure this ing of the project. It assumes that preparation of a Categorical project's grants. We have allocated $5,000 for the coordination/ Exemption (CE) will be adequate to comply with the requirements support as needed. of the California Environmental Quality Act (CEQA), under Class 3 (New Construction or Conversion of Small Structures) per CEQA 8. PERMITTING ASSISTANCE Guidelines Section 15303. The City is assumed to be the Lead Agency for the project under CEQA. The following are the tasks to Our team will prepare the Title 22 Engineering Report Addendum be undertaken for this effort. for the MF/RO system for approval by the Division of Drinking Water (DDW). The addendum will be drafted early in the design Based on a review of the project site and potential activities phase to provide DDW ample time for review and approval before involved in the implementation of the project, it is anticipated that starting up. Coordination with the DOW will occur as part of devel- the project would not involve "unusual circumstances" that would oping the litle 22 Engineering Report Addendum. This will include have the potential to result in potentially significant environmental email communication and a meeting to discuss an addendum if effects. The proposed project falls under the Exemption for New Construction or Conversion of Small Structures (Class 3) because it consists of the construction and operation of a small treatment 9. BIDDING SERVICES system at a previously disturbed site requiring the addition of a limited number of new, small facilities or structures. As such, As directed by the City, our team offers a not-to-exceed maximum a Notice of Exemption (NOE) will be prepared with supporting fee which includes 15 hours of bid support, responding to bidders' information such as project plans and other reports referenced as questions, and preparing addendums as needed.
necessary. Our environmental subconsultant, HELIX, will file the NOE with the Orange County Clerk to begin the 35-day challenge Per our experience with similar projects, bidding services will re- period. quire more effort than anticipated. The additional effort can be discussed and included in the scope during the bidding and con- struction support phase.
& LEE+RO

WATER INFRASTROCTURE ENGINEERS

Page 28 ends

City of San Clemente
Recycled Water Quality improvement Project
We understand the importance of hitting your schedule deadlines and are committet to delivering for you. Our team is poised to hegin work immediately, stay focused throughout the project delivery, and stay in lock step

5. PROJECT SCHEDULE with you through dose collaboration and leveraging our indepth understanding of your facility, strategies, and procedures. We developed a milestone task schedule demonstrating some of the most critical steps.

We look forward to going trough this with you to gain mutual buy-in to the process that will result in on-time delivery.

Task Name Stor Finish
Notice-to-Proceed Thu 9/22/22 Thu 9/22/22
2 Design Phase Thu 9/22/22 Wed 7/26/23
Review of Existing Documents Thu 9/22/22 Wed 10/5/22
Kick-Off Meeting Wed 10/5/22 Wed 10/5/22 · 10/5
Field Visit Wed 10/5/22 Wed 10/5/22 • 10/5
Feasibility Study Thu 10/6/22 Wed 11/2/22
Field Visit Wed 11/2/22 Wed 11/2/22 · 11/2
Review of Feasibility Study by the City Thu 11/3/22 Wed 11/16/22 Field Visit Wed 11/16/22 Wed 11/16/22 * 11/16
Feasibility Study Workshop Wed 11/16/22 Wed 11/16/22 * 1116 Submit Final Feasibility Study Thu 11/17/22 Wed 12/7/22 30% Plans Submittal Thu 11/24/22 Wed 1/11/23
30% Plans Submittal reviow by the City Thu 2/12/23 Wed 1/25/23 Preparation of CEQA Documents Thu 1/26/23 Wed 3/22/23
60% PS&E Submittal Thu 1/26/23 Wed 3/15/23
60%6 PS&E Submittal Review by the City Thu 3/16/23 Wed 3/29/23 908 PS&E Submittal Thu 3/30/23 Wed S/17/23
90% PS&E Submittal review by the City Thu 5/18/23 Wed 5/31/23 Permitting Assistance Thu 6/1/23 Wed 7/12/23
Grant Application Assistance Thu 1/26/23 Wed 5/32/23
Final PS&E Submittal Thu 6/1/23 Wed 7/5/23
Final PS&E Submittal review by the City Thu 7/6/23 Wed 7/19/23 Bid Documents Submittal Thu 7/20/23 Wed 7/26/23
Bidding Support Services Thu 9/7/23 Wed 10/11/23
Summary Insctive Milestone Duratice-only Start-only External Milestone Manual Progress Project: Project Schedule
Date: Tue 8/16/22 Spie ........ Proyet Summary Inactive Suramary Macual Summary Rollup Finish-only Deadine inactive Task Marual Task Miceal Summary Extemsal Tasks Progress LEE+RO

WATER CNERASTRUCTURE ENGINEERS

Page 29 ends

foporo.com
City of 5an Clemente
Recycied Water Quality Improvement Project

6. PROJECT FEE
Exhibit 6-1 - Fee Estimate
PIC, GA/OC PM & Lead Project Task Designers & Assistant Administrative Direct Costs
Engineers Engineer Engineers Engineers
E2 & Ta LEE RO LEE RO Subconsukants Costs Total
Task Description
Hours Cost Printing, Cost
Trussel Mileage, and
$287 $258 $214 $180 $160 S134 Environmental Other Direct Technologies
Costs
Amount Amount Amount Amount Amount Amount Amount Amount Project Management $36,120 $0 $5,360 212 $50,664 $50,664 $27,552 48 $12,384 50 $39,936 $39,936
Project Meetings and Field Visits $10,320 $1,712 $1,440 $1,280 $14,752 $3,660 51,500 $19,912 Review of Existing Documents $3,096 $3,424 $2,160 $8,680 $8,680 Feasibility Study 40 $10,320 $5,136 $3,840 88 $19,296 218 $52,350 $71,646 Preliminary, and Progress PS&E $47,988 210 $44,940 530 $95,400 1100 $176,000 25 $3,350 2,051 $367,678 1,100 $227,610 $1,500 $596,788 Final PS&E $10,320 $3,424 $7,200 $19,200 $2,412 $42,556 60 $10,060 $500 $53,116 CEQA Document $9.722 $10,578
Grant Application Assistance $4,644 $0 $268 20 $4,912 $88 $5,000 Permitting Assistance $0 $8,132 $2,520 $0 $10,652 $34,880 $45.532 Bidding Support - Response to
RFis and Preparing Addendums $3.355 $3,355
Total for Non-Optional Work ( Task 1 thr. 9) $36.736 $135,192 316 $67,624 604 $108,720 1,252 $200,320 $11,390 2,909 $559,982 1,569 $331,915 $9.722 $3.588 $905,207 LEE+RO

Page 30 ends

City of San Clemente
Recycled Water Quality Improvement Project
Exhibit 6-2 - Hourly Billing Rate Schedule
(Effective from November 1, 2022. to October 31, 2023)

BILLING RATES

PERSONNEL CLASSIFICATION
($/HOUR)

ENGINEERS
Engineer 8 E8 Managing Engineer $287
Engineer 7 E7 Supervising Engineer $258
Engineer 6 E6 Principal Engineer $240
Engineer 5 E5 Senior Engineer $214
Engineer 4 E4 Engineer $200
Engineer 3 Associate Engineer $180
Engineer 2 E2 Assistant Engineer $160
Engineer 1 E1 Junior Engineer $137

CAD / DESIGNERS
Designer 6 16 Principal Designer $200
Designer 5 15 Senior Designer $180
Designer 4 T4 Designer $160
Designer 3 13 Associate Designer $137
Designer 2 T2 Assistant Designer $119
Designer 1 Junior Designer $100

FIELD PROFESSIONALS
Field Professional 5 F5 Senior Resident Engineer $214
Field Professional 4 F4 Resident Engineer $200
Field Professional 3 F3 Senior Inspector $180
Field Professional 2 F2 Inspector $160
Field Professional 1 F1 Assistant Inspector $137

ADMINISTRATIVE
Administrative 4 A4 Senior Contract Manager $156
Administrative 3 A3 Contract Manager $144
Administrative 2 Senior Word Processor $134
LEE+ RO

WATER INFRASTROCTURE ENGINEERS

Page 31 ends

City of San Clemente
Recycled Water Quality Improvement Project
Exhibit 6-3 - Other Direct Cost (ODC) Billing Rate Schedule (Effective from November 1, 2022 to October 31, 2023)
Automobile Mileage IRS Published Rate
$0.08 / sheet (8.5 x 11 Bond B & W)
$0.20 / sheet (8.5 x 11 Bond Color)
In-house Reproduction $0.15/ sheet (11 x 17 Bond B & W) $0.50 / sheet (11 x 17 Color)
$1.25/ sheet (24 x 36 Bond)
Mylar Original Drawing $8.00 / sheet (24 × 36 or 22 × 34) Computers & Work Stations No Charge
Subconsultant Invoice Amount Plus 5%, Unless Client Specifies Subconsultant Mark-up Otherwise
Bulk Reproduction by Outside Printing Firm Invoice amount plus 10% Handling Charge Overnight Mailing, Air Fare, Project-Specific Software, At Cost Equipment Rental, etc.
& LEE+RO

WATER INFRASTRUCTURE ENGINEERS

Page 32 ends

APPENDIX A
LEE + RO

RESUMES
& LEE+RO

WATER INFRASTROCTORE ENGINEIRS
City of San Clemente
MF-RO Facility at San Clemente WRP

KEVIN SALEH, PE

PROJECT MANAGER
Mr. Saleh has over two decades of experience as a civil engineer. His professional experience includes planning, design, construction management, and construction support services for a variety of public works projects, with specific areas of practice in water and wastewater. His relevant experience includes water distribution and treatment facilities, pumping facilities, treatment plant projects/processes, reservoirs, pressure reducing, and surge facilities. Wastewater projects LICENSE/CERTIFICATION include conveyance systems, pumping stations, and treatment plant projects and processes.

Civil Engineer, CA #C90535 EXPERIENCE
Civil Engineer, MD #36759
Ground Water Recovery Plant Expansion. Orange County, California. City of San Juan EDUCATION Capistrano. Project Engineer responsible for the design, permitting, and construction support for BS, Civil Engineering, the Groundwater Recovery Plant (GRWP) expansion from 5.0mgd to 7.7mgd. The expansion project University of Tabriz upgraded the Reverse Osmosis (RO) plant, including new chemical storage and feed systems, converting from potassium permanganate to sodium permanganate in the Greensand filters and Higher National Diploma, changing the media in Greensand filters, adding additional capacity to the RO filters by increasing Computer Programming/System the flux rate and new filter cartridges, additional finished water storage, chlorine disinfection as the Analysis, Toronto, Canada primary disinfectant before finished water storage, and aqua ammonia as secondary disinfection before distribution.

Project Management Certificate,
Cranberry Run Water Treatment Plant. Carroll County, Maryland. The City of Westminster.

California State University,
Project Engineer/Resident Engineer. Cranberry Run WTP is a new 5 MGD water treatment plant that Fullerton
replaced an aging conventional water treatment process. The main building is utilized to house microfiltration membrane treatment equipment, chemical feed systems & controls. Bar screen, raw water pumps, and equipment are housed in a separate pump house.

Siemens provides membrane filtration equipment, chemical feed system, instrumentation, and controls. Responsibilities included preparing architectural renderings, assisting in the process and mechanical design, and yard piping design, including 300-ft 16-inch and 250-ft 18-inch DI yard piping. Cost estimation and preparation of bid documents during the design. He was also the resident engineer during the construction, responsible for quality control, preparation of daily and monthly reports, coordinating and running weekly progress meetings, reviewing and approving contractor's monthly invoices, resolving the site issues, reviewing the contractor's submittals, RFIs, and RFCs; and coordination with the mechanical supplier (Siemens) for ongoing work, look ahead schedule, and delivery of equipment on time and per schedule. The total construction cost was $12M.
1 MGD Tertiary Membrane Filtration. Riverside County, California. The city of Corona. Project Engineer responsible for preparation of plans, including membrane feed pump station, membrane effluent piping, and technical specifications. Also responsible for engineering services during construction. His duties included reviewing submittals, responding to RFls, weekly site visits, and attending construction meetings to construct a 1 MGD tertiary membrane filtration plant.

Cement Hill Water Treatment Plant Chemical System Rehabilitation, Suisun Solano Water Authority. Civil engineer providing design and construction support services for the Cement Hill Water Treatment Plant, Chemical System Project. The project will convert the plant disinfection system from chlorine gas to sodium hypochlorite. Both on-site generation of low strength hypochlorite generation and medium strength (12.5%) bulk deliveries will be evaluated. The bulk hypochlorite system will likely consist of two 12,000-gallon hypochlorite storage tanks and multiple hypochlorite metering pumps for dosing at the various raw water and residual dosing locations.

LEE+ RO

WATER INFRASTAUCTURE ENGINEERS

Page 1 ends

City of San Clemente
MF-RO Facility at San Clemente WRP
The project also includes replacement and reconfiguration of the plant filter aid and coagulant KEVIN SALEH, PE dosing systems as well as replacement of all chemical piping between the metering pumps and PROJECT MANAGER dosing locations. This project is currently in construction.

Calcium Thiosulfate Chemical Feed System Project, Union Sanitary District, CA. Civil engineer who provided construction supoort services for the project to replace an existing calcium thiosulfate storage and metering facility with a new fully functional de chlorination facility to handle higher and more frequent plant discharges to an emergency outlet. The project included new chemical metering pumps, storage tank, piping, electrical, and instrumentation for the new de-chlorination facility. The project also included conducting a pump evaluation to determine the best available chemical metering pump type for this application.

Turtle Rock Zone 3 Reservoir Chloramine Booster Station, Irvine Ranch Water District. Project Manager for this Chloramine Booster Station Installation project. The Turtle Rock Zone 3 Reservoir (TR Z3 Res) is located at 13½ Minaret Drive in Irvine and supplies water to the surrounding Turtle Rock neighborhood and the Zone 3 to 4 Pump Station (TR Z4 PS) which serves the uppermost portion of the neighborhood. IRWD has experienced degraded water quality at the TR Z3 Res due to nitrification caused by the loss of chlorine residual, excess free Ammonia and low water supply turnover. Currently, IRWD doses chlorine and Ammonia at the Turtle Rock Zone 1 to 3 Pump Station to reduce nitrification in the system but this process is susceptible to chemical precipitation in the pipe where the chemical is injected and has required multiple replacements of the injection pipe.

This project will install a chioramine booster station at TR Z3 Res similar to chloramine booster| stations that are in service at multiple reservoirs throughout IRWD's potable system to address and avoid the nitrification and in-pipe chemical precipitation issues.

Honby Well PFAS Treatment Preliminary Design and Site Layout, Santa Clarita Valley Water Agency. Project Manager for Preliminary Design Report and site layout for PFAS treatment (using IX system) of 950gpm discharge flow of Honby Well and chloramination system layout including sizing of on-site Sodium Hypochlorite generation, Brine, Sodium Hypochlorite, and Liquid Ammonium Sulfate (LAS) tanks and calculation of required dosing of chlorine and Ammonia.

S Wells PFAS Treatment Preliminary Design and Site Layout, Santa Clarita Valley Water Agency Project Manager for Preliminary Design Report and site layout for PFAS treatment of 7,000gpm discharge flow of S6 to S9 Wells (using IX system) and chloramination system layout including sizing of on-site Sodium Hypochlorite generation, Brine, Sodium Hypochlorite, and Liquid Ammonium Sulfate (LAS) tanks and calculation of required dosing of chlorine and Ammonia located in S9 Well site.

Calcium Thiosulfate Chemical Feed System Project, Union Sanitary District, CA. Civil engineer who provided construction supoort services for the project to replace an existing calcium thiosulfate storage and metering facility with a new fully functional de-chlorination facility to handle higher and more frequent plant discharges to an emergency outlet. The project included new chemical metering pumps, storage tank, piping, electrical, and instrumentation for the new de-chlorination facility. The project also included conducting a pump evaluation to determine the best available chemical metering pump type for this application.

Tejon Ranch Wastewater Treatment Plant and Reclaimed Water Treatment Plant Process Design. Kern County, California. Project Engineer for preparation of Technical Memorandum for wastewater treatment plant's process design.

Prop 50 Wells and IX Treatment System, City of Corona. Project Engineer responsible for sizing lon Exchange vessels, Preliminary Design Report preparation, and the project's plans and specifications for the inlet flow of 1,600gpm in a Nitrate removal facility.

Sodium Hypochlorite Storage Facility, City of Anaheim. Project Engineer responsible for design of Sodium Hypochlorite storage facility including sizing and design of containment area, storage tanks, and piping materials determination and mechanical layout. He was also responsible for engineering services during construction including reviewing submittals. responding to RFls, as needed site visits, and attending in construction progress meetings with the City representatives and the contractor.

LEE+ RO

WATER INFRASTRUCTURE ENGINEERS

Page 2 ends

City of San Clemente
MF-RO Facility at San Clemente WRP
ADAM S. BETSWORTH, PE

LEAD CIVIL ENGINEER
Adam S. Betsworth is a licensed Civil Engineer and has 15 years of civil engineering, design, and construction experience in water and wastewater conveyance systems including water transmission mains, trunk sewers, and force mains, storage tanks, and pump stations. In his experience Adam has calculated and resolved complex mathematical and engineering problems and formulas to meet project specifications. Adam is an expert in Civil 3D and presented projects to clients, from concept to 3D model designs using Civil 3D in conjunction with product samples and presentation material. Adam has proper understanding of government rules and regulations

LICENSE/CERTIFICATION
as needed to complete projects. He also has the ability to draft plans and concepts using Civil 3D, Civil Engineer, CA #C73790
LDD, and AutoCAD.

Land Surveyor, CA #L9180

EXPERIENCE

EDUCATION
BS, Civil Engineering, Broadway Pump Station Bypass Sewer, Sunset Beach Sanitary District. Project Engineer for the California State Polytechnic Broadway Pump Station Bypass Sewer project. A project report and preliminary design will be University, Pomona developed for approximately 3,300 LF of 15-inch diameter bypass sewer main alongside Sunset Beach Greenbelt. The Sunset Beach Sanitary District (District) wishes to abandon the existing Broadway Sewer Pumping Station after confirming the feasibility of re-directing influent gravity sewer flows via a new gravity main to connect to existing City of Huntington Beach's Warner Avenue Gravity Sewer (WAGS). The design services will include an analysis of pipe alignments materials, construction techniques, permits, and grant application support. The main goals of the Project Report are to be the vehicle used to apply for a grant should the proposed federal infrastructure program afford the opportunity; be used to identify and provide necessary data to permit the project through all local, regional, state, and federal agencies; work with permitting agencies, particularly the City of Huntington Beach and Caltrans to develop alignment alternatives and pick a preferred alignment; assist in the preparation of the necessary CEQA and possibly NEPA action for the project; and, identify funding sources working with District staff to proceed with Preliminary Design Report for San Dimas Forcemain Replacement Project, Los Angeles County.

Dept. of Public Works. Civil Engineer providing civil and mechanical engineering design services for a PDR for the replacement of the force main and modifications to the existing San Dimas Pump Station. The project involves studying various possible alignments for the replacement of the force main and a recommendation of the optimal alignment, replacement of existing asphalt paving at the pump station site, minor mechanical piping and valve modifications, modifications to the electrical system including installation of new VFDs or soft starts, and lastly, wet well coating repairs.

Preliminary Design Report for Fountain Springs and Indian Creek Pump Stations, Los Angeles County, Dept. of Public Works. Civil Engineer providing civil and mechanical engineering design services for a PDR for the Fountain Springs and Indian Creek Pump Stations. The Fountain Springs Pump Station will consist of demolition of existing pump station, construction of a new pump station including all civil, structural, mechanical, electrical, I&C and an additional wet well to handle 2 hrs of peak wet weather flow; new five (5) - 125 HP pumps, each rated at 3,150 gpm @ 100 ft. TDH; and rehabilitation of the existing dual force main. The Indian Creek Pump Station will consist of demolition of the existing pump station, construction of a new pump station including all civil, structural, mechanical, electrical, I&C and an additional wet well to handle 2 hrs of peak wet weather flow; two (2) new - dual train 350 gpm @163 feet of TDH (total of 325 feet) pumps installation of new dual 6" diameter forcemain (design will include surge analysis); and design of new access road with better geometrics to allow for easier access by vactor trucks and other maintenance vehicles
LEE+RO

WATER INFRASTAUCTURE ENGINEERS

Page 3 ends

City of San Clemente
MF-RO Facility at San Clemente WRP
Watson Road Booster Station, County of Riverside- A water booster station project in which Adam ADAM BETSWORTH, PE was responsible for the on-site grading, wall plans, buildings, and pump station.

LEAD CIVIL ENGINEER
Redlands/Hemlock Booster Station, County of Riverside- A water booster station project in which Adam was responsible for the on-site grading, wall plans, buildings, and pump station.

Plano Lift Station Odor Control System Feasibility Study, Santa Margarita Water District. Civil Engineer providing civil and mechanical engineering design services for a feasibility study of Plano LS Odor Control System and Realignment of Inlet Sewer. Adam is performing a complete investigation of the existing conditions based on existing and available data and develop alternatives that are constructible and economical to the District. A feasibility letter report with figures and costs, will be prepared summarizing the findings and recommendations.

Secondary Effluent Line Replacement Project and Davis St. Manhole Replacement Project, City of San Leandro. Civil Engineer providing final design services for the Secondary Effluent (SE) Line Replacement Project and Davis Street Manhole Replacement project. The project includes installing CIPP liner In the existing 36" SE pipeline between the SE wet well at Secondary Clarifier No. 1 and the Effluent Pump Station at the City's Water Pollution Control Plant (WPCP); Installing elbows on the existing 30" and 33" Sanitary Sewer (SS) pipes and install new manholes in close vicinity of the new elbows in Davis Street (in front of the Headworks) to connect the 30" SS and 33" SS to the Headworks at the City's WPCP. Conducting CCTV inspection of the 30" and 33" SS pipes between the intersection of Davis Street and Doolittle Drive and the influent junction box in Davis Street in front of the abandoned Headworks.

Hilltop Green Lift Station Force Mains, West County Wastewater District. Civil Engineer who provided civil and mechanical engineering design services to design a 1,000 ft dual force main to replace the existing primary w force main constructed in 1966-67, made up 10-in ACP pipe, and recently required emergency repairs. The replacement force main is a 12-inch HDPE pipe connecting from the Hilltop Green Lift Station to near La Paloma Road. Evaluation included routing alternatives HDD was used at two segments within the alignment.

La Honda Lift Station Force Main Improvements, West County Wastewater District. Civil Engineer who provided civil and mechanical engineering design services to provide replacement dual force mains (6) from the lift station to the 24" gravity main. Alternative alignments were considered, and a new manhole was added to the scope.

OMUC Recycled Watermain Improvements, City of Ontario. Prepared plans to install recycled waterline for Ontario Municipal Utilities Company.

Border Avenue & Brentwood Drive Water Transmission Pipeline Replacement, City of Corona - Responsible for the design of replacing 1 mile of 16 inch and 12 inch water transmission pipeline in the streets of Border Avenue and Brentwood Drive. Included a traffic control plant.

Las Brisas Pipeline Design, Murrieta - Prepared plans to install a 24" CML&C transmission waterline in Las Brisas Road and Hancock. Reviewed submittals from the contractor for this project.

La Sierra Pipeline, City of Riverside - A 30" CML&C water transmission pipeline project in which Adam was responsible for the design of the pipeline from start to completion, includes reviewing submittals, preparing reports, and revisions.

Banning Water Canyon Main Replacement, City of Banning. Prepared plans to replace several miles of waterline in challenging areas of dirt road.
"A" Street Pipeline, City of Perris - Prepared plans for a waterline railroad crossing that involved a Jack and Bore under an existing railroad. This requiring special prerequisites and coordination with the railroad agencies.

Adams Gilley, Dekay, March Air Force Base - A pipeline project in which Adam was responsible for preparing plans to repiace waterline in Gilley Street which has "historical" concrete that needed to be protected in place.

O LEE+RO

WATER INFRASTRUCTURE ENGIHEERS

Page 4 ends

City of San Clemente
MF-RO Facility at San Clemente WRP

MURTHY KADIYALA, PE/PLS

LEAD PIPELINE ENGINEER
With 19 years of experience in a variety of projects in Municipal Water and Wastewater System Planning, Design and Construction Management, Murthy has helped find solutions to many design challenges in his career. Murthy has provided engineering and construction support services for many Water and Wastewater pipeline installations and rehabilitation projects and helped close them out successfully. He is an expert Water System hydraulic modeler and has also served in the LICENSE/CERTIFICATION responsible role of a Water and Wastewater Plan Checker for many years. His added knowledge Civil Engineer, CA #C73472 of the service connections to private developments including land title and encumbrances has Land Surveyor, CA #L9180 enabled him to identify all required facilities and potential issues early in the design process. His Land Surveying experience helps add a different perspective to projects.

EDUCATION

EXPERIENCE
MS, Civil Engineering,
Michigan State University Wastewater Treatment Plant Upgrades and Expansion, Public Works and Utilities, City of Colton. Site Civil Engineer the for upgrading and expansion of the City of Colton's wastewater BE, Civil Engineering, treatment plant (WWTP). The City of Colton (City) owns and operates the WWTP under a NPDES Osmania University, Permit issued by the California Regional Water Quality Control Board (RWQCB). The permitted plant Hyderabad, India capacity is 10.4 million gallons per day (MGD). The existing WWTP provides secondary treatment, nutrient removal, solids removal and solids digestion utilizing conventional and extended aeration. anaerobic digestion, solids dewatering and drying. The WWTP consists of three treatment plants The WWTP has been in service for over 50 years. The City has partially upgraded certain plant facilities. However, most of the WWTP components are at the end of their useful service life and require upgrade or replacement. LEE + RO is providing engineering services for the design and construction of Colton WWTP Upgrades and Expansion including following new construction and/ or improvements of the major process components: new 24" gravity sewer (from South Rancho Avenue) to the WWTP, connect the existing 30" gravity sewer to the new 24" gravity sewer with an 8' bypass manhole, new headworks including new screens, screening disposal system and odor control scrubber, new influent pump station, new influent metering structure, new vortex grit removal system and odor control scrubber, blower at the grit chamber, two new aeration basins (i.e. oxidation ditches), upgrades to existing aeration basins (i.e. new 100 HP aerators with VFDs and new MCCs), two new secondary clarifiers, upgrade the existing secondary clarifiers (i.e. trough and weir brush cleaners and re-coat clarifier mechanisms), new RAS, WAS and scum pump stations, upgrade the existing RAS and WAS pump stations (ile replace pumps and VFDs), new rotary drum sludge thickener facility and new polymer facility for rotary drum sludge thickener facility. 1W Water System Modeling, Central Contra Costa Sanitary District. Provided hydraulic modeling of the 1W system at the District's wastewater treatment plant. The system is supplied by an existing hydropneumatics tank which is to be replaced. The model was run for several feasible locations for the proposed replacement tank. The distribution pipe was mostly routed along pipe racks though a maze of underground tunnels to the far corners of the treatment plant. Six (6) strap-on ultrasonic flow meters and five (5) pressure loggers were installed, and the recorded data was used to calibrate the model for demand distribution and pipe roughness. The model results were used to identity and remedy low pressure areas in the 1W system.

Santiago Canyon Pump Station Improvements, Irvine Ranch Water District. Provided hydraulic modeling for the project to increase pumping capacity at Manning, Read, Shaw, and Williams pump stations to meet the Tier 1 fire flows in their respective zones to provide improved reliability and upgrade the facilities to current District standards. LEE + RO updated the existing hydraulic mode! for the Santiago Canyon area consisting of several pressure zones and ran the model for existing.

LEE+RO

WATER INFRASTRUCTURE ENGINEERS
Pade 5 lee-ro.com
City of San Clemente
MF-RO Facility at San Clemente WRP
interim and buildout conditions for average day, max day plus fire flow and peak hour scenarios.

MURTHY KADIYALA, PE/PLS Global fire flow analyses were performed with and without proposed pump station and future LEAD PIPELINE ENGINEER pipeline improvements. The model results were used not only to confirm and select the proposed pumps and pressure reducing valves at the four pump stations, but also to confirm the master planned pipeline improvements.

IIC East Zone A to B Booster Pump Station Upgrades Project, Irvine Ranch Water District. Murthy provided pipeline design services for the booster pump station upgrades project. The existing Zone A-B Booster Pump Station contains four Goulds pumps (three duty and one standby), model 14RHMC, and one spare pump can for an additional pump. Each pump has a capacity of 2,000 gpm at a TDH of 201 feet. The pumps are housed in a 24- inch diameter pump barrel. The project recommends installing a 5th Goulds pump, model 14RHMC, with the same capacity of 2,000 gpm at a TDH of 201 feet.

Pressure Reducing Station Modifications at Via Vista Grande, Avocado Mesa, and Carancho West, Rancho California Water District. Murthy provided construction phase for the pressure reducing station modifications. The existing PRS facilities (Avocado Mesa, Carancho West, and Via Vista Grande) were designed and constructed in below grade vaults and have reached the end of their expected service life. To reduce access issues (due to pipe runs located within confined below grade concrete vaults) and eliminate the confined space entry requirements when performing routine maintenance, facility inspections, and facility repairs, RCWD desires to demolish the existing below grade PRS structures and construct new above grade PRS facilities located within masonry block equipment enclosures (approx 4 - 5' tall).

Overland Drive and Margarita Road Potable Water Pipeline Replacement - Rancho California Water District. As the Project Manager, Murthy has provided design phase services for the replacement of a potable water line and associated pavement restoration work. This project is located within the city of Temecula and consists of the design of a replacement pipeline for approximately 2,432 linear feet of existing 16-inch diameter C905 PVC potable water pipeline The existing pipeline, installed in 1999, experienced two catastrophic failures from 2018 to June 2019. During repair work, District staff observed that the pipeline ruptured from what appears to be "over-belled " joints, which has resulted in failure at the joints and subsequent splitting longitudinally down the pipe section. LEE + RO performed a pipe material evaluation, alignment| selection, pipeline replacement/repair alternatives and provided a technical memorandum and performed bid phase services. The project included development of engineered traffic control plans through primarily commercial developments consisting of Costco, restaurants and a strip mall, and coordination with the City for plan checking and approval thereof.

Irrigation Lateral Replacement Project, Coachella Valley Water District, Palm Desert. Murthy is the Project Manager providing engineering and design services for three Irrigation Lateral replacement projects. Irrigation Lateral 119.64-7.5 includes the replacement of 18,500 LF irrigation piping of various sizes (ranging from 18 to 30 in. dia.). The existing pipeline has experienced hydraulic surging and numerous leaks that adversely impact the delivery of canal water to the District's customers. Replacing the concrete pipe with new C905 PVC pipe and the removal of baffle stands converts the canal water distribution system from gravity flow to a pressurized system, effectively eliminating the surging and water losses. This $7 million project will also install new in-line meters at the delivery points to reduce energy consumption. Existing irrigation service must be maintained during construction and a temporary highline for bypassing will be required to maintain service. The existing pipeline alignment lies in a 10- foot wide USBR easement. There are several locations along the alignment where the pipeline easement has been encroached upon by farmers' crops and local residences, which makes replacing those portions of the alignment in the same trench problematic for the District. The District placed this project on hold during final design to consider alternative alignments and/ or construction methods. Irrigation Lateral 123.45-1.3-2.2 Phase 1 and Phase 2 replaces approximately 7,900 LF of 20-inch and 24-inch diameter concrete pipe between 59th Ave. and 62nd Ave. along with approximately 2,600 LF of 14 inch diameter concrete sub-laterals. Phase 1 construction is complete, and Phase 2 is currently in design, LEE+ RO

WATER INFRASTRUCTURE ENGINEERS

Page 6 ends

City of San Clemente
MF-RO Facility at San Clemente WRP

JAY JUNG, PE

LEAD MECHANICAL ENGINEER
Jay Jung has 15 years of process research and design, as well as water treatment facilities engineering projects. His areas of expertise include experiment setup, pilot or full-scale testing. sampling and data analysis, and development of treatment process trains. He also has considerable experience with feasibility studies, analysis of existing process trains, and preparation of project or preliminary design reports. During the last ten years, Mr. Jung has been a project engineer responsible for development of plant design criteria, P&IDs, hydraulic profiles, and detailed facility design drawings and specifications. His area of expertise includes chemical conditioning

LICENSE/CERTIFICATION
and chemical handling facilities, disinfection, spent backwash water treatment, granular activate Civil Engineer, CA #C75672
carbon adsorption, and membrane biofiltration.

EDUCATION EXPERIENCE
PH. D. Candidate University of
Southern California (Completed 4 Water Reclamation Plant 2 (WRP 2) Improvements, Coachella Valley Water District. CVWD Years In Ph.D. Program) operates WRP 2, a 33,000 gpd aerated pond treatment plant that services the remote community of North Shore near the Salton Sea. The plant, constructed in 1976, had difficulty meeting permit MS, Environmental Engineering, conditions set by the Regional Board due to the age and condition of the equipment and pond.

University of Southern California Jay was the Project Manager with responsible charge over the design improvements including re- MS, Environmental Engineering, grading the existing ponds and installing a new HDPE liner; installation of new floating aerators, Yonsei, Korea demolition of abandoned process facilities, re-grading the site to drain onsite stormwater to the aeration pond and providing a permanently instailed (75 kW) diesel standby generator.

Water Treatment Plant Chlorine Conversion Project, City of El Centro, Project Manager providing engineering, design, and construction support services for the conversion of gaseous chlorine system to bulk liquid sodium hypochlorite disinfection systems at City's WTP. The City of El Centro (City) owns and operates a Water Treatment Plant (WTP) that receives its water supply from the Colorado River through the Imperial Irrigation District's (IID) canals. The City's WTP has a design capacity of 21 MGD, with an average daily demand of 7.8 MGD and current peak flows of 13-14 MGD. The WTP currently operates a gaseous chlorine water disinfection system to disinfect the water prior to discharging it into the City's supply lines. The City had concern regarding the usage of chlorine gas as a disinfectant, as chlorine gas is toxic and poses dangers to the public and operations staff. Since the WTP is located adjacent to residential areas, the risk of chlorine gas exposure to the public is greatly increased in the unlikely event of a large leak. Thus, the City desires to convert from a gaseous chlorine system to a 12.5% bulk sodium hypochlorite disinfection system.

Chemical System Upgrading for Ozone Oxidation Retrofit (ORP) project, Diemer Water Treatment Plant, Metropolitan Water District of Southern California. Project Manager for preliminary design report, final design, and construction support services a $8.5 million chemical tank farm project supporting the $130 million ORP facilities at the 520 mgd Diemer Water Treatment Plant in Yorba Linda. Several chemical projects were designed and constructed: sodium hypochlorite, sulfuric acid, hydrogen peroxide, and caustic systems. Each system included unloading, bulk storage, metering, containment, electrical and I&C, and safety systems such as eye-wash fountains. The hypochlorite system included two 4,600-gallon tanks and feed system was designed for flow- paced feed control. The caustic system included three 33,000-gallon tanks and the feed system for flow-paced feed control with pH trim. The sulfuric system consisted of two 33,000-gallon tanks and feed system flow-paced feed control with pH trim. The hydrogen peroxide system consisted two 2,000-gallon tanks and feed system.
& LEE+RO

WATER INFRASTRUCTURE ENGINEERS

Page 7 ends

City of San Clemente
MF-RO Facility at San Clemente WRP
Chemical Systems Capacity Upgrades & Modules 1&2 Rehab Project, Mills Filtration Plant, JAY JUNG, PE Metropolitan Water District of Southern California (Current). Working as a Process Engineer for LEAD MECHANICAL the final design of chemical storage and feeding system upgrades for 326 mgd treatment capacity.

ENGINEER The chemical systems include sulfuric acid, caustic soda, alum/ferric, poly-dadmac, chlorine, sodium hypochlorite, aqueous ammonia, dry polymer, and fluorosilicic acid.

Oxidation Retrofit Project (ORP), Diemer Water Treatment Plant, Metropolitan Water District of Southern California. Process Engineer for the final design of chemical storage and feeding systems (caustic soda, sodium hypochlorite, and hydrogen peroxide) supporting a $73.2 million ORP project at the Diemer.

ORPs, Skinner Filtration Plant, Metropolitan. Project Engineer for design of chemical storage and feeding systems (sulfuric acid, hydrogen peroxide, and caustic) supporting a $130 million ORP project and design of the site electrical power distribution system supporting the ORP, Washwater Reclamation Plant No. 2 and No. 3, and the chlorine containment and handling project.

ORP, Weymouth Filtration Plant, Metropolitan. Project Engineer for preparation of the preliminary design report for chemical storage and feeding systems (caustic, sulfuric acid, hydrogen peroxide and sodium hypochlorite) and site electrical power distribution system supporting a $120 million ORP project at the Weymouth Filtration Plant. Also, Jay involved in the final design and construction support of ORP switchgear building generator and aboveground diesel storage tank. The work includes design of two 1600kVA emergency generator, 10,000 gallons of diesel storage tank and associated fuel supply/return system, and fire sprinkler system.

Chemical Systems Upgrades & Modules 182 Rehab Project, Mills Water Treatment Plant, Metropolitan. Process Engineer for the preliminary and final design of chemical storage and feeding system upgrades with an estimated construction cost of $17 million for the 326 mgd treatment capacity. The chemical systems include sulfuric acid, caustic soda, alum/ferric, poly-dadmac, chlorine, sodium hypochlorite, aqueous ammonia, dry polymer, and fluorosilicic acid.

ORP, Diemer Water Treatment Plant, Metropolitan. Process Engineer for the final design of chemical storage and feeding systems supporting a $73 million ORP project at the Diemer Water Treatment Plant. The work includes process design calculations for chemical feed systems including sulfuric acid, caustic soda, and hydrogen peroxide system; preparation of final design including process flow diagrams, mechanical design, P&ID, and specifications for equipment.

Chlorine Containment and Handling Facilities (CCHFs) for Skinner, Jensen, and Mills Filtration Plants, Metropolitan Water District of So. Ca. Civil Engineer for the preparation of studies, preliminary design reports and final design documents for CCHFs at three MWD water treatment plants. Each CCHF has an estimated construction cost of approximately $20 million and contains either 90-ton chlorine rail cars or 19-ton trailers including chlorinators, evaporators, chlorine gas and solution piping, ventilation, and a chlorine scrubbing system.

Back Basin Ground Water Treatment Plant, Elsinore Valley Municipal Water District, Lake Elsinore, California. Project Engineer for a groundwater treatment project. Prepared a start-up and testing procedures plan and training of plant personnel during the commissioning of the 5mgd groundwater treatment plant. The treatment process involved pressure filtration including air scour and backwashing with water; ferric chloride, caustic soda, and ammonia storage and feeding systems; disinfection with on-site generated sodium hypochlorite; high service pumping; recovery and recycle of backwash wastewater after settling out solids; and monitoring of turbidity, pH, total chlorine residual, free chlorine residual, and ammonia in the process water. & LEE+RO

WATER INFRASTRUCTURE ENGINEERS

Page 8 ends

City of San Clemente
MF-RO Facility at San Clemente WRP

MICHAEL ASSADOURIAN, PE

LEAD ELECTRICAL ENGINEER
Michael Assadourian has over 25 years of experience covering, electrical and control systems engineering, design, construction and project management for water and wastewater treatment plants, pump stations, emergency power generation systems, water conveyance facilities. petrochemical plants, and refineries. He has in-depth knowledge of power distribution and lighting systems, both NEMA and IEC standards-based; motor controls and variable frequency drives:
coordination with power & utility companies; and SCADA and radio/microwave systems. His work LICENSE/CERTIFICATION experience includes P&ID development, electrical system condition assessment. ETAP analysis, Electrical Engineer, CA #E14390 load flow and short-circuit analysis, and protective device coordination studies. He has extensive experience in retrofitting existing plants with new power and controls and resolving construction- EDUCATION related problems. Michael has provided a wide variety of construction support services including MS, Industrial and Systems equipment & shop drawings review, processing of RFis, resolving construction issues, and Engineering & Management, electrical system commissioning and start-up.

University of Southern California

EXPERIENCE
BS, Electrical Engineering, Water Reclamation Plant No. 10 (WRP 10) Plant B & Plant C Improvements, Coachella Valley University of Southern California Water District, Palm Desert. Electrical / Instrumentation & Controls Engineer for a $5.43 million upgrading and rehabilitation project at the 18 MGD capacity WRP 10. The project scope included the replacement of RAS and WAS pumps and VFDs and electrical system upgrades: replacement of 54 slide gates in the aeration basins and mixed liquor distribution channels; replacement of secondary clarifiers to the RAS pump stations; replacement of tank drain valves; and associated electrical and control systems.

Water Reclamation Plant #2 Improvements, Coachella Valley Water District (CVWD). Electrical / Instrumentation & Controls Engineer for the $2.2 million water reclamation plant improvements project. The project included the replacement of the existing MCC-1 with a new 400A Distribution Panel DP-1, a new 300A ATS, a new 400A main service panel, a new PLC panel for feed and control, and eight new aerator pumps at iwo oxidation ponds. The project also included the installation of new conduits, feeders, starters, and breakers for all aerator pumps.

Hyperion Secondary Effluent Pump Station (HSEPS) Expansion Project at Hyperion Treatment Plant (HTP), West Basin Municipal Water District, Carson. Electrical Engineer for a $14.7 million capacity expansion project (from 70 to 90 mgd) including a connection of 60" secondary effluent supply piping to the pressurized HTP's secondary effluent channel (wet tapping) and addition of two new 20 MGD pumps (190 feet of TDH), each driven by 800 HP, 4,160V motor and VFD. Work includes CFD modeling of pump intake system to satisfy the Hydraulic Institute's requirements:
construction of a 40 feet deep vertical structure in a tight site for installation of the additional vertical turbine pumps; mitigation of construction impact at the El Segundo Water Recycling Plant and HTP (minimum shutdown period); connection of 48" pump effluent header to the existing 60- inch Pressure Main in Vista Dei Mar; and addition of a 3,000 kW emergency generator with a fuel storage system.

Water Treatment Plant Chlorine Conversion Project, City of El Centro. Electrical Engineer providing engineering, design, and construction support services for the conversion of gaseous chlorine system to bulk liquid sodium hypochlorite disinfection systems at City's WTP. The City of El Centro (City) owns and operates a Water Treatment Plant (WTP) that receives its water supply from the Colorado River through the Imperial Irrigation District's (IID) canals. The City's WTP has a LEE+ RO

WATER INFRASTRUCTURE ENGINEERS

Page 9 ends

City of San Clemente
MF-RO Facility at San Clemente WRP
MICHAEL ASSADOURIAN, PE design capacity of 21 MGD, with an average daily demand of 7.8 MGD and current peak flows of LEAD ELECTRICAL ENGINEER 13-14 MGD. The WTP currently operates a gaseous chlorine water disinfection system to disinfect the water prior to discharging it into the City's supply lines. The City had concern regarding the usage of chlorine gas as a disinfectant, as chlorine gas is toxic and poses dangers to the public and operations staff. Since the WTP is located adjacent to residential areas, the risk of chlorine gas exposure to the public is greatly increased in the unlikely event of a large leak. Thus, the City desires to convert.

Turtle Rock Zone 3 Reservoir Chloramine Booster Station, Irvine Ranch Water District. Electrical Engineer for this Chloramine Booster Station Installation project. The Turtle Rock Zone 3 Reservoir (TR Z3 Res) is located at 13½ Minaret Drive in irvine and supplies water to the surrounding Turtle Rock neighborhood and the Zone 3 to 4 Pump Station (TR Z4 PS) which serves the uppermost portion of the neighborhood. IRWD has experienced degraded water quality at the TR 23 Res due to nitrification caused by the loss of chlorine residual, excess free ammonia and low water supply turnover. Currently, IRWD doses chlorine and ammonia at the Turtle Rock Zone 1 to 3 Pump Station to reduce nitrification in the system but this process is susceptible to chemical precipitation in the pipe where the chemical is injected and has required multiple replacements of the injection pipe.

This project will install a chloramine booster station at TR Z3 Res similar to chloramine booster stations that are in service at multiple reservoirs throughout IRWD's potable system to address and avoid the nitrification and in-pipe chemical precipitation issues.

Treatment Plant and Electrical System Improvements (FY2013 Southside Plant Improvements), J. B. Latham Wastewater Treatment Plant, South Orange County Wastewater Authority.

Electrical and Controls Engineer for this $7.5 million project. The Southside Plant Improvements Project consists of four individual components; (1) replacement of the Plant No. 2 power supply; (2) construction of an Enhanced Primary Coagulation System (chemical feed system) for Plant No.2; (3) mechanical rehabilitation of the thirteen (13) rectangular secondary clarifiers; and (4) implementation of structural and seismic improvements.

MCC and Control Panels Condition Assessment, Elsinore Valley Municipal Water District.

Electrical Engineer providing engineering and field services to conduct condition assessments for the MCCs and Pump Control Panels and subsequently prepare a prioritized list for future Capital Improvement Projects (CIP) to rehabilitate these facilities. The District operates 129 facilities, including 54 booster stations, 38 lift stations, 27 well sites, 5 recycled water pump stations, 3 wastewater treatment plants, and 2 water treatment plants. Original construction dates for these facilities range from the early 1970s to 2016, with a few of the older facilities having various rehabilitation improvements projects completed around 2004. Due to the general age of the equipment, some of the Motor Control Centers (MCCs) and Pump Control Panels have become difficult to maintain since replacement parts are difficult to find and have the potential to impact reliable operations.

RP-5 Flow Equalization and Effluent Monitoring Project, Inland Empire Utilities Agency (IEUA).

Electrical Engineer for this project. RP-5 produces Title 22 recycled water with a current capacity of 10 mgd. The project is comprised of several components, including use of recycled water to match the capacity of the Recycled Water Pump Station by implementing an automated system that will bypass peak flows into the equalization basin, providing a new flow metering system at the inlet of the chlorine contact basin to better control chemical usage and allow for more accurate dosing of chlorine, replacement of the sodium hypochlorite pumping system and a redesign of the existing sodium bisulfite pumps, and a shade structure to cover the sodium bisulfite pumps. & LEE+RO

WATER INFRASTRUCTURE ENGINEERS

Page 10 ends

City of San Clemente
MF-RO Facility at San Clemente WRP

SHIV MURTI, PE

LEAD CONTROLS ENGINEER
Shiv Murti is a SCADA and electrical controls engineer for five water treatment and six pumping plants, and many water distribution control structures for more than 25 years. During this period, 1 worked on more than 80 projects including chemical tank farms, chlorination, ozonation of water| treatment plants, a solar generation plant, and automation of distribution facilities.

LICENSE/REGISTRATION EXPERIENCE
Electrical Engineer, CA #E11391
Mills Water Treatment Plant Electrical System Improvement - Stage 1 Project, Metropolitan EDUCATION Water District of So. Ca. (MWD). Electrical and I&C Engineer for the Mills plant electrical system MS, Electrical Engineering, reliability improvement project. This project increased the reliability of the Mills plant electrical Indian Institute of Technology, system. The plant had a single radial system with only one source of power from the Riverside Kharagpur, India Public Utility (RPU). That system offered no redundancy. The plant was very vulnerable to a total plant shut down caused by single point of failure. If the plant lost the utility source, they either BS, Electrical Engineering, had to bring generators) on the line, or the plant would experience a total black out. This project Indian Institute of Technology, provided a second source of utility power and upgraded the whole plant power system to a dual Kharagpur, India source redundant system.

Replacement of Filter Valves and Actuators at Filter Buildings No. 1 and No. 2. Weymouth Water Treatment Plant, Metropolitan Water District of Southern California. Electrical and I&C Engineer who providing engineering services for replacement of filter valves, actuators and related mechanical, electricai and instrumentation facilities for Filter Building No. 1 and Filter Building No. 2 at MWD's Weymouth Water Treatment Plant, located in La Verne, California. Services included are P&IDs, instrumentation and electrical engineering work for the project. The Weymouth plant. is the original water treatment plant in MWD built in 1941. With several expansions, the Weymouth plant is currently treats up to 520 MGD of water. The plant has about 288 filter valves and actuators between two Filter Buildings. Filter Buildings Nos. 1 and 2 both contain forty-eight (48) filters each, with each filter consisting of five (5) each of the Influent Valves, Effluent Valve, Backwash Valve, Surface Wash Header Valve and Drain Valve. Piping associated with these valves was installed in 1940 (filters 1 through 24) and 1960 (filters 25 through 48). Filter building valves and many of the miscellaneous valves are beyond their originally intended life. The actuators are at the end of their service life. The reliability of the treatment process is being reduced due to the increasing rate of valve actuator failures. The project scope includes installation of the valves and actuators. The work requires review prior evaluation, review structural evaluation of filter gates in Filter Building No. 1. review Metropolitan 3D CAD drawings of Filter Building Nos. 1 and 2. review recent filter valves projects at other similar Metropolitan plants and evaluate applicability at the Weymouth plant, review of valve and actuator design criteria, research existing filter valve controls, review recent similar filter valve rehabilitation/replacement projects documents at other Metropolitan treatment plants, evaluate current operator preferences, and power supply and signal infrastructure options. The rehabilitation work needed to be accomplished with minimal impacts to the current operations.

Seal Beach Pumping Station Replacement, Orange County Sanitation District. Electrical and 1&C Engineer for the Orange County Sanitation District's new 34 mgd Seal Beach Pump Station. The new pump station, located adjacent to the Seal Beach Naval Weapons Station, will replace the existing pump station facility, which will be demolished once the new one is up and running and will eliminate the need for the upstream Westside Pump Station in the future, in addition we will also be designing to add a new 54 inch gravity sewer line. The project includes the completion of LEE+RO

WATER INFRASTRUCTURE ENGINEERS

Page 11 ends

City of San Clemente
MF-RO Facility at San Clemente WRP
the preliminary design and final design phases, including demolition, civil, mechanical, structural.

SHIV MURTI, PE
architectural, HVAC, electrical, instrumentation and control systems design. The pump motors

LEAD CONTROLS
will be controlled by variable frequency drives (VFDs) with constant speed bypass and the VFDs ENGINEER will be fitted with anti-ragging technology. A new electrical building will house the new electrical equipment including 480V arc-resistant switchgear, with an automatic open transition transfer scheme, emergency standby generator, portable generator connections, MCCs, VFDs, PLCs and network communication equipment, fire alarm system and security systems.

As-Built Pump Station, Los Angeles Department of Water and Power. Electrical and | & C Engineer for the project which consists of field investigations to verify pipe lengths, sizes etc. to create a mechanical and civil as-builts; point to point measurements to allow for the creation of electrical as-builts; and point clouds and survey data created by Tetra Tech will be utilized.

Sr. Engineer (Annuitant): Metropolitan Water District of So. California 2018 - 2020 Similar responsibilities as my fuli-time employment at MWD detailed below.

Sr. Engineer: Metropolitan Water District of So. California 1992 - 2017 • Review of specifications and design documents including process and instrumentation diagrams (P&IDs), electrical control, wiring and plan drawings. • Development of specifications for Remote Terminal Units (RTUs) and Programmable Logic Controllers (PLC) based on project requirements.
• Purchased more than 50 RTUs (for a proprietary SCADA system), PLCs, and other control system components.
• Coordination with in-house engineering teams, plant operations teams, outside consultants, and contractors during the project life cycle.
• Review of contractor submittals and shop drawings to verify adherence with the design specifications.
• Construction and start-up support of projects and continuing support to the clients (Operations and Water Quality groups) after the start-up
• HMI design and field testing of the screens.

Configuration and field testing of more than 10,000 points including hardwired, software, historical, alarm management, and MODBUS network points in the SCADA database. • Application development in C for equipment control and data acquisition, and in VB for report generation using Excel Macros.

Sr. Engineer: Bechtel Power Corporation 1981 - 1986 & 1991 - 1992 • Electrical controls engineer for a coal-fired power plant, nuclear plant, and an oil refinery. • Design of electrical controls and instrumentation for the power plant and refinery processes. • Purchasing of the electrical and instrumentation items.

Electrical Engineer: TMSI (the power group of DMJM) 1986 - 1988 • Electrical engineer for a 12 MW landfili gas burning power plant in So. California.

Duties included design, construction, and start-up support. • Purchasing of electrical and instrumentation items.

Electrical Engineer: McDonnell Douglas Aircraft Company 1988 - 1991| • Electrical load analysis for MD-11 aircraft.
• Test set up, conducting tests, and analyzing test results for the aircraft power system.

Electrical Engineer: Hindustan Aeronautics Limited, India 1971 - 1980 Before immigrating to the US, I worked in India for approximately nine years as an electrical engineer in an aerospace company for aircraft electrical systems. • LEE+RO

WATER INFRASTRUCTURE ENGINEERS

Page 12 ends

City of San Clemente
ME-RO Facility at San Clemente WRP

JAMES GINGRICH, PE/SE

LEAD STRUCTURAL ENGINEER
James Gingrich is a California registered structural engineer with more than 30 years of structura!! anaiysis, engineering, design, constructability analysis, value engineering, project coordination and construction management experience. He has been the structural project manager, QA/QC reviewer, and lead structural engineer for planning, investigation and condition assessment, preparation of preliminary & final design, seismic analysis and upgrading, and construction phase LICENSE/CERTIFICATION engineering services for a wide variety of concrete and steel structures for water conveyance Civil Engineer, CA #C34701 and pumping facilities, water storage, treatment and distribution facility projects for Metropolitan Structural Engineer, CA #S3023 Water District of Southern California. His experience and expertise include rehabilitation & retrofit engineering & designs for existing facilities. His representative experience includes lead designer EDUCATION for the Lake Matthew Outlet Facilities, Colorado River Aqueduct Pumping Plant Seismic Upgrades, BS, Civil Engineering. and Oxidation Retrofit (Ozone Disinfection) Projects for Metropolitan Water District of Southern California State California's Mills, Jensen, Weymouth, Skinner, and Diemer Water Treatment Plants.

Polytechnic University; EXPERIENCE
Pomona
Hyperion Secondary Effluent Pumping Station (HSEPS) Expansion Project, Hyperion Treatment Graduate courses it Plant (HTP), West Basin Municipal Water District (WBMWD), Carson. Lead Structural Engineer Structural Dynamics & for a $13.7 million pumping capacity expansion project (from 70 to 90 mgd) including a connection Advanced Structural Analysis, of 60-inch secondary effluent supply pipe to the pressurized HTP's secondary effluent channel Cal State University, (wet tapping) and addition of two new 20 MGD pumps (190 feet of TDH), each driven by 800 Los Angeles HP, 4,160V motor and VFD. Work included CFD modeling of pump intake system to satisfy the Hydraulic Institute's requirements; construction of a 40 feet deep vertical structure in a tight site for installation of the additional vertical turbine pumps; mitigation of construction impact at the El Segundo Water Recycling Plant and HTP (minimum shutdown period); connection of 48" pump effluent header to the Existing 60-inch Pressure Main in Vista Del Mar, a busy highway; and addition of a 3,000-KW emergency generator.

Booster Pump Station 3501 Replacement, Coachella Valley Water District. Structural Engineer for the replacement of a domestic water booster pump station at site 3501.The district experienced capacity and supply issues in the high zone and desired a new pumping facility that would provide service through the year 2030. The existing site included two above ground steel reservoirs, six (6) vertical turbine pumps of various sizes that supply water to the sky valley pressure zone, a portable emergency generator, a surge tank, and connections to an existing lower pressure zone. The new $3.3 million booster pump station project includes four (4) new 200 hp vertical turbine pumps with reduced voltage soft starts, instrumentation and controls, a new 1,200a electrical service and utility transformer, a new electrical building with HVAC to house the new switchboard, ATS, MCC and electrical panels and SCADA panel, a new chemical storage building, a new air compressor for the surge tank, a new 750kw stationary diesel-fueled emergency generator and load bank.

The existing pump station remains online throughout the construction process and will not be demolished until the new booster pump station is commissioned and is fully operational. New fill and drain piping (yard piping) will be provided for the existing reservoirs to optimize the site layout and operations. New seismic valves will be installed at the reservoir connections. This project is currently in construction.

Oxidation Retrofit Projects (ORPs) at Five Water Treatment Plants, Metropolitan Water District of Southern California (MWD). Lead structural engineer responsible for structural analysis and preparation of structural drawings & specifications and construction phase engineering for the $850 million ORP projects at 520 mgd Weymouth, 750 mgd Jensen, 220 mgd Mills, 630 mgd LEE+RO

WATER INFRASTRUCTURE ENGINEERS

Page 13 ends

City of San Clemente
MF-RO Facility at San Clemente WRP
Skinner, and 300 mgd capacity Diemer Water Treatment Plant. Also, served as lead QA/QC JAMES GINGRICH, PE/SE structural engineer for structural designs produced by outside consultants during preliminary design and provided Structural QA/AC reviews for final design.

LEAD STRUCTURAL
ENGINEER Filter Building and Filter Complex Seismic Upgrades, Weymouth Water Treatment Plant, MWD Lead structural engineer for preliminary and final design of a large seismic upgrade project for the filter buildings and filter complex at the 520 mgd capacity Weymouth Water Treatment Plant in the City of La Verne. In 2016 received the American Concrete Institute Excellence in Concrete Construction Awards (First Place Award in Repair and Restoration Category at Southern California Chapter and Second Place at the National Convention)
Phase 4 Plant Expansion, Skinner Water Treatment Plant, MWD. Served as lead structural engineer responsible for the preparation of Module 7 structural construction drawings, calculations and specifications. The phase 4 plant expansion project included addition of 110 mgd Module No. 7 (clarifiers and filters), a 34 mgd capacity Washwater Reclamation Plant No. 3, new and consolidated chemical tank farms and feed systems, sludge handling facilities expansion, new water pumping stations; and related work.

Seismic Retrofit of Electrical Buildings Nos. 1 and 2, Mills Water Treatment Plant, MWD. Served as design manager and lead structural engineer for the preliminary and final design for the seismic retrofit of two existing buildings, including mentoring & training the design and structural calculations of junior structural engineers.

Lake Mathews Outlet Facilities, MWD. Lead structural engineer responsible for the preparation of structural construction drawings, calculations and specifications. Performed the finite element dynamic structural analysis of the new outlet tower structure.

Development of Structural Design Manual Structural Engineering Guidelines, MWD. Lead efforts for the development, preparation and maintenance of Metropolitan's Structural Design Manual, standard structural details, master structural specifications, and standards such as the structural portions of the standard Preliminary Design Report, and submittal review procedures.

Lake Perris Dam and Outlet Facilities, Department of Water Resources (DWR), State of California.

Participated on the value engineering team evaluating proposed remediation measures and developed alternative options for the seismic rehabilitation of the Lake Perris dam and outlet tower.

Seismic Retrofit of Colorado River Aqueduct (CRA) Pumping Plant Buildings, MWD. Served as project manager and lead structural engineer for the seismic retrofit of the pump house buildings at the Hinds, Eagle Mt, Iron Mt, Gene and Intake pumping plants. Developed seismic retrofit concepts, and prepared construction drawings including calculations and specifications for construction and Metropolitan forces work. •
Seismic Retrofit of Colorado River Aqueduct (CRA) Discharge Pipelines, MWD. Served as project manager and lead structural engineer for the seismic retrofit of the delivery pipelines (penstocks) at the Hinds, Eagle Mt, Iron Mt, Gene and Intake pumping plants. Developed retrofit concepts and prepared construction drawings, calculations and specifications for construction and Metropolitan forces work. Performed the finite element dynamic structural analysis of the pipelines.

Seismic Retrofit of Electrical Buildings Nos. 1 and 2, Mills Water Treatment Plant, MWD. Served as design manager and lead structural engineer for the preliminary and final design for the seismic retrofit of two existing buildings, including mentoring & training the design and structural calculations of junior structural engineers.

Inland Feeder Pressure Control Structure, MWD. Served as design manager responsible for the coordination of multi-disciplined team and the preparation of construction drawings and specifications.

Colorado River Aqueduct (CRA) Quagga Mussel Study, MWD. Served as design manager responsible for preparing report evaluating the effects of the Quagga mussel infestation on the facilities (pumping plants, siphons, intake structures, tunnels etc.) along the entire reach of the Colorado River Aqueduct.

LEE+RO

WATER INFRASTAUCTURE ENGINEERS

Page 14 ends

City of San Clemente
MF-RO Facility at San Clemente WRP

ERIC LOVERING, PE

TECHNICAL ADVISOR & QA/QC
Eric Lovering is a California State registered "Civil" and "Electrical" engineer with 19 years of diversified planning, engineering, design, and construction experience. Eric has extensive training and hands-on knowledge in hydraulics, civil, mechanical, and electrical engineering including instrumentation & controls (I&C), programmable logic controllers (PLCs) and SCADA LICENSE CERTIFICATION systems. As lead mechanical/electrical engineer and project manager, Eric has successfully Civil Engineer, CA #C70807 completed the design, construction, start-up and commissioning of water, recycled water, and Electrical Engineer, CA #E18727 wastewater pumping facilities (capacities range from 200 galions/minute to 450 million gallons/ day) projects and emergency power generation systems (capacities from 150 kW to 10 mega

EDUCATION
Watt). Eric has developed exceptional skills in hydraulic analysis, pump selection, pumping BS, Aeronautical Engineering. sysyy6tem control logics, surge controls, and related electrical and I&C/SCADA system design and University of California, Davis construction. Additionally, he has completed pump station evaluations, condition assessments, and development of rehabilitation and upgrading schemes. Eric has been serving in the position of LEE + RO's Chief Engineer since 2020.

EXPERIENCE
UV Disinfection System Replacement, South Bay Water Reclamation Plant, City of San Diego.

Project Manager for the for the replacement of the UV disinfection system located at South Bay Water Reclamation Plant (SBWRP). The existing Trojan UV4000 systems were identified by the City to be beyond their useful life and the units do not meet the current energy efficiency standards. The new system designed by LEE & RO reduced the operations and maintenance costs and allows the City to apply for SDG&E energy credits based on the power savings by using the new system in lieu of the existing system. The total anticipated construction cost is estimated to be around $2.6 million.

Emergency Generators, Weymouth Water Treatment Plant, Metropolitan Water District of Southern California. Eric provided mechanical and building systems engineering for the planning and design of a 4.5 MW capacity emergency power system facility consisting of two. 2,250 kW generators and diesei fuel storage supporting a 600 mgd capacity water treatment plant. The project included a new 7,000 square feet building housing two new generators and

4.16 kV switchgear.

Main Switchgear Building, Weymouth Water Treatment Plant, Metropolitan. Lead Engineer for the design of a new $8 million, 5,000 square foot main switchgear building housing 12kV and 4.16kV switchgear, two 1.000 kW emergency generators, and other electrical equipment.

Responsible for engineering and design of mechanical, HVAC and building piping and plumbing.

Headworks & Grit System Improvements, Point Loma Wastewater Treatment Plant, City of San Diego. Construction Manager for a $21 million Headworks & Grit System Improvement project at the 240 mgd PLWTP. The project included field-testing of the existing headworks to optimize flow distribution, to develop a reliable hydraulic profile, and to determine the most-efficient grit tank cross-sectional dimension configuration. The project includes reconfiguration & reconstruction of the south aerated grit tanks, a new two-story grit dewatering building with grit storage bins, facility ventilation upgrades, and odor control scrubber modification. Due to heavy & deep concrete structure retrofit work in the extremely congested project site, an extensive constructability analyses was performed during design.

LEE+ RO

WATER INFRASTRUCTURE ENGINEERS

Page 15 ends

City of San Clemente
MF-RO Facility at San Clemente WRP
Replacement of Switchgear & MCC at Cajalco Intake Plant, West Municipal Water District.

Project Manager for the replacement of switchgear & MCC at Cajalco Intake Plant. The Intake

ERIC LOVERING, PE
TECHNICAL ADVISOR & QA/QC Plant's existing main electrical switchgear had reached the end of its useful life. The switchgear is provided with 4160V, 3-phase, 1200A overhead service, which is then distributed on-site to three major areas, Intake Pump Station, Booster Pump Station No. 1, and Booster Pump Station No. 2, as well as via overhead power line to the Plant facility, Hillside Irrigation, and Hillside Domestic tank and booster pump areas. WMWD requested the replacement of the 4160V switchgear including the service entrance meter and main circuit breaker sections, motor control centers sections, feeder breaker sections as well as the section that connects the existing solar PV system; excluding components that serve the decommissioned Booster Station No. 1 loads Safety deficiencies will be improved such as grounding, arc-flash, and reliability. All the pumps will require new starters and controls. In addition, the PLC/SCADA system will need to be completely replaced. A feasibility evaluation was conducted for conversion of entire 4160V MCCs to 480V equipment, which includes but is not limited to circuit protection, transformer, starter sections, and motors.

Miramar Pump Station Rehabilitation, San Diego County Water Authority. Project Manager for upgrading of an 80 cfs (51.7 MGD) capacity potable water pump station delivering water from the Miramar Water Treatment Plant to member agencies. The pump station is equipped with two vertical turbine pumps (400 and 800 HP) and one 1,000 HP horizontal split case pump. The scope of work included comprehensive condition assessment and hydraulic & surge analysis This $5 million upgrade project includes replacement of pumps, seismic reinforcement, forced air ventilation, replacement of all existing 2.3 kV electrical equipment with 4.16 kV system, addition of automatic pump controls, SCADA integration, noise control, and site improvements, including new perimeter fencing.

CRA Pumping Plants 230kV Line Reactors and 6.9kV Bus Bracing Improvements, Metropolitan.

Lead Engineer for the study of potential fault currents in the circuit breakers in the switch houses at four CRA pumping plants (Intake, Gene, Eagle Mountain, and Hinds) and design of 230kV line reactors and 6.9 kV bus bracing. This project provided safe fault current protection for the CRA pumping plants by reducing the momentary fault current load on the 6.9kV circuits below 70,000 amps and upgraded the capacity of the 6.9kV buses to at least 70,000 amps. All five switch houses were rehabilitated to withstand the available fault current at each plant. In addition, new line reactors in the yard limit the fault currents to match the existing breaker ratings (70,000 amps). Hinds Eagle and Gene required six line reactors, one for each phase.

Santiago Hills II Zone 5 to 6 Domestic Water and Zone C+ to D Recycled Water Booster Pump Station Project, Irvine Ranch Water District. Project Manager for the combined domestic water pump station and recycled water pump station facility for a new 398 acre medium- and high- density residential development. The $2.0 million domestic water pump station consists of four (4) 15 HP and two (2) 100 HP variable frequency drive pumps including standby pumps with a combined total capacity 1,500 gpm and the $1.9 million recycled water pump station consists of four (4) 15HP variable frequency drive pumps with a combined total capacity of 1,300 gpm. Both stations have 5hp jockey pumps. The scope of work included hydraulic analysis and modeling, PDR, final design, and bid & construction phase engineering services. The project included perimeter wall and access, masonry building, mechanical equipment and yard piping, and instrumentation and controls. Final design included preparation of a Project Manual describing sequencing associated with connections and tie-ins to existing facilities, utility research, permit coordination, and all civil, structural, mechanical, HVAC, and architectural elements.

Turtle Rock Zone B+ Recycled Water System Analysis and Modification, Irvine Ranch Water District. Project Manager for $1.2 million in improvements to the recycled water pump station.

Performed comprehensive analysis including distribution system modeling and surge analysis for the system and implemented a number of system improvements: Removed two small pumps (75 and 50 hp sizes); modified time of use (TOU) operations so that the pumps do not operate during the SCE's on-peak charge periods; replaced existing PLC system and VFDs for two 100 hp pumps; and converted an existing pressure reducing station from a back-up Zone B connections to a primary Zone D connections to provide anticipated demands.

LEE+RO

WATER INFRASTRUCTURE ENGINEERS

Page 16 ends

City of San Clemente
MF-RO Facility at San Clemente WRP

MARIO MANANSALA, PE

TECHNICAL ADVISOR & QA/QC
Mario Manansala is an electrical engineer with over 40 years' experience in designing electrical power distribution systems; preparing construction bid documents, including plans and specifications; performing electrical calculations in support of the electrical plans; coordinating construction activities to ensure projects are fully completed in an efficient manner; performing

LICENSE/CERTIFICATION
field inspections to ensure work is performed in accordance with the design intent; and developing Electrical Engineer, CA #E13693 and implementing test procedures so that the design requirements of the installation are met. He Arizona (1995), Philippines (1975) has broad knowledge of NEC, IEEE, UL, and NFPA codes and standards applicable to electrical system design and operation. Having worked with several electrical manufacturers such as Westinghouse, ABB and Klockner Moeller, he has a long practical experience with the industrial EDUCATION application of electrical equipment.

BSEE, Electrical Engineering,
University of The Philippines EXPERIENCE
WRP 10 Improvements Project, Coachella Valley Water District. Electrical Engineer providing construction phase services for the Water Reclamation Plant 10 (WRP1O) Improvements projet.

WRP10 contains three separate liquid stream activated sludge secondary treatment trains, referred to as Plant A, Plant B, and Plant C, and two tertiary treatment trains. 2 mgd Plant A was constructed in 1974. Subsequently Plant B and C were constructed to expand the total secondary treatment capacity to 18 mgd. This $3.5 million project is to rehabilitate and upgrade Plants B and C and includes the follwing project elements: (1) Replace Plant B Waste Activated Sludge (WAS) Pumps & VFDs; (2) Replace Plant C Return Activated Sludge Pumps & VFDs; (3) Replace Plant B Secondary Clarifier Rotary Scum Troughs; (4) Replace Plants B and C Aeration Basin Influent and Effluent Channel Aeration Piping and Diffuser Replacement and Reconfiguration; (5) Replace and Rehabilitate Plants B and C Aeration Basin Froth Spray Lines and Spray Nozzles; (6) Replace Plant C Aeration Basin and Secondary Clarifier Inlet/Outlet Gates (total 54 Gates); Replace Plant B Scum Pumps and Piping; (7) Replace Plant CRAS V-notch Flow Control Devices with Telecoping Valves (total 12 Valves): and (8) Replace Plant B and C Sections of Aeration Air Piping on Top of Walkways WRP 7 PLC Replacements Project, Coachella Valley Water District. Electrical Engineer providing construction phase services for the PLC Replacements project. The treatment processes at the Coachella Valley Water District (CVWD) WRP 7 are controlled by individual programmable logic controllers (PLCs). The PLCs and cabinets at WRP 7 were beyond their useful lives and CVWD wished to replace seven of them with new GE RX3i PLCs and new cabinets. LEE + RO conducted an assessment of the control system and identified the existing as-built conditions, identifying exactly what I/O is terminated in each PLC and where all the wiring within each PLC cabinet comes from and goes to. We also visually inspected exposed conduit and wiring associated with these process controls and assessed and documented their condition; and made recommendations regarding their reuse and/or replacement. All systems remained operational during the assessment work LEE + RO then prepared specifications regarding sequencing of the construction work so that shut downs and interruptions will be kept to a minimum during construction.

WRP 10 Plant B & Plant C Improvements, Coachella Valley Water District, Palm Desert.

Electrical Engineer during construction phase engineering services for a $5.3 million upgrading and rehabilitation project at the 18 MGD capacity WRP 10. Mario is responsible for reviewing the contractor's electrical shop drawing submittals, RFIs and requests for change order.

LEE+RO

WATER INFRASTRUCTURE ENGINEERS

Page 17 ends

City of San Clemente
MF-RO Facility at San Clemente WRP
MARIO MANANSALA, PE Reclamation Plant 1 (RP-1) Digester Gas Flare Replacement Project, Inland Empire Utilities TECHNICAL ADVISOR & QA/QC Agency, Chino. Electrical Engineer for the engineering & design of three new waste gas flares for the disposal of biogas generated by a 60 mgd treatment plant. RP-1 has seven digesters are operated as phased thermophilic digestion. Multi-stage digestion produces acid and methane phase gases. Low quality acid phase gas is flared at all times. This $7 million project is to replace aging candlestick flares with three new clean enclosed burners. The new flares will combust up to the full flow of biogas (e.g. 1,000 cim). The digester gas handling system and flares will be designed to meet the latest SCAQMD emission limits of NOx, CO, and PM10.

Michelson Water Recycling Plant Unit Substation T-1 Replacement Project, Irvine Ranch Water District. Electrical design engineer for the Unit Substation T-. The Unit Substation T-1 is comprised of two 5kV load breaks, a 1000kVA transformer, and multiple 480V distribution sections. The existing equipment shall be replaced in kind and at the same location to accommodate the existing conduits and conductors. The F1 and F2 feeders will be interrupted during construction, which will affect downstream Unit Substations T-2, T-9, T-3, and T-10 and the recently installed battery energy storage system (BESS). The 5kV power to the downstream unit substations and BESS shall be maintained during construction. Substation T-1 also distributes 480V power to DSB-200 and MCC-301, which provides power to critical treatment processes. The 480V power shall be maintained during the construction process without the extended use of temporary generators. A primary component of the Project will be the development of a construction phasing plan to ensure continuous, uninterrupted operation of MWRP during the construction period.

Mills Water Treatment Plant Electrical System Improvement Project, Metropolitan. Lead Electrical Engineer for the Mills plant electrical system reliability improvement project. This project increased the reliability of the Mills plant electrical system. The plant had a single radial system with only one source of power from the Riverside Public Utility (RPU). That system offered no redundancy.

The plant was very vulnerable to a total plant shut down caused by single point of failure. If the plant lost the utility source, they either had to bring generators) on the line, or the plant would experience a total black out. This project provided a second source of utility power and upgraded the whole plant power system to a dual source redundant system.

Replacement of Switchgear & MCC at Cajalco Intake Plant, West Municipal Water District.

Electrical Engineer providing bidding and construction phase services for the replacement of switchgear & MCC at Cajalco intake Plant. The Intake Plant's existing main electrical switchgear had reached the end of its useful life. The switchgear is provided with 4160V, 3-phase, 1200A overhead service, which is then distributed on-site to three major areas, Intake Pump Station, Booster Pump Station No. 1, and Booster Pump Station No. 2, as well as via overhead power line to the Plant facility. Hillside Irrigation, and Hillside Domestic tank and booster pump areas. WMWD requested the replacement of the 4160V switchgear including the service entrance meter and main circuit breaker sections, motor control centers sections, feeder breaker sections as well as the section that connects the existing solar PV system; excluding components that serve the decommissioned Booster Station No. 1 loads. Safety deficiencies will be improved such as grounding, arc-flash, and reliability. All the pumps will require new starters and controls. In addition, the PLC/SCADA system will need to be completely replaced. A feasibility evaluation was conducted for conversion of entire 4160V MCCs to 480V equipment, which includes but is not limited to circuit protection. transformer, starter sections, and motors.

Plant 143, Highland, California, East Valley Water District. Mr. Manansala was the electrical engineer for preliminary design report and the final design for this water treatment plant upgrade.

The design involved the electrical system supporting the upgrades to the chemical feed systems, washwater recycle system, the new emergency generators, and the electric utility service. Mr.

Manansala provided the electrical design and the construction support. & LEE+RO

WATER INFRASTRUCTURE ENGINEERS

Page 18 ends

City of San Clemente
MF-RO Facility at San Clemente WRP

DHIRU PATEL, PE

PRINCIPAL-IN-CHARGE
Dhiru Patel has over 30 years of water and wastewater facilities engineering, project management and business management experience. He has managed and overseen projects involving study, PDR, final design and construction support phases for distribution, conveyance, treatment and supporting facilities for water/wastewater/water reclamation projects. He has extensive experience with project management, plant and process engineering studies, preliminary engineering, final LICENSE/CERTIFICATION design, construction engineering support, troubleshooting. and operations and maintenance Chemical Engineer, CA #CH4264 (O&M) support for water and wastewater treatment facilities. Dhiru serves as Principal-in-Charge and Project Director for many of our as needed engineering services contracts. As the Principal- EDUCATION in-Charge for this contract, Dhiru will have corporate responsibility for the entire project team's MS, Chemical Engineering,
University of Southern California EXPERIENCE
BS, Chemical Engineering. Hyperion Secondary Effluent Pumping Station (HSEPS) Expansion Project, Hyperion Treatment Indian Institute of Technology, Plant (HTP), West Basin Municipal Water District (WBMWD), Carson. Principal-in-Charge for $14 Bombay, India million pumping capacity expansion project (from 70 to 90 mgd) including a connection of 60-inch secondary effluent supply pipe to the pressurized HTP's secondary effluent channel (wet tapping) and addition of two new 20 MGD pumps (190 feet of TDH), each driven by 800 HP, 4,160V motor and VFD. Work includes CFD modeling of pump intake system to satisfy the Hydraulic Institute's requirements; construction of a 40 feet deep vertical structure in a tight site for installation of the additional vertical turbine pumps; mitigation of construction impact at the El Segundo Water Recycling Plant and HTP (minimum shutdown period); connection of 48" the Existing 60-inch Pressure Main in Vista Del Mar, a busy highway; and addition of a 3,000-kW emergency generator.

Mills Water Treatment Plant, Chemical Systems Upgrades, Modules 1 & 2 Rehabilitation and Single Point Injection Facility Upgrades, Metropolitan Water District of Southern California.

Project Manager for conceptual studies, preliminary design and final design for the Chemical Systems Upgrade project, Modules 1 & 2 Rehabilitation project, and the Single Point Injection project to enable the Mills plant to operate at 326 mgd capacity. The chemical systems include new feed pumps, feed pump controis, and control valves for injection of chemicals ahead of the modules or filters. Modules 1& 2 were inactive for number of years and required complete new instrumentation and controls. The single point injection enhances operational flexibility and reduces O&M costs.

Water Treatment Plant Improvements and Rehabilitation Projects. Metropolitan Water District of Southern California, Los Angeles. Principal in Charge and QA/QC officer (since 2002) for numerous plant improvements and rehabilitation projects at the five water treatment plants (aggregate construction cost over $175 million at 600 mgd Weymouth, 700 mgd Skinner, 600 mgd Jensen, 300 mgd Mills, and 500 mgd Diemer Plants): $50 million new chlorine storage/containment and chlorination systems at Skinner, Jensen and Mills; $20 million electrical system improvements at Weymouth; $15 million electrical system for Weymouth Oxidation Retrofit Program (ORP) project:
$5 million chemical tank farms at Diemer: $24 million Module 1 and 2 rehabilitation and chemical system improvement at Mills; $7 million Washwater Reclamation Plant No. 2 improvements at Skinner; and $15 million site electrical system improvements supporting the ORP and Module 7 LEE+RO

WATER INFRASTRUCTURE ENGINEERS

Page 19 ends

City of San Clemente
MF-RO Facility at San Clemente WRP
DHIRU PATEL.PE
Metropolitan Water District, Post-Ozonation Neutralization Alternatives Evaluation - Skinner,

PRINCIPAL-IN-CHARGE
Diemer and Weymouth Water Filtration Plants. Project Manager for the life cycle cost benefits evaluation of lime siurry and sodium hydroxide options for post-ozonation neutralization for Skinner, Weymouth and Diemer water treatment plants for MWD. The evaluation includes review of existing caustic storage and handling facility design and operations, review existing data provided by MWD, conceptual layout for alternative lime storage and handling, equipment selection/sizing, reliability evaluation, capital and O&M cost estimates, life cycle cost benefit evaluation and report preparation of and briefing packages for presentation to MWD.

On-Call Water Recycling Plant and Recycled Water Distribution Projects, West Basin Municipal Water District, Carson. Principal-In-Charge and Project Director responsible for overseeing various engineering services and construction management services projects for West Basin. The engineering services projects include the Verification of Electrical System Documentation Project at the Edward C. Little Water Reclamation Facility and satellite facilities, the Ferric Chloride Full Scale Demonstration Test Project at Hyperion Wastewater Treatment Plant, and the Variable Frequency Drives Design Project for the barrier pumps at the Edward C. Little Water Reclamation Facility. The construction management services project includes the Construction Management, Inspection and Testing Services for Anza Ave. Lateral and Imperial Ave. Lateral Project in El Segundo and Torrance.

Water Reclamation Plant No. 10 (WRP 10) Upgrading and Rehabilitation, Coachella Valley Water District, Palm Desert. Principal-in-Charge for a $5 million upgrading and rehabilitation project at the 18 MGD capacity WRP 10 in Palm Desert. Project scope included replacement of RAS and WAS pumps and VFDs and electrical system upgrading; replacement of 54 slide gates in the aeration basins and mixed liquor distribution channels; replacement of secondary scum skimmers and scum pump stations; installation of channel agitation systems for mixed liquor distribution channels; hydraulic/weir modification of the RAS system from the secondary clarifiers to the RAS pump stations; replacement of tank drain valves; and associated electrical and control systems.

Water and Water Reclamation Plant, City of Lompoc. Project Manager for a Risk Management and Prevention Plan (RMPP) projects for City's Water and Wastewater Treatment Plants. The project involved facility design and operations review, HAZOP study, seismic evaluation and retrofit, as- built drawings preparation, operator training, development of catastrophic scenarios for chlorine and sulfur dioxide release, air dispersion modeling using ALOHA model, emergency evacuation area determination and recommendations for mitigation of risks. Santa Barbara APCD and the City staff and the general public reviewed the RMPP document.

Fluoridation Systems and Fluoridation Tank Farm Roof Design for Water Filtration Plants, Metropolitan Water District of Southern California. Project Manager for providing process engineering and PDS based P&ID development support for fluoridation storage and handling facilities at Jensen, Diemer, Weymouth and Mills Filtration Plants. Project manager for architectural, electrical and structural design for fluoridation tank farm roof design at Mills Filtration Plant.

Post-Ozonation Neutralization Alternatives Evaluation - Skinner, Diemer and Weymouth Water Filtration Plants, Metropolitan Water District of Southern California. Mr. Patel was the task manager for the life cycle cost benefits evaluation of lime slurry and sodium hydroxide options for post-ozonation neutralization for three MWD water filtration plants. The evaluation includes review of existing facility design and operations, review existing data provided by MWD, conceptual layouts, process design, equipment selection/sizing, reliability evaluation, capital and operations and maintenance cost estimates, life cycle cost benefit evaluation and preparation of letter report and briefing packages for presentation to MWD.
& LEE+RO

WATER INFRASTRUCTURE ENGINEERS

Page 20 ends

APPENDIX B

TRUSSELL

TECHNOLOGIES

RESUMES
LEE+RO

WATER INFRASTROCTRE ERGINFERS
Trussell
R. Shane Trussell, Ph.D., P.E., BCEE Resume
supplies, leading innovative, effective engineering
and research projects throughout California.

PROJECT EXPERIENCE (Select Projects)
City of San Diego/Stantec
Title: Pure Water San Diego Program
Year: 2015-Present
R. Shane Trussell, Ph.D., P.E., BCEE Trussell Technologies, Inc. is part of a consulting team including Stantec and Brown and Caldwell,
EDUCATION working with the City of San Diego to implement the • Ph.D. Civil and Environmental Engineering, Pure Water Program. The Program is being University of California, Berkeley developed in two phases. Phase 1 of the program is • M.S., Civil and Environmental Engineering, the North City Pure Water Project that will develop University of California, Los Angeles 30 MGD through reservoir water augmentation. The • B.S., Chemical Engineering, University of City is now pursuing Phase 2 of the Program that will produce an additional 53 MGD through a potential
California, Riverside raw water augmentation (direct potable reuse) REGISTRATION project. Trussell Technologies is supporting these Civil Engineer, State of California - No. 66887 efforts with regulatory guidance for permitting potable reuse facilities and predesign of the
CERTIFICATIONS advanced treatment processes. Trussell developed Board Certified Environmental Engineer, American the predesign for the North City Pure Water Facility Academy of Environmental Engineers - No. 11- which includes ozone, biologically activated carbon, 10042 membrane filtration, reverse osmosis, and ultraviolet Specialty: Water Supply & Wastewater light/advanced oxidation process systems. Trussell's regulatory guidance secured the first reservoir water
SUMMARY augmentation permit for the City's North City Project.

R. Shane Trussell is the President and Chief The City is now looking to Trussell to develop a Executive Officer of Trussell Technologies, Inc. Dr. successful regulatory strategy for the Phase 2 DPR Trussell is a registered Civil Engineer in the State of project through interactions with regulators, design California with more than 20 years of hands-on of a demonstration facility, and development of a experience with the processes used to treat water, testing and monitoring plan for the Phase 2 DPR wastewater, and potable reuse. Dr. Trussell has demonstration facility. extensive involvement in numerous potable reuse Role: Project Manager projects throughout the state, ranging from feasibility studies and pilot testing to design and regulatory Metropolitan Water District of Southern permitting. Dr. Trussell led two major research CA/Sanitation Districts of LA County efforts funded by the WateReuse Research Title: Regional Recycled Water Advanced Foundation (now Water Research Foundation): Purification Center Demonstration Project WRRF 11-02 (Equivalency of Advanced Treatment Year: 2016 - present Trains for Potable Reuse) and WRRF 14-12 The Metropolitan Water District of Southern (Demonstrating Redundancy and Monitoring to California (MWD) and the Sanitation Districts of Los Achieve Reliable Potable Reuse), with a combined Angeles County (LACSD) are developing plans for a project budget total of $3.4 million, to advance the 150 million gallon per day (mgd) advanced water implementation of potable reuse in California. purification facility (AWPF) at the Joint Water Recently, the State Water Board selected Dr. Pollution Control Plant (JWPCP) in Carson, CA.

Trussell to co-lead a state-funded project to evaluate Trussell Tech is supporting the development of this strategies for dealing with peaks of chemical project through full-scale planning support and work contaminants. The State Board is now using the at the 0.5 mgd Advanced Purification Center (APC) findings from this research to develop statewide demonstration plant which includes tertiary regulations for DPR. Dr. Trussell is an industry membrane bioreactors (MBRs), reverse osmosis leader in potable reuse and developing water (RO), and ultraviolet with advanced oxidation TRUSSELL TECHNOLOGIES, INC. | R. Shane Trussell, Ph.D., P.E., BCEE Resume Trussell
R. Shane Trussell, Ph.D., P.E., BCEE Resume
(UVIAOP). At the APC, Trussell Tech assisted in California State Water Resources Control design development, led the operations of the plant, Board/Water Research Foundation/Kennedy and developed and executed a 15-month test plan Jenks
which included robust chemical and pathogen Title: DPR-4: Treatment for Averaging Potential sampling. At the time, an MBR pathogen crediting Chemical Peaks framework had not yet been established in Year: 2018 - 2021 California. Trussell worked alongside regulators to Trussell Technologies, in collaboration with Orange develop a thorough test plan whose results served County Water District and Kennedy Jenks, were as precedent for receiving pathogen credits from contracted with the Water Research Foundation to MBRs. In addition to the innovative work at the APC, address knowledge gaps for developing criteria for Trussell has also led the development of the DPR Direct Potable Reuse (DPR), specifically Treatment concept for the Regional Recycled Water Program for Averaging Potential Chemical Peaks. The State through preliminary assessments of the feasibility of is concerned about specific chemical compounds expanding their existing groundwater recharge plans that can pass through IPR trains and wants to to include DPR. Trussell led the development of two identify options to better control these compounds separate memos to describe what would be needed for DPR. The primary objective of the project is to to implement DPR. develop a framework to control peaks of chemical Role: Technical Advisor contaminants from passing through to consumers and threatening public health. Dr. Trussell's report
Monterey Regional Water Pollution Control showed the value of a combination of strategies- Agency (MRWPCA) including treatment, monitoring, and blending- Title: Pure Water Monterey Groundwater Recharge allowing utilities the flexibility to adapt their systems Project - Engineering Report based on their site conditions.

Year: 2015 - Present Role: Co-Project Investigator
Technologies partnered with Nellor
Environmental Associates and Todd Groundwater to WateReuse Research Foundation prepare an Engineering Report for this Project on Title: Demonstrating Redundancy and Monitoring to behalf of MRWPCA and the Monterey Peninsula Achieve Reliable Potable Reuse (WRRF 14-12) Water Management District. The submitted Year: 2014 - 2018 Engineering Report details treating the Regional This high profile $3.1 million research project, funded Treatment Plant secondary effluent through the by a Proposition 84 Integrated Regional Water proposed Advanced Water Treatment Facility Management Implementation Grant, involves the (AWTF) using ozone, microfiltration, reserve creation of a general framework for potable reuse osmosis, and ultraviolet light/advanced oxidation safety, with subsequent implementation of the processes. This highly purified product water will be framework during yearlong demonstration testing. re-mineralized and conveyed to a well field for The project focused on demonstrating how a facility injection into the Seaside Basin aquifer to augment might meet current and future potable reuse the region's potable water supply. In addition to the regulations with high levels of treatment Engineering Report, Trussell Technologies has also performance (e.g., additional log removals of assisted MRWPCA in several other projects related microbiological parameters, demonstrated to the implementation of a groundwater recharge contaminant removal) and operability. The project, such sampling the additional alternative demonstration testing is taking place at the City of wastewater sources, conducting bench- and pilot- San Diego's Demonstration Pure Water Facility. Dr. scale testing of the advanced treatment processes, Trussell was the principal investigator of this brine disposal planning, assisting with technical research project, directing technical avenues of aspects of the CEQA review, and assisting research to inform the current source water with design services for the AWTF. Trussell augmentation regulation development as well as the Technologies continues to provide permitting implementation of full-scale potable reuse facilities. support for this groundwater recharge project. Role: Project Manager Role: Project Manager
TRUSSELL TECHNOLOGIES, INC. | R. Shane Trussell, Ph.D., P.E., BCEE Resume Trussell
Celine C. Trussell, P.E., BCEE Resume
PROJECT EXPERIENCE (Select Projects)
Stanislaus Regional Water Authority West Yost
Associates
Title: Regional Surface Water Supply Project
The Stanislaus Regional Water Authority is seeking to
develop a reliable supplemental surface water supply.

Trussell Tech is part of the Program Management
team, which will be guiding and performing technical
Celine C. Trussell, P.E., BCEE to inform decisions regarding the proposed Surface Water Treatment Plant Project. Trussell Tech
will take the lead in evaluating the proposed source

EDUCATION
water which will include a review of historical water
M.B.A., University of California San Diego quality data and development of a sampling plan to (UCSD) Rady School of Management address any data gaps. Trussell Tech will work with M.S., Civil Engineering, University of Califomia, California's Division of Drinking Water (DDW) to gain approval of the proposed source water monitoring and
Los Angeles (UCLA) will also review the collected data and prepare a M.S./B.S., Grandes Ecoles Engineering Program, technical memorandum summarizing the results.

Civil Engineering, Ecole Speciale des Travaux addition to the water quality sampling plan, Trussell Publics (E.S. T.P.), Paris, France Tech will be evaluating treatment alternatives for the new source water. This will include the development of
treatment goals, evaluation of source water impacts,
REGISTRATION and recommendation of treatment processes. In Civil Engineer, State of California - No. C66094 addition, Trussell Tech will execute a bench-scale testing plan to evaluate the impacts of enhanced
coagulation using jar tests and ozonation using

CERTIFICATION
solution ozone testing. Trussell Tech will be performing Board Certified Environmental Engineer, all necessary data analysis and will prepare a report American Academy of Environmental Engineers -
No. 11-20061 Role: Project Manager
SUMMARY Fallbrook Public Utilities District/ Infrastructure Engineering Corporation
Ms. Trussell is a principal engineer in the San Title: Santa Margarita River Conjunctive Use Project Diego office of Trussell Technologies, Inc. Ms. Facilities Design Trussell has more than 15 years of experience in Year: 2014 - 2016 the field of environmental engineering. Her areas Fallbrook Public Utility District (FPUD) is integrating a of focus are water treatment and design with an new potable water supply into their portfolio through emphasis on conventional water treatment and Santa Margarita River Conjunctive Use Project membrane applications with a predominant (SMRCUP), where FPUD will receive infiltrated Santa Margarita River (SMR) water from Marine Corps Base
emphasis on reverse osmosis (RO) treatment for
Camp Pendleton (MCBCP). Trussell Tech was hired to
groundwater, recycled water and seawater
assist in designing the SMRCUP facilities, including
desalination. Ms. Trussell's experience in drinking developing a raw water quality characterization of the water treatment includes source water quality and source water, defining treatment goals, and developing treatability studies, treatment plant designs, a preliminary treatment train that meets treatment costing, and permitting. Her work in RO treatment goals, while maintaining affordability, and then further includes feasibility studies, pilot testing, detailed developing this design to the 100%-level for use in a she sate apocation. it- bid package. Trussell Tech designed the pre-treatment and post-treatment facilities, and worked with the
Trussell has also conducted extensive pilot regulators to ensure the project met their requirements. studies of water treatment processes Role: Project Manager (conventional water treatment, ozone, DAF,
Actiflo, MF/UF, RO, etc.).

TRUSSELL TECHNOLOGIES, INC. | Celine C. Trussell, P.E., BCEE Resume Trussell
Celine C. Trussell, P.E., BCEE Resume
California American Water City of San Diego South Bay Water Reclamation Title: Owner's Representative for Monterey Peninsula Plant Water Supply Project Title: Design of MF/RO System
Year: 2014 - Present Year: 2022 - present
California American Water (CAW) is pursuing the South Bay Water Reclamation Plant (SBWRP) is a 15 Monterey Peninsula Water Supply Project (MPWSP) to MGD capacity facility that produces recycled water for develop a new water supply to replace the region's local customers. Trussell Technologies is performing a existing reliance on the Carmel River and Seaside design-bid-build project of a MF/RO system that will Aquifer. This project includes a new desalination facility replace the existing trailer mounted Electrodialysis to produce drinking water from seawater pulled from Reversal (EDR) units for demineralization purposes. the Pacific Ocean via beach wells, the potential for Mr. Tackaert is serving as the MF/RO design lead to expansion of CAWs current Aquifer Storage and provide a MF/RO system that will bring ease of Recovery activities, and related facilities. Trussell operation to City staff and that reliably meets its Tech, with expertise in desalination, post treatment, treatment goals. corrosion control, and DDW permitting, is serving as Role: Project Engineer the owner's representative for the MPSWP with
regards to these topics. Trussell Tech is assisting CAW City of San Juan Capistrano/Southwest Water with development of the desalination facility conceptual Title: Greensand Media Filter Design, Filter Study and design, (including Install of New RO membranes
greensand filters for iron and manganese removal), Year: 2006 - 2008 reverse osmosis, post-treatment, disinfection; The City of San Juan Capistrano retained the services technical guidance during Build of Trussell Tech to provide troubleshooting and procurement process, including the preparation of resolution of colored water issues in its distribution performance standards, RFP system. In the same timeframe, Southwest Water documents, and application to Proposition 50 grant Company (SWC), the operator of the San Juan funding. Trussell Tech is also working with CAW to Capistrano Desalter (SJCD), hired Trussell Tech to ensure a smooth permitting process with DDW on this rehabilitate and redesign the pretreatment of the SJCD new water supply and treatment plant and developing which treats up to 5 mgd of highly mineralized strategies to minimize the potential for future corrosion groundwater for the City. The groundwater is also issues within the distribution system. contaminated with iron and manganese. Trussell Tech Role: Project Manager assisted the City with the following: water quality characterization, pretreatment alternatives evaluation, Davis-Woodland JPA/ West Yost Associates and bench-scale and full-scale evaluations of the Title: Davis Woodland Water Supply Project pretreatment filters. Trussell Tech diagnosed the cause Year: 2009 - Present of membrane fouling, identified changes in chemical The Cities of Davis (Davis) and Woodland (Woodland) feed methods to prevent clogging of pipelines with and the University of California at Davis (UC Davis) are recommended changes working in partnership to develop a regional water pretreatment to prevent future fouling, selected new supply. The Davis-Woodland Water Supply Project RO membranes, met with CDPH and SWC to discuss (DWWSP) is intended to divert and treat Sacramento CDPH requirements and continued to provide suppor during implementation. In July 2008, all media filters a a part of it proger, Tre the SJCD were retrofitted with the newly redesigned greensand and anthracite media. Ms. Trussell was in
and current water quality of the Sacramento River; charge of designing the new greensand filter media for conducted bench-scale tests assessing enhanced iron and manganese pretreatment, and overseeing the coagulation, disinfection by-product formation and installation of new media and RO membrane modules. ozone demand of this water; prepared permitting Role: Project Engineer documents for submittal to DDW, participated in
process train selection and conceptual-level facility
design for a new 40 mgd treatment facility; and
assisted in preparation of procurement documents for
selection of a Design-Build-Operate team to construct
and operate this new water treatment facility.

Role: Project Manager
TRUSSELL TECHNOLOGIES, INC. | Celine C. Trussell, P.E., BCEE Resume Trussell
Brett Faulkner, P.E. Resume
PROJECT EXPERIENCE (Select Projects)
Padre Dam Municipal Water District
Title: Indirect Potable Reuse Full Advanced
Treatment Demonstration Project
Year: August 2013 - Present
This innovative groundwater recharge project is the
first to seek Division of Drinking Water (DDW)
approval for the minimum use of the groundwater
aquifer for treatment and storage. To justify shorter
storage times, the project team demonstrated
Brett W. Faulkner, P.E. increased pathogen removal through the advanced treatment process. Our team worked with the
EDUCATION District to develop a novel, cost-effective strategy M.S., Environmental Engineering, San Diego which includes seeking DDW approval for free State University chlorine disinfection of the recycled water used as feedwater. Trussell Technologies coordinated with
B.S., Civil Engineering, University of Colorado both an Independent Advisory Panel and DDW to gain approval for a demonstration testing plan and
REGISTRATION designed and provided procurement services for Civil Engineer, State of California-No. 87912 an advanced water treatment demonstration facility that began its 12-month testing period in March
CERTIFICATION Faulkner
Grade III Wastewater Treatment Plant demonstration testing that included pathogen and Operator-Certificate Number 41525 chemical challenge tests, as well as the evaluation of brine management options for the reverse
SUMMARY osmosis (RO) process. Through pilot testing, the Brett Faulkner is a registered professional RO process was able to demonstrate stable engineer in the state of California with over ten operation at 95% recovery, which is being carried forward in the full-scale facility design. Mr.
years of experience from numerous
Faulkner also trained the Padre Dam operators on
wastewater, recycled water, and potable reuse how to operate and troubleshoot each unit process projects. Mr. Faulkner's expertise is in water and is on call to provide support to the ops staff and wastewater treatment processes with an currently running the facility. Mr. Faulkner also emphasis on process design and optimization. manages and oversees process performance data Mr. Faulkner also operated the City of San and optimization of the demonstration facility.

Diego's Pure Water Demonstration Facility
(PWDF) as a certified Grade 3 wastewater Role: Project Engineer/Operations Support operator in the State of California for over 2
San Elijo Joint Powers Authorities
years. The PWDF has a production capacity of
1 MGD and includes ozone, biologically Title: Process Optimization Plan and As Needed Assistance
activated carbon filtration, membrane filtration, Year: 2008 - 2015 reverse osmosis, and UV advanced oxidation. San Elijo Joint Powers Authority (SEJPA) owns Mr. Faulkner is skilled in GPS-X, a dynamic and operates the San Elijo Water Reclamation wastewater simulation modeling software, and Facility (SEWRF) in Cardiff By the Sea, California has utilized biological modeling to assist in the and produces up to 3 MGD of recycled water. evaluation, optimization, and/or sizing of Trussell Technologies worked with SEJPA to biological treatment processes at more than 10 develop an operations plan for the whole facility to facilities ranging from improve treatment, eliminate guesswork, and Faulkner currently provides routine operational minimize the operating cost of the SEWRF. Our support and/or as-needed engineering services staff also provided the SEJPA with the conceptual to 5 wastewater agencies. design for their 0.5 MGD MF/RO demineralization facility that has been operating since 2013.

Trussell Technologies has also provided ongoing
TRUSSELL TECHNOLOGIES, INC. | Brett W. Faulkner, Resume Trussell
Brett Faulkner, P.E. Resume
technical support and recommendations for the MF City of Santa Barbara and RO operation and maintenance procedures. Title: Engineering Services for Membrane Filtration Our recommendations to MF and RO operations
ensured that membrane processes operate stably Year: 2016 - Present and are able to rebound in performance quickly In the winter of 2015, the City of Santa Barbara during any challenging water quality events. The commisioned a 3-mgd tertiary facility to produce biological part of the operations plan resulted in recycled water using membrane filtration (MF). more consistent and effective biological treatment After experiencing issues with MF production, the that produces non-nitrified secondary effluent City retained the services of Trussell Tech to help typically below 3 NTU, and improvements to the ensure that recycled water requirements can be chemical dosing and feed logic that have reduced reliably achieved. Trussell Tech has been working alum and polymer use by over 95%. to analyze and track wastewater process Role: Project Engineer parameters at the El Estero Wastewater Treatment Plant and has been engaged in process operations
Vallecitos Water District in order to best manage the feedwater quality Titie: Aeration Basin Improvement Design supplying the MF system. Trussell Tech has also Year: 2018-Present been involved in the optimization of MF system Technologies, (Trussell Tech) cleaning procedures and has led discussions recently completed an evaluation and preliminary between the City and the MF system supplier to design that assessed the viability, benefits, and implement modifications and improvements to the associated with retrofitting the existing MF system. Trussell Tech continues to be involved at the Meadowlark Water in routine operational support for the facility where Reclamation • Facility (MWRF) with biological process optimization and implemented selectors. There are anticipated operational and modifications have led to the reliable achievement treatment benefits associated with the selectors, of MF production requirements. including biological phosphorus removal and Role: Project Engineer reductions in sludge bulking and
coagulant dosing for tertiary filtration. City of San Diego Water Planning Department anaerobic selector zones at the beginning of each Implementation of Extended Testing of Advanced aeration basin will be created using non-structural Water Purification Facility (AWPF) baffles; a compressed gas system will provide Year: 2013 - 2015 mixing with minimal oxygen transfer. Another Mr. Faulkner operated and conducted testing of component of the upgrade additional advanced treatment barriers specific to equipment: the unreliable existing panels will be potable reuse using the City's 1 MGD Pure Water replaced because they are no longer supplied by Demonstration Facility. The project team built upon the manufacturer. New fine bubble diffusers will a National Water Research Institute (NWRI) be installed. Trussell Tech also assisted with the Panel's recommendations for treatment and procurement of nitrate and TSS probes to provide monitoring needs associated with potable reuse. real-time process control and monitoring of the Ozone and biologically activated carbon (BAC), activated sludge process. Final design documents applied upstream of MF/UF and RO, was (i.e., specifications and drawings) were developed investigated as a means of providing additional for the diffusers, mixing system, and non- disinfection credits for virus and protozoa, structural baffles. Finally, Trussell Tech retained removing contaminants of emerging concern the services of Ewing Construction Services to (CECs), and potentially reducing organic fouling of create a Level 2 Opinion of Probable Construction the membrane systems. Mr. Faulkner was the lead Cost, so the Vallecitos Water District can secure operator for the extended testing project, an appropriate budget for the project and gauge performed the majority of maintenance and repairs bid submittals. for the facility, and was available on-call to address Role: Project Manager, Lead Designer and troubleshoot any operational issues through the duration of the project.

Role: Project Engineer/Operator
TRUSSELL TECHNOLOGIES, INC. | Brett Faulkner Resume
Trussell
Rodrigo A. Tackaert, P.E. Resume
PROJECT EXPERIENCE (Select Projects)
City of San Diego Pure Water Program
Title: Implementation of up to 83 MGD of
Potable Resuse by 2035
Year: 2015 - present
Pure Water San Diego is the City's 20-year
program to provide a safe, secure and
Rodrigo A. Tackaert, P.E sustainable local drinking water supply for San Diego. This project builds upon 10+
EDUCATION years of operation and testing of the 1.0
• M.Sc., Environmental Engineering, MGD Pure Water Demonstration Facility Technical University of Munich (PWDF) located at North City Water • B.S., Chemical Engineering, University of Reclamation Plant. The facility employs full- California, San Diego advanced treatment train (MF, RO, UVIAOP) with a pre-treatment process consisting of
REGISTRATION ozone and biologically active carbon (BAC). • Civil Engineer, State of California - No. Trussell Technologies is partnered with 90651 Brown and Caldwell and Stantec to develop
design of the full-scale AWP facilities for
CERTIFICATION Phase 1 and Phase 2 of the program. Mr.
• State of California Grade III Wastewater Tackaert has been involved with multiple Operator - No. 43566 aspects of the program, including design and •CA-NV AWWA Grade V Advanced Water procurement of the 42 MGD MF system and Treatment Operator - No. 153 operation and maintenance of the 1.0 MGD PWDF. He is also involved with the design of
SUMMARY the MF and RO systems for the small-scale
Rodrigo Tackaert is a registered Civil facility being constructed to inform the Phase Engineer in the State of California, a certified 2 full-scale facility.

Grade III Wastewater Operator, and certified Role: Project engineer Grade V Advanced Water Treatment
Operator, with six years of experience. He City of San Diego South Bay Water holds a B.S. in Chemical Engineering from Reclamation Plant the University of California at San Diego and Title: Design of MF/RO System a M.Sc. in Environmental Engineering from Year: 2022 - present the Technical University of Munich, South Bay Water Reclamation Plant Germany. Mr. Tackaert has been engaged in (SBWRP) is a 15 MGD capacity facility that the design of multiple potable reuse projects produces recycled water for local customers. as well as optimization of monitoring Trussell Technologies is performing a strategies, evaluation of treatment train design-bid-build project of a MF/RO system performance, and execution of pilot testing that will replace the existing trailer mounted for product pre-qualification. He has vast Electrodialysis Reversal (EDR) units for experience with membrane treatment demineralization purposes. Mr. Tackaert is processess, including MF and RO. Mr. serving as the MF/RO design lead to provide Tackaert incorporates his operational a MF/RO system that will bring ease of expertise to provide utilities with designs that operation to City staff and that reliably meets serves the intended function while keeping its treatment goals. the operator experience in mind. Role: Project Engineer TRUSSELL TECHNOLOGIES, INC. | Rodrigo A. Tackaert, P.E. Resume Trussell
Rodrigo A. Tackaert, P.E. Resume
Padre Dam Municipal Water District US Bureau of Reclamation Title: East County Advanced Water WateReuse Research Foundation Purification Program Title: Realizing Reverse Osmosis Potential Year: 2014 - present for Potable Reuse: Demonstrating
Padre Dam and its partners established the Enhanced Pathogen Removal East County Joint Powers Authority (JPA) to Year: 2015 - 2017 undertake the East County Advanced Water This project investigated pathogen removal Purification Program. This Program will use by RO systems and ability to measure state-of-the-art technology to purify East San performance. The objective was to enhance Diego County's recycled water to produce up pathogen removal credits for potable reuse to 30 percent of East County's drinking water projects using RO. To achieve this, supply. Trussell Technologies has been part challenge tests were performed to establish of the Program since 2014, with the design the degree of virus removal and ability of and operational support of the 100,000 gpd standard and novel surrogates to track virus demonstration facility to demonstrate removal. In addition, efforts were made to identify surrogates that provide higher
development of the 11.5 MGD full-scale removal credit than traditionally employed AWPF consisting of MF/RO and UV/AOP. methods while being conservative under Trussell Tech continues to provide technical both intact and compromised conditions. All support related to regulatory support and testing was performed at the 1 MGD North permitting. Mr. Tackaert was also project City Pure Water Demonstration Facility. engineer of a study that evaluated high Role: Project Engineer recovery for the reverse osmosis system California State Water Resources Control conducted at the demonstration facility. The Board/Water Research findings from the study informed the RO Foundation/Kennedy Jenks technology and recovery for the design of the Title: DPR-4: Treatment for Averaging future full-scale AWPF. Potential Chemical Peaks
Role: Project Engineer Year: 2019 - 2021
Trussell Technologies, in collaboration with
Carmel Area Wastewater District Orange County Water District and Kennedy Title: Membrane Filtration and Reverse Jenks, were contracted with the Water Osmosis Operational Support Research Foundation to address knowledge Year: 2018 - present gaps for developing criteria for Direct Potable Trussell Tech documenting performance of Reuse (DPR), specifically Treatment for the MF and RO processes, providing Averaging Potential Chemical Peaks. The State is concerned about specific chemical
independent data analysis of the process compounds that can pass through IPR trains performances, and supporting CAWD with and wants to identify options to better control the implementation of improvements to these compounds for DPR. The primary maximize the production capacity of recycled objective of the project is to develop a water and improve the reliability of the framework to control peaks of chemical Advanced Water Treatment processes. contaminants from passing through to Trussell Tech provides technical review of consumers and threatening public health. Mr. the MF and RO process performance data, Tackaert provided technical writing for the water quality and maintenance activities, and report which showed the value of a technical recommendations. combination of strategies-including Role: Project engineer treatment, monitoring, and blending-allowing utilities the flexibility to adapt their systems
based on their site conditions.

Role: Project Engineer
TRUSSELL TECHNOLOGIES, INC. I Rodrigo A. Tackaert, P.E. Resume

APPENDIX C

ADDENDA

ACKNOWLEDGEMENT
LEE+RO

WATER INTRASTRUCTORI ENTERS

OFFICIAL NOTICE

CALIFORNIA
August 8, 2022
TO: Prospective Consultants
PROJECT: RECYCLED WATER QUALITY IMPROVEMENT PROJECT
PROJECT NO. 17407
FROM: Belgin Cuhadaroglu, Project Manager
SUBJECT: Addendum No. 1 to Request for Proposals (RFP) for the Recycled Water Quality Improvement Project, Project No. 17407
Transmitted herewith is Addendum No. 1
The attached changes to the documents for the above project shall be incorporated into the REP for this project.

The Consultants shall sign this page as acknowledgment of receipt of Addendum No. 1 and attach it to his/her bid proposal. Proposals will not be accepted without this form attached.

We acknowledge receipt of Addendum No. 1 for the above mentioned project and hereby accept its terms and conditions as part of our bid.

Signature Date 8/17/2022
LEE + RO, Inc.

Consultant's Name
Recycled Water Ouality Improvement Project, Project No. 17407 Addendum No. 1
EXHIBIT "A-I"

FEDERALLY REQUIRED PROVISIONS FOR SERVICES

ALL APPLICABLE REQUIREMENTS SHALL APPLY
DRAFT
55452 01100\31193624.5
EXHIBIT "B"

SCHEDULE OF SERVICES
(NOT APPLICABLE)
DRAFT
55452 011001311936245
EXHIBIT "C"

INSURANCE REQUIREMENTS

3.2.12 Insurance.

3.2.12.1 Time for Compliance. Consultant shall not commence work under this Agreement until it has provided evidence satisfactory to the City that it has secured all insurance required under this section. In addition, Consultant shall not allow any subconsultant to commence work on any subcontract until it has provided evidence satisfactory to the City that the subconsultant has secured all insurance required under this section.

3.2.12.2 Types of Insurance Required. As a condition precedent to the effectiveness of this Agreement for work to be performed hereunder, and without limiting the indemnity provisions of the Agreement, the Consultant, in partial performance of its obligations under such Agreement, shall procure and maintain in full force and effect during the term of the Agreement the following policies of insurance. If the existing policies do not meet the insurance requirements set forth herein, Consultant agrees to amend, supplement or endorse the policies to do so.
(A) Commercial General Liability: Commercial General Liability Insurance which affords coverage at least as broad as Insurance Services Office "occurrence" form CG 0001, or the exact equivalent, with limits of not less than $1,000,000 per occurrence and no less than $2,000,000 in the general aggregate. Defense costs shall be paid in addition to the limits. The policy shall contain no endorsements or provisions (1) limiting coverage for contractual liability; (2) excluding coverage for claims or suits by one insured against another (cross-liability); or (3) containing any other exclusion(s) contrary to the terms or purposes of this Agreement. (B) Automobile Liability Insurance: Automobile Liability Insurance with coverage at least as broad as Insurance Services Office Form CA 0001 covering "Any Auto" (Symbol 1), or the exact equivalent, covering bodily injury and property damage for all activities with limits of not less than $1,000,000 combined limit for each occurrence. (1) a Personal Automobile Liability policy for the Consultant's own vehicle stipulating "Automobile Liability Insurance with a limit of not less than $1,000,000 each accident"; and (2) a non-owned auto endorsement to the Commercial General Liability policy if Consultant uses vehicles of others (e.g., vehicles of employees).
(C) Workers' Compensation: Workers' Compensation
Insurance, as required by the State of California and Employer's Liability Insurance with a limit of not less than $1,000,000 per accident for bodily injury and disease.

Professional Liability (Errors & Omissions): Professional Liability insurance or Errors & Omissions insurance appropriate to Consultant's profession with limits of not less than $1,000,000 per claim. Covered professional services shall specifically include all work to be performed under the Agreement and delete any exclusions that may potentially affect the work to be performed (for example, any exclusions relating to lead, asbestos. pollution, testing, underground storage tanks, laboratory analysis, soil work, etc.). If coverage is written on a claims-made basis, the retroactive date shall precede the effective date of the initial Agreement and continuous coverage will be maintained or an extended reporting period will be exercised for a period of at least three (3) years from termination or expiration of this Agreement. 55452.01100\31193624.5

3.2.12.3 Insurance Endorsements. Required insurance policies shall contain the following provisions, or Consultant shall provide endorsements on forms approved by the City to add the following provisions to the insurance policies:
(A) Commercial General Liability:
(1) Additional Insured: The City, its officials, officers, employees, agents, and volunteers shall be additional insureds with regard to liability and defense of suits or claims arising out of the performance of the Agreement.

Additional Insured Endorsements shall not (1) be
restricted to "ongoing operations"; (2) exclude "contractual liability"; (3) restrict coverage to "sole" liability of Consultant; or (4) contain any other exclusions contrary to the terms or purposes of this Agreement. For all policies of Commercial General Liability insurance, Consultant shall provide endorsements in the form of ISO CG 20 10 10 01 (or endorsements providing the exact same coverage) to effectuate this requirement.

Cancellation: Required insurance policies shall not
be canceled or the coverage reduced until a thirty (30) day written notice of cancellation has been served upon the City except ten (10) days shall be allowed for non-payment of premium. (B) Automobile Liability:

Cancellation: Required insurance policies shall not
be canceled or the coverage reduced until a thirty (30) day written notice of cancellation has been served upon the City except ten (10) days shall be allowed for non-payment of premium.

3.2.12.4 Professional Liability (Errors & Omissions):

Cancellation: Required insurance policies shall not be
canceled or the coverage reduced until a thirty (30) day written notice of cancellation has been served upon the City except ten (10) days shall be allowed for non-payment of premium. (B) Contractual Liability Exclusion Deleted: This insurance shall include contractual liability applicable to this Agreement. The policy must "pay on behalf of the insured and include a provision establishing the insurer's duty to defend.

3.2.12.5 Workers' Compensation:
• Cancellation: Required insurance policies shall not be canceled or the coverage reduced until a thirty (30) day written notice of cancellation has been served upon the City except ten (10) days shall be allowed for non-payment of premium.

3.2.12.6 Primary and Non-Contributing Insurance. All policies of Commercial General Liability and Automobile Liability insurance shall be primary and any other insurance, deductible, or self-insurance maintained by the City, its officials, officers, employees, agents, or volunteers shall not contribute with this primary insurance. Policies shall contain or be endorsed to contain such provisions.

3.2.12.7 Waiver of Subrogation. All policies of Commercial General Liability and Automobile Liability insurance shall specifically allow Consultant or others providing 55452 011001311936245
insurance evidence in compliance with these specifications to waive their right of recovery prior to a loss. Consultant hereby waives its own right of recovery against the City, its officials, officers, employees, agents, and volunteers, and shall require similar written express waivers and insurance clauses from each of its subconsultants.

3.2.12.8 Deductibles and Self-Insured Retentions. Any deductible or self- insured retention greater than $5,000 must be approved in writing by the City and shall protect the City, its officials, officers, employees, agents, and volunteers in the same manner and to the same extent as they would have been protected had the policy or policies not contained a deductible or self-insured retention.

3.2.12.9 Evidence of Insurance. The Consultant, concurrently with the execution of the Agreement, and as a condition precedent to the effectiveness thereof, shall deliver either certified copies of the required policies, or original certificates on forms approved by the City, together with all endorsements affecting each policy. Required insurance policies shall not be in compliance if they include any limiting provision or endorsement that has not been submitted to the City for approval. The certificates and endorsements for each insurance policy shall be signed by a person authorized by that insurer to bind coverage on its behalf. At least fifteen (15 days) prior to the expiration of any such policy, evidence of insurance showing that such insurance coverage has been renewed or extended shall be filed with the City. If such coverage is cancelled or reduced and not replaced immediately so as to avoid a lapse in the required coverage, Consultant shall, within ten (10) days after receipt of written notice of such cancellation or reduction of coverage, file with the City evidence of insurance showing that the required insurance has been reinstated or has been provided through another insurance company or companies.

3.2.12.10 Failure to Maintain Coverage. In the event any policy of insurance required under this Agreement does not comply with these specifications or is canceled and not replaced immediately so as to avoid a lapse in the required coverage, City has the right but not the duty to obtain the insurance it deems necessary and any premium paid by City will be promptly reimbursed by Consultant or City will withhold amounts sufficient to pay premium from Consultant payments. In the alternative, City may cancel this Agreement effective upon notice.

3.2.12.11 Acceptability of Insurers. Each such policy shall be from a company or companies with a current A.M. Best's rating of no less than A- VII and authorized to transact business of insurance in the State of California, or otherwise allowed to place insurance through surplus line brokers under applicable provisions of the California Insurance Code or any federal law.

3.2.12.12 Enforcement of Agreement Provisions (non estoppel).

Consultant acknowledges and agrees that actual or alleged failure on the part of the City to inform Consultant of non-compliance with any requirement imposes no additional obligation on the City nor does it waive any rights hereunder.

3.2.12.13 Requirements Not Limiting. Requirement of specific coverage or minimum limits contained in this Appendix are not intended as a limitation on coverage, limits, or other requirement, or a waiver of any coverage normally provided by any insurance.

3.2.12.14 Insurance for Subconsultants. Consultant shall include all subconsultants engaged in any work for Consultant relating to this Agreement as additional insureds under the Consultant's policies, or the Consultant shall be responsible for causing 5545201100131193624 5
subconsultants to purchase the appropriate insurance in compliance with the terms of these Insurance Requirements, including adding the City, its officials, officers, employees, agents, and volunteers as additional insureds to the subconsultant's policies. All policies of Commercial General Liability insurance provided by Consultant's subconsultants performing work relating to this Agreement shall be endorsed to name the City, its officials, officers, employees, agents and volunteers as additional insureds using endorsement form ISO CG 20 38 04. 13 or an endorsement providing equivalent coverage. Consultant shall not allow any subconsultant to commence work on any subcontract relating to this Agreement until it has received satisfactory evidence of subconsultant's compliance with all insurance requirements under this Agreement, to the extent applicable. The Consultant shall provide satisfactory evidence of compliance with this section upon request of the City.
55452.01100131193624.5
EXHIBIT "D"

COMPENSATION
In the event that this Agreement is renewed pursuant to Section 3.1.2, the rates set forth above may be increased or reduced each year at the time of renewal, but any increase shall not exceed the Consumer Price Index, All Urban Consumers, Los Angeles-Long Beach-Anaheim, CA.

DRAFT
55452.01100\31193624.5

WORKER'S COMPENSATION INSURANCE CERTIFICATION

WORKERS' COMPENSATION DECLARATION
I hereby affirm under penalty of perjury one of the following declarations:
(ONE OF THE BOXES BELOW MUST BE CHECKED)
I have and will maintain a certificate of consent from the California Labor Commission to self-insure for workers' compensation, as provided for by Section 3700 of the Labor Code, for the performance of the work to be performed under this contract.

I have and will maintain workers' compensation insurance, as required by Section 3700 of the Labor Code, for the performance of the work to be performed under this contract. My workers' compensation insurance carrier and policy number are:

Carrier
Policy Number
I certify that, in the performance of the work under this Agreement, I shall not employ any person in any manner so as to become subject to the workers' compensation laws of California, and hereby agree to indemnify, defend, and hold harmless the City of San Clemente and all of its officials, employees, and agents from and against any and all claims, liabilities, and losses relating to personal injury or death, economic losses, and property damage arising out of my failure to provide such worker's compensation insurance. I further agree that, if I should become subject to the workers' compensation provisions of Section 3700 of the Labor Code, I shall forthwith comply with those provisions.

WARNING: FAILURE TO SECURE WORKERS' COMPENSATION

COVERAGE IS UNLAWFUL, AND SHALL SUBJECT AN EMPLOYER TO

CRIMINAL PENALTIES AND CIVIL FINES UP TO ONE HUNDRED THOUSAND DOLLARS ($100,000), IN ADDITION TO THE COST OF COMPENSATION DAMAGES AS PROVIDED FOR IN SECTION 3706 OF THE LABOR CODE, INTEREST, AND ATTORNEY'S FEES.
55452.01100131193624.5
Dated: _ 20_
Consultant
By:

Title
Address
55452.01100131193624.5